1. Course no PGPPM 23
2. Module M 56
3. Course Title Construction quality, safety andenvironment
4. Candidate Name G.S.VINOD VASAN5. Reg. No. 211-03-31-9250-21336. Assignment No. 17. Date of Dispatch8. Last date of receipt 28 February 2012
-
8/2/2019 PGPPM-23
2/34
ASSIGNMENT
You have been selected as a project manager for a prestigious high rise building in Mumbai
which will be housing very rich personalities from industry and film world.
Your company management has asked you to formalize Quality management system (QMS)
for interior finishes, plumbing and prevention of rainwater seepage so that the overall quality
standard and image of the company is raised.
-
8/2/2019 PGPPM-23
3/34
QUALITY POLICY STATEMENT:
To consistently meet and strive to exceed the agreed requirements of our clients in the most cost
effective manner by providing a high standard of Management, Technical expertise, Workmanship
and timely completion of the project.
This will be achieved by employing highly professional people with drive and determination to work
as a team with our Clients, Architects, Consultants subcontractors and Suppliers in a non-
adversarial manner. It is our commitment to maintain a management system which reflects the way
our business works, our clients needs and the requirements of the international standard for
Quality systems ISO 9001:1994
QUALITY MANAGEMENT SYSTEM
An established system of Management of Quality is followed aiming to achieve the following
Establishing an international standard of procurement and work practices. Resolving specific problem areas covering technical, product or system issues Investigating new methods of work and ideas. Innovation in the existing procedures and practices Continuous Improvement
This is achieved by proper planning, monitoring, control and co-ordination of the following
Design Intent Documentation Subcontractor Selection Contract Project Program Procurement Strategies Construction and Review of Methodologies
-
8/2/2019 PGPPM-23
4/34
DESIGN
Programs and Manage the flow of Design information plan the project and oversee the work ofthe subcontracts so that the project is completed in accordance with the drawings, specifications,
program, safety and cost plan.
Systematically assess proposed design, drawings and specifications for practicability,Buildability, program effect, coordination, potential Quality and value for money and make
appropriate recommendations to the Designers.
DOCUMENTATION
All pertinent incoming/ out going documents for the project will be controlled in accordancewith the Document control procedure, which will ensure their effective recording and review. It
will also provide for the subsequent controlled distribution of Documents and Destruction or
removal of obsolete documents
The Document control procedure will identify all requirements for long term storage,maintenance and retrieval of archive records including defect liability period (DLP).
Ensuring the subcontractor to maintain records and detail it in their Quality Plan and submit tocontractors/Consultants for inspection and approval as and when required.
Generating handover documentation, performance histories, performance reviews and testingand commissioning reports during handover phase.
SUB-CONTRACTORS
All subcontractors are thoroughly reviewed in terms of Quality, Buildability and performanceduring the bid process and during project mobilization. Continuing reviews are undertaken at
regular contract progress meetings with all relevant parties.
All changes and addition to subcontracts are reviewed on receipt to ensure that the requirementsare adequately defined and will be able to be met by the subcontractor appointed.
All the guarantees, warranties and performance parameter setout in the specifications/agreedwith the clients and consultants are forming part of subcontracts to ensure that the set out
standards are met.
-
8/2/2019 PGPPM-23
5/34
PROJECT PROGRAMME
Requirements to Client
A detailed contract programme shall be prepared and monitored on a weekly basis and reportedto client as and when required. A target schedule shall be prepared by the planning engineer and
issued to the package managers package wise for monitoring on a weekly basis.
Progress photographs shall be taken and issued to client. Reasons for the slippage in the activities shall be documented; the mitigation strategy for the
same shall be agreed by the team.
Delay trackers shall be maintained and reasons for the delay shall be documented.
Requirements from Subcontractors
Subcontractors to submit a master Programme for the entire scope of works as outlined in thecontract and adopt the same as a base Programme after the approval
The programme shall be updated on a weekly basis and submitted. Subcontractors to submit weekly/ Bi-weekly programs, which will be matched with the baseline
and will be closely monitored.
PROCUREMENT
Goods and services will be procured from acceptable services and conformance to thespecifications. The selection of such sources will be by short listing based on the analysis of
Pre- Qualification Questionnaire from the following,
- Procurement database- Client standing lists- Architects/Consultants- Design team Input- Project Team recommendations- Enquiries from Trade Sub-Contractors
A thorough Technical Bid Analysis (TBA) would be carried out to ensure all the specificationsare well understood by the subcontractors before they are awarded the subcontract
The appointed Subcontractors/Suppliers will be required to provide appropriate Qualitydocuments with the means to confirm the Quality is being competently addressed and
implemented at all levels.
-
8/2/2019 PGPPM-23
6/34
Subcontracts and purchase orders will contain all relevant information and are reviewed prior toissue.
