  • 7/29/2019 Plant Assessments

    1/10

    Emerson Process Management - CSI

    DoctorKnow Application PaperTitle: Plant Assessments

    Source/

    Author:

    1997 Reliability Week Paper

    Product: GeneralTechnology: Vibration

    Classification:CSI Services holds the belief that the maintenance organization is a value added function and, in

    fact, produces a product. That product is reliability.

    Historically, maintenance has been categorized as a cost center and considered a "necessary evil."

    Most of the attention is focused on production with cost cuts typically affecting the maintenance

    department. Only recently has the awareness increased to the point where companies realize that

    improvements to the maintenance function may significantly improve the bottom line.

    Although incremental changes can produce improvements, significant increases in availability,

    capacity, and profit require a structured approach. In order to effectively create the "road map" to

    improvement, one must first determine where to start. CSI provides an assessment service that

    evaluates the maintenance function as it relates to entire organization. That information is then

    used to develop a plan by which the company can move toward benchmark status.

    Depending on the size of the facility, the assessment process will typically involve two

    management consultants from CSI that visit the facility for four to five days. The compiled datawill result in a report that contains an executive overview, a summary of the observations,

    strengths and "opportunities for improvement" in each category, recommendations for

    improvement, an implementation plan and schedule, and appendices containing support

    information.

    The Assessment covers five keys areas:

    (1) Reliability Programs

    s Predictive Maintenance Program (PdM)

    s Preventive Maintenance Program (PM)

    s Proactive Maintenance

    s System/Equipment Reliability Prioritization (RCM/SERP) Plant Material

    Condition

    (2) Work Management

    s Management involvement, support and culture

    s Organization

    http://www.compsys.com/DRKNOW/APLPAPR.NSF/ap...3D232D9B83FEB3D852565A2005F12FB?OpenDocument (1 de 10)05/07/2010 16:41:14

  • 7/29/2019 Plant Assessments

    2/10

    Emerson Process Management - CSI

    s Planning and Schedulings Use of Management Information Systems

    s Effectiveness of Work Control (Screening & authorization of work; use of

    s Work Requests

    (3) Work Execution

    s Work practices including Emergency Work Procedures

    s Procedures (Adequacy/compliance)

    s Contract Maintenance

    s Document control

    s Material control

    (4) Training

    s Skills assessment & developments Job descriptions

    s Awareness training needs

    s Training facilities

    (5) Performance Monitoring & Assessment

    s At the plant, system & component level

    s Goals & Objectives

    s Selection & use of Indices

    s Reports, Tracking & Trendings Overall Effectiveness

    PLANT ASSESSMENTS

    (General category descriptions and selected excerpts)

    The following pages offer general descriptions of the five primary categories and contain brief

    examples extracted from a typical assessment. A full assessment provides specific strengths,

    opportunities for improvement, recommendations, and implementation steps for all twenty-four

    evaluation criteria. Additional concentration on specific issues can be performed at the customer's

    request. All collected data, discussions, and written and verbal reports are considered confidential.

    Based on hundreds of assessments over several years, the final report has developed into a

    structured format that clearly and concisely identifies the key issues. The report is divided intoseveral sections, including:

    an Executive Overview with observation summaries Strengths and "Opportunities for

    http://www.compsys.com/DRKNOW/APLPAPR.NSF/ap...3D232D9B83FEB3D852565A2005F12FB?OpenDocument (2 de 10)05/07/2010 16:41:14

  • 7/29/2019 Plant Assessments

    3/10

    Emerson Process Management - CSI

    improvement" in each category with Recommendations for improvement in each category an

    Immediate Action Plan and schedule Appendices containing support information

    I. EXECUTIVE OVERVIEW

    The executive overview is a cover letter that hits the highlights of the assessment process. It

    contains the basic information pertaining to the plant, provides a synopsis of the findings in each of

    the five categories, and contains the benchmark rankings. The following paragraphs provideexcerpts of the executive overview.

    EXCERPT:

    A Plant Assessment was conducted at the Speciality Products Division on June 18-21 by CSI

    Services. The primary purpose of the assessment was to evaluate the Maintenance Program. The

    results of this assessment are included herein. We wish to thank you for the excellent assistance in

    setting up interviews, the plant tour, and providing us a better understanding of the needs at the

    Austin Division.

