pgppm 12 construction finance management
TRANSCRIPT
ASSIGNMENT
ON
CONSTRUCTION FINANCE
MANAGEMENT
PGPM 12
SUBMITTED BY
K.VINOTH KUMAR,PG PPM,REG NO: 211-05-31-9361-2133
NICMAR/CODE OFFFICE
1. Course No : PGPM 12
2. Course title : Construction Finance Management
3. Assignment No : 02
4. Date of dispatch : 15-03-2012
5. Last date of receipt of
Assignment at CODE office :
Assignment
An offer has been given by a charitable trust to develop and build a facility on a 10,000 sq.m. of plot in a prime locality of Pune where 5000 sq.m. of area will be used by the trust for housing, health facilities for senior citizens. 5000 sq.m.will be given free to developer as a cost of development.
Cost of land is Rs.10, 000/ sq.m.
Specification for flooring:
10% Granite 40% Kota stone
50% Mosaic cement tiles
R.C.C Framed structure
Aluminium sliding windows – Class A.
Rest specification as used for Class A. constructions.
Discuss the final viability of the project and the financial planning of the project. Developer would like to have minimum 18% net profit on his investment. Developer can invest only Rs.10 lakhs as his own funds and can rise not more than Rs. 50 lakhs as bank loan.
SOLUTION:
1. PROJECT SCOPE / SPECIFICATIONS
The Scope of work consists of constructing a housing and health facility center
for senior citizen on a 5000 sqm plot in a prime locality in Pune. The land
belongs to a charitable trust.
To utilize the space provided by charitable trust for a social & noble
cause.
To provide a better place for senior citizens.
To make the society aware about the responsility towards our elders.
Specification for flooring
10% Granite
40% Kota Stone.
50% Mosaic Tiles
RCC Framed Structure
Aluminum sliding windows- Class A
It will be based on latest technology of construction. The building will be
of framed structure, Structural glazing, external cladding using composite
aluminum sections will also be applied. Beside these finishes for internal as
well as external will be of the best type prevailing in the industry referring to
Class- A specifications.
The work will be completed in 12 months (365 days) as per Project
implementation Schedule.
Facilities to be provided:
Parking facility
Security & Announcement Booth
Landscaping
Lighting Arrangement
Public Toilets
Fire Fighting System
Cafeteria
Health facilities
Elevators.
2. TECHNICAL STUDIES
a) TECHNOLOGY
The technology used will the general building practice adopted by all the
contractors. Equipments like concrete mixers, mobile crane, vibrators
needles; concrete pumps etc will be deployed. Stuttering will be made up of
wood & steel as per the requirement. All scaffoldings will be of steel as per
IS code. Safety will be given utmost importance.
b & c) COST OF CONSTRUCTION & MANPOWER COSTS
Land Area allotted = 5000 sqm.
Coverage Index = 40%
Total built up area: 40% of 5000 = 2000 sqm.
On studying various such projects given below is the percentage breakup
for different items along with the rate.
Item Percentage Rate in Rs./sqm.
Structural Work 65 % 3,700
Masonry Work 11 % 705
Steel Work 3 % 265
Aluminum Work 1 % 100
Wood Works 1 % 100
Plastering Work 4 % 300
Painting works 4 % 330
Total 89 % 5,500
In the above table the total percentage comes to 89%. The rest of 11% counts
for the flooring. In our project we have 3 different types of flooring.
a) Granite 10%
b) Kota 40%
c) Mosaic 50%
Given below is the rate and percentage breakup for the flooring item.
Item Percentage of
11%
Rate in
Rs./sqm.
Area of flooring in sqm.
Granite 1.1% 2,500 200
Kota 4.4% 1,000 800
Mosaic 5.5% 250 1000
Total 11% 2000
So the cost of construction (rates given below are inclusive of material and
equipment) will be calculated as given below.
Item Area in sqm. In
respect to built
up area.
Rate in Rs./ sqm. Amount in Rs.
Structural works 2000 3,700 74,00,000
Masonry Works 2000 705 14,10,000
Steel Works 2000 265 5,30,000
Aluminum Works 2000 100 2,00,000
Wood Works 2000 100 2,00,000
Plastering Works 2000 300 6,00,000
Painting Works 2000 330 6,60,000
Mosaic Flooring 1000 250 2,50,000
Kota flooring 800 1,000 8,00,000
Granite flooring 200 2,500 5,00,000
Total cost of construction 1,25,50,000
d.Sufficiency of –Design:
The responsible person has to check & satisfied himself before regarding
correctness and sufficiency of the design for the works. prices shall, except
as otherwise provided, cover all its obligations under the contract and all
matters and things necessary for the proper completion and maintenance of
the works. The design in itself should be complete and should cover all the
points required in a finished building.