Necessary inspection/test shall be conducted on purchased equipment/specialized items at thesuppliers or Subcontractors premises including access for the Clients representative/ architects
and Consultants if required, to ensure the right material/product usage.
CONSTRUCTION
Methods of monitoring the activities of Subcontractors will include, but not limited to, the
following
Management of the subcontractors process in accordance with the contract and Head Contractto avoid the rework caused due to not understanding the design. This is made clear through to
the subcontractor by asking them to submit method statements, which will be reviewed and
approved, before they procure and execute the works.
Auditing subcontractors Quality Management Systems and their implementation. Involvingsubcontractors quality dept. and senior management personnel
Review and approval of method statements and monitoring their implementation Witnessing activities, inspections and tests Surveillance and site inspection Checklists Mock up and Approval. Material Inspection and Testing ( MTR) Corrective Action Requests (CAR) Control of Non-conforming Products Review of records and Data. Closeout Procedures DLP Quality audit from BLL HO
-
8/2/2019 PGPPM-23
7/34
Management of the Subcontractors process in accordance with the subcontract and Head Contract
The subcontract will be ensured to be followed by contractors in its full spirit and
contents. This will be monitored by means of progress meetings. All changes will be
reviewed on receipt to ensure that the requirements are adequately defined and executable.
All these are properly documented and will be ensured executed by means of Progress
Certificates and Change management procedure as agreed between Client, Contractor,
Architects and Consultants.
Auditing Contractor and Subcontractors Quality Management Systems and theirimplementation.
The Construction manager (head of QA/QC) will be in-charge of arranging audits of
all activities to ensure compliance with the operating procedures. He will carry these out by
periodical audits in accordance with the checklists /records/MTRs as set out in this
documents. The audit program will cover the following categories of audits.
Internal Audits of Contractor Site and HO External Audits of suppliers and Subcontractors where appropriate by package managers Audits of Contractor by Architects and Consultants on behalf of clients. All quality audits whether internal or external, will be carried out in accordance with the
quality system auditing procedures. These procedures will also cover the distribution or
reports and method of follow up and close out of findings
A summary of visits and audit and comments of auditing personnel shall be issued
monthly, attached as part of PCG report. Findings and discussions of PCG shall be
implemented and used for closeout and regularly issued in the next PCG.
-
8/2/2019 PGPPM-23
8/34
Review and Approval of Method Statements and monitoring their implementation.
Subcontractors will be instructed to submit a ten point Method Statement prior to the
commencement of any work in which they need to describe point to point the system and
procedures followed by the contractor in purview of Quality, Safety, Documentation while
executing the work. These method statements will be analyzed and approval will be given
under three heads
A- Approved for constructionB- Approved with suggestionsC- Rejected
If the Status of approval is B or C the contractor has to re-submit the document and
get the approval prior to work.
Witnessing activities, inspections and tests
Subcontractor shall give sufficient intimation for witnessing inspection and testing
and will provide the details of the tests need to be conducted and observations to be made.
However contractor will provide sufficient guidelines for ensuring proper Inspection and
tests and will also have an overall supervision of works to ensure the utmost Quality of
works.
Package managers on the guidelines set in this manual do inspection and testing of
the materials on day-to-day basis.
The broad guidelines have been already agreed in the consultants meetings, they
shall be used to update existing or develop the MTRs and Checklist.
Surveillance and site inspection
Contractor engineers will have a thorough surveillance and regular site inspections to ensure
that subcontractors are performing to the required standards so as to deliver a high Quality
product as per the contract, Specifications and Client Expectations.
Checklists
Contractor has got a vast range of checklist to cater to almost all works and practices
in the industry. Further customized checklist will be prepared based on the broad heads
agreed between consultants and Contractor
-
8/2/2019 PGPPM-23
9/34
Mock up and Approval
Contractor will submit samples of materials and Mockups prior to start of any work
thro Mockup-flow chart Subcontractor will be instructed to submit samples of materials
and Mock up of works prior to the start of any work . The same will be got approved from,
client/ consultant to ensure utmost justification to their expectations.
Corrective Action Requests (CAR)
Incase of the works getting done which is not conforming to the method statements
resulting in faulty works/unacceptable quality, BLL will raise corrective action request on
the subcontractor asking for the review of works with reference to the methods agreed.
In case of methods agreed does not result in final expected product, Contractor will
raise the CAR on subcontractor asking for a discussion/ to find the causes and involve the
entire project team to review the revised method statements addressing all the root causes
for the failure. The package managers are asked to make closeout reports for the CARs,
which will be sent.
Control of Non-conforming Products ( NCR)
Subcontractors will be asked to identify non-conforming work by means of physical
identification or quarantine. The subcontractor will be issued with, or be required to issue, a
non-conformance report and required to state what action will be taken to correct non
conforming work and prevent its recurrence.
Review of records and Data.
