planning participation in the german energiewende on the ......analysis takes the entire process of...
TRANSCRIPT
1
Planning Participation in the German Energiewende – on the relevance of a context- and process-oriented perspective
Giulia Molinengo, Ina Richter, Patrizia Nanz, Mathis Danelzik
(++ preliminary version – not for further distribution ++)
Abstract:
Public participation never takes place in a vacuum. The German Energiewende serves as a
volatile political field for practicing and testing participation in transformative energy
infrastructure contexts. Factors such as intense conflicts and limited space for informal
participatory processes require a context specific planning of participatory processes that reacts
to timely dynamics.
Social-science research has mostly described and evaluated participatory processes in a rather
static manner while placing attention on the analysis of formats and methods. Based on
empirical findings of the project DEMOENERGY – The transformation of the energy system as
engine for democratic innovations, we argue for a context- and process-oriented perspective,
which centers on a temporal analysis that bears methodological consequences, too.
The paper discusses what such an analytic perspective comprises and what can be learned
from it, demonstrated on the phase of planning public participation in electricity grid expansion
projects in Bavaria, Germany. Using the example of challenges and changes in defining the
participatory space, we outline the benefits of a context- and process-oriented perspective.
1. Introduction: Offering another analytical lens
The transformation of the German energy system called ‘Energiewende’ proves to be a great
challenge that is accompanied by conflicts on various levels. These include the conflicts about
visions of the Energiewende, which technologies to employ, the specifics of technologies in
infrastructural planning as well as the information, deliberation and decision making processes
regarding infrastructural projects. Forms of public participation – which have blossomed in
practice such as consensus conferences, round tables, planning cells, online-dialogues and the
like (i.e. Participedia.net lists around a 100 such processes) – have entered this field as
mechanisms that are supposed to avoid or cope with such conflicts. Different actors see it as a
means for increased legitimacy of planning, political processes and outcomes, others mainly
hope for increased acceptance of projects and smoother implementation. Meanwhile, factors
such as the technical complexity of issues, intense protests, incongruences on various political
levels and continual changes in regulatory frameworks are challenging such processes
(Kamlage et al. forthcoming).
2
The research project “DEMOENERGY – The transformation of the energy system as engine for
democratic innovations,”1 (www.demoenergie.de) co-initiated two dialogue-oriented participation
processes to include citizens in the planning of energy infrastructure projects. Engaging in action
research (Gergen 2003; Reason/Bradbury 2008) the team of researchers designed and
implemented two local participatory processes in the German state of Bavaria in
transdisciplinary cooperation with a transmission system operator (TSO). Objective of the
participatory processes was to plan the course of a high voltage transmission line in two
locations with the respective local citizens and other stakeholders.
Based on empirical findings of the research project DEMOENERGY we convey in the following
that empirical findings are calling for an expansion of the theoretical lenses used to understand
public participation processes. We argue for the importance of examining the planning of public
participation as a social process. Specifically, this applies for the relevance of an analytical
perspective that takes into account the temporal dynamics of this process, with a focus on how
interactions of actors as well as changing contexts shape the participation process in time.
Research on participation has early started to analyze the processes and outputs of individual
participatory actions. A variety of single case studies was conducted such as on public mediation
(Geis 2005, Weidner/Fietkau 1995), planning cells (Dienel 1986, Ortweil 2001), consensus
conferences (Schicktanz/Naumann 2003), participatory budget (Esterling et al. 2010, Schneider
2011, Taubert et al. 2011), future councils, wisdom councils and participatory processes in
context of the Local Agenda 21 (Behringer 2002, Strele 2012). Today there is a large body of
literature regarding the various methods and formats such as planning cells.
For the purpose of evaluating participatory interventions, research practice has established a
heuristic that divides participatory processes into the phases input, process and outcome (also
output and impact) (i.e. Kamlage 2013; Mandarano 2008; Warburton et al. 2006). Evaluation
studies so far mainly concentrated on the process element or aspects of it such as inclusivity of
the process (Abelson/Gauvin 2006, p. 12). The focus of process evaluation lies on the phase of
a participatory program being in progress, i.e. it relates to the implementation of the program
(ibid.; Gastil et al. 2007, p. 207). More recently research focus shifted to studying the
performance of participatory interventions. Studies evaluating outcomes center on the analysis
of the consequences of public participation, the results and long-term effects of the process
(Abelson/Gauvin 2006, p. 12). Referring to the third phase of the applied heuristic – context -
there is increasing evidence that aspects of context matter for the positive as well as negative
benefits and success of the participatory intervention (Delli Carpini et al. 2004; Rowe/Frewer
2004). Yet, literature on categories and details about contextual factors still remains scarce. First
meta-analysis studies that aim at gaining insights into the interplay of contextual and design
factors and how they influence outcomes of participatory processes point to the type of issue,
the pre-existing level of conflict and mistrust as well as differences across local, state and
national decision-making processes or agencies (Beierle/Cayford 2002), but also interests of
participants (Newig/Fritsch 2009, p. 495) as being worthwhile for further evaluation. However,
1 The project was funded by the German Ministry for Education and Science from June 2013 to March
2016.
3
especially insights in interests and motives of participants and how these influence the
participatory process from the period of planning on, still remain an empirical gap in participatory
studies.
Figure 1: Prominent focus of evaluation research
Heuristics that divide participatory processes into rather distinct and fixed phases have their
merits, but have also – together with the long existing focus on formats and methods – lead to a
rather ’static’ view of participation processes within participation research. Seldom, process
analysis takes the entire process of initiating, planning and implementing public participation
intervention and its results into account.
In light of our empirical findings, we find that - in order to give a satisfactory explanation for any
aspect of the participatory processes in context of infrastructure planning that we worked on - we
need to take into account, that 1) contextual factors are relevant to the planning of the process,
that they are shaped by various dynamics over time and become relevant to the participatory
process at different points in time; 2) that those dynamics span all phases of the processes from
their early planning to the interpretation of their results in the aftermath of the last event and
therefore cut across the phases of the mentioned heuristic; 3) that participatory processes are
social phenomena that involve actors with different belief systems, interests, constraints for
action and whose interactions are influencing the course of the participatory process.
