Training in Spray Applications

TRANSCRIPT

Page 1: Perma Training Demonstrations 11 05 09

PermaDri Spray Demonstration Training

Fresno Facility Spray DemonstrationsPlus Field Application Pictures

Page 2: Perma Training Demonstrations 11 05 09

Set Up Information Facing spray machine open A and B regulator located

on pump by turning plastic gray lever handle ½ turn from left to right.

Allow pressure to build in regulator.

Use the red line on regulator gauge to determine pressure setting.

Adjust pressure setting on regulator by turning the gray knob on regulator left (up) or right (down) to adjust pressure higher or lower to desired setting.

Page 3: Perma Training Demonstrations 11 05 09

Start Up Start Spray Machine and let material circulate. Make sure

both A and B sides are mixed well before spraying.

‘B’ Side

Page 4: Perma Training Demonstrations 11 05 09

Hoses

Green + Yellow Supply Hoses Wrapped in an optional protective Skin for Wear and Tear Protection.

Inlet and Return Hoses “A” Side (Rubber) with field fabricated screen filter on intake

Inlet and Return Hoses “B” Side (Salt) includes in-line filter

Page 5: Perma Training Demonstrations 11 05 09

B SideA Side

Pressure Gauge Follow Red Line

Page 6: Perma Training Demonstrations 11 05 09

Gray Pressure Adjustment Valve

Page 7: Perma Training Demonstrations 11 05 09

Single Gun Set Up – Green “A” side and Yellow “B” Side

Page 8: Perma Training Demonstrations 11 05 09

Skid Mount Pump Raised on Pallets

Page 9: Perma Training Demonstrations 11 05 09

Salt Side “B” Inlet and Return to stir barrel

“B” Line 1 salt supply used with single gun

Line 2 for Two Gun Set Up

Page 10: Perma Training Demonstrations 11 05 09

Cart Mount with reel and Electric Drive

Page 11: Perma Training Demonstrations 11 05 09

Spray Pattern

Take spray gun and in a container spray A side only to make sure you have a good spray fan and do same with B side.

Then spray both A and B side simultaneously making sure that both the A and B side spray fans come together approximately 12-18 inches from end of spray wand tips.

Page 12: Perma Training Demonstrations 11 05 09

Complete Skid Mount Set-up

Page 13: Perma Training Demonstrations 11 05 09

Turning plastic gray lever on regulator ½ turn from left to right

Page 14: Perma Training Demonstrations 11 05 09

Take spray gun and in a container spray A side only to make sure you have a good spray fan and repeat with B side.

Page 15: Perma Training Demonstrations 11 05 09

Spray into Trash Barrel to check spray pattern: Spray both A and B sides simultaneously to check “spray fan”

Page 16: Perma Training Demonstrations 11 05 09

Complete gun assembly attached hose

Page 17: Perma Training Demonstrations 11 05 09

Brass Valve Seat properly positioned

Page 18: Perma Training Demonstrations 11 05 09

Adjusting spray tips vertically

Page 19: Perma Training Demonstrations 11 05 09

Attaching wands

Page 20: Perma Training Demonstrations 11 05 09

Wands securely attached

Page 21: Perma Training Demonstrations 11 05 09

Spray Application Practise

Beginning at the lowest point of substrate, start spraying substrate by leading with the A side (emulsion) followed by the B side (calcium chloride) going from right to left covering the desired area and immediately spraying directly back over applied material from left to right to starting point.

Page 22: Perma Training Demonstrations 11 05 09

Wands must be perpendicular to substrate

Page 23: Perma Training Demonstrations 11 05 09

Feathering at end of spray pattern to avoid ridges in applied membrane

Page 24: Perma Training Demonstrations 11 05 09

50% overlap-leading with A side followed by B side from right to left

Page 25: Perma Training Demonstrations 11 05 09

Immediately spraying directly back over applied material from left to right

Page 26: Perma Training Demonstrations 11 05 09

Spray application “WRONG “Too much angle to the Spray pattern

Page 27: Perma Training Demonstrations 11 05 09

“Good” Spray Angle 90 Degrees/Perpendicular to the substrate

Page 28: Perma Training Demonstrations 11 05 09

Good angle and excellent 50% overlap

Page 29: Perma Training Demonstrations 11 05 09

Building Coverage Start next pass by moving spray gun towards

applicator ½ the width of applied material (point wands at the closest edge of applied material) and start covering 50% of applied material and 50% of substrate leading with A side followed by the B side going from right to left the complete distance of the applied material and immediately spraying directly back over applied material from left to right to starting point.