The records and Data generated in the due course of project will be analyzed using
Statistical Techniques and forms the base of a continuous improvement process.
-
8/2/2019 PGPPM-23
10/34
Close Out Procedures.
Project Finalization Plan shall be prepared integrated in to the program and implemented thro
checklists for the following areas.
1. Technical Close-out :(This shall be done package-wise and detailed program andchecklists shall be prepared.
2. Contractual close-out: Ensuring obligations in head contracts are closed out andcorresponding close-out of subcontracts package-wise and all their accounts settled
3. Establishment of Handover procedure for subcontractors to Contractor and Contractor toClients
4. Design close-out: Furnishing of As-built documentation from subcontractor toContractor, Contractor to clients and Consultants to Clients
5. Handing over to the Operation and Maintenance Team
For achieving all the above five points a project finalization meeting shall be conducted to
define the team, roles and responsibility
Defect liability Period
Contractor shall serve DLP as per the conditions of contract,
Contractor shall inform all the list of all vendors with a name of contact person,addresses and any other form of communications available with the vendor for
establishing the long-term service set up and contact during the DLP. Also Contractor
will identify the contact during the DLP who shall be informed by the client in case of
any support required from the vendors.
Incase, vendor fails to address the issue to the satisfaction of the client, Contractor beintimated by the client. Contractor on advise from the client shall initiate a process of
addressing the defect/operational issues during DL period, shall coordinate with the
vendors and consultants (if required) to arrive at the required action plan to be carried
out by the vendor.
-
8/2/2019 PGPPM-23
11/34
QUALITY CONTROL STANDARDS AND SPECIFICATIONS:
The quality of construction depends upon right materials used, the correct methods followed and
produce end product of acceptable performance. Quality control attempts to ensure just that much.
The means of quality control are tests, inspection, supervision and analysis of data etc. Quality tests
are conducted in laboratories and inspection and supervision are carried out on the site and experts
in office do the data analysis.
Specification
The project authorities prepare the process of working out specification of various facilities
where concrete will be used. However, the standards and specifications for concrete and its various
ingredients are universally standardised and they are required to be in conformity with it. Indian
Standards IS for concrete and it basic ingredients viz cement aggregatescoarse and fine, water
admixtures and various aspects of concreting, its placement and final acceptance should be as per IS
specification.
Tests
Tests are used to determine the various properties of the materials, which help in their
selection as well as for ascertaining the quality of final product. The test results are compared with
the prescribed standards and specifications and judgments are arrived at. Proper methods of
sampling, prescribed procedures of testing, well qualified and trained personnel for testing work
and properly equipped laboratories are necessary.
What to Test
The manufactured goods such as cement and steel carry their suppliers warrantee but this does
not mean that they are not to be tested. In case of materials like aggregate and water the properties
may vary widely over time and space and proper selection has to done to meet the engineering
requirements. The raw materials are processed to obtain the final product. The processing needs to
be tested and supervised carefully. Testing of final product is important. This helps to ascertain:
i. Conformity to specificationii. Validity of design assumptioniii. Need of modification due to any erroriv. Comparative position of work at different sites.
The data analysis and interpretation becomes meaningful only if observations are adequate
and frequencies are numerous in relation to the volume and importance of work.
-
8/2/2019 PGPPM-23
12/34
INSPECTION
Inspection is the act of physical verification of the subject work on the site and under normal
day-to-day working conditions. The inspection for quality is done by quality control Inspectors who
are posted at all active sites and who should be persons at deputy engineer and above levels. They
are a member of the quality control team and unrelated to the production process directly.
1. The duties of quality control inspectors are as under:2. Check that the input materials brought at site are as per specifications.3. Check that the working is proceeding in accordance with the specifications and bring the
substandard work to notice of concerned authorities.
4.
Inspect personally and regularly the work in progress at sites.5. Review the previous days "Daily QC" reports filed by the Field Quality Control units
and convey immediately to the concerned site incharge and any adverse results and
recommendation for rectification.
6. Verify that the results of the tests received from labs have been duly attended to andsend them to seniors in the department.
7. Prepare daily report of inspection on the prescribed forms and send to seniors in thedepartment.
8. Check to ensure that QA manual for workers and supervisors are available at hand atworkstations that they are not in torn stage, that they are easily accessible and that they
are being referred to.
9. Check to ensure that copies of contract conditions particularly regarding specificationsand related matters are available at site offices and are being referred to.
10.Check that all equipments plants are in proper working condition and that they conformto IS specifications.
11.Investigate the case where the test results of input materials are satisfactory but that of inprocess stage are not, or there is a discrepancy in test results during in process and end
product stage and find out the causes of mishap.
12.Investigate the human factor and machine condition/capability more particularly.
-
8/2/2019 PGPPM-23
13/34
Concreting- Making and transportation
Ingredients of Concrete
Cement
Use of appropriate grade of cement as recommended by the consultant and confirming to IS456:2000
Manufactures test certificate should accompany each consignment and cement should beconsumed within one month of manufacturing date.
