PROJECT ACHIEVEMENTS Engaged to MMJV Infrastructure Projects Team (MMJV RED Department), these are some of the projects under my supervision to completion; Education – 2Storey Double Classroom Project Year 2013 / Project: 1x 2Storey Double Classroom Project / Location: Zindaga Village, Mumeng LLG – Wafi-Golpu Project Site/ Project Cost K319,888.00/ Engaged Contractor: Beteka Building & Engineering Contractors Community Infrastructure - Community Hall Building Project Year 2013 / Project: 1x Community Hall Project / Location: Finschiff Village, Wampar LLG – Wafi- Golpu Project Site/ Project Cost at K305,000.00/ Engaged Contractor: PNG Forest Project Team Health Infrastructure Community Health Centre Building Project Year 2013 / Project: 1x Community Health Centre Project / Location: Zindaga Village, Mumeng LLG – Wafi-Golpu Project Site/ Project Cost at PGK120,000.00/

Upload: gedion-roroa

Post on 13-Apr-2017

84 views

Category:

Documents


3 download

TRANSCRIPT

PROJECT ACHIEVEMENTS Engaged to MMJV Infrastructure Projects Team (MMJV RED Department), these are some of the projects under my supervision to completion;

Education – 2Storey Double Classroom Project Year 2013 / Project: 1x 2Storey Double Classroom Project / Location: Zindaga Village, Mumeng LLG – Wafi-Golpu Project Site/ Project Cost K319,888.00/ Engaged Contractor: Beteka Building & Engineering Contractors

Community Infrastructure - Community Hall Building Project Year 2013 / Project: 1x Community Hall Project / Location: Finschiff Village, Wampar LLG – Wafi-Golpu Project Site/ Project Cost at K305,000.00/ Engaged Contractor: PNG Forest Project Team

Health Infrastructure – Community Health Centre Building Project Year 2013 / Project: 1x Community Health Centre Project / Location: Zindaga Village, Mumeng LLG – Wafi-Golpu Project Site/ Project Cost at PGK120,000.00/

Engaged Contractor: Boheta Limited Education

Infrastructure –

Elementary Classroom.

Note; The project is located in a remote village that only chopper is used for all deliveries. Year 2013 / Project: 1x Elementary Classroom Project / Location: Zilani Village, Golpu Project Site/ Project Cost at PGK107,000.00/ Engaged Contractor: Boheta Limited (I’m standing in white sun-hat, with the engaged contractor team)

Health Infrastructure

– Aid Post.

Note; The project is yet to be used by the villagers.

Year 2013 / Project: 1x Aid Post + H-Set Staff House Project / Location: Bavaga Village, Mumeng LLG – Wafi-Golpu Project Site/ Project Cost at PGK130,000.00/ Engaged Contractor: Beteka Engineering & Construction Ltd