As our example will show, decisions on the design of participatory processes highly depend on
the moment in time the decision is taken, as well as the information, interests, various contexts,
idiosyncracies, and the composition of decision takers present at this moment. For outlining this
perspective we will use the example of a crucial question regarding the design of participatory
processes that emerged in the two DEMOENERGY case studies in Bavaria, namely how to
draw the distinction between those invited to participate and those who are not. Using this
Prominent focus of analysis
INPUT PROCESS
OUTPUT/
OUTCOME/
IMPACT
4
example we intend to shed some light on elements and dynamics that apparently play a relevant
role in influencing the development and course of a participatory process. On this basis, we
identify and describe the main pillars of a context- and process-oriented perspective on public
participation. The final step of this paper will outline implications for research as well as practice
of public participation that stem from the outlined perspectives.
DEMOENERGY – a short overview of the two participatory processes
With the abandonment of nuclear energy and increasing capacity in volatile renewable energy
sources, the distribution of energy generation and supply sees remarkable changes. These
result in a political program to expand Germany’s high voltage electricity grid and to provide
more international links to other nations’ grids.2 One of the priority projects within this grid
expansion program is The ‘Ostbayernring’, a 185 km long high voltage transmission line built in
the 1970s in the North-Eastern part of Bavaria. The German state assigned one of the four
TSO’s responsible for the German high voltage grid the task to increase its capacity.
Scientists of the DEMOENERGY project planned and initiated, in collaboration with the TSO,
two participatory processes along this high voltage transmission line. The intention was to better
involve citizens and relevant stakeholders at an early stage in the planning process of such
infrastructure projects. The initiated participatory processes were informal, meaning that they
were not part of the formal regulatory process. They preceded a process, in which the regional
government determined which variants were eligible to be further assessed and pursued in
subsequent planning stages. The informal participatory processes were supposed to offer co-
design elements to citizens and thereby go beyond mere consultation opportunities provided by
formal regulation for public participation.
In order to do so, the team of DEMOENERGY3 engaged in the design of the participatory
process in cooperation with the TSO. The planning phase lasted from the beginning of 2014 until
the beginning of September of the same year. A core group of initiators – including researchers
of DEMOENERGY, management and communication staff of the TSO and external consultants
– progressively included further actors into the process: a communication agency, environmental
planners and other members of the TSO’s staff punctually provided their expertise in planning
meetings. From the end of September 2014 until June 2015 two participatory processes took
place in Windischeschenbach (around 5.000 inhabitants) and surrounding villages and in
Schwandorf (around 20.000 inhabitants). The design of each participatory process included
three public events, to which the entire population of those areas was invited. It encompassed as
well the establishment of a planning group of about 20 persons, including 8 randomly selected
local citizens, the mayors of affected municipalities, local organizations, public authorities and
the TSO staff. This planning group had the task of working out citizens’ proposals in details and
2 According to the national Power Grid Development Plan, approximately 3800 km of new lines in the
transmission grid and new power transformers will need to be built until 2020, see ÜNB 2013, p. 136. 3 With the support of external professional consultants that were additionally responsible for facilitating the
participatory meetings.
5
making sure that the process would run transparently and fairly. The public events provided
opportunity for the whole population to give feedback to the work of the planning group, to
receive information about the process and infuse new inputs to the planning. Thereby the most
important task was to suggest alternative courses of the power line.
The results of the participatory processes consisted in collecting, assessing and comparing
suggested variants, which led to the development of several alternative courses for the power
line, all of which had been proposed by citizens throughout the process. These variants are
going to be submitted by the TSO to the responsible regulatory authorities, who will determine,
which of those line are eligible to be further assessed and pursued in subsequent planning
stages.
2. Case study: the shaping of participatory spaces as social process
The distinction of whom to include in the participatory process does not necessarily involve a
spatial dimension. However, given the spatially-bound nature of adverse effects of most
infrastructural projects4 as well as common goals of infrastructural planners5, spatially-bound
notions of affliction by adverse effects or risks are commonly chosen criteria to determine whom
to involve (for a discussion of concepts of affliction see Bauriedl et al. 2013). The ideal of such a
definition would be a perfect congruence of who might suffer adverse effects by the project and
who gets to have a say in its planning. It is this geographical shape that we call ‘participatory
space’ henceforth as opposed to the specific venues, in which participatory events take place.
Participatory spaces based on spatial- and affliction-criteria also have exclusionary effects.
Spatial criteria often exclude actors whose stakes are not spatial in nature, for example
companies with a special interest in overall net stability. Because these interests do not manifest
in any one specific line project, but concern the quality of the grid as a whole, they tend to keep
latent in each discussion about any specific line.
Potential affliction is notoriously difficult to assess, both because the meaning of affliction is
subjective (Bohner 2003), and because it is difficult to anticipate how the planning will evolve
and who might become potentially afflicted later on in the process. Whichever way potential
affliction and consequently a participatory space is conceptualized, there might exist actors just
beyond its border that feel the need to be included. When a congruence of those potentially
afflicted and those included in the participatory space is aspired, the constitution of the
participatory space additionally defines the scope that proposals within the participation process
can attain. Because this scope might run counter to what participating actors consider sound
proposals, pressure to enlarge the participatory space can also emerge from within the
participatory processes. Lastly, planners’ normative concepts, understanding of the participatory
process as well as their interests are unavoidably inscribed in its genesis and constitution. For all
4 For example, loss of harvest and visual impediments in the case of transmission lines
5 For example, finding solutions to conflicting claims to land use or gaining acceptance in a specific
geographical space
6
those structural reasons, participatory spaces always carry the potential to be or become
contentious during the process. Conflicts can arise over the criteria used to define them, the
indicators with which the criteria are operationalized and/or the concrete geographical form a
participatory space takes on.