Cement should be properly stored in stacks not more than ten bags, clear from the wallsby one meter and protected at all time from moisture. However do not wrap the bag with
polythene sheets as sweating may occur.
Identify each lot of cement and follow a FIFO (first in first out) method of issue of bags. Each consignment of cement should be tested in house for consistency, setting time, and
strength.
Aggregate for concrete
For RCC works coarse aggregates confirming to IS 383 and IS 2386 having maximumsize of 20mm and down.
It should be obtained from crushed granite, trap, and basalt quarry. it should bechemically inert , rounded or angular in shape and free from dust, foreign matter and not
thin ,porous ,laminated or flaky.
Fine aggregate shall be gritty sand with FM range between 2.6 to 3.2, silt content shouldnot be more than 5% and there should be no traces of salt. Aggregates with specific
gravity less than 2.6 should not be used.
If dirty wash the sand before use. Sand should be clear of organic materials
Water
Water must be clean, fresh and free from oil, alkali, acid and organic matter. Potable water is considered good for concreting and curing. IS 456:2000 gives permissible limits of solids.
-
8/2/2019 PGPPM-23
14/34
Admixtures
Use of admixtures/additives must be done only after obtaining clearance fromtechnical consultants.
Accelerators, plasticizers, retarders, integral water proofing compound are theadditives commonly used.
Expiry date of the chemical must be checked before use.
Mixing of concrete
In-situ mixing
Ensure adequate stock of all ingredients of concrete Use calibrated farma for measurement or in case of weigh batching, use a weigh
batcher machine.
Charge the rotating drum with 25% of required water to rotate 3-4 times. Generally 20-25 litres of water is recommended to one bag of cement. The water
cement ratio is kept to 0.4 0.5. The moisture content of aggregates should be
checked at frequent intervals.
Load the hopper with the coarse aggregate followed by the fine aggregate.Above this the entire quantity of cement should be spread. Then the quantity
of fine aggregate followed by balance coarse aggregate should be loaded. This
type of sandwiching is done to avoid the spillage of cement while discharging
into the drum. Immediately after loading the drum balance quantity of water is
added.
The drum should be rotated for at least 1.5-2 minutes. The rotation of drum isabout 15-20 revolutions per minute.
If plasticizer is used one litre of water must be held back. Add requisite quantityof plasticizer to water and mix it thoroughly. This mixture is poured into the
drum after the drum has rotated for about one minute. The drum must be rotated
for atleast one minute after adding the plasticizer mixture to ensure proper
dispersion.
-
8/2/2019 PGPPM-23
15/34
GRADE Characteristic
strength after 7 days
(n/mm2)
Characteristic
strength after 28
days (n/mm2)
Minimum cement
content per cum
M10 7 10 220kgs
M15 10 15 280kgs
M20 13.5 20 320kgs
M25 17 25 360kgs
No grade below M20 shall be used for RCC works. Concrete must be placed in position and compacted within half an hour of
mixing of the same.
Always keep a supervisor on the mixer to monitor the works. Use large band lies, wheelbarrows, and hoist machine to expedite
transporting process. Wet the surface of the carrier to avoid moisture loss due
to adsorption.
Be careful to avoid segregation and wastage during transportation. In case ofsegregation, remix the concrete before placing.
Concrete by vision must be homogeneous in colour, well graded, fluffy and itshould form a shape of ball when rounded in the hands.
Batching plant mix (RMC)
Preference for RMC concrete from reputed companies possessing automatedbatching plant, at least 30 cum per hour capacity supported by adequate number
of transit mixers.
The logistics should be worked out so as to receive atleast one load of 6 cumevery ten to fifteen minutes.
Check the empty transit mixer for preset concrete in the drum. Preset quantityaffects the quantum of concrete received.
Concrete should be received with a delivery challan and data cycle sheetshowing grade, quantity, water cement ratio, slump, cement content, time of
manufacturing, dosage of additive added, weight of various ingredients of
concrete.
-
8/2/2019 PGPPM-23
16/34
Go through the data cycle sheet before accepting the concrete, and get yourselfconfirmed whether the weights of the ingredients as per the data cycle sheet is
similar to the one in the design mix report prepared for the project. This is very
essential because, the RMC shall be accepted for the work only based on this
validation.
Do not accept concrete after 3 hours of mixing. Do not recharge the concrete by adding additive, water, cement without prior
permission from the project in-charge.
Slump recommended for RMC mix is 100mm to 125mm Place the concrete pump on horizontal, hard even surface and keep the approach
area free of materials to facilitate easy maneuverability of transit mixers. The
approach should not slope towards t5he concrete pump.
The horizontal section of pipe should be at least 7 meters before the vertical bendis put.
