Peter Dummet, Darwin Port Corporation delivered the presentation at the 2013 Mining the Territory Conference. Mining the Territory Conference is part of the Northern Territory Resources Week. It provides the perfect platform for stakeholders in the NT mining industry to hear the latest information on this booming region. For more information about the event, please visit: http://www.miningnt.com.au/miningnt2013conferenceTRANSCRIPT
PORT of DARWIN - Australia’s northern gateway of choice.
11 December 2012
MINING THE TERRITORY CONFERENCE Darwin Port Corporation – Supply Chain & Port Development Peter Dummett
General Manager Port Development Darwin Port Corporation
12 September 2013
Help me, help you…
DPC – Multi facilities & multi users
DPC – Our people
DPC- An important cog
Exports
East Arm
Wharf
Imports
The port is critical to your supply chain
Congestion
Your supply chain
Mining operations can consume a significant amount on their
supply chain.
E.g. $100/tonne
• Road: 200kms - quads
• Rail: 1,500kms - dedicated train
• Sea: 3,000nms - panamax vessel
Road 30%
Load Rail 5%
Rail 40% Terminal
costs 8%
Port 7%
Shipping 10%
Product characteristics
DPC - Cargo trade
• Two thirds dry bulk
• Mineral peak was 3 years ago
• Recent growth has been in container & break bulk
cargo Peak
0
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
00/01 01/02 02/03 03/04 04/05 05/06 06/07 07/08 08/09 09/10 10/11 11/12 12/13
Outward Inward
DPC - Plans for the future
Current utilisation rate is 40%
DPC – Pond F
$15M and 2 years lead time
DPC- Dry bulk material handling infrastructure
• Overland conveyor
• 2nd rail dump
• 2nd ship loader and additional berth
Infrastructure When
Estimated
cost
Overland conveyor 5 Mtpa $60-100M
2nd rail dump 7-8 Mtpa $10-50M
Stockpile land development 7-8 Mtpa $50M
2nd ship loader & berth 9 Mtpa $150-180M
Dredging ? $50M
Alternative Loading Facilities for Bulk Minerals
Alternatives for:
• High value or low
volume products
• Environmental issues
• Storage issues
DPC – New customers
DPC - Safety and environment
• DPC implemented H&S culture
• New customers need to adhere
Bulk Cargo Exports Comparison
• Darwin - 2 Mtpa
• Gladstone - 66 Mtpa
• Dampier - 174 Mtpa
• Port Headland - 246 Mtpa
• Total Australian Ports- 848 Mtpa
The outcome?
PORT of DARWIN - Australia’s northern gateway of choice