Due to these reasons, the concept of participatory space constitutes a core element of the
design of a participatory process, especially in the context of infrastructure projects. As we will
show the participatory space is shaped by various factors – composition of actors, contextual
factors, information available and needed – that may change over time. Therefore, the genesis
of the core element ‘participatory space’ can only adequately when considering temporal
dynamics. In order to show the merit of such analysis, we will provide a rudimentary version and
give an overview of the development of the participatory spaces across time in the two empirical
cases of DEMOENERGY, from the planning phase to the closing public events of the
participatory processes.
Starting points for defining a participatory space
The German state had assigned one of the four TSO’s responsible for the German high voltage
grid the task to increase the capacity of the ‘Ostbayernring’. In this case the pylons’ statics were
not able to endure additional cable, and an one-in-one replacement of pylons would have
stressed net stability due to long deactivation phases (and been an expensive solution).
Therefore the responsible TSO (in agreement with the government regulatory authority) planned
to build a new line running parallel to the existing one. After completion, the former line would be
decommissioned and dismantled.
This arrangement diminishes certain planning challenges as it provides guidance over the
course of the planned line as well as the hope to impact few new stakeholders, landscapes,
wildlife sanctuaries and other protected areas. Switching to the least impacting flank of the old
line additionally gives the chance to alleviate negative impacts and even to create improvements
to the status quo. Nevertheless, impacts are unavoidable over the whole course of the 185 km,
begging the question whom to include in which manner in planning procedures.
Due to financial resources, manpower, time constraints and conceptual issues, both researchers
and the TSO quickly excluded the option to involve the citizens of all ca. 50 municipalities the
power line runs through. The initiators also agreed that participatory processes only made sense
where planning obstacles might make circumventions by the new line necessary, thereby
possibly leaving a course parallel to the existing line. At this point, initiators knew they would
focus resources for participatory processes on specific localities along the line, but were not
clear on what grounds to select the areas yet. The TSO saw a strong interest in a consistent
argumentation that would allow the company to justify its decision to implement participatory
processes in some spots along the course of the power line and not in others. Finally, three
communities were identified by the initiators as so-called ‘hot-spots’ and therefore eligible for a
participatory process. An initial ‘hot-spot’ definition concerned “those spots where a parallel
7
planning to the existing power line would have sensitively reduced the distance between the new
power line course and the residential areas (< 70 m)”. Once a hot-spot definition had been
articulated, initiators discussed the dimensions of the participatory space in each of the three
resulting ‘hot-spots’. The TSO’s approach to this issue was strongly influenced by advice by the
TSO’s legal counsel as well as by the regulatory body responsible for assessing the TSO’s plans
at a later stage. They both agreed that the circumvention of the hot-spots should as quickly as
possible realign with the existing line. While the legal counsel foresaw legal issues with newly
affected rights of property holders, which are seen as more sensitive by German courts than a
renewal of already existing restrictions of property rights, the regulatory body was concerned
with the feasibility of the regulation process of a project that was supposed to be oriented by the
existing line, if it veered away in a too substantial manner.
With this anchor to the existing line, the participatory space’s dimensions were at least partly
defined: participation space obtained starting and endpoints, which needed to be connected by
the citizens’ and other actors’ proposals for circumventing the bottleneck. They were supposed
to be so far apart as to allow for substantial and reasonable alternative courses, yet as close
together as possible to conform to the maxim to quickly return to the existing line. The existence
of those conflicting premises as well as their underlying rationale effected that the distance
between start and end-points was not permanently settled, but rather a point of insecurity and
contention, at first among the initiators, later on within the participatory process. Furthermore,
the participation space’s shape was not yet fully defined.
Early decisions on the shape of participatory space
Contexts and interests factoring into decisions over the scope of the participatory space among
others included:
- financial aspects: In addition to the immediate costs of planning and executing the
participatory processes, larger participatory spaces tend to produce more proposals for the
future course of the line covering a larger geographical area. Gathering the needed
information to evaluate the line’s interference with those sites involve in-field research by
environmental planners. Their work is a major cost factor, and likely to be increased by more
expansive participatory spaces.
- political aspects: If participatory spaces can be contained in one or few municipalities or
other relevant administrative units, the complexity of interests and actors involved is eased.
Given this point weight fosters less expansive participatory spaces, depending on the given
political-administrative partition of space.
- Logistics and resources: Enlarging the participatory space usually increases the complexity
of the process and its logistics such as advertising the process in a larger territory, covering
this territory with additional information events, bundling the feedback from those
interactions, and so on.
8
In addition to conceptual difficulties, those factors increased importance for initiators to prevent a
continually expanding participatory space, which in turn made consistent borders of such space
even more important.
Certain idiosyncratic occurrences and developments heavily influenced the deliberation on the
scope of participatory processes by initiators in late summer of 2014. Shortly before summer
break, a regional nature conservation authority offered a very skeptical preliminary assessment
of building the new line parallel to the existing line in yet another spot - in Schwandorf, one of the
areas where participatory processes were planned. However, the spot scrutinized by the
authority had not been discussed by the initiators as a bottleneck eligible for a participation
process. The spot lay only a few kilometers further south to one of the three original hotspots.
Map 1 is an early document that identifies the original hotspot Irlaching (which is part of the city
Schwandorf) – with the existing transmission line running in between parts of the village (within
the upper red ellipse) as well as the spot seen critical by the nature conservation authority near
Ettmannsdorf (lower red ellipse, with the most problematic part in the very upper end of the
ellipse; also part of Schwandorf). The latter also posed questions about how close a new line
would encroach on resident housing.
9
Map 1
This development raised the question among the initiators, whether to focus attention to the
latter spot. A participatory process based around the question whether and how a circumvention
of the bottleneck at Ettmannsdorf should take place seemed prudent, as it tackled what had
emerged as the most important and unresolved planning issue in this project. Additionally,
circumventions of the bottleneck in Ettmannsdorf might have rendered decisions around the
original hot-spot Irlaching meaningless anyway, as possible solutions might not even affect
Irlaching. However, as can be seen in map 2, the decision to base a participatory process
around the bottleneck in Ettmannsdorf would expand the scope of the participatory process by
several orders, as it would involve possible larger circumventions around the whole city of
Schwandorf, with every conceivable variant affecting new localities.
