pipeline costs
TRANSCRIPT
-
8/12/2019 Pipeline Costs
1/19
TECHNICAL MEMORANDUM
To: Ed Filadelfia Date: May 13, 2013From: Paul Tinhpheng
John CiccotelliReference: 1343122/06-7
Through: Ernest Marquez CoR Contract: 0801922c.c: Gary Valladao Document No. TM-016 DRAFTSubject: Hidden Valley-Hole Lake Improvements FEMA Application Project
Alternatives
INTRODUCTION
This memorandum evaluates alternatives to provide recycle water to the Hidden ValleyWetlands and Hole Lake, while considering options to also divert stormwater passingthrough the Hole Lake watercourse to the Hidden Valley Wetlands. The blendedrecycled water (and optional stormwater flow) will provide a permanent supply to theHidden Valley Wetlands. The alternatives consider adding recycle water to the HoleLake Wash to greatly improve water quality in the lower reaches of the wash andenhance habitat areas for the Santa Ana sucker.
2010 STORM EVENT
In 2010, a large storm destroyed a natural channel that conveyed a portion of finaleffluent from the Regional Water Quality Control Plant (RWQCP) and stormwater fromthe Hole Lake Wash to the Hidden Valley Wetlands. This project proposes to reinstatea conveyance method that cannot be destroyed in future flooding events.
The RWQCP and the adjacent Hole Lake wash are currently discharging into the SantaAna River. The flow from Hole Lake now reaches the river through an estuary area thatwas once isolated from the river by the natural channel. The RWQCP had beentraditionally diverting effluent through the wetlands for additional nitrogen removal. Alleffluent from the plant now enters the Santa Ana River.
PROJECT ALTERNATIVES
MWH developed eight project alternatives for conveying recycled water from theRWQCP to Hole Lake Wash and Hidden Valley Wetlands. The piping alignment andnew recycled water pump station location are shown in Figures 1 through 3.
The alternatives are based on different recycled water flows (2 and 10 mgd), pipingsystems (pressurized or gravity fed), and blending options (blending with Hole LakeWash stormwater or no blending). The 10 mgd flow is similar to the flow that waspreviously entering the wetlands. The 2 mgd flow is a preliminary value that is expectedto provide partial restoration of the wetlands.
-
8/12/2019 Pipeline Costs
2/19
-
8/12/2019 Pipeline Costs
3/19
Date: May 03, 2013
Existing Junction BoxNo. 16
Connection to CCB 3Discharge
Final Effluent PumpStation Discharge Final Effluent Pump
Station
-
8/12/2019 Pipeline Costs
4/19
-
8/12/2019 Pipeline Costs
5/19
FEMA Application Support - Project Alternatives May 13, 2013
TM-016_Hidden Valley-Hole Lake Project Alternatives_20130513 2
MWH studied the alignment of the old hydro-power conveyance channel as a possiblelocation for a gravity or force main. The conveyance channel is severely deteriorated foraround 25 % of its length and substantially deteriorated for around 50% of its length. Insome areas, retaining walls will need to be constructed to provide lateral soil support.Furthermore, the channel is mostly located on a steep embankment and large pipelineswill demand geotechnical investigation to guarantee stability. Lastly, the general terrainis not suited for construction. For these reasons, MWH has abandoned the use of theold hydro-power conveyance channel as a possible pipe alignment.
Parts of the old hydro-power conveyancechannel that remain intact
Deteriorated section of old hydro-powerconveyance channel
Table 1 provides a summary of the project alternatives.
Table 1Project Alternatives
Alternative Blending Option Recycled Water Flow Piping System Total Cost1
No Blending
10 MGD Pressurized $11,300,000
2 2 MGD Pressurized $8,700,0003 2 MGD Gravity Fed $8,900,0004 10 MGD Gravity Fed N/A5
Blending
10 MGD Pressurized $12,900,0006 2 MGD Pressurized $9,200,0007 2 MGD Gravity Fed $9,500,0008 10 MGD Gravity Fed N/A
-
8/12/2019 Pipeline Costs
6/19
FEMA Application Support - Project Alternatives May 13, 2013
TM-016_Hidden Valley-Hole Lake Project Alternatives_20130513 3
ALTERNATIVES 1 - 4
For Alternatives 1 through 4, recycled water blending with stormwater from the HoleLake Wash is not provided. Recycled water is conveyed directly to the Hidden ValleyWetlands with a bleed-off of 2 cfs of recycled water to the Hole Lake Wash.
For these alternatives, it is assumed that the Hole Lake Wash discharge is provideddownstream of the Jurupa Avenue culvert. Alternative 4, which is designed for a 10 mgdgravity fed system, is considered not feasible given that a 62-inch gravity pipe isrequired. A pipe of this size is not considered constructible along the horse trailalignment and a cost estimate is not provided.
The City may seek Santa Ana sucker habitat creation credit with these alternatives.
ALTERNATIVES 5 - 8
For Alternatives 5 through 8, recycled water blending with Hole Lake Wash stormwateris provided.
For these alternatives, it is assumed that the Hole Lake Wash discharge is providedupstream of the Jurupa Avenue culvert where an existing holding pond providesretention time for blending of the recycled water and stormwater. To convey recycledwater upstream of the culvert, a jack-and-bore crossing will be required across JurupaAvenue. Half of the average dry-weather stormwater flow (2 cfs) will be diverted forblending and conveyance to the Hidden Valley Wetlands. An equal amount of recycledwater flow will be bled-off for discharge to the Hole Lake Wash holding pond. Thesealternatives will allow the City to seek Santa Ana sucker habitat creation credit andstormwater treatment credit.
