planning and organizing for pharma manufacturing facility construction
TRANSCRIPT
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 1/33
Page 1
Planning and Organizing
for Pharmaceutical
Manufacturing Facility
onstruction
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 2/33
Page 2
• Stringent Mandatory GovernmentRegulatory Requirements
• Market Demand to Reduce Cost
• Increase Efficiency
• New Technology
Forces Affecting the Region
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 3/33
Page 3
Requirement
Upgrade facilities orconstruct new
ones designed tohigher standards
of constructionand technology
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 4/33
Page 4
Objectives
• PICS cGMP compliant
• Multi-product/Dedicated/ Segregated
• Flexible
• Compact
• Local / National Building Compliant
• Safe and Environment Friendly
• Controlled Cost
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 5/33
Page 5
• Change Control Initiation Form,Form 02v-001
• Review of Major/Critical Changes Form,Form 02v-002
Change
Type CodeType of change Critical Major Minor
C4Change in manufacturing location / new or
renovated facility √
• Change Control Committee
• Validation Committee• Risk Management Committee
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 6/33Page 6
• Impact Assessment• Conditions to be fulfilled
• Impact on sites SOPs, batch and documentation
• Impact on supply
• Training of Personnel
• Responsibilities
• Cleaning Validation
• Process Validation
• Equipment Qualification
• Safety• Cost
• Regulatory impact
• Downstream impact on customers
• Priority
• Timeline
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 7/33Page 7
• Recommended Consequent Actions• Document Change (Lay-out, Room Book, SMF, SVMP, SOPs,
SOIs, EMF, UMF, IMF etc.)• Training
• Regulatory Action/ variation application
• Allocate budget and resources
• Customer approval
• Qualification/requalification
• Process Validation
• Room Temperature Profiling• Cleaning Validation
• Increased Testing / Sampling
• Trial production batch
• Laboratory experiment
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 8/33
Page 8
Stages
• Strategic Planning
• Conceptual Design
• Detailed Design and Engineering
• Pre-construction
• Construction / Installation
• Commissioning
• Acceptance
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 9/33
Page 9
Manufacturing Strategic Planning
• Policies, goals and objectives clearly defined
• Identify the products and product risks
• Process requirements and process risks
• Product lines and volume requirements• Cost drivers
• Capacities, flexibility and technology• Organization in the facility
• Schedule
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 10/33
Page 10
Teams Identified
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 11/33
Page 11
Validation Team
• Initially the team consist of;
• Construction Manager• Production Manager (end
user of the facility)
• Plant Engineer (end userof the facility)
• QA Manager / Validation
Manager
• JM Tolmann Validation Team
• Managing Director• QA Validation Supervisor
• Production Supervisor• QC Supervisor
• MSD In-Charge
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 12/33
Page 12
Conceptual Design Team
• Facility engineers andproduction managers who
are projected to use thefacility when finished.
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 13/33
Page 13
Detailed Design EngineersTeam
• Architect• Civil Engineer
• Mechanical Engineer
• Electrical Engineer• Sanitary Engineer
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 14/33
Page 14
Construction Management Team
• Civil Engineer• Mechanical Engineer
• Electrical Engineer
• Sanitary Engineer
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 15/33
Page 15
Conceptual Design
• Process Requirements
• Process Line/Equipment
• Material Requirements
• Utility Requirements
• Operating Cost• Safety and Environmental
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 16/33
Page 16
Conceptual Design
• Facility Requirements(number and areas of functional areas required)
• Process and production
• Materials receipt, dispatch,staging, storage
• Mechanical utilities andmaintenance
• Personnel related activities
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 17/33
Page 17
Conceptual Design
• Room Book• Classification
• Occupancy
• Dimension• Architectural Finishes
• Access Requirements
• Floor Loading• Environmental Factors
• Utilities and Services
• Safety
• Fixed Furniture
• Equipment
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 18/33
Page 18
Building Cephalosporin Series No. 13RBDS01
Storey 1 Reference Drawing No.