10
Map 2: Existing transmission line in black. The here blue colored ellipses approximate the ellipses from map 1 in the context of
greater Schwandorf; the new line had to have the same southern arrival point, a transformer station that needed to be connected to
the new line.
The timing of the skeptical assessment by the natural conservation authority together with the
envisioned proceeding of the planning by the TSO put considerable time pressure on the
initiators to make a decision. According to the plans of the TSO at that time, participation
processes were supposed to be finished in March of 2015, so that the next formal regulatory
11
procedure could start shortly after. The need for additional information, vacation time of
important decision makers as well a complex project structure left initiators with the undesirable
situation to decide this issue only in mid-September, while first public information events – where
binding statements to the public about the object of the planning and participation processes had
to be made – were scheduled for the end of September.
When the decision had to be taken in mid-September, not all information required was at hand –
which would prove consequential later. Uncertainties pertained technical issues (if and where it
would be possible to place pylons regarding the nature reserve, the river, characteristics of the
ground and a face just South of the problematic area) and whether the preliminary skeptical
assessment by the nature conservatory authority would persist after a more detailed
assessment. The researchers and the TSO made the joint decision to define the whole citizenry
of Schwandorf as the subjects in the participatory process, with the bottleneck in Ettmannsdorf
as the new hot-spot, and the issue of Irlaching as part of that new broader process.
This significant ‘last-minute’ expansion under suboptimal circumstances in Schwandorf
increased concern about the feasibility of the participatory processes, which in turn led to a
preference by the TSO to handle other aspects of the scope of the participatory spaces in the
different localities more restrictive. It meant that aspects of the participatory space in Schwandorf
had effects on the participatory space in the other location (Windischeschenbach). Question
about the shape of the participatory space were handled more restrictively partly due to
circumstances that had nothing to do with the local case, but with the overall participatory
structure (limited resources and impressions initiators had at the time).
At this point, different approaches to participatory spaces emerged among the initiators. The
researchers of DEMOENERGY argued from a normative, deliberative democratic perspective
and called for rather broad and therefore inclusive participatory spaces, which would maximize
the chance for a congruency of potential affliction and participation. The researchers argued that
if cases of potential affliction of non-participants would occur later on in the process, this issue
could only be solved in dissatisfying ways. One way could entail to broaden the participatory
space at a later stage within the process, which would pose challenges and potentially court
resentments. Another way could be to accept the potential affliction of non-participants, which
would probably cause even more intense upset. Resentments and potential protests by affected
citizens were of concern for the TSO. However, the proposal by the researchers traded off the
maximized chance for congruency of those potentially afflicted and those participating against
potentially more difficult logistics, increased time pressure, higher costs, and more complex
political structures to accommodate. As the issue of affliction of non-participants was just a
potential at this point, and as this proposal occurred in a time where all initiators where working
over capacity on this issue, these trade-offs were considerable, but ultimately not convincing for
the TSO, who differed on the assessment of the respective risks of the mentioned factors.
As we will see in details in the next paragraphs, the issue of actors, who felt potentially afflicted
but were not given satisfying participation opportunities, immediately arose as soon as local
actors made proposals for the course of the line to be built.
12
Participants shaping the participatory space
Local actors influenced the development and interpretation of the participatory space throughout
the duration of the participatory process from the moment they engaged with it (the first
opportunity was an early information event preceding the kick-off of the actual participation
process). Again, beliefs, roles, interests, constraints and resources (knowledge, power, financial
resources) of those actors mattered. The two maps below indicate the initial and final stage of
the participatory space in Windischeschenbach, one of the two localities where DEMOENERGY
collaborated with the TSO to conduct a participation processes:
Map 3: early proposal by the TSO framing the subject of participation
Map 3 stems from 6th of August 2014. It shows a very early draft by the TSO prepared for the
regulatory authority and it was used to describe one of the defined hot-spots (close to the yellow
inscription). It includes a first idea by the TSO of how to possibly circumvent that bottleneck in
Windischeschenbach. This proposal involved only the urban parts of Windischeschenbach
(instead of the whole municipality) and suggested two possible alternative courses, going around
the main center of the city with either a northern or a southern alternative. Even though the TSO
had prepared the map just as a first point for discussion with the regulatory body, the map does
demonstrate how the TSO conceived of the issue at the time. This framing is based on
prioritizing the maxim to realign the circumventions as early as possible with the existing line.
The TSO thought of the issue at the time in rather narrow terms - at least when compared to
how participants later on would see the issue at hand.
13
Map 4: final participation space spans in between the three red circles.
Map 4 entails the collection of all variants proposed by citizen and other actors within the
participation process that made it to the final stages of the process (25th of June 2015). The
participatory space in its final form spans in between the three red circles. The turquoise ellipse
approximates the initial framing depicted in Map 3. Clearly, the participatory space has
expanded considerably. This expansion occurred in different steps after citizens and affected
mayors got involved:
14
1. The first public informative event6 was held at the end of September 2014. Attendees were
given the opportunity to draw their first proposals for alternative lines into provided maps, which
intentionally were showing not only the municipality of Windischeschenbach but also its
surrounding areas. A number of citizens proposed alternative courses going beyond the borders
of the participatory space at the time, immediately creating a possible situation of potential
affliction of non-participants at the event. As a result, the initiators agreed to extend the
participatory space to villages in the north, south-west and south-east of the city center of
Windischeschenbach, namely Püllersreuth, Pfaffenreuth and Seidlersreuth, because it was
foreseeable at the time that citizens’ proposals would likely affect them. However, each of those
villages belongs to a different municipality. Thereby, the inclusion of rather few additional
citizens raised the political complexity of the process from one municipality to four municipalities
involved. Among the initiators was also doubt whether this criterion for inclusion would prove
consistent enough as the inclusion of those specific villages was rather an effect of the
idiosyncratic information present at the time (some proposals already appeared during the first
information event, while others entered later). It was not due to an unambiguous criterion.