For Alternatives 5 and 6, a pump station at the Hole Lake Wash will convey divertedstormwater to the pressurized pipeline from the RWQCP to the Hidden Valley Wetlands.
For Alternatives 7 and 8, a distribution box will collect diverted stormwater and recycledwater. Blended flow will convey by gravity to the Hidden Valley Wetlands. Alternative 8,which is designed for a 10 mgd gravity fed system, is considered not feasible given thata 70-inch gravity pipe is required. A pipe of this size is not considered constructiblealong the horse trail alignment and a cost estimate is not provided.
A schematic of Alternatives 1 through 4 is provided as Figure 4 and a schematic ofAlternatives 5 through 7 is provided as Figure 5. Details for each project alternative areprovided below.
COST ESTIMATES
Cost estimates are provided for Alternatives 1 through 3 and 5 through 7 based on anAACE International Class 4 Cost Estimate. Details are attachment to this technicalmemorandum. The construction cost estimates also include the rehabilitation work atthe Hidden Valley Wetlands, as previously scoped by the City.
-
8/12/2019 Pipeline Costs
7/19
New Recycled Water Pump
Station
Hole Lake
Hidden Valley W
Hole Lake Wash
Jurupa AveCulvert
Alternative 3Diversion Structure
Figure 4Alternatives 1, 2, & 3
No Stormwater Blending
Recycled Water Only
Recycled Water
Holding Pond
-
8/12/2019 Pipeline Costs
8/19
New Recycled Water Pump
Station
HoLak
Hidden Valley
Alternatives 4 & 5 Pump Station
Hole Lake Wash
Jurupa AveCulvert
Figure 5Alternatives 4, 5, & 6Stormwater Blending
Blended Stormwater &
Recycled Water
Recycled Water
Holding Pond
Alternative 6Diversion Structure
-
8/12/2019 Pipeline Costs
9/19
FEMA Application Support - Project Alternatives May 13, 2013
TM-016_Hidden Valley-Hole Lake Project Alternatives_20130513 4
ALTERNATIVES DESCRIPTION
Alternative 1
Flow to Hidden Valley Wetlands = 10 mgdFlow to Hole Lake Wash = 1.3 mgd (2 cfs)Total Flow = 11.3 mgd
Pipe System to Hidden Valley Wetlands = PressurizedBlending with Hole Lake Wash stormwater = No
Construction Cost = $ 8,700,000Design & Bid Services Cost (15%) = $ 1,300,000City Engineering & Operating Cost (15%) = $ 1,300,000Total Cost = $11,300,000
Project Description: 11 MGD vertical turbine pump station (3 pumps) at the WQCP
o TDH = 80 fto Power = 200 HP
26-inch pressurized pipeline from pump station to Hole Lake Washo 2,000 ft lengtho CML steel pipeo Throttling valve at Hole Lake Washo 5 ft depth
12-inch blowoff and flow meter at Hole Lake Wash 24-inch pressurized pipeline from Hole Lake Wash to Hidden Valley Wetlands
o 7,500 ft lengtho CML steel pipeo 5 ft depth
Alternative 2
Flow to Hidden Valley Wetlands = 2 mgdFlow to Hole Lake Wash = 1.3 mgd (2 cfs)Total Flow = 3.3 mgd
Pipe System to Hidden Valley Wetlands = PressurizedBlending with Hole Lake Wash stormwater = No
Construction Cost = $6,700,000Design & Bid Services Cost (15%) = $1,000,000City Engineering & Operating Cost (15%) = $1,000,000Total Cost = $8,700,000
Project Description: 3 MGD vertical turbine pump station (3 pumps) at the WQCP
o TDH = 95 ft
-
8/12/2019 Pipeline Costs
10/19
FEMA Application Support - Project Alternatives May 13, 2013
TM-016_Hidden Valley-Hole Lake Project Alternatives_20130513 5
o Power = 60 HP 14-inch pressurized pipeline from pump station to Hole Lake Wash
o 2,000 ft lengtho CML steel pipeo Throttling valve at Hole Lake Washo 5 ft depth
12-inch blowoff and flow meter at Hole Lake Wash 14-inch pressurized pipeline from Hole Lake Wash to Hidden Valley Wetlands
o 7,500 ft lengtho CML steel pipeo 5 ft depth
Alternative 3
Flow to Hidden Valley Wetlands = 2 mgdFlow to Hole Lake Wash = 1.3 mgd (2 cfs)Total Flow = 3.3 mgd
Pipe System to Hidden Valley Wetlands = Gravity fedBlending with Hole Lake Wash stormwater = No
Construction Cost = $6,900,000Design & Bid Services Cost (15%) = $1,000,000City Engineering & Operating Cost (15%) = $1,000,000Total Cost = $8,900,000
Project Description: 3 MGD vertical turbine pump station (3 pumps) at the WQCP
o TDH = 59 fto Power = 40 HP
14-inch pressurized pipeline from pump station to Hole Lake Washo 2,000 ft lengtho CML steel pipeo 5 ft depth
12-inch blowoff and flow meter at Hole Lake Wash 20-inch gravity pipeline from Hole Lake Wash to Hidden Valley Wetlands
o 7,500 ft lengtho PVC pipeo 5 ft depth
Alternative 4 (considered not feasible)
Flow to Hidden Valley Wetlands = 10 mgdFlow to Hole Lake Wash = 1.3 mgd (2 cfs)Total Flow = 11.3 mgd
Pipe System to Hidden Valley Wetlands = Gravity fedBlending with Hole Lake Wash stormwater = No
-
8/12/2019 Pipeline Costs
