PERT/CPM
Activity list for the Rehabilitation of Warehouse ProjectActivityActivity DescriptionImmediate PredecessorsEstimated Duration
APurchase of Construction Materials-------1 day
BDismantling of Front Wall and GateA2 days
CDemolition of FloorB3 days
DLaying of reinforcement barsC4 days
EFilling of CementD8 days
FFabrication of Web Member and trussesC3 days
GInstallation of Web members and trussesF5 days
HRepair and installation of front wall and gateE,G2 days
Scheduling of the Warehouse Rehabilitation Project with PERT/CPMFigure 1. The project network for the Rehabilitation of WarehouseSTARTABCCC
DCC
FCC
ECC
HCC
GCC
FINISH0823352104
Path and path lengths through the Warehouse Rehabilitation Project
PathLength
START A B C D E H FINISH 0 + 1 + 2 + 3 +4 + 8 + 2 + 0 = 20 days
START A B C F G H FINISH 0 + 1 + 2 + 3 + 3 + 5 + 2 + 0 = 16 days
The critical part for the rehabilitation of warehouse: START A B C D E H FINISH Estimated project duration = 20 days
Scheduling Individual Activities
Such procedure can determine when can the individual activities start and finish (at the earliest) if no delays occur. The starting and finishing times of each activity if no delays occur anywhere in the project are called the earliest start time and the earliest finish time of the activity.
ES = earliest start time for a particular activityEF = earliest finish time for a particular activityWhere:EF = ES + (estimated) duration of the activity
The latest start time for an activity is the latest possible time that it can start without delaying the completion of the rehabilitation, assuming no subsequent delays in the project. The latest finish time has the corresponding definition with respect to finishing the activityLS = latest start time for a particular activityLF = latest finish time for a particular activityWhere:LS = LS (estimated) duration of the activity
Figure 2. Earliest start time (ES) and earliest finish time (EF) values for the activities in Figure 1.
STARTABCCC
DCC
FCC
ECC
HCC
GCC
FINISH0823352104ES = 0EF = 1
ES = 1EF = 3
ES = 3EF = 6
ES = 6EF = 9
ES = 9EF = 14
ES = 6EF = 10
ES = 10EF = 18
ES = 14EF = 16
ES = 16EF = 16
ES = 0EF = 0
ES = 18EF = 20
ES = 20EF = 20
Figure 2. Latest start time (LS) and latest finish time (LF) values for the activities in Figure 1.
STARTABCCC
DCC
FCC
ECC
HCC
GCC
FINISH0823352104LS = 0LF = 1
LS = 1LF = 3
LS = 3LF = 6
LS = 6LF = 9
LS = 9LF = 14
LS = 6LF = 10
LS = 10LF = 18
LS = 14LF = 16
LS = 16LF = 16
LS = 0LF = 0
LS = 18LF = 20
LS = 20LF = 20
Identification Slack in the Schedule
The slack for an activity is the difference between its latest finish time and its earliest finish time. In symbols,Slack = LF - EF
ActivitySlack (LF EF)On Critical Path
A0Yes
B0Yes
C0Yes
D0Yes
E0Yes
F0Yes
G0Yes
H0Yes
Each activity with zero slack is on critical path through the rehabilitation of warehouse network such that any delay along its path will delay project completion.