PIONEER HIGH SCHOOL WEST STADIUM PHASE 1

Upload: kelley-davidson

Post on 23-Dec-2015

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

PIONEER HIGH SCHOOL WEST STADIUM

PHASE 1

Page 2: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

EXECUTIVE SUMMARYErickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract with a GMP of $9,893,520 in early June 2013. In mid June a Preliminary Notice to Proceed was issued; followed by a process in which the GMP contract was subjected to a public comment period as part of a contract validation process that ended late July. A Final Notice to Proceed was then issued mid July, with Abatement, Demolition, Removal and Earthwork Operations commencing early August .

Page 3: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

The Phase 1 project documents have been reviewed and approved by DSA and the Designer/Builder team is working together to create a final set for Construction that will include Constructability Review, Value Engineering, Scope Reductions, DSA Comments and the previously issued Addendum One.

Page 4: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

The procurement process (Subcontracts – Submittals – Fabrication – Delivery) continues with a focus on the Visitor Bleacher Deferred Approval Submittals currently at DSA under review. Field operations include Demolition, Removals and Grading. Cost controls are in place to mitigate the use of Contingencies and avoid surprises as much as possible. Our Quality Control program is gradually being implemented as we transition from demolition to construction. Safety, Security, SWPPP, Dust Control, and Housekeeping continue to be of high priority.

Page 5: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

CONSTRUCTION PROGRESSStart Date – July 22, 2013 Substantial Completion Date – June 3, 2014

Initial Survey and SWPPP measures are in place. Although some areas of demolition and removal were impacted by Value Engineering and Scope Reduction discussions, overall Abatement, Demolition, Removal and Earthwork Operations continue at this time. EHCC has been working to coordinate ongoing field operations with design changes in a fast track manner.

Page 6: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

As of this report, Abatement of stucco at home bleachers is complete; Demolition of fence & fabric, North four (4) tennis courts, interior fencing, backstops, fence around tracks, bleachers, trees along Slauson Avenue, and light poles are complete. Removal of debris offsite around identified work areas is ongoing. Earthwork and grading in baseball and football fields are ongoing.

Page 7: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Installation of control point and benchmark elevations, staking of walls at Millergrove and contour ball fields are also complete. New 6” POC irrigation complete. Finish grading at ball fields & over-excavation of wall at Millergrove are ongoing. Overall site housekeeping and safety procedures are practiced on a daily basis.

Page 8: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Upcoming new activities for next month include:

Fine GradingBleacher/Building Pad Over &

recompactionConcrete FoundationsMasonry Retaining Walls &

waterproofingFencingUnderground UtilitiesUnderground Electrical & Irrigation

Sleeves

Page 9: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Efforts from the Subcontractors, Architects, Engineers, the District, Inspectors and Erickson Hall have resulted in mitigation of the schedule impacts incurred to date. Challenges have included the Bid/Budget Approval Process, Document Revisions to accommodate VE and Scope Reduction changes, Clarifications (RFIs) and DSA review time and comments.

Page 10: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Demolition of Fence & Fabric, Tennis Courts

Page 11: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Demolition of Fence & Fabric, Tennis Courts

Page 12: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Demolition of Fence & Fabric, Tennis Courts

Page 13: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Falling Trees & Haul-off along Slauson Avenue

Page 14: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Falling Trees & Haul-off along Slauson Avenue

Page 15: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Falling Trees & Haul-off along Slauson Avenue

Page 16: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Abatement of Stucco

Page 17: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

New 6” POC Irrigation

Page 18: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Grading & Earthwork – Clearing & Grubbing of Ball Fields

Page 19: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Grading & Earthwork – Clearing & Grubbing of Ball Fields

Page 20: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Grading & Dust Control

Page 21: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Demolition of Bleachers

Page 22: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Demolition of Bleachers

Page 23: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Removal & Haul-off of Debris

Page 24: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Staking Contours

Page 25: PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract

Demolition of Light Poles