11/19
FEMA Application Support - Project Alternatives May 13, 2013
TM-016_Hidden Valley-Hole Lake Project Alternatives_20130513 6
Project Description: 11 MGD vertical turbine pump station (3 pumps) at the WQCP
o TDH = 56 fto 140 HP
26-inch pressurized pipeline from pump station to Hole Lake Washo 2,000 ft lengtho CML steel pipeo 5 ft depth
12-inch blowoff and flow meter at Hole Lake Wash 62-inch gravity pipeline from Hole Lake Wash to Hidden Valley Wetlands
o 7,500 ft lengtho RCP pipeo 5 ft depth
Alternative 5
Flow to Hidden Valley Wetlands = 10 mgdFlow to Hole Lake Wash = 1.3 mgd (2 cfs)Total Flow = 11.3 mgd
Pipe System to Hidden Valley Wetlands = PressurizedBlending with Hole Lake Wash stormwater = Yes
Construction Cost = $ 9,900,000Design & Bid Services Cost (15%) = $ 1,500,000City Engineering & Operating Cost (15%) = $ 1,500,000Total Cost = $12,900,000
Project Description: 11 MGD vertical turbine pump station (3 pumps) at the WQCP
o TDH = 88 fto Power = 250 HP
24-inch pressurized pipeline from pump station to Hole Lake Washo 2,000 ft lengtho CML steel pipeo Throttling valve at Hole Lake Washo 5 ft depth
12-inch blowoff and flow meter at Hole Lake Wash 1.3 MGD submersible pump station (3 pumps) at Hole Lake Wash
o TDH = 11 fto Power = 3 HP
26-inch pressurized pipeline from Hole Lake Wash to Hidden Valley Wetlandso 7,500 ft lengtho CML steel pipeo 5 ft depth
-
8/12/2019 Pipeline Costs
12/19
FEMA Application Support - Project Alternatives May 13, 2013
TM-016_Hidden Valley-Hole Lake Project Alternatives_20130513 7
Alternative 6
Flow to Hidden Valley Wetlands = 2 mgdFlow to Hole Lake Wash = 1.3 mgd (2 cfs)Total Flow = 3.3 mgd
Pipe System to Hidden Valley Wetlands = PressurizedBlending with Hole Lake Wash stormwater = Yes
Construction Cost = $7,000,000Design & Bid Services Cost (15%) = $1,100,000City Engineering & Operating Cost (15%) = $1,100,000Total Cost = $9,200,000
Project Description: 3 MGD vertical turbine pump station (3 pumps) at the WQCP
o TDH = 108 fto Power = 90 HP
12-inch pressurized pipeline from pump station to Hole Lake Washo 2,000 ft lengtho CML steel pipeo Throttling valve at Hole Lake Washo 5 ft depth
12-inch blowoff and flow meter at Hole Lake Wash 1.3 MGD submersible pump station (3 pumps) at Hole Lake Wash
o TDH = 11 fto Power = 3 HP
14-inch pressurized pipeline from Hole Lake Wash to Hidden Valley Wetlandso 7,500 ft lengtho CML steel pipeo 5 ft depth
Alternative 7
Flow to Hidden Valley Wetlands = 2 mgdFlow to Hole Lake Wash = 1.3 mgd (2 cfs)Total Flow = 3.3 mgd
Pipe System to Hidden Valley Wetlands = Gravity fedBlending with Hole Lake Wash stormwater = Yes
Construction Cost = $7,300,000Design & Bid Services Cost (15%) = $1,100,000City Engineering & Operating Cost (15%) = $1,100,000Total Cost = $9,500,000
Project Description: 3 MGD vertical turbine pump station (3 pumps) at the WQCP
-
8/12/2019 Pipeline Costs
13/19
FEMA Application Support - Project Alternatives May 13, 2013
TM-016_Hidden Valley-Hole Lake Project Alternatives_20130513 8
o TDH = 63 fto Power = 50 HP
14-inch pressurized pipeline from pump station to Hole Lake Washo 2,000 ft lengtho CML steel pipeo 5 ft depth
12-inch blowoff and flow meter at Hole Lake Wash Distribution box at Hole Lake Wash 28-inch gravity pipeline from Hole Lake Wash to Hidden Valley Wetlands
o 7,500 ft lengtho PVC pipeo 5 ft depth
Alternative 8 (considered not feasible)
Flow to Hidden Valley Wetlands = 10 mgdFlow to Hole Lake Wash = 1.3 mgd (2 cfs)Total Flow = 11.3 mgd
Pipe System to Hidden Valley Wetlands = Gravity fedBlending with Hole Lake Wash stormwater = Yes
Project Description: 11 MGD vertical turbine pump station (3 pumps) at the WQCP
o TDH = 56 fto 150 HP
26-inch pressurized pipeline from pump station to Hole Lake Washo 2,000 ft lengtho CML steel pipeo 5 ft depth
12-inch blowoff and flow meter at Hole Lake Wash 70-inch gravity pipeline from Hole Lake Wash to Hidden Valley Wetlands
o 7,500 ft lengtho RCP pipeo 5 ft depth
-
8/12/2019 Pipeline Costs
14/19
MWH JLLWalnut Creek 5/3/2013
City of RiversideFEMA Proposal Support
Hidden Valley Water Conveyance ProjectAlternative #1
Grand Total Price: 8,700,000$Item
# Description Quantity UOM Unit Price Total Price Comments
A. Conveyance to Hidden Valley Wetlands $6,413,7631 11 MDG Vertical Turbine Pump Station 1 lot $ 2, 500 ,0 00 $ 2, 50 0, 00 0 TDP = 80, PS cost curve < 10 MGD, 3 pumps, 200 hp2 26" C200 CML Pressurized Pipeline, 5' cover 2,000 lf $310 $620,000 from PS to Hole Lake. Mostly paved areas3 Jack & Bore at Van Buren Avenue 175 lf $738 $129,063 includes pits4 26" Throttling Valve at Hole Lake Wash 1 ea $31,200 $31,2005 12" Blow off 1 ea $3,000 $3,0006 12" Flowmeter 1 ea $15,000 $15,0007 24" C200 CML Pressurized Pipeline, 5' cover 7,500 lf $310 $2,325,000 at horse trail8 Pipel ine Testing/Commissioning 9,500 lf $5 $47,5009 Piping Tieins/Connects 2 ea $20,000 $40,000
