![Page 1: Pirquitas Construction Progress Photos - SSR Mining · Progress Photos July, 2008 Project Update: • Primary crusher is on site • Secondary crusher building erection well underway](https://reader034.vdocument.in/reader034/viewer/2022042914/5f4fba879c70fe036a79bb1a/html5/thumbnails/1.jpg)
1 July 2008
Pirquitas Construction Progress Photos
July, 2008
Project Update:
• Primary crusher is on site
• Secondary crusher building erection well underway • Foundation work completed for ball mill, silver float circuit and jig area, and has commenced for zinc and tin circuits
• Earthworks completed for water supply reservoir
• Office building completed, assay laboratory nearing completion
![Page 2: Pirquitas Construction Progress Photos - SSR Mining · Progress Photos July, 2008 Project Update: • Primary crusher is on site • Secondary crusher building erection well underway](https://reader034.vdocument.in/reader034/viewer/2022042914/5f4fba879c70fe036a79bb1a/html5/thumbnails/2.jpg)
2 July 2008
Process Plant North Panoramic View – Plant facility in the background
Secondary Crusher Building Erection
![Page 3: Pirquitas Construction Progress Photos - SSR Mining · Progress Photos July, 2008 Project Update: • Primary crusher is on site • Secondary crusher building erection well underway](https://reader034.vdocument.in/reader034/viewer/2022042914/5f4fba879c70fe036a79bb1a/html5/thumbnails/3.jpg)
3 July 2008
Ball Mill Foundation – Setting up to pour plinths
Process Building Lateral View from Jig Area
![Page 4: Pirquitas Construction Progress Photos - SSR Mining · Progress Photos July, 2008 Project Update: • Primary crusher is on site • Secondary crusher building erection well underway](https://reader034.vdocument.in/reader034/viewer/2022042914/5f4fba879c70fe036a79bb1a/html5/thumbnails/4.jpg)
4 July 2008
Process Building ‐ Silver Circuit Foundation
Process Building ‐ Zinc Circuit Foundation
![Page 5: Pirquitas Construction Progress Photos - SSR Mining · Progress Photos July, 2008 Project Update: • Primary crusher is on site • Secondary crusher building erection well underway](https://reader034.vdocument.in/reader034/viewer/2022042914/5f4fba879c70fe036a79bb1a/html5/thumbnails/5.jpg)
5 July 2008
Generator Building Structure
Water Supply Reservoir
![Page 6: Pirquitas Construction Progress Photos - SSR Mining · Progress Photos July, 2008 Project Update: • Primary crusher is on site • Secondary crusher building erection well underway](https://reader034.vdocument.in/reader034/viewer/2022042914/5f4fba879c70fe036a79bb1a/html5/thumbnails/6.jpg)
6 July 2008
Man Camp Panoramic View
Jujuy Office
![Page 7: Pirquitas Construction Progress Photos - SSR Mining · Progress Photos July, 2008 Project Update: • Primary crusher is on site • Secondary crusher building erection well underway](https://reader034.vdocument.in/reader034/viewer/2022042914/5f4fba879c70fe036a79bb1a/html5/thumbnails/7.jpg)
7 July 2008
Assay Laboratory
Open Pit Pre‐stripping 1
![Page 8: Pirquitas Construction Progress Photos - SSR Mining · Progress Photos July, 2008 Project Update: • Primary crusher is on site • Secondary crusher building erection well underway](https://reader034.vdocument.in/reader034/viewer/2022042914/5f4fba879c70fe036a79bb1a/html5/thumbnails/8.jpg)
8 July 2008
Open Pit Pre‐stripping 2
Open Pit Pre‐stripping 3