2. Before starting the participatory process, the communication department of the TSO
conducted a series of meetings with groups of all the mayors whose municipality was potentially
affected by the new infrastructure project. The purpose of the meetings was to inform them
about the plans to build a new line. During one of the meetings, the mayor of
Kirchendemenreuth, a municipality located to the South of Windischeschenbach, suggested an
alternative course of the power line by following a highway that cuts through the same area in a
North-South direction.7 The TSO staff and the researchers had not considered that solution to
this point, having being influenced by other planning logics, mainly the maxim of realignment.
The mayor proposed this solution employing his local knowledge, and perceiving an interest to
have the new line not run through Kirchendemenreuth just as central as the existing line does.
Even though he was aware that such a course would also create new adversary effects on some
citizens of his municipality. His proposal was met with the promise to keep in conversation about
the proposal by the TSO. However, an inclusion of his whole municipality into the participatory
process was not offered by the initiators of the process. The absence of such offer needs to be
understood against the backdrop of the maxim of realignment with the existing line (to the TSO it
seemed quite possible to return to a parallel course much sooner), the fear of ever expanding
participatory spaces that would endanger feasibility present among the initiators at the time.
3. During the first proper public event of the participation process, the mayor of
Kirchendemenreuth expressed outrage over this fact and demanded to be included in a planning
group that constituted an important element of the participation process. As mentioned earlier,
the planning group consisted of about 20 people, including eight randomly selected citizens
living in the participatory space, the mayor of Windischeschenbach, local organizations, public
6 Main purpose of the event was to inform about the plan to replace the line as well as the public
participation that would begin in Windischeschenbach at the end of October. 7 The end result of this proposal can be seen in map 4. There are two black lines extending south from the Southern
red circles. The Western line represents the new line parallel to the existing line. The eastern black line represents a
later version of the idea to – for a while – have the transmission line run parallel to the freeway and let it return to the
existing line further south (at the very bottom of the map).
15
authorities and TSO staff. The planning group had the task of working through citizens’
proposals in detail and making sure that the process would run in a transparent and fair way.
The eight seats for citizen were distributed to five citizen of Windischeschenbach, and one each
to a citizen of the aforementioned villages of Püllersreuth, Pfaffenreuth and Seidlersreuth.
Therefore, a citizen of the mayor’s municipality but not him as the mayor of Kirchendemenreuth
was allowed involvement. The initiators had estimated that the interest of mayors in having a
seat in the planning group would be minimal. However, that assumption rested on a narrow
framing in which municipalities other than Windischeschenbach would only be marginally
affected by finding a solution to the hot-spot. But the mayor’s interest was in pushing another
course of the new line in his municipality. It was independent from finding a solution to a hot-spot
as well as the definition of a hot-spot that was not of concern to him.
The participation processes offered the mayor an opportunity to push for this goal in a public
forum, which he might otherwise have struggled to pursue effectively. He was joined by two
other mayors, to which the villages Seidlersreuth and Pfaffenreuth belong to. The initiators
spontaneously conceded having made a mistake and offered those seats within the planning
group. However, the initiators insisted on not expanding the participatory space to his whole
municipality, mostly because the composition of the planning group would have had to be done
from scratch, with excluding already invited members in order to make room for new members8.
From the perspective of the initiators, the departure point for such a fundamental change in
participatory space had passed. As the citizenry of the southern municipality as a whole would
not be included in the participatory process, the proposals concerning the course of the line to
the South of Windischeschenbach would also not be object of this participatory process (due to
the principle to avoid potential affliction of non-participants). It was agreed that discussion about
Southern options would continue between the TSO and the mayor in parallel to the participation
process in which the mayor also participated as member of the planning group. The mayor
obtained a publicly renewed promise by the TSO in this regard.
4. The issue kept being a source of contention that posed challenges for all actors involved. The
mayor and the initiators went back to this issue several times, with fluctuating discontentment by
the mayor. This dispute had other effects as well:
- Within the participatory process in Windischeschenbach-Püllersreuth-Pfaffenreuth-
Seidlersreuth, planning occurred with two potential Southern end-points (both southern red
dots in map 4) that made both southern connections possible (see footnote 7).
- An additional informative event was organized by the TSO in the Southern municipality to
inform the population about the intermediary results of the planning process.
- The results of the alternative courses in Kirchendemenreuth were presented during the last
meeting of the planning group, as they are interconnected in certain respects, and were
presented at the final public event, to which (also a new feature) the population of
Kirchendemenreuth was invited as well.
8 Along with considerable other conceptual and practical problems.
16
In June 2015, in order to avoid that the process in Windischeschenbach-Püllersreuth-
Pfaffenreuth- Seidlersreuth would determine the course of the line in Kirchendemenreuth, or the
other way round, both variants in Kirchendemenreuth were merged with the variants that
resulted from the process in Windischeschenbach-Püllersreuth-Pfaffenreuth- Seidlersreuth. That
happened in agreement with the planning group. The results were six main alternative courses
of the power line to be. These are considerably more variants than the TSO initially envisioned
as a result of the participatory process. Six variants are also more than the regulatory body
reviewing these variants in the subsequent regulatory procedure had hoped to have to review.
However, after having observed the public participation process, the responsible government
agency accepted the additional work as a result of more deeply involving citizens and other
actors than usual.
The impact of the participatory space on the participatory process as a whole
The detailed description of the processes that shaped the participatory space demonstrates how
actors exert different types of influence on this core element of participatory processes. The next
step consists of discussing how these influences significantly impacted, in turn, the participatory
process as a whole. More examples could be found, but two of them may offer an idea:
1. Citizens were encouraged in various events to pencil in proposals for variants they preferred.
As already described, the participatory space was adapted in parts accordingly to these
proposals. This adaptation had an important effect. Some citizens drew new alternative courses
that went beyond the borders of the space the TSO had anticipated for examination by
environmental planners. Those proposals could not have been compared properly to variants
running through pre-examined areas without the collection of additional data by the
environmental planners. Initially, the TSO planned to have the participation processes end in
March of 2015, in order to stay in schedule with the planning of the project overall. However, the
collection of additional data became necessary to secure a proper participation process. At the
beginning of 2015, the environmental planners were assigned to collect the necessary data.
