pg 1 what is a value stream? all actions (value and non-value-added) currently required: – to...
TRANSCRIPT
Pg 1
What Is A Value Stream?
All actions (Value and Non-Value-Added) currently required:
– To design a product from concept to launch
– To produce a product from raw material into the arms of the customer
Simple, effective text reference on VSM: Learning To See, by Mike Rother, John Shook (ISBN# 0-9667843-0-8).
Pg 2
Steps In Value Stream Mapping
• Select a product family or service based on end customer• Have one person lead the mapping effort• Map the current state at the “door to door” (start to end) level for
the plant• Map the desired future Lean value stream• Develop an implementation plan to achieve the future state
Pg 3
Value Stream Mapping ExampleRequest For Quotation Process
Revise
Continue
C/T = 14 daysW/T = 2 daysVA/T = 1 day
CustomerMeetings
C/T = 14 daysW/T = 2 daysVA/T = 1 day
VerifyCustomer
Requirements
C/T = 5 daysW/T = 2 daysVA/T = 4 hours
Consult WithManufacturing
Engineer
C/T = 5 daysW/T = 2 daysVA/T = 1 day
CreatePreliminary
RFQ
C/T = 14 daysW/T = 2 daysVA/T = 1 day
Gather StrawmanRequirements
C/T = 3 daysW/T = 4 hoursVA/T = ~ 0
Assign Buyer
C/T = 5 daysW/T = 1 dayVA/T = ~ 0
Review andApproval Cycle
C/T = 5 daysW/T = 2 daysVA/T = 1 day
Create FinalRFQ
C/T = 5 daysW/T = 1 dayVA/T = ~ 0
Review andApproval Cycle
C/T = 2 daysW/T = 1 dayVA/T = 2 hours
Release RFQ
Continue
TriggeringEvent
C/T = Calendar TimeW/T = Work TimeVA/T = Value-Added Time
“As Is” ProcessCycle Time*:
C/T = 58 daysW/T = ~14 daysVA/T = 5 days
MeasurableDeliverable
* Assumes no revisions!Revise
Iterate
Pg 4
Tips For Mapping The Current Process
• Collect data yourself by walking the pathways of material and information– “Walk the process” repeatedly
• Begin with a quick “door-to-door” walk• Start at shipping and work upstream• Bring a stopwatch and gather your own times• Map entire stream yourself• Draw by hand in pencil first (or use flipcharts, white boards)
Pg 5
Typical Process Data
• Cycle Time • Changeover time• Uptime• Production batch sizes• Number of operators• Number of product variations• Pallet size• Working time • Scrap rate
Pg 6
Current State Value Stream(Also Referred To As The “As Is” State)
Pg 7
• Takt Time (T/T): Production pace needed to meet the customer demand (VOC) Compare to cycle time.
• Cycle Time (C/T): How often a unit or product is completed by the operation; start to finish (VOP)
• Changeover Time (C/O): Time to switch from producing one product type to another
• Lead Time (L/T): Time it takes for one unit to complete the process (includes NVA time that unit or product waits between operations)
• Total Cycle Time: Cumulative time it takes for unit or product to complete all operations (does not include wait time between operations)
• Uptime: Is calculated by dividing the actual machine time available to run by the time scheduled to run
• Working Time (W/T): Time per period minus breaks, clean up…
Time Definitions
Pg 8
Reduce Cycle Time – Eliminate Waste
Baseline Lead Time
Improved Lead Time
• Lead Time – The actual duration of a task from start to finish (the calendar time)
• Work Time – The shortest time currently possible for a task
• Value-Added Time – The amount of the work time that is actually Value-Added… the rest is waste!
Value-Added TimeWork Time
Lead Time
Value Add:1)It must transform the product or service2)The customer must be willing to pay for it3)It must be done correctly the first time
Pg 9
Future Lean Value Stream(Also Referred To As The “To Be”
State)• Produce to customer demand• Develop continuous one-piece flow• Control production with pull systems• Send the customer schedule to only one process (the pacemaker)• Level the production mix at the pacemaker• Level the production volume at the pacemaker• Shorten changeovers and produce in small “lots” upstream from
the pacemaker
Pg 10
ImplementingThe Future Lean Value Stream
• Begin with completed map of future value stream, broken down into a series of connected flows or “loops”
• Develop value stream plan:– Exactly what you want to do by when, step by step– Measurable goals– Clear checkpoints with named reviewer(s)
Pg 11
Future State Value Stream
Pg 12
1. Map “As Is” Process – 2. Prioritize Waste Opportunities –
3. Identify Lean Methods and Assign Action Items –
4. Map “Future State”, Perform Demo, and Deploy –
Level 0
Level 1
Lean Solution Responsibility Due Date
Demo OK?
Step-by-step Process For Waste Elimination
Pg 13
Identify The Value Stream For The ProcessBusiness Process Example
The Top-level Value Stream For A Sales Order Process:
C/T = 0
InitialContact
?No
Yes
C/T = 5 min.
Wait forSales Person
C/T = 10 min.
SalesPitch
C/T = 30 min.