Reduce the length of pipe to the minimum to reduce frictional losses andexcessive strain on the pump.
The pipeline should be independently supported on vertical segment and not onthe shuttering. The vibrations due to pumping should not affect or displace
shuttering works.
Pump rich slurry (one bag) before pumping concrete to lubricate the innersurface of pipes.
In case of intermittent supply keep the current transit mixer unloading inprogress until the next mixer arrivers at site. This avoids choking of pipeline due
to non-pumping for long duration. Avoid reverse stroke to clear a choke. The
fluid gets flushed out and the problem gets compounded.
Do not bend the flexible end pipe by more than 135 degrees while concreting. In constricted areas do not unload directly from the pipe. Use bandly and mumty
to shift and place concrete in such areas.
Be excessively careful while passing the ball while clearing the concrete in thepipeline after the days work is over. Due to negligence somebody could get hurt.
Employ professional hands for connecting pipeline. They will do a neater andfaster job without any safety problems.
Leave the pipeline, under the pomp and adjacent areas clean of concrete dumping
-
8/2/2019 PGPPM-23
17/34
after the work is completed.
PLACING AND COMPACTION
Do not use chutes longer than 4.sm or inclined at more than 45 to horizontal topour concrete.
Place cement concrete to the required depth and vibrate it until entrapped airinside concrete is released.
Pour concrete into beams and then over the slab portion. Bond new concrete to previously poured concrete. If the previous pour was less than 4 hours prior, the laitance film and porous
layer shall be removed from the surface of previous pour.
If the previous pour was more than 4 hours prior but less than 30 days oldobserve the above process and expose aggregate with wire mesh and wash with
clean water.
If the joint is more than a month old use bonding agents as per specification ofthe manufacturer.
If the beam more than 500mm deep, concrete it in layers. Columns, beam, slab level of concrete top should be pre-marked before start of
concreting works.
Check the slab level during concreting with line dori method and also theleveling instrument.
Use appropriate needles for vibration depending on the aggregate size,reinforcement spacing and element to concrete. For big footings use 60m needle,
for slabs use 40mm needle and for starters and precast lintels use 25mm needle.
Vibrators should operate for a speed not less than 10,000 rpm. Ensure that just
adequate vibration is only done. Over vibration is very bad.
Use wooden runner to ram so as to form slurry on top of the concrete surface. Clean the shuttering works of all spilled concrete immediately after concreting. Leave vertical construction joints after consultation with the structural engineer. Match the vibrators, masons to the rate of concreting. All surfaces of shuttering shall be moistened before placing of concrete to reduce
water loss due to absorption.
Slab should be sprayed with water after covering with hessain cloth 3 hours after
-
8/2/2019 PGPPM-23
18/34
concreting, i.e. initial setting is over and ensure that hessain cloth will remain
wet till ponding of water.
Pond water to a depth of 25mm using bunds the next day and keep waterstanding for 7 days a stretch.
In case ponding is not possible, cover it with hessain cloth and keep it moistthrough out.
Do not ignore curing of slab to facilitate marking of columns for the upper slab. The beam bottoms should be cleaned using high-pressure cleaners.
Testing of concrete
Slump test
Conduct slump cone test, one during the start, one at midday and one towards theclose of days work.
Again any load on suspect can be tested on case-to-case basis.
Cube test
The sample is made at the point of discharge of mixture. Take 3 samples after 7 days and 3 samples after 28 days. The test frequency shall be in accordance with IS 456-2000. For concrete manufactured at site, there must be representative samples for
the days work and for different elements like footing, slab, column, wall.
In case of cube failure, the element to be identified and nondestructive test tobe conducted. Cube results of RMC supplier for same batch can be tested.
-
8/2/2019 PGPPM-23
19/34
QUALITY CONTROL IN SERVICES:
PLUMBING OPERATIONS
Most of the plumbing failures like water closets urinal sinks washbasins taps etc. are manufactured
units. If care is taken to obtain these items from repeated manufacturers, much of these trouble
faced later can be avoided. Plumbing problems do not usually arise out of fault in the components
used but it is their faulty installation, which cause trouble. A plumbers skill includes an ever-
widening knowledge of different types of metals and Fittings in the market.
There is a tendency on the part of plumber workman to do a shoddy job, as plumbing is time-
consuming job. Short cuts in labour are employed by workman and most of the job is covered by
flouring or concrete. As bulk of the job is hidden it is difficult to list out the quality of work. It is
only when leakages appear attention is drawn towards the installation and by that time it is too late.
WATER SUPPLY
In India major piping material is galvanised iron although plastics have started making in roads.