10 Horse Trail Replacement 7,500 lf $10 $75,00011 Pavement Replacement 12,000 sf $4.00 $48,000 at 6' wide for 2000'12 Contractor Mobilization/General Conditions 1 ls 10% $580,000
B. Hidden Valley Wetlands Mitigation $834,0001 Clear ing & Grubbing Channel 3,000 lf $25 $75,000 remove sediments/debris2 36" Dia RCP 1,200 lf $360 $432,000 replace/reroute influent pipe3 Trench Shoring 1,200 lf $10 $12,000 for 36" RCP placement4 Manhole 3 ea $15,000 $45,000 access manholes spaced at 400'5 Pond Influent Piping 1 ls $50,000 $50,000 small dia RCP & PVC distribution piping to ponds6 Distribution Pipe Flush 1 ls $20,000 $20,000 remove impacted silt from remaining influent piping7 Inf luen t Pond Sediment Removal 5,000 cys $20 $100,000 remove sediments from silted in influent pond8 Permitting 1 ls $50,000 $50,000 USACE, DF&G, DF&WS9 Contractor Mobilization/General Conditions 1 ls $50,000 $50,000
Running Subtotal: $7,247,800
Project Administration & Management $1,450,0001 Construction Oversight & Mgt 1 ls 0% $0 Excluded2 Engineering 1 ls 0% $0 3 Geotechnical 1 ls 0% $0 4 Engineering During Construction 1 ls 0% $0 5 Misc Owner's Soft Costs (All) 1 ls 0% $0 Excluded6 Land Acquisition 1 ls 0% $0 ditto
7 Scope Contingency/Market Conditions 1 ls 20% $1,450,000 Scope definition/market allowance/estimating8 Interest During Construction 1 ls 0% $0 Excluded, allowance for financing costs9 Owner's Construction Contingency/Mgt Reserve 1 ls 0% $0 Excluded, allowance for changed field conditions
Grand Total: $8,700,000 Total Estimated Constr Costs w/ Contingency
Cost Range: $5,800,000 $9,400,000 Per AACE cost estimate guidelines
Assumptions:
1) Nonstandard environmental mitigations excluded.2)
Notes
1) This OPCC is classified as a Class 4 cost estimate per AACE guidelines. Stated accuracy range = 20% to + 30%2) Pricing basis = 2nd Qtr 2013, escalation to midpoint of construction is excluded.3) Pricing assumes competitive market conditions at time of tender (+3 bidders/trade).4) Owner soft costs and project management expenses excluded.5) Special Inspections not included.
OPCC Disclaimer
Opinion of Probable Construction CostsCurrency: USD-United States-MAY 2013 Dollar
The client hereby acknowledges that MWH has no control over the costs of labor, materials, competitive bidding environments, unidentified field conditions, financial and/or commodity market conditions, or any other factors likely to affect theOPCC of this project, all of which are and will unavoidably remain in a state of change, especially in light of high market volatility attributable to Acts of God and other market forces or events beyond the control of the parties. As such, Clientrecognizes that this OPCC deliverable is based on normal market conditions, defined by stable resource supply/demand relationships, and does not account for extreme inflationary or deflationary market cycles. Client further acknowledges thatthis OPCC is a "snapshot in time" and that the reliability of this OPCC will degrade over time. Client agrees that MWH cannot and does not make any warranty, promise, guarantee or representation, either express or implied that proposals, bids,project construction costs, or cost of O&M functions will not vary significantly from MWH's good faith Class 2 OPCC
AACE In tern atio nal CL ASS 4 Cos t Esti mate - Class 4 estimates are generally prepared based on limited information and subsequently have fairly wide accuracy ranges. Typically, engineering is 10% to 40% complete. They are typically usedfor project screening, determination of feasibility, concept evaluation, and preliminary budget approval. Virtually all Class 4 estimates use stochastic estimating methods such as cost curves, capacity factors, and other parametric and modelingtechniques. Expected accuracy ranges are from -15% to -30% on the low side and +20% to 50% on the high side, depending on the technological complexity of the project, appropriate reference information, and the inclusion of an appropriatecontingency determination. Ranges could exceed those shown in unusual circumstances. As little as 20 hours or less to perhaps more than 300 hours may be spent preparing the estimate depending on the project and estimating methodology(AACE International Recommended Practices and Standards).