3. FINANCIAL AND ECONOMICS EVALUATION
A project involves the current outlay (or current and future outlays) of
funds with the expectation of getting future benefits. While capital expenditure
decisions are extremely important, they also pose difficulties. Capital
expenditure decisions involve substantial investment. Due to the inherent
uncertainty, future predictions become difficult. It is difficult to identify and
measure the costs and benefits of a capital expenditure since they are spread out
over a long period of time, usually 10 to 20 years for industrial projects and 20
to 50 years for infrastructure projects. Capital expenditure decisions are
irreversible; a wrong capital investment decision often cannot be reversed
without incurring a substantial loss. Capital loss increases with advances in
technology. Capital investment decisions have an enormous bearing on the
future of an organization. Capital budgetary proposals, therefore, demand a
conscious approach in the early stages of the project formulation.
Capital budgeting is the process of analysing the financial benefits of
acquiring a capital asset with a view to determine the viability of the project. It
is a complex process, as it takes into consideration depreciation, taxes and cash
flow.
a)Total investment costs
b)Project Financing Proposed
Proposed capital structure and loan requirements
Invest by the developer : 10 lakhs.
Bank loan : 50 Lakhs
Interest Calculations
1st
Quarter
2nd
Quarter
3rd
Quarter
4th
Quarter
Balance at beginning of
quarter
50 37.5 25 12.5
Interest @ 14% 1.75 1.75 1.75 1.75
Repayment 12.5 12.5 12.5 12.5
Balance at end of quarter 37.5 25 12.5 0
c) Operating Cost with quarterly breakup.
The following operating is calculated using the quarterly schedule and cost of
construction.
For 1st quarter
Structural Works 37,00,000
Masonry Works 4,02,857.14
Total 41,02,857.14
For 2nd quarter
Structural Works 37,00,000
Masonry Works 6,04,285.71
Steel works 5,30,000
Plastering Works 1,50,000
Total 49,84,285.71
For 3rd quarter
Masonry Works 4,02,857.14
Aluminum works 1,00,000
Wood Works 1,50,000
Plastering Works 4,50,000
Painting Works 3,30,000
Total 14,32,857.14
4th quarter
Aluminum Works 1,00,000
Wood Works 50,000
Painting Works 3,30,000
Flooring Works 15,50,000
Total 20,30,000
1st quarter 41,02,857.14
2nd quarter 49,84,285.71
3rd quarter 14,32,857.14
4th quarter 20,30,000.00
Total 1,25,50,000.00
d) Cash Flows
Given below is the cash flow statement on quarterly basis
0 1st 2nd 3rd 4th
Initial investment(A) -10
Operational flows(B)
Add. Revenue 125.00 125.00 125.00 125.00
Operating Cost 41.03 49.84 14.33 20.30
Interest 1.75 1.75 1.75 1.75
Profit before tax 82.22 73.41 108.92 102.95
Tax @ 30 % 24.67 22.02 32.68 30.89
Profit After tax 57.55 51.39 76.24 72.06
Terminal Flows(C)
Repayment -12.5 -12.5 -12.5 -12.5
Total Flows(A+B+C) -10 45.05 38.89 63.74 59.56
Pv factor at 18% discounted
rate
1 0.85 0.72 0.61 0.52
-10 38.29 28.00 38.88 30.97
Total Pv’s 126.14
NPV 116.14
Payback period:
Average return per quarter = 51.81 Lakhs
Total investment + Bank Loan = 60 Lakhs
Payback period = 60/51.81 = 1.16 = 3 and 1/2 months
Pay–back Period. It is the time (in years) that a project/plant takes to pay back
the initial cost of the investment from the expected future net cash flows
resulting from the investment.
4. CONCLUSIONS/ RECOMMENDATIONS
According to the NPV method the project is financially feasible as the
NPV is positive. Also according to the payback measure the initial investment
and the bank loan amount is recovered in 3 and ½ months.
So the project is financially feasible.
5. BIBLIOGRAPHY / REFERENCES
Construction Finance Management NICMAR Pune.