However, as important in-field research information was unattainable in winter, the expansion of
the participatory and planning space together with the timing of the data collection resulted in
considerable delay in the process of three months. The new end of the participatory process was
set for June 2015 by the initiators. This schedule was set due to a number of time pressures
existing for the TSO and for the researchers, but imposed immense pressure on the
environmental planners, on the preparation of the results of the participatory process and on the
submission of the documentation to the regulatory authority. It also affected a quick succession
of planning group workshops and public events in both participatory processes, with four events
in 18 days in two different cities. This posed a risk to the quality of the participation process. The
tight schedule resulting from this delay also diminished the amount of influence citizens were
able to exert in the public closing events. Due to time constraints, the mechanism for feedback
on the results had to be more restrictive than initially planned. While the initial plan was to
include the multitude of feedback in an appendix to the documents presented to the regulatory
body, under these new conditions the feedback mechanism became reserved for comments that
17
fundamentally challenged the feasibility of a variant. Instead the closing event focused on
informing participants how to insert their comments and requests in the subsequent formal
regulation procedure. Even though the results were already thoroughly vetted by the process
overall, this example shows how changes within the participatory space, lack of specific
information at a certain point in time and resulting time pressure reduced the citizens’ ability to
have an active say on the final results.
2. Since the second participation process in Schwandorf had started, the participation space – or
rather the planning space - was contested. Due to preliminary assessments about infeasibility of
an Eastern circumvention of the urban center of Schwandorf, the TSO decided to restrict the
participatory space to the Western part of the city areal including all Western villages in the
municipality. However starting with the first event of the participatory process, some participants
questioned this decision and argued for an inclusion of the Eastern side of the city into the
planning and participation space. The TSO didn’t comply with this request, with the
argumentation that there were clear hindrances in this part of the city that would have not
allowed creating competitive variants for the new course of the power line. After the mid-point of
the participatory process, a citizen initiative established itself centering on the goal to lobby for a
course to the East of the city. The TSO reacted to this development by inviting the members of
the citizen initiative to partake in the participatory process. The TSO also assigned its
environmental planners to assess an alternative course in the east and to evaluate its feasibility.
However, being almost at the end of the process, these steps had to happen very quickly,
including coming up with an Eastern variant. Therefore, the variant assessed was not a result of
critical citizens’ local knowledge, but a proposal by the environmental planners contracted by the
TSO without the involvement of citizens. Additionally, the evaluation of this alternative course
had to happen on the basis of the available data, which were incomplete. The variant used to
demonstrate the problems of an Eastern circumvention consequently never was accepted by the
members of the citizen initiative or, ostensibly during the closing public event, a large number of
other citizens. Nor was the assessment by the environmental planners on the disadvantages of
an Eastern variant. Together with a couple of other topics, the issue of an Eastern alternative
took up the whole final event, with the concrete results on the other variants that had been
developed by citizenry of Schwandorf being intentionally disallowed time. A couple of weeks
after the final public event, a second citizen initiative was founded and claimed an Eastern
variant as a goal, too.
This development is in stark contrast to how the views on the work of environmental planners
contracted by the TSO developed in Windischeschenbach, where the circumstances allowed the
environmental planners to gain trust in their work despite them being contracted. In Schwandorf,
however, because Eastern variants were not vetted publicly and transparently through the
participation process, the argumentation of the TSO and the environmental planners basically
came down to an appeal to trust them. In an already heated atmosphere, this did not suffice.
The damage resulting from the dynamic unfolding over a restriction of planning and participatory
space was impossible to reel in at this point.
18
3. A context-sensitive and process-oriented perspective – cornerstone of understanding participation processes as multi-faceted social phenomena
The previous section described how the question of whom to include in the participatory process
has developed across the whole duration of the participatory process in Windischeschenbach
and Schwandorf. It also discussed how changes related to participatory spaces had relevant
influences on the course and results of the participatory processes themselves. In the present
section we intend to situate these empirical findings in the larger framework of our proposal for
examining participatory processes as multi-faceted social phenomena through a context-
sensitive and process-oriented perspective. We believe that this analytical perspective can shed
light on elements and dynamics that heavily influence the planning and the course of
participatory processes and that research so far has rarely addressed. Against the backdrop of
our experiences as co-initiators of participatory processes, we hypothesize that no core element
of those processes can fully be understood without taking into account how they emerge from
the interaction of actors and contextual factors through time. To take this into account we
describe and discuss in the following section the main pillars of such a context-sensitive and
process-oriented perspective on public participation.
Integration of temporal dynamics
A process-oriented perspective integrates temporal dynamics into the analysis of participatory
processes as social phenomena. Such analysis presupposes continuous data collection, but in
return allows a detailed tracking of developments throughout the phases of any process,
including the planning process. It helps to understand why a participation process design has
taken the shape it has, and sheds light on why interactions within the participatory process have
unfolded as they have. Considering the example of the participatory space, a process-oriented
perspective can for instance explain how actors criticizing participatory spaces have had diverse
impacts on the space due to their timing in the process or how the systemic tendency for
continuously enlarging participation spaces has been negotiated with initiators’ concerns for
feasibility throughout the process. It allows capturing how the enlargement of participatory and
planning space has – via scarcity of time available to cope with its ramification – had effects on
other core elements such as the nature of the closing public event or the quality of the
documents available to the planning group.
Additionally, a process-oriented perspective is able to capture unsuccessful attempts by actors
to exert influence, ideas not being followed through and other aspects, which are not revealed
when looking at the final form of the participatory process or its results. In our case, such
aspects proof to inform our understanding of citizen participation, its actors and their motives
and concepts nevertheless.
A process-oriented perspective helps to improve the description of why and how time is an
important factor for conceptualizing participation processes. The value of a process-oriented
19
perspective in this regard lies not merely in identifying matters of timing, contradicting time
regimes, different time horizons or strategies to take control of time as relevant for public
participation. Moreover it lies in detailing the interplay of these factors with each other and other
aspects of the phenomenon.