Prepared by MWH Global, Inc. 5/3/2013 Page 1
-
8/12/2019 Pipeline Costs
15/19
-
8/12/2019 Pipeline Costs
16/19
MWH JLLWalnut Creek 5/3/2013
City of RiversideFEMA Proposal Support
Hidden Valley Water Conveyance ProjectAlternative #3
Grand Total Price: 6,860,000$Item
# Description Quantity UOM Unit Price Total Price Comments
A. Conveyance to Hidden Valley Wetlands $4,884,3631 3 MDG Vertical Turbine Pump Station 1 lot $ 1, 400 ,0 00 $ 1, 40 0, 00 0 TDP = 59, PS cost curve < 10 MGD, 40 hp2 14" C200 CML Pressurized Pipeline, 5' cover 2,000 lf $360 $720,000 from PS to Hole Lake. Mostly paved areas3 Jack & Bore at Van Buren Avenue 175 lf $738 $129,063 includes pits4 14" Throttling Valve at Hole Lake Wash 1 ea $16,800 $16,8005 12" Blow off 1 ea $3,000 $3,0006 12" Flowmeter 1 ea $15,000 $15,0007 20" C200 CML Pressurized Pipeline, 5' cover 7,500 lf $260 $1,950,000 at horse trail8 Pipel ine Testing/Commissioning 9,500 lf $5 $47,5009 Piping Tieins/Connects 2 ea $20,000 $40,000
10 Horse Trail Replacement 7,500 lf $10 $75,00011 Pavement Replacement 12,000 sf $4.00 $48,000 at 6' wide for 2000'12 Contractor Mobilization/General Conditions 1 ls 10% $440,000
B. Hidden Valley Wetlands Mitigation $834,0001 Clear ing & Grubbing Channel 3,000 lf $25 $75,000 remove sediments/debris2 36" Dia RCP 1,200 lf $360 $432,000 replace/reroute influent pipe3 Trench Shoring 1,200 lf $10 $12,000 for 36" RCP placement4 Manhole 3 ea $15,000 $45,000 access manholes spaced at 400'5 Pond Influent Piping 1 ls $50,000 $50,000 small dia RCP & PVC distribution piping to ponds6 Distribution Pipe Flush 1 ls $20,000 $20,000 remove impacted silt from remaining influent piping7 Inf luen t Pond Sediment Removal 5,000 cys $20 $100,000 remove sediments from silted in influent pond8 Permitting 1 ls $50,000 $50,000 USACE, DF&G, DF&WS9 Contractor Mobilization/General Conditions 1 ls $50,000 $50,000
Running Subtotal: $5,718,400
Project Administration & Management $1,144,0001 Construction Oversight & Mgt 1 ls 0% $0 Excluded2 Engineering 1 ls 0% $0 3 Geotechnical 1 ls 0% $0 4 Engineering During Construction 1 ls 0% $0 5 Misc Owner's Soft Costs (All) 1 ls 0% $0 Excluded6 Land Acquisition 1 ls 0% $0 ditto
7 Scope Contingency/Market Conditions 1 ls 20% $1,144,000 Scope definition/market allowance/estimating8 Interest During Construction 1 ls 0% $0 Excluded, allowance for financing costs9 Owner's Construction Contingency/Mgt Reserve 1 ls 0% $0 Excluded, allowance for changed field conditions
Grand Total: $6,860,000 Total Estimated Constr Costs w/ Contingency
Cost Range: $4,600,000 $7,400,000 Per AACE cost estimate guidelines
Assumptions:
1) Nonstandard environmental mitigations excluded.2)
Notes
1) This OPCC is classified as a Class 4 cost estimate per AACE guidelines. Stated accuracy range = 20% to + 30%2) Pricing basis = 2nd Qtr 2013, escalation to midpoint of construction is excluded.3) Pricing assumes competitive market conditions at time of tender (+3 bidders/trade).4) Owner soft costs and project management expenses excluded.5) Special Inspections not included.
OPCC Disclaimer
Opinion of Probable Construction CostsCurrency: USD-United States-MAY 2013 Dollar
The client hereby acknowledges that MWH has no control over the costs of labor, materials, competitive bidding environments, unidentified field conditions, financial and/or commodity market conditions, or any other factors likely to affect theOPCC of this project, all of which are and will unavoidably remain in a state of change, especially in light of high market volatility attributable to Acts of God and other market forces or events beyond the control of the parties. As such, Clientrecognizes that this OPCC deliverable is based on normal market conditions, defined by stable resource supply/demand relationships, and does not account for extreme inflationary or deflationary market cycles. Client further acknowledges thatthis OPCC is a "snapshot in time" and that the reliability of this OPCC will degrade over time. Client agrees that MWH cannot and does not make any warranty, promise, guarantee or representation, either express or implied that proposals, bids,project construction costs, or cost of O&M functions will not vary significantly from MWH's good faith Class 2 OPCC
AACE In tern atio nal CL ASS 4 Cos t Esti mate - Class 4 estimates are generally prepared based on limited information and subsequently have fairly wide accuracy ranges. Typically, engineering is 10% to 40% complete. They are typically usedfor project screening, determination of feasibility, concept evaluation, and preliminary budget approval. Virtually all Class 4 estimates use stochastic estimating methods such as cost curves, capacity factors, and other parametric and modelingtechniques. Expected accuracy ranges are from -15% to -30% on the low side and +20% to 50% on the high side, depending on the technological complexity of the project, appropriate reference information, and the inclusion of an appropriatecontingency determination. Ranges could exceed those shown in unusual circumstances. As little as 20 hours or less to perhaps more than 300 hours may be spent preparing the estimate depending on the project and estimating methodology(AACE International Recommended Practices and Standards).