Pipes are jointed either by threading or by welding. During erection trash and debris should be kept
out of pipefittings and fixture. Care should be taken to prevent animals from entering into piping
system. The support of piping is critical for both successful operation of the system as well as for
the safety of the structure. The basic source of stability support is the anchorage of the support. All
pipes are to be tested to 50-kg/cin2 and pipe network tested for 10 kg/cm2 before putting them into
operation. For water supply galvanized pipes are available in three grades, which are banded with
distinguishing colours of paint. It is advisable to get pipe from repeated manufacturers only. Great
care has to be taken for jointing these pipes which is done by cutting threads and using sockets.
Workmen have a tendency to do a shoddy job. Plumber white lead (safeda) should be used while
making joints.
In water supply installation fitments are provided in the form of ball valves, globe valves, gate
valves and water taps. Ball valves are available in two types; high pressure valves used in water
mains having a pressure of 1.75 kg/cm sq. Low pressure valves have domains having pressure tube
1.5 kg/cm sq and 3.5 kg/cm sq. Every bit or stage tap should be tested on an internal hydraulic
-
8/2/2019 PGPPM-23
20/34
pressure of 20 kg/cm sq and pressure maintained for at least 2 minutes during which it will not
sweat or leak. The length of the spindle lead should be such that when the washer plate is resting on
Resting without a washer the length of the thread equals to not less than their fourth of the external
diameter of the threaded portion of the spindle. Globe valves are used for throttling. Valves are
rated according to pressure. This should be checked to ensure that valves of the proper strength of
materials are used.
SANITARY FITTINGS
For sanitary Fittings there are two types of pipes available; one is the sand cost view pipe
confirming to IS 1759 and the other one is spun cost iron pipe conferring to IS 3989. The weight of
the pipe should be checked. For sand cost iron pipes the weights for 1.8-meter length should be as
under:
75 mm dia, weight 16.52 kg excluding ears
100 mm dia, weight 21.67 kg excluding ears
For spun cast iron pipe the weight per 1.75-meter length should be as under:
75 mm dia 12.2 kg
100 mm dia 18.4 kg
In these, tolerance upto 10% may be allowed while jointing the pipe the interior of socket and the
exterior of spigot end should be thoroughly cleaned and dried. The spigot end should be inserted
into the socket right upto the back of the socket and carefully centered by 2 to 3 taps of treated spun
yarn twisted into coils of uniform thickness well caulked with the back of the socket. Lead is to be
poured later and well caulked for a tight fit. Vitreous china sanitary fittings are classified as first
category, commercial and off grade. Standard firm mark the class of fittings and mention whether it
conforms to IS specification. The wrapping paper is different for first class and different for
commercial fittings. Off grade fittings should be avoided at all costs.
Work basis can have tolerances up to 4mm or less. All internal angles should be cleanable and all
flat ruins should slope towards the bowl.
For water closet the test of performance is that six pieces of usual toilet papers of 150 x 115 mm
should get flushed three times out of four. When flushed there should be no smudge left. In case of
flushing cistern the chain should be capable of holding 50 kg load without any distortion. It is better
to insist on ISI mark cistern. For pipes the test is by a hammer and when striking it should emit
clear ringing sound.
-
8/2/2019 PGPPM-23
21/34
Floor traps should be checked for water set
1. Pipes - check for size, strength and quality2. Check valves and fittings for conformity to specification and pressure3. Check for jointing4. Check for hydraulic pressure and test for leakage5. Pipe installation should be approachable for maintenance6. Sanitary fixtures must be checked for dimension makes finish and ISI grade marking7. HCI pipe for dimension weight make finish and whether coated with anticorrosive paint8. Class of GI pipe size and made9. Water supply fittings weight makes finish and ISI mark10.Lead connection pipes and plastic connection pipes for weight size and ISI marks11.Flushing cistern whether it has ISI marks12.Sizes of brackets for wash basins sinks and flushing cisterns13.Ms clamps for fixing HCI pipes, their size and mode of fixture in cement blocks14.Quality and quantity of lead in joints15.Water tanks - thickness of sheets size of tank size of various fittings, whether tanks are
painted with priming red lead cost outside and two costs of bitumen paints inside
16.Manhole covers road gully gratings weights size, make and finish17.Home pipe class make decision and finish18.Testing of system and general quality of lines levels etc.19.Stoneware pipe makes dimension glazing and finish.
INSPECTION AND TESTING
All sanitary appliances and fitments shall be carefully examined for defects before they are installed
and also on the completion of the work.
Pipes are liable to get damaged in transit and, notwithstanding tests that may have beenmade before dispatch, each pipe shall be carefully examined on arrival on the site.
Preferably, each pipe shall be rung with a hammer or mallet and those that do not ringtrue and clear shall be rejected. Sound pipes shall be carefully stored to prevent damage.
Any defective pipes shall be segregated, marked in a conspicuous manner and their use in
the works prevented.
Cast iron pipes shall be carefully examined for damage to the protective coating. Minordamage shall be made good by painting over with hot tar or preferably bitumen. But if
-
8/2/2019 PGPPM-23
22/34
major defects in coating exist, the pipes shall not be used unless recoated.