Sensitivity for contexts
Within our analysis of the participatory space, we came across several contextual factors which
considerably influenced the way this participatory process was planned and implemented. As
studies show context proves to be relevant to design, outputs and outcome of participatory
processes (i.e. Drazkiewicz et al. 2015; Beierle/Cayford 2002). In our case context factors as
well played an important role: Insecurity about specific regulation of planning criteria (i.e. how to
assess a variant bundled with the existing line vs. bundled with other infrastructure vs.
unbundled) left its mark on the early stages of the participatory process, as did its concretion and
changes to regulation later on in the process.
In our case, changing contextual factors proved to be of great relevance. Factors such as
rumors about federal plans to put another new high voltage transmission line in the same region
entered into both participatory processes at various moments. They posed repeatedly questions
to the initiators of how to accommodate such developments and thereby to preserve a fitting
between participatory process design and its surrounding conditions, but without breaching
commitments already made about the process and its design. These examples outline how
different contextual factors receive significance at different points in time, and might be changing
in nature and relevance in the course of a participatory process. They therefore cannot be
considered as merely pre-existing input-factors informing the process design before
implementation.
Focus of the analysis under a context-sensitive perspective ** ideally the analysis would cover the whole outcome phase
INPUT PROCESS OUTPUT/
OUTCOME
Contextual factor 1
Contextual factor 2
Contextual factor 3
20
The interplay of actors
Various parts of the case study highlighted another significant aspect: Dynamics and contextual
factors highly depend on the presence, absence and actions of actors. Arguing for a focus on
participatory processes as multi-faceted social phenomena, the multitude of actors and how they
are positioned in regard to the participatory process is a central factor. Various actors’ belief
systems, interests and constraints for action are influencing the course of participatory
processes. In return, the interplay of actors is influenced by a participatory process and its core
elements such as the participatory space.
The description of the development of the participatory spaces’ borders has exemplified a series
of moments where different actors such as the team of researchers, the staff of the TSO, mayors
and administrative authorities significantly shaped the design and steps to be taken within the
process. As we have shown, researchers and the TSO were in constant negotiation over the
shape of the participatory space, being led by different interests, normative concepts and other
factors. Once local actors started to interact within the participatory process, they exerted
considerable influence on the design of its core elements as well.9
More examples could be provided. In all of those examples, timing as well as inclusion of the
multitude of actors (and the quality of their inclusion) demonstrated to be key. It highlights that
participatory processes are configured powerfully through those emerging dynamics as well as
through initial design.
9 Initiating round tables between the TSO and mayors, influencing the agenda of upcoming events,
deciding which steps in the assessment of the impact of proposed lines needed which intensity of scrutiny.
The interaction of actors with the context factors ** ideally the analysis would cover the whole outcome phase
INPUT PROCESS OUTPUT/
OUTCOME
Contextual factor 1
Contextual factor 2
Contextual factor 3
Actor 1
Actor 2
Actor 3
21
Our described examples highlight the fact that the act of planning participatory processes relates
to various questions of power. The significance to integrate the interactions of actors in an
analysis of participatory processes as multi-faceted social phenomena, including a focus on
individual motives and interests, their belief systems and power over the process, is self-evident.
Considering everything we have been arguing, it also seems prudent to understand the act of
planning as just as integral to the phenomenon in question as the participatory process itself.
4. Implications for research and practice
Understanding participatory processes as multi-faceted social phenomena, including a context-
sensitive and process-oriented approach to participation, provides implications for research as
well as practice. Such a perspective raises sensibility for the relevance of the dynamics of public
participation.
Instead of, for example, analyzing the effectiveness and efficacy of methods and formats for a
certain theme or evaluating only a given moderated process from beginning to end, such a
context- and process-oriented approach would take a much broader view on participation: It
takes into account the phase of preparing a participatory process as well as the phase of
impacting actors (and a given community) after a certain process. It also would cautiously look at
the levels of information, motives, interests, idiosyncracies and interactions of all actors involved
and the specific composition of political actors and decision-makers.
The analysis of the role of the participatory space in a participatory process shows that
fundamental aspects such as a) questions of who is entitled to participate and who is excluded
and b) the (geographical) area of influence of the participants' proposals are constantly
negotiated during the participatory process, not only in the input phase as proposed heuristics
for evaluating participation suggest. Such negotiations are altering the criteria that define the
participatory space throughout the entire process. Without applying a process-oriented
perspective the evolution of the participatory spaces would remain opaque. For scientific
evaluations this poses a) the questions on which contextual factors to take into account and b)
how the involved actors are dealing with the given and changing contextual factors. Especially
the last point implies a more actors-centered approach that focuses more generally on the
interactions between the involved actors as well as in more detail on the actual power of certain
players, their belief systems, interests and conditions for acting (such as temporal constraints)
that implicitly and explicitly guide their actions to influence the participatory process (the TSO,
scientists and participants involved).
For the practice of planning, such a perspective draws attention to the setup of planning
procedures and constellations of initiators and the kind of setting most able to cope with the
outlined challenges. The kind of iterative planning approach seems prudent that from the
beginning envisages necessary adaptations of core elements of the process (for example,
participatory spaces) as well as the planning structures and constellations themselves. Such an
22
approach would take into account that planning does not end with the implementation of the
process, the first event of the participatory intervention, but rather accompanies it throughout.
5. References
Abelson, J. and F-P. Gauvin 2006, Assessing the Impacts of Public Participation: Concepts,
Evidence and Policy Implications. Research Report P|06, Public Involvement Network.
Bauriedl, S., Baasch, S., Rau, I., Kropp, C. and A. Knierim 2013, „Konzeptionelle Überlegungen
zum Betriff „Betroffenheit“ in der sozialwissenschaftlichen Partizipationsforschung.
Diskussionspapier, in Knierim, A., S. Baasch, M. Gottschick (eds.) Partizipation und
Klimawandel. Ansprüche, Konzepte und Umsetzung, Klimawandeln in Regionen
zukunftsfähig gestalten, 1 oekom: 121-130.