Prepared by MWH Global, Inc. 5/3/2013 Page 1
-
8/12/2019 Pipeline Costs
17/19
MWH PTArcadia, CA 5/13/2013
City of RiversideFEMA Proposal Support
Hidden Valley Water Conveyance ProjectAlternative #5
Grand Total Price: 9,900,000$
Item # Description Quantity UOM Unit Price Total Price Comments
A. Conveyance to Hidden Valley Wetlands $7,109,3001 11 MGD Vertical Turbine Pump Station 1 lot $3,000,000 $3,000,000 TDP = 90, PS cost curve < 10 MGD, 3 pumps, 250 hp2 24" C200 CML Pressurized Pipeline, 5' cover 2,000 lf $310 $620,000 from PS to Hole Lake. Mostly paved areas3 Jack & Bore at Van Buren Avenue & Jurupa Avenue 350 lf $738 $258,300 includes pits4 26" Throttling Valve at Hole Lake Wash 1 ea $31,200 $31,2005 12" Blow Off 1 ea $3,000 $3,0006 12" Flowmeter 1 ea $15,000 $15,0007 26" C200 CML Pressurized Pipeline, 5' cover 7,500 lf $310 $2,325,000 at horse trail8 Pipeline Testing/Comissioning 9,500 lf $5 $47,5009 Piping Tieins/Connects 2 ea $20,000 $40,000
10 Horse Trail Replacement 7,500 lf $10 $75,00011 Pavement Replacement 12,000 sf $4 $48,000 at 6' wide for 2000'12 Contractor Mobilization/General Conditions 1 ls 10% $646,300
B. Hole Lake Wash Pump Station $315,000
1 1.5 MGD Vertical Turbine Pump Station 1 lot $300,000 $300,0002 10" C200 CML Pressurized Pipeline 100 lf $150 $15,000
C. Hidden Valley Wetlands Mitigation $834,0001 C le ar ing & Grubbing Channel 3,000 lf $25 $75,000 remove sediments/debris2 36" Dia RCP 1,200 lf $360 $432,000 replace/reroute influent pipe3 Trench Shoring 1,200 lf $10 $12,000 for 36" RCP placement4 Manhole 3 ea $15,000 $45,000 access manholes spaced at 400'5 Pond Influent Piping 1 ls $50,000 $50,000 small dia RCP & PVC distribution piping to ponds6 Distribution Pipe Flush 1 ls $20,000 $20,000 remove impacted silt from remaining influent piping7 Influent Pond Sediment Removal 5,000 cys $20 $100,000 remove sediments from silted in influent pond8 Permitting 1 ls $50,000 $50,000 USACE, DF&G, DF&WS9 Contractor Mobilization/General Conditions 1 ls $50,000 $50,000
Running Subtotal: $8,258,300
Project Administration & Management $1,651,6601 Construction Oversight & Mgt 1 ls 0% $0 Excluded2 Engineering 1 ls 0% $0 ditto3 Geotechnical 1 ls 0% $0 ditto4 Engineering During Construction 1 ls 0% $0 ditto5 Misc Owner's Soft Costs (All) 1 ls 0% $0 Excluded
6 Land Acquisition 1 ls 0% $0 ditto7 Scope Contingency/Market Conditions 1 ls 20% $1,651,660 Scope definition/market allowance/estimating8 I nt er es t During Construction (Financing) 1 ls 0% $0 Excluded, allowance for financing costs9 Owner's Construction Contingency/Mgt Reserve 1 ls 0% $0 Excluded, allowance for changed field conditions
Grand Total: $9,900,000 Total Estimated Constr Costs w/ Contingency
Cost Range: $6,600,000 $10,720,000 Per AACE cost estimate guidelines
Assumptions:1) Non standard environmental mitigations excluded.2)
Notes:
1) This OPCC is classified as a Class 4 cost estimate per AACE guidelines. Stated accuracy range = 20% to +30%2) Pricing basis = 2nd Qtr 2013, escalation to midpoint of construction is excluded.3) Pricing assumes competitive market conditions at time of tender (+3 bidders/trade).
4) Owner soft costs and project management expenses excluded
5) Special inspections not included
OPCC Disclaimer
The client hereby acknowledges that MWH has no control over the costs of labor, materials, competitive bidding environments, unidentified field conditions, financial and/or commodity market conditions, or any other factors likely to affect the OPCC of thisproject, all of which are and will unavoidably remain in a state of change, especially in light of high market volatility attributable to Acts of God and other market forces or events beyond the control of the parties. As such, Client recognizes that this OPCCdeliverable is based on normal market conditions, defined by stable resource supply/demand relationships, and does not account for extreme inflationary or deflationary market cycles. Client further acknowledges that this OPCC is a "snapshot in time" and thatthe reliability of this OPCC will degrade over time. Client agrees that MWH cannot and does not make any warranty, promise, guarantee or representation, either express or implied that proposals, bids, project construction costs, or cost of O&M functions willnot vary significantly from MWH's good faith Class 4 OPCC
AACE In tern ation al CLA SS 4 Cost Esti mate - Class 4 estimates are generally prepared based on limited informati on and subsequently have fairly wide accuracy ranges. Ty pically, engineering is 10% to 40% complete. T hey are typically used for projectscreening, determinati on of feasibility , concept evaluation, and preliminary budget approval. Virtually all Class 4 estimates use stochastic estimating methods such as cost curves, capacity factors, and other parametric and modeling techniques. Expectedaccuracy ranges are from -15% to -30% on the low side and +20% to 50% on the high side, depending on the technological compl exity of the project, appropr iate reference informat ion, and the inclusion of an appropriate contingenc y determination. Rangescould exceed those shown in unusual circumstance s. As little as 20 hours or less to perhaps more than 300 hours may be spent preparing the estimate dependi ng on the project and estimating methodology (AACE Int ernational Recommende d Practices andStandards).