Page 30: Perma Training Demonstrations 11 05 09

Spraying workable size areas

Page 31: Perma Training Demonstrations 11 05 09

Good distance from substrate

Page 32: Perma Training Demonstrations 11 05 09

Wands vertical to substrate

Page 33: Perma Training Demonstrations 11 05 09

Comfortable working distance from body

Page 34: Perma Training Demonstrations 11 05 09

Draping hose over shoulder takes weight off arm and wrist

Page 35: Perma Training Demonstrations 11 05 09

Good spray pattern-observe lines

Page 36: Perma Training Demonstrations 11 05 09

Immediate walk-ability-however it leaves footprints for first 30 minutes or so at 20C or 70F

Page 37: Perma Training Demonstrations 11 05 09

Building thickness on vertical substrate

Page 38: Perma Training Demonstrations 11 05 09

Over 2 inches in thickness ( Note: Do not spray this thick on a project!) w/o any sag

Page 39: Perma Training Demonstrations 11 05 09

Dust mask and goggles

Page 40: Perma Training Demonstrations 11 05 09

Reviewing thickness

Page 41: Perma Training Demonstrations 11 05 09

2 prong moisture meter

Page 42: Perma Training Demonstrations 11 05 09

Checking Thickness 60 – 80 mils for corrosion, wear and impact

Note Water Streaming out of Instant Set Water Based Coating

Page 43: Perma Training Demonstrations 11 05 09

Before Application of Rubber Spray or LRI “Vezlar”

Page 44: Perma Training Demonstrations 11 05 09

After Coating Applied

Page 45: Perma Training Demonstrations 11 05 09

Van Haus Crew preparing the floor in areas of Peeling Previous Coating

Page 46: Perma Training Demonstrations 11 05 09

Upper Left picture of A+B membrane over A side only – Bottom Left Sun coming up RH Job

finished

Page 47: Perma Training Demonstrations 11 05 09

Preparation ahead of fabric embedment

Page 48: Perma Training Demonstrations 11 05 09

Three Coursing for Strength in Corners with dis-similar materials of concrete and steel

Page 49: Perma Training Demonstrations 11 05 09
Page 50: Perma Training Demonstrations 11 05 09

“3 Coursing” in Critical Angle Change

Page 51: Perma Training Demonstrations 11 05 09
Page 52: Perma Training Demonstrations 11 05 09
Page 53: Perma Training Demonstrations 11 05 09
Page 54: Perma Training Demonstrations 11 05 09
Page 55: Perma Training Demonstrations 11 05 09
Page 56: Perma Training Demonstrations 11 05 09
Page 57: Perma Training Demonstrations 11 05 09
Page 58: Perma Training Demonstrations 11 05 09
Page 59: Perma Training Demonstrations 11 05 09
Page 60: Perma Training Demonstrations 11 05 09
Page 61: Perma Training Demonstrations 11 05 09
Page 62: Perma Training Demonstrations 11 05 09
Page 63: Perma Training Demonstrations 11 05 09

“A” Side Only Application took less than 50 minutes on 15,000 sq ft or

1,500 Sq M

Page 64: Perma Training Demonstrations 11 05 09

A + B Side Spraying to build a Membrane in the Thickener

Page 65: Perma Training Demonstrations 11 05 09
Page 66: Perma Training Demonstrations 11 05 09

LP Gauging the Thickness of the membrane

Page 67: Perma Training Demonstrations 11 05 09
Page 68: Perma Training Demonstrations 11 05 09

Thickener Concrete Bottom Spray Primed with “A” Side Only

Page 69: Perma Training Demonstrations 11 05 09

Thickener Walls Prepared and Bottom Concrete Primed Ready for Mine Spray

Page 70: Perma Training Demonstrations 11 05 09
Page 71: Perma Training Demonstrations 11 05 09