Each pipe shall be carefully re-examined for soundness before laying. Close inspection shall be maintained at every stage in the work, particularly as to the
adequacy of timber supports used in excavation and the care and thoroughness exercised
in Filling.
Careful note shall be kept of the condition of any sewer, manhole or other existing workwhich may be uncovered and any defects evident shall be pointed out immediately to the
Authority.
No work shall be covered over or surrounded with concrete until it has been inspectedand approved by the Authority.
Testing
Comprehensive tests of all appliances shall be made by simulating conditions of use. Overflow
shall be examined for obstructions.
SMOKE TEST
All soil pipes, waste pipes, and vent pipes and all other pipes when above ground shall be approved
gastight by a smoke test conducted under a pressure of 25 mm of water and maintained for 15min
after all trap seals have been filled with water. The smoke is produced by burning only waste or
tarpaper or similar material in the combustion chamber of a smoke machine. Chemical smokes are
not satisfactory.
WATER TEST FOR PIPES OTHER THAN CAST IRON
Glazedware and concrete pipes shall be subjected to a test pressure of at least 1.5m head of water at
the highest point of the section under test. The tolerance figure of 2 litres/cm of diameter/km may
be allowed during a period of ten minutes. The test shall be carried out by suitably plugging the low
end of the drain and the ends of connections, if any, and filling the system with water. A knuckle
bend shall be temporarily jointed in at the top end and a sufficient length of the vertical pipe jointed
to it so as to provide the required test head, or the top end may be plugged with a connection to a
hose ending in a funnel which could be raised or lowered till the required head is obtained and
Fixed suitably for observation.
Subsidence of the test water may be due to one or more of the following causes:
-
8/2/2019 PGPPM-23
23/34
Absorption by pipes and joints: Sweating of pipes or joints: Cleavage at joints or from defective pipes: Trapped air.
Allowance shall be made for (a) by adding water until absorption has ceased after which the test
proper should commence. Any leakage will be visible and the defective part of the work should be
cut out and made good. A slight amount of sweating which is uniform may be overlooked, but
excessive sweating from a particular pipe or joint shall be watched for and taken as indicating a
defect to be made good. This test will not be applicable to sanitary pipe work above ground level.
FOR CAST IRON PIPESCast iron sewers and drains shall be tested as for glazedware and
concrete pipes. The drain plug shall be suitably strutted to prevent their being forced out of the pipe
during the test.
TESTS FOR STRAIGHTNESS AND OBSTRUCTIONThe following tests shall be carried out
by inserting at the high end of the sewer or drain a smooth ball of a diameter 3mm less than the pipe
bore. In the absence of obstruction, such as yarn or mortar projecting through the joints, the ball
should roll down the invert of the pipe, and emerge at the lower end and by means of a mirror at
one end of the line and lamp at the other. If the pipeline is straight, the full circle of light may be
observed. If the pipeline is not straight, this will be apparent. The mirror will also indicate
obstruction in the barrel.
TEST RECORDSComplete records shall be kept of all tests carried out on sewers and drains
both during construction and after being put into service.
-
8/2/2019 PGPPM-23
24/34
CHECKLISTS.
Following checklists shall be prepared based on the project progress and the requirements. As the
project progresses the following list shall be revised as and when required by the project team in
concept with the project manager concept (Specimen checklist attached).
CIVIL WORKS
Excavation, Back filling and Compaction (a) Shallow (b) Deep
Anti-termite treatment
Laying PCC in FoundationConcreting- For Foundation, Columns, Beams, Slabs, Lintels, Retaining walls
Pre-casting- Lintels and Curbs
Stone Cladding-
Water Proofing
Block work/Brick works
Stone Masonry
Internal / External Plastering
IPS Flooring
Rough in Sanitary works
Tiling and Dadoing
FINSIHES WORKS
Doors
Windows
Flooring
Ceiling- Gypsum, Modular
Furniture
Painting
Plumbing Fixtures and Granite Counters
-
8/2/2019 PGPPM-23
25/34
EXTERNAL WORKS
Site Grading
Roads
Parking
Drains
Walkways and Pathways
Curbs
External Signage
ELECTRICAL
Race ways
Lighting inspection
Cable trays ( Installation Inspection)
Cable trays ( Material Inspection)
Earthing Pits
Junction Box ( Installation Inspection)
Junction Box (Material inspection)
Lighting (Material / Installation Inspection)
LT cables ( Installation Inspection)
LT cables ( Material Inspection)
MV/LT Panel (Installation Inspection)
MV/LT Panel (Material Inspection)
PDB/LDB Material Inspection
PDB/LDB Installation InspectionPoint Wiring ( Installation Inspection)
Sockets and Switches ( Material Inspection)
Transformer ( Installation Inspection)
Transformer ( Material Inspection)
AIR CONDITIONING
Material Inspection
-
8/2/2019 PGPPM-23
26/34
Installation Inspection
Commissioning
PLUMBING AND SANITARY
Equipment
Piping
Panels
Performance tests
FIRE DETECTION AND FIRE FIGHTING SYSTEM
Material Inspection
Installation inspection
Commissioning
GENERAL
Welding Inspection
Final Check and take Over
-
8/2/2019 PGPPM-23
27/34
SAMPLE FORMATS
CHECKLIST FOR CONCRETING
LOCATION:
AM
PM
Sl.