ConfigureProduct
C/T = 10 min.
CompleteOrder Form
C/T = 5 min.
Promiseto Ship
C/T = 7 days
PendingOrder Queue
C/T = 6 days
Batch SimilarOrders
C/T = 3 days
Check Avail.Material
C/T = 1 day
Work OrderIssued
Pg 14
Case Example Step 1:As Is Map, Creation Of A Request For Quotation
Revise
Continue
C/T = 14 daysW/T = 2 daysVA/T = 1 day
CustomerMeetings
C/T = 14 daysW/T = 2 daysVA/T = 1 day
VerifyCustomer
Requirements
C/T = 5 daysW/T = 2 daysVA/T = 4 hours
Consult WithManufacturing
Engineer
C/T = 5 daysW/T = 2 daysVA/T = 1 day
CreatePreliminary
RFQ
C/T = 14 daysW/T = 2 daysVA/T = 1 day
Gather StrawmanRequirements
C/T = 3 daysW/T = 4 hoursVA/T = ~ 0
Assign Buyer
C/T = 5 daysW/T = 1 dayVA/T = ~ 0
Review andApproval Cycle
C/T = 5 daysW/T = 2 daysVA/T = 1 day
Create FinalRFQ
C/T = 5 daysW/T = 1 dayVA/T = ~ 0
Review andApproval Cycle
C/T = 2 daysW/T = 1 dayVA/T = 2 hours
Release RFQ
Continue
TriggeringEvent
C/T = Calendar TimeW/T = Work TimeVA/T = Value-Added Time
“As Is” ProcessCycle Time*:
C/T = 58 daysW/T = ~14 daysVA/T = 5 days
MeasurableDeliverable
* Assumes no revisions!Revise
Iterate
Pg 15
Case Example Step 2: Prioritize Waste/Defect Opportunities
Dark Gray - Greatest Potential BenefitGray - Worthwhile Opportunity
Revise
Continue
C/T = 14 daysW/T = 2 daysVA/T = 1 day
CustomerMeetings
C/T = 14 daysW/T = 2 daysVA/T = 1 day
VerifyCustomer
Requirements
C/T = 5 daysW/T = 2 daysVA/T = 4 hours
Consult WithManufacturing
Engineer
C/T = 5 daysW/T = 2 daysVA/T = 1 day
CreatePreliminary
RFQ
C/T = 14 daysW/T = 2 daysVA/T = 1 day
Gather StrawmanRequirements
C/T = 3 daysW/T = 4 hoursVA/T = ~ 0
Assign Buyer
C/T = 5 daysW/T = 1 dayVA/T = ~ 0
Review andApproval Cycle
C/T = 5 daysW/T = 2 daysVA/T = 1 day
Create FinalRFQ
C/T = 5 daysW/T = 1 dayVA/T = ~0
Review andApproval Cycle
C/T = 2 daysW/T = 1 dayVA/T = 2 hours
Release RFQ
Continue
Iterate
Revise
Pg 16
Waste Opportunity Impact Ease Priority Six Sigma/Lean Method
1. Eliminate first iteration loop to determine customer needs
2. Reduce time to gather strawman requirements
3. Reduce time required to consultwith manufacturing engineer
4. Eliminate first approval cycle
5. Reduce final approval cycle
6. Reduce time to assign buyer
5 3 15
5 2 10
3 3 9
4 3 12
4 4 16
3 3 9
Hold focused customer needs negotiation meeting
Use template or checklist to accelerate info. gathering
Involve ME in customer meetings or use a “feed forward” of info.
Use customer-defined template and feed forward of prelim. info.
Use a reservation system to enable immediate review
Implement real-time priority system to eliminate queue
Case Example Step 3:Identify Lean Methods And Assign Action Items
Now assign responsibilities and due dates and get started!
Pg 17
Case Example Step 4:Map “Future State”, Perform Demo, And Deploy
Targets for First RoundImprovement:
C/T = 16 days W/T = ~8 days VA/T = 5 days
“As-Is” ProcessCycle Time:
C/T = 58 days W/T = ~14 days VA/T = 5 days
Revise
Continue
C/T = 14 daysW/T = 2 daysVA/T = 1 day
CustomerMeetings
C/T = 2 daysW/T = 2 daysVA/T = 1 day
Hold FocusedCustomer Needs
Negotiation
C/T = 5 daysW/T = 2 daysVA/T = 4 hours
Consult WithManufacturing
Engineer
C/T = 5 daysW/T = 2 daysVA/T = 1 day
CreatePreliminary
RFQ
C/T = 5 daysW/T = 2 daysVA/T = 1 day
Gather StrawmanRequirements
C/T = 1 dayW/T = 4 hoursVA/T = ~ 0
Assign Buyer
C/T = 5 daysW/T = 1 dayVA/T = ~ 0
Review andApproval Cycle
C/T = 5 daysW/T = 2 daysVA/T = 1 day
Create FinalRFQ
C/T = 1 dayW/T = 1 dayVA/T = ~0
Review andApproval Cycle
C/T = 2 daysW/T = 1 dayVA/T = 2 hours
Release RFQ
Continue