physical material prerequisite programs in small and very small plants dennis burson extension meat...
TRANSCRIPT
![Page 1: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/1.jpg)
Physical Material Prerequisite Programs in Small and Very Small Plants
Dennis BursonExtension Meat Specialist
University of NebraskaLincoln, NE 68583-0908
![Page 2: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/2.jpg)
ISO 9000
HACCP
GMP SOPs
![Page 3: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/3.jpg)
Prerequisite Programs Prerequisite programs will
influence the likelihood that a food safety hazard will occur.
The Hazard Analysis should consider the occurrence and severity of the hazard.
![Page 4: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/4.jpg)
Small and Very Small Plants are Unique Small number of employees.
Observation of equipment and product Close relationship with management/owners
Few pieces of equipment used in production
Close to consumer (friends or neighbors)
May depend more on prerequisite programs
![Page 5: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/5.jpg)
Examples of Prerequisite Programs
Slaughter Fabrication Processing
![Page 6: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/6.jpg)
Slaughter Concern
BB’s or Buckshot in cow and bull slaughter A multi step system of identification
Visual observation on the slaughter floor Visual observation on the fabrication floor Metal detection of lean trimmings after
fabrication.
![Page 7: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/7.jpg)
Detection on the Slaughter Floor
Plant rewards the employee for discovery of BB’s
Plant maintains records of employee findings
Early detection would also help to identify supplier.
![Page 8: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/8.jpg)
Cow and Bull Metal Detection of Lean Trimmings
Provides a second check in the system
Detection of metal that cannot be seen by workers
Less able to connect to the supplier Limited to the accuracy of the
detector
![Page 9: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/9.jpg)
Informing Suppliers Plant has assisted with Beef Quality
Assurance meetings. Producers supported other educational
meetings about Physical Contamination in Cows and Bulls.
Some plants have required producers to be trained in Quality Assurance.
These actions can reduce the occurrence of Physical Contamination.
![Page 10: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/10.jpg)
Fabrication Knife Inventory Control Equipment Monitoring
![Page 11: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/11.jpg)
Knife Inventory Processor has a knife
check out and check in for all employees.
While this is effective at keeping knives out of product, this program does not provides improvement over time.
![Page 12: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/12.jpg)
Equipment Monitoring Plant had history
of equipment breakdown.
Plant established a SOP for checking equipment.
![Page 13: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/13.jpg)
Pre-operational SOP Needle tenderizer and mechanical
tenderizer will be inspected prior to the start of production by Operational Manager. Inspection will focus on the intactness of the needles or blades. Inspection will be recorded on the SOP Tenderizing Equipment Log.
![Page 14: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/14.jpg)
Operational SOP Needle tenderizer and mechanical
tenderizer will be inspected twice daily (morning and afternoon) during production by the Operations Manager. Inspection will focus on the intactness of the needles or blades. Inspection will be recorded on the SOP Equipment Inspection Log.
![Page 15: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/15.jpg)
SOP Tenderization Equipment Inspection LogDate Time Pre-
Op.Op. Equipment Accep
t/ Reject
Inspector
![Page 16: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/16.jpg)
Increased SOP Inspection
Records will establish the dependability or faults of the equipment being used.
The data collected in the records will allow the plant to make better decisions on monitoring frequency.
![Page 17: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/17.jpg)
Very Small Processor Plant operator set up
ham pumping and instructed employee to pump hams.
After pumping a tip of one needle was missing
Owner took the hams to local medical facility to x-ray each ham
![Page 18: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/18.jpg)
Very Small Processor No records were being kept on
equipment, however, the plant operator was able to detect a problem.
Plant operator was truly concerned about his customers.
![Page 19: Physical Material Prerequisite Programs in Small and Very Small Plants Dennis Burson Extension Meat Specialist University of Nebraska Lincoln, NE 68583-0908](https://reader035.vdocument.in/reader035/viewer/2022081516/56649dc75503460f94abc531/html5/thumbnails/19.jpg)
Summary Prerequisite programs can work to
reduce physical contamination by utilizing many approaches.
Some prerequisite programs must be ongoing.
Increased inspection may provide additional information.
Very Small Processors know their equipment and are concerned about customers.