No
Description Date Sign Remarks
FORM WORK :
1. Form work drawing checked
for size and details including
services.
Alignment
Plumb & Level
Condition of form work
surface
Props and Bracings
Release agent / shuttering oil
2. REINFORCEMENT :
Bar Bending Schedule
approved
Check for location of service
conduits
Extra reinforcement around
openings inserts
Reinforcement check against
BBS
Ref Drawing No
Anchorages and lap length
-
8/2/2019 PGPPM-23
28/34
Cover block in place
Links, stirrups, spacers
Rebars clean
Starter bars for column3. CONCRETE :
Availability of
materials/Equipments
Mix
No. of cubes/Slump taken
Kickers
CuringVisual inspection after
deshuttering
4. SAFETY
PPE
Access
Housekeeping
Walk way provided
-
8/2/2019 PGPPM-23
29/34
CHECKLIST FOR CEMENT
MATERIAL:CEMENT
AM
PM
Sl.
No.
Description Date Signature Remarks
1Make of Cement
2. Date of Manufacture
3. Date of receipt on site
4. Storage
5. Test certificate
6. Check Grade 43/53
7. Certificate from external
agency
8. Fineness
9. Initial setting time
10. Final setting time
11. Compressive strength
12. Soundness
13. Specific gravity
14. Any further checks
-
8/2/2019 PGPPM-23
30/34
CHECKLIST FOR FIXING ALUMINIUM DOORS
Location:
Sl.
No.
Description Date Signature Remarks
1 Is approved method statement
available?
2 Is sample approved?
3 Check for grouting of vertical
members of the door frames into the
floor.
4 Check for plumb for the door frames
with reference to masonry opening.
5 Check for fastening of door frames to
walls by screws?
6 Check for the provision and proper
functioning of the following:
a. Joints cleatsb. Pivotsc. Door closersd. Floor springse. Boltsf. Locksg. Weather strippingh.
Glazing beads
i. EPDM rubber gasketsj. Others
7 Final check for paint, surface finish,
glazing.
8 Check for overall satisfactory
functioning of aluminium door.
9 Check for protection of frame / glass10 Check for sealing of gaps
-
8/2/2019 PGPPM-23
31/34
CHECKLIST FOR PLASTIC EMULSION PAINT
Location:
Sl.
No.
Description Date Signature Remarks
1 Is method statement approved?
2 Surface to be painted is clean
and free from dead mortar, dirt,
dust, grease etc.
3 Application of mist coat (Putty)
4 Check for suitability, stability
and safety of scaffolding.
5 Check for mixing of paint with
water. Is it as per
manufacturers specification?
6 Check for proper covering of
floor surface protection to other
finishes.
7 Check for number of coats and
thickness.
8 Check for surface finish and
shade of paint as per approval.
-
8/2/2019 PGPPM-23
32/34
CHECKLIST FOR PLUMBING WORK
Location:
Sl.
No.
Description Date Signature Remarks
1 Check for completion of chasing
2 Check for alignment, level of
pipeline
3 Check for fixing and clamping
arrangement
4 Check for leakage test
-
8/2/2019 PGPPM-23
33/34
CHECKLIST FOR FIRE FIGHTING SYSTEMCOMMISSIONING
LOCATION:
Sl.
No.
Description Date Signature Remarks
1 Equipment and location
2 Drawing no./Rev.
3 Equipment as per spec/Drg.
4 Pipes & fittings as per spec.
5 Proper sizes used.
6 Welding joints proper
7 Bolted /threaded joints proper
8 Depth of laying of U/G pipe
9 Concrete pedestal provided
10 Insulation provided
11 Hydro test done
12 Holiday test done
13 Openings in wall closed
14 Posts height as per drg.
15 Hose box height as per drg.
16 Commissioning test report
available
17 Commissioning test report
available18 Proper colour code used
19 Pipe line flushed & cleaned
11 Safety:
1PPE
2 Access
3 Barricade / Hazard tape
-
8/2/2019 PGPPM-23
34/34
Organizational structure for flow of command for quality control
Quality Assurance Organization Unit at Site
Conclusions:
Quality cannot exist in isolation. It is apparent from the above that the concept of
quality should be the over all determinant in any construction process as opposed to
being a mere system of post construction checks and balances or error rectification.
Quality is best maintained if it is incorporated from the inception stages itself.