Room No. 111 Working hours 8 hrs /shift
Room description Bottle Blowing Room Class D
General Room Data Fittings Data
Length (m) 2.39 Flooring Epoxy finished, coved sides
Width (m) 1.90 Walls Concrete
Clearance height (m) 2.44 Ceiling False ceiling, hardiflex Area (m2) 4.54 Paint color White, Semi-gloss latex
Room volume (m3) 11.68 Number of doors 1
Number of Persons 1 Type of doors Wooden Sliding Door
Number of Equipment 1 Doors locked N/A
Room Conditions Number of windows N/A
Temperature (oC) 24 Type of windows N/A
Relative Humidity (%) 62 Utilities
Pressure differential Purified water None
Air exchange (1/h) Compressed air 1
Noise level dB(A) HVAC 1
Room Book Data Sheets
Form 02v-030
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 19/33
Page 19
Monitoring Instrument Others
Thermohygrometer None Air Conditioning Units (#, HP) None
Thermometer None Electric Fan None
Magnehelic None Tap Water Supply None
Pressure Gauge 1 Cabinet 1
Electro/Data Technology Table (Number, Type) None
Gen. room lighting (Lux) Chair/Bench (Number, Type) None
Lamps (Number, Watts) 1 Hood Outlet None
Light switches (Number) 1 Hatch None
Sockets 110V (Number, Ph) Louver None
Sockets 220V (Number, Ph) 1Ph,3Ph Ladder None
Telephone (Local Number) None Ceiling Manhole None
Paging system None Safety
LAN/Internet outlet None Emergency Light None
CCTV None Smoke Detector None
Control Panel None Fire Exit None
Sanitary System Fire Extinguisher None
Floor drains 1 Safety Shower NoneSink / Wash Basin None First Aid Kit / Cabinet None
Equipment/s (Manufactur ing, Laboratory, Office)
Bottle Blowing Machine
Name Signature Date
Compiled by
Checked by
Released by
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 20/33
Page 20
Conceptual Design
• Site Inspection• Soil Information
• Topography
• Existing Structures• Access
• Circulation
• Site Services
• Any planning constraints
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 21/33
Page 21
Conceptual Design
• Design Concepts
CONCEPTS
CONCEPTS
CONCEPTS PROJECT
GOALS REFINE SELECT
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 22/33
Page 22
Conceptual Design
• Final Design Scheme• Include detailed layouts of buildings,
process equipment, areaclassifications and preliminary HVACutilities
• Cost Estimate
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 23/33
Page 23
GMP Zonal Concept
AREA DEFINITION COMMENT
WarehouseOfficesLaboratoriesSecondary Packaging
Not defined -
Production PrimaryPackaging
Rooms and equipmentaccording to therequirements of the EUGMP Guideline,
Chapter 3
Standard arrangementFilter correspondswith room Class D, butwith regular monitoring
Sterile Production Class A, B, C, D See EU GMP Guideline
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 24/33
Page 24
Technical Details for the Layout of
RoomsVentilationTechnology
Filter stages, pressure characteristics, airexchange, air flow
Components Walls, doors, ceilings, floors, windows
Layout Personnel and material locks (PAL, MAL), Materialand Personnel Flow
Other buildingservices
Gases, Water, Waste Water, Plumbing, Lighting
Control Systems for Pressure differential, temperature, moisture,particles
Equipment Cleanability and sterility; no shedding of wear debris,oil, particles, microorganisms; ease of operation,maintenance and repair
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 25/33
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 26/33
Page 26
Detailed Design & Engineering
• Detailed engineering, lay-
out and specifications• Architectural
• Structural• Mechanical
• Electrical• Sanitary
• Process
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 27/33
Page 27
Pre-construction
• Review of design and specifications
• Qualification of suppliers,contractors, materials, prototypes
of design• Bidding and negotiation
• Final project cost estimate• Contracts review and signing
• Secure Permits
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 28/33
Page 28
Construction/Installation
• Monitoring, inspection and evaluation
of materials, construction andinstallation
• Coordinate work• Schedule delivery of materials,
equipment, labor
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 29/33
Page 29
Commissioning
• Tests
• Test Runs• Calibration
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 30/33
Page 30
Acceptance
• Completion of tests, test runsand calibration
• Conformance to design anddefined specifications
• Secure permits and licenses• Regulatory agency approval
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 31/33
Page 31
Stages
• Strategic Planning
• Conceptual Design
• Detailed Design and Engineering• Pre-construction
• Construction /Installation• Commissioning
• Acceptance
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 32/33
Page 32
PLANNING
DQ
VENDOR QUALIFICATION
TESTING IQ
TESTING OQ
FINAL RESULTS
STRATEGIC PLANNING
CONCEPTUAL DESIGN
DETAILED DESIGN & ENG’R
PRECONSTRUCTION
CONSTRUCTION AND
INSTALLATION
COMMISSIONING
ACCEPTANCE
VALIDATION PLANNING AND CONSTRUCTION
• VMP
• GMP Critical Reviews
• Requirement Analysis
• User Requirements
• Risk Assessment
• Functional Specification
8/9/2019 Planning and Organizing for Pharma Manufacturing Facility Construction
http://slidepdf.com/reader/full/planning-and-organizing-for-pharma-manufacturing-facility-construction 33/33
Page 33