Behringer, J. 2002, Legitimität durch Verfahren?: Bedingungen semi-konventioneller
Partizipation: eine qualitativ-empirische Studie am Beispiel von Fokusgruppen zum Thema
"Lokaler Klimaschutz. S. Roderer Verlag, Regensburg.
Beierle, T. and J. Cayford 2002, Democracy in Practice, Public Participa-tion in Environmental
Decisions. RFF Press Book, Washington.
Bohner, G. 2003, “Einstellungen”, in Stroebe, W., K. Jonas, M. Hewstone (eds.)
Sozialpsychologie. Eine Einführung, Heidelberg, Berlin, Springer: 266-315.
Iterative planning approach
INPUT
PROCESS
OUTPUT/
OUTCOME /
IMPACT
Adaptation of
the design of
the
participatory
process
Contextual factor 2
Actor 2
23
Delli Carpini, M., F. Lomax Cook and L. R. Jacobs 2004, “Public Deliberation, Discursive
participation, and Citizen Engagement: A Review of the Empirical Literature”, in: Annu.
Review Political Science 7: 315–44.
Dienel, P. C. 1978, Die Planungszelle. Der Bürger als Chance. Verlag für Sozial-wissenschaften,
Wiesbaden
Drazkiewicz, A., Challies, E. and J. Newig 2015, “Public participation and local environmental
planning: Testing factors influencing decision quality and implementation in four case studies
from Germany”, in Land Use Policy 46: 211–222.
Esterling, K. et al 2010, The Difference that Deliberation Makes, Evaluating the »Our Budget,
Our Economy« Public Deliberation, Preliminary analysis America Speaks, Our Budget, Our
Economy. See
http://www.archonfung.net/docs/articles/2010/AmericaSpeaksPrelimAnalysis_finalAF.pdf, last
access on 31.07.215.
Gastil, J., Knobloch, K. and M. Kelly 2007, “Evaluating Deliberative Public Events and Projects”,
in Nabatchi, T., Gastil, J., G.M. Weiksner and M. Leighninger (Eds.) Democracy in Motion.
Evaluating the Practice and Impact of Deliberative Civic Engagement. University Press,
Oxford: 205-230.
Geis, A. 2005, Regieren mit Mediation: Das Beteiligungsverfahren zur zukünftigen Entwicklung
des Frankfurter Flughafens. VS Verlag, Wiesbaden.
Gergen, K. J. 2003, “Action Research and Orders of Democracy”, in Action Research 1/1: 39-56.
Kamlage, J.-H. 2013, „Dialogorientierte Verfahren der Bürgerbeteiligung in lokalen Konfliktfällen.
Wirkungen des Tunneldialogs in Schwäbisch Gmünd“, in pnd online 2/2013, see
http://www.planung-neu-59denken.de/images/stories/pnd/dokumente/2-3_2013/kamlage_jan-
hendrik.pdf, last access on 31.07.2015.
Kamlage, J.-H., Richter, I. und P. Nanz (forthcoming), „An den Grenzen der Bürgerbeteiligung.
Dialogorientierte Bürgerbeteiligung im Netzausbau“, in Ratke J. and Holstenkamp L.
(eds.) Energiewende und Partizipation - Transformationen von Gesellschaft und Technik,
Springer VS.
Mandarano, L. A. 2008, “Evaluating Collaborative Environmental Planning Outputs and
Outcomes: Restoring and Protecting Habitat and the New York-New Jersey Harbor Estuary
Program”, in Journal of planning education and research 27/4: 456-468.
Newig, J. and O. Fritsch 2009, “More Input - Better Output: Does Citizen In-volvement Improve
Environmental Governance?”, in Blühdorn, I. (ed.), In Search of Legitimacy. Policy Making in
Europe and the Challenge of Complexity. Barbara Budrich Publishers, Opladen/Farmington
Hills, 205-224.
Ortweil, W. 2001, Planungszellen - Bürgergutachten »Neuss-Innenstadt 2010« Kommunikation
und Beteiligung bei Verkehrsprojekten: Beschleunigung oder Behinderung?. Fachkongress,
28. und 29. September 2000 in Wuppertal (p. 168-183). DVWG, Bergisch Gladbach.
The participedia project, www.participedia.net.
24
Reason, P. & Bradbury, H. 2008, The Sage handbook of action research. 2. Aufl. London:
SAGE.
Rowe, G. and L. J. Frewer 2004, “Evaluating Public-Participation Exercises: A research
agenda”, in Science, Technology, and Human Values, 29/4: 512-557.
Schicktanz, S. and J. Naumann (eds.) 2003, Bürgerkonferenz: Streitfall Gendiagnostik: ein
Modellprojekt der Bürgerbeteiligung am bioethischen Diskurs. Opladen, Leske und Budrich.
Schneider, S. 2011, Bürgerhaushalt Oldenburg. Evaluationsbericht, Dokumentation, see
http://www.oldenburg.de/fileadmin/oldenburg/Benutzer/PDF/20/Buergerhaushalt/2010_Evalu
ationsbericht.pdf, last access: on 31.07.2015
ÜNB (2013): Netzentwicklungsplan Strom 2013. Zweiter Entwurf der Übertragungsnetzbetreiber.
Strele, M.K. 2012, BürgerInnen-Räte in Österreich, Gemeinsames Forschungsprojekt des
Lebensministeriums und des Büros für Zukunftsfragen, see
http://www.vorarlberg.at/pdf/endberichtforschungsproje.pdf, last access on 31.07.2015.
Taubert, N., Krohn, W. and T. Knobloch 2011, Evaluierung des Kölner Bürgerhaushalts. Kassel
University Press, Kassel. Telekommunikation und Gesellschaft 1999, Heidelberg, p, 51-61.
Warburton, D., Rainbow, E. and R. Wilson 2006, Making a Difference: A guide to evaluating
public participation in central government, see http://www.involve.org.uk/evaluation-guide/
2006, last access: 31.07.2015.
Weidner, H. and H.-J. Fietkau 1995, „Umweltmediation. Erste Ergebnisse aus der
Begleitforschung zum Mediationsverfahren im Kreis Neuss“, in Zeitschrift für Umweltpolitik
und Umweltrecht 18: 451-480.