Opinion of Probable Construction CostsCurrency: USD-United States-MAY 2013 Dollar
Prepared by MWH Global, Inc. 5/13/2013 Page 1
-
8/12/2019 Pipeline Costs
18/19
MWH PTArcadia, CA 5/13/2013
City of RiversideFEMA Proposal Support
Hidden Valley Water Conveyance ProjectAlternative #6
Grand Total Price: 7,000,000$
Item # Description Quantity UOM Unit Price Total Price Comments
A. Conveyance to Hidden Valley Wetlands $4,716,8001 2 MGD Vertical Turbine Pump Station 1 lot $1,300,000 $1,300,000 TDP = 110, PS cost curve < 10 MGD, 3 pumps, 90 hp2 12" C200 CML Pressurized Pipeline, 5' cover 2,000 lf $260 $520,000 from PS to Hole Lake. Mostly paved areas3 Jack & Bore at Van Buren Avenue & Jurupa Avenue 350 lf $738 $258,300 includes pits4 12" Throttling Valve at Hole Lake Wash 1 ea $31,200 $31,2005 12" Blow Off 1 ea $3,000 $3,0006 12" Flowmeter 1 ea $15,000 $15,0007 14" C200 CML Pressurized Pipeline, 5' cover 7,500 lf $260 $1,950,000 at horse trail8 Pipeline Testing/Comissioning 9,500 lf $5 $47,5009 Piping Tieins/Connects 2 ea $20,000 $40,000
10 Horse Trail Replacement 7,500 lf $10 $75,00011 Pavement Replacement 12,000 sf $4 $48,000 at 6' wide for 2000'12 Contractor Mobilization/General Conditions 1 ls 10% $428,800
B. Hole Lake Wash Pump Station $315,000
1 1.5 MGD Vertical Turbine Pump Station 1 lot $300,000 $300,0002 10" C200 CML Pressurized Pipeline 100 lf $150 $15,000
C. Hidden Valley Wetlands Mitigation $834,0001 C le ar ing & Grubbing Channel 3,000 lf $25 $75,000 remove sediments/debris2 36" Dia RCP 1,200 lf $360 $432,000 replace/reroute influent pipe3 Trench Shoring 1,200 lf $10 $12,000 for 36" RCP placement4 Manhole 3 ea $15,000 $45,000 access manholes spaced at 400'5 Pond Influent Piping 1 ls $50,000 $50,000 small dia RCP & PVC distribution piping to ponds6 Distribution Pipe Flush 1 ls $20,000 $20,000 remove impacted silt from remaining influent piping7 Influent Pond Sediment Removal 5,000 cys $20 $100,000 remove sediments from silted in influent pond8 Permitting 1 ls $50,000 $50,000 USACE, DF&G, DF&WS9 Contractor Mobilization/General Conditions 1 ls $50,000 $50,000
Running Subtotal: $5,865,800
Project Administration & Management $1,173,1601 Construction Oversight & Mgt 1 ls 0% $0 Excluded2 Engineering 1 ls 0% $0 ditto3 Geotechnical 1 ls 0% $0 ditto4 Engineering During Construction 1 ls 0% $0 ditto5 Misc Owner's Soft Costs (All) 1 ls 0% $0 Excluded
6 Land Acquisition 1 ls 0% $0 ditto7 Scope Contingency/Market Conditions 1 ls 20% $1,173,160 Scope definition/market allowance/estimating8 I nt er es t During Construction (Financing) 1 ls 0% $0 Excluded, allowance for financing costs9 Owner's Construction Contingency/Mgt Reserve 1 ls 0% $0 Excluded, allowance for changed field conditions
Grand Total: $7,000,000 Total Estimated Constr Costs w/ Contingency
Cost Range: $4,660,000 $7,570,000 Per AACE cost estimate guidelines
Assumptions:1) Non standard environmental mitigations excluded.2)
Notes:
1) This OPCC is classified as a Class 4 cost estimate per AACE guidelines. Stated accuracy range = 20% to +30%2) Pricing basis = 2nd Qtr 2013, escalation to midpoint of construction is excluded.3) Pricing assumes competitive market conditions at time of tender (+3 bidders/trade).
4) Owner soft costs and project management expenses excluded
5) Special inspections not included
OPCC Disclaimer
Opinion of Probable Construction CostsCurrency: USD-United States-MAY 2013 Dollar
The client hereby acknowledges that MWH has no control over the costs of labor, materials, competitive bidding environments, unidentified field conditions, financial and/or commodity market conditions, or any other factors likely to affect the OPCC of thisproject, all of which are and will unavoidably remain in a state of change, especially in light of high market volatility attributable to Acts of God and other market forces or events beyond the control of the parties. As such, Client recognizes that this OPCCdeliverable is based on normal market conditions, defined by stable resource supply/demand relationships, and does not account for extreme inflationary or deflationary market cycles. Client further acknowledges that this OPCC is a "snapshot in time" and thatthe reliability of this OPCC will degrade over time. Client agrees that MWH cannot and does not make any warranty, promise, guarantee or representation, either express or implied that proposals, bids, project construction costs, or cost of O&M functions willnot vary significantly from MWH's good faith Class 4 OPCC
AACE In tern ation al CLA SS 4 Cost Esti mate - Class 4 estimates are generally prepared based on limited informati on and subsequently have fairly wide accuracy ranges. Ty pically, engineering is 10% to 40% complete. T hey are typically used for projectscreening, determinati on of feasibility , concept evaluation, and preliminary budget approval. Virtually all Class 4 estimates use stochastic estimating methods such as cost curves, capacity factors, and other parametric and modeling techniques. Expectedaccuracy ranges are from -15% to -30% on the low side and +20% to 50% on the high side, depending on the technological compl exity of the project, appropr iate reference informat ion, and the inclusion of an appropriate contingenc y determination. Rangescould exceed those shown in unusual circumstance s. As little as 20 hours or less to perhaps more than 300 hours may be spent preparing the estimate dependi ng on the project and estimating methodology (AACE Int ernational Recommende d Practices andStandards).
