PetroChina LNG
Program Management ITT
Customer Expectations
![Page 2: Petrochina lng amec PMO submission 2007](https://reader038.vdocument.in/reader038/viewer/2022100807/58d1390f1a28ab455d8b46fb/html5/thumbnails/2.jpg)
Background 1 at 2007
Client : PetroChina Oil & Gas Distribution Company
Three (3) world class LNG receiving terminals been built in
the next five years by Petrochina in Tangshan, Jiangsu
and Dalian
PetroChina set up dedicated LNG management hub in
Beijing HQ
Petrochina looking for LNG program management
contractor to enable its “series of LNG projects”
management capability.
![Page 3: Petrochina lng amec PMO submission 2007](https://reader038.vdocument.in/reader038/viewer/2022100807/58d1390f1a28ab455d8b46fb/html5/thumbnails/3.jpg)
Background 2
ITT issued July 2006
MaisonWorleyParsons only competitor to AMEC (China)
MWP started pre-award interface with Petrochina LNG Nov 2006
AMEC (China) to enable corporate commitment of resources to ITT
Director level engagement in Beijing to begain ASAP
![Page 4: Petrochina lng amec PMO submission 2007](https://reader038.vdocument.in/reader038/viewer/2022100807/58d1390f1a28ab455d8b46fb/html5/thumbnails/4.jpg)
requirements analysis workscope
Establish Program Management System (tKEY MILESTONE)
Set up core LNG industry technical standards and codes
Upgrade existing IT/IS system for new LNG Business Hub.
Enable Petrochina LNG Program Management improvements.
Coach Petrochina LNG managers / personnel
Location : PETROCHINA HQ BEIJING
Five areas of Petrochina requirements
![Page 5: Petrochina lng amec PMO submission 2007](https://reader038.vdocument.in/reader038/viewer/2022100807/58d1390f1a28ab455d8b46fb/html5/thumbnails/5.jpg)
The message we have passed
Vision
Strategy
Compliance
Plans
Procedures
Instructions
Reservoir
Facilities
People
• No Accidents
• No Spills/leaks
• Maximum
Production
• Controlled Costs
• Facilities Integrity
Resources Systems &
Procedures
Best
Results
+
![Page 6: Petrochina lng amec PMO submission 2007](https://reader038.vdocument.in/reader038/viewer/2022100807/58d1390f1a28ab455d8b46fb/html5/thumbnails/6.jpg)
• Systems set up
• codes & standards
• IT/IS upgrade
• Training
•
•6months
Pre-definition
IPMT lead
PMO support
•
•Assistantce to PD
• Coaching
•IPMT set up
• Timescle 4 months
Definition
PMO lead
PMC support
• PMT management
Execution
PMO Manage
PMC support
PMC contract
award
PMT
award
EPC award
PMT
definition
PMT
Implementation
time
Schedule arrangement
![Page 7: Petrochina lng amec PMO submission 2007](https://reader038.vdocument.in/reader038/viewer/2022100807/58d1390f1a28ab455d8b46fb/html5/thumbnails/7.jpg)
MC Hand
Over
Resource Arrangement
•PMC •EPC
•
Pre-definition •
Definition
•
Implementation
PMC award EPC award
PMT
Definition
PMT
Implementation
时间
Operation
![Page 8: Petrochina lng amec PMO submission 2007](https://reader038.vdocument.in/reader038/viewer/2022100807/58d1390f1a28ab455d8b46fb/html5/thumbnails/8.jpg)
Petrochina Expectations
Meet or exceed Petrochina expectations as per work scope
Develop specific PMO procedures for LNG value chain in China
Meet or exceed ISO 9000 requirements.
Design PMO system for Petrochina Beijing HQ newly established
business hub to enable specific LNG projects.
Develop specific systems & procedures for Petrochina LNG
program / project level management
![Page 9: Petrochina lng amec PMO submission 2007](https://reader038.vdocument.in/reader038/viewer/2022100807/58d1390f1a28ab455d8b46fb/html5/thumbnails/9.jpg)
AMEC current position (2007)
Maison WorleyParsons began clarifications & pre-negotiation
MWP (competitor ) presented “texual” procedures to Petrochina.
Petrochina verifies AMEC (China) advantage is strong Chinese
energy industry knowledge and history of cooperation.
AMEC (China) good opportunity realisation
Petrochina contractually agrees PMO winner will get priority
treatment in PMT award for 1st LNG terminal project.
![Page 10: Petrochina lng amec PMO submission 2007](https://reader038.vdocument.in/reader038/viewer/2022100807/58d1390f1a28ab455d8b46fb/html5/thumbnails/10.jpg)
immediate action
Review requirements analysis by Petrochina
Develop short term “realistic, workable” texual procedure list
Engage with Petrochina at clarification/negotiation meetings.
Establish timescales after Petrochina review AMEC procedure list.
Maintain AMEC professional profile / capability
Continue / improve Chinese LNG program directors engagement