Prepared by MWH Global, Inc. 5/13/2013 Page 2
-
8/12/2019 Pipeline Costs
19/19
MWH PTArcadia, CA 5/13/2013
City of RiversideFEMA Proposal Support
Hidden Valley Water Conveyance ProjectAlternative #7
Grand Total Price: 7,300,000$
Item # Description Quantity UOM Unit Price Total Price Comments
A. Conveyance to Hidden Valley Wetlands $5,211,8001 2 MGD Vertical Turbine Pump Station 1 lot $1,200,000 $1,200,000 TDP = 65, PS cost curve < 10 MGD, 3 pumps, 50 hp2 14" C200 CML Pressurized Pipeline, 5' cover 2,000 lf $260 $520,000 from PS to Hole Lake. Mostly paved areas3 Jack & Bore at Van Buren Avenue & Jurupa Avenue 350 lf $738 $258,300 includes pits4 14" Throttling Valve at Hole Lake Wash 1 ea $31,200 $31,2005 12" Blow Off 1 ea $3,000 $3,0006 12" Flowmeter 1 ea $15,000 $15,0007 Distr ibut ion Structure 1 ea $100,000 $100,0008 28" C200 CML Pressurized Pipeline, 5' cover 7,500 lf $320 $2,400,000 at horse trail9 Pipe line Testing/Comissioning 9,500 lf $5 $47,500
10 Piping Tieins/Connects 2 ea $20,000 $40,00011 Hor se Trail Replacement 7,500 lf $10 $75,00012 Pavement Replacement 12,000 sf $4 $48,000 at 6' wide for 2000'13 Contractor Mobilization/General Conditions 1 ls 10% $473,800
B. Hidden Valley Wetlands Mitigation $834,0001 Clea ring & Grubbing Channel 3,000 lf $25 $75,000 remove sediments/debris2 36" Dia RCP 1,200 lf $360 $432,000 replace/reroute influent pipe3 Trench Shoring 1,200 lf $10 $12,000 for 36" RCP placement4 Ma nhole 3 ea $15,000 $45,000 access manholes spaced at 400'5 Pond Influent Piping 1 ls $50,000 $50,000 small dia RCP & PVC distribution piping to ponds6 Distr ibut ion Pipe Flush 1 ls $20,000 $20,000 remove impacted silt from remaining influent piping7 Influent Pond Sediment Removal 5,000 cys $20 $100,000 remove sediments from silted in influent pond8 Permitt ing 1 ls $50,000 $50,000 USACE, DF&G, DF&WS9 Contractor Mobilization/General Conditions 1 ls $50,000 $50,000
Running Subtotal: $6,045,800
Project Administration & Management $1,209,1601 Construction Oversight & Mgt 1 ls 0% $0 Excluded2 Engineering 1 ls 0% $0 ditto3 Geotechnical 1 ls 0% $0 ditto4 Engineering During Construction 1 ls 0% $0 ditto5 Misc Owner's Soft Costs (All) 1 ls 0% $0 Excluded6 Land Acquisition 1 ls 0% $0 ditto7 Scope Contingency/Market Conditions 1 ls 20% $1,209,160 Scope definition/market allowance/estimating8 Interes t During Construction (Financing) 1 ls 0% $0 Excluded, allowance for financing costs9 Own er's Construction Contingency/Mgt Reserve 1 ls 0% $0 Excluded, allowance for changed field conditions
Grand Total: $7,300,000 Total Estimated Constr Costs w/ Contingency
Cost Range: $4,870,000 $7,920,000 Per AACE cost estimate guidelines
Assumptions:1) Nonstandard environmental mitigations excluded.2)
Notes:
1) This OPCC is classified as a Class 4 cost estimate per AACE guidelines. Stated accuracy range = 20% to +30%2) Pricing basis = 2nd Qtr 2013, escalation to midpoint of construction is excluded.3) Pricing assumes competitive market conditions at time of tender (+3 bidders/trade).
4) Owner soft costs and project management expenses excluded
5) Special inspections not included
OPCC Disclaimer
Opinion of Probable Construction CostsCurrency: USD-United States-MAY 2013 Dollar
The client hereby acknowledges that MWH has no control over the costs of labor, materials, competitive bidding environments, unidentified field conditions, financial and/or commodity market conditions, or any other factors likely to affect the OPCC of thisproject, all of which are and will unavoidably remain in a state of change, especially in light of high market volatility attributable to Acts of God and other market forces or events beyond the control of the parties. As such, Client recognizes that this OPCCdeliverable is based on normal market conditions, defined by stable resource supply/demand relationships, and does not account for extreme inflationary or deflationary market cycles. Client further acknowledges that this OPCC is a "snapshot in time" andthat the reliability of this OPCC will degrade over time. Client agrees that MWH cannot and does not make any warranty, promise, guarantee or representation, either express or implied that proposals, bids, project construction costs, or cost of O&Mfunctions will not vary significantly from MWH's good faith Class 4 OPCC
AACE Int ernat ion al CLA SS 4 Cost Es timat e - Class 4 estimates are generally prepared based on limited information and subsequently have fairly wide accuracy ranges. Typically, engineering is 10% to 40% complete. They are typically used for projectscreening, determination of feasibility, concept evaluation, and preliminary budget approval. Virtually all Class 4 estimates use stochastic estimating methods such as cost curves, capacity factors, and other parametric and modeling techniques. Expectedaccuracy ranges are from -15% to -30% on the low side and +20% to 50% on the high side, depending on the technological complexity of the project, appropriate reference information, and the inclusion of an appropriate contingency determination.Ranges could exceed those shown in unusual circumstances. As little as 20 hours or less to perhaps more than 300 hours may be spent preparing the estimate depending on the project and estimating methodology (AACE International RecommendedPractices and Standards).