    The Plant Assessment covers five major areas as delineated in Appendix A. 'Strengths "and

    'Opportunities for lmprovement" are noted for each area. Recommendations will be noted in

    'Opportunities for Improvement." The Recommendations for immediate action are covered in

    Appendix B. We have included additional information, as requested, to ensure adequate

    implementation of the recommendations. This additional information is listed in the Table of

    Contents and described in the attached text.

    In general, we were impressed with the enthusiasm of your maintenance workforce. The ability of

    maintenance to respond to emergency work requests appears to be excellent. The plant has been

    running very well-evidenced by the yield rate in excess of 93%. On the other hand, we noted that

    the maintenance process is highly "reactive, "with an estimated 70% of unplanned work. This

    '"reactive "environment is placing a burden on the maintenance workforce and it is keenly felt at all

    levels.

    The following is a short synopsis of the five areas covered in the attached report:

    (1) Reliability Programs - The Preventive Maintenance procedures represent a good start toward

    consistently planned Maintenance activities. However, the tasks are not "hard-lined' on a scheduleto ensure their completion. Many PM's are performed by contractors. These tasks have not been

    reviewed for appropriateness or adequacy. The procedures should include data collection and

    accountability measures. A start has been made in Predictive programs with...

    (2) Work Management - Plant management is seen as a plus by all interviewed. However, workers

    in Maintenance and Operations felt the processes were not conducive to efficiency. Work is

    conducted in a totally reactive environment. Work prioritization changes constantly, and

    interruptions are the rule. A few key PM's are scheduled and completed, but everything else is

    accomplished on a situational basis. There is no planning on a daily basis, although...

    (3) Work Execution - The constant stream of changing priorities and interruptions lowers the

    effectiveness and percentage of direct work activities. There are a high motivation and strong work

    http://www.compsys.com/DRKNOW/APLPAPR.NSF/ap...3D232D9B83FEB3D852565A2005F12FB?OpenDocument (3 de 10)05/07/2010 16:41:14

  • 7/29/2019 Plant Assessments

    4/10

    Emerson Process Management - CSI

    ethic present in the Maintenance craft. However, skill levels are not adequate in all cases, due to

    the lack of a comprehensive training plan. There is no culture for ...

    (4) Training -A program is in the offing, but is stalled in place. No job descriptions or progression

    path exists for Maintenance workers. Skills are lacking in key areas, and efforts are being made to

    address this issue. The scheduling of...

    (5) Performance Measurement - The key indicator is yield, and it is tracked in detail. But, little isknown about individual machine performance. Scheduled/non-scheduled Maintenance is tracked

    indirectly through Line A downtime, but not comprehensively for all of maintenance. Budget

    adherence is also tracked. Maintenance process performance is...

    Overall, we graded these five areas against Benchmark Reliability Based criteria. Your scores:

    Reliability - 2%

    Work Management - 13.5%

    Work Execution - 4%Training- 18.9%

    Performance Measures - 27.6%

    Overall - 9.8%

    This places you in the bottom quartile. We believe that you have the attitude and willingness to

    make changes that will result in rapid improvement. Some of your initiatives need implementation

    processes to make them work - such as the procedure project. The following attachment will breakdown the assessment into categories, with findings and recommendations for each category. Then,

    a timetable for implementation of key recommendations will give you a course to chart future

    actions. We are available at any time to assist you with any of these activities.

    II. STRENGTHS AND OPPORTUNITIES FOR IMPROVEMENT

    This assessment section would break out each of the five primary categories into their component

    parts. Each contributing component is discussed in terms of the strengths noted and theopportunities for improvement. The following provides a brief description of each of the

    categories. For illustrative purposes, some excerpts are provided as examples.

    (1) Reliability Programs - It is estimated that only 4% of all plants are taking substantive action in

    this area. This is the most crucial step to benchmark status. Areas covered here include:

    s Predictive Maintenance Program (PdM) - Vibration Analysis, Infrared

    Thermography, Tribology, Motor Current Analysis, Balancing, Precision

    Alignment, etc.

    s Preventive Maintenance Program (PM) - PM or, Interval-Based Maintenance,

    is not an effective tool when employed by itself. Usually too many PM tasks

    http://www.compsys.com/DRKNOW/APLPAPR.NSF/ap...3D232D9B83FEB3D852565A2005F12FB?OpenDocument (4 de 10)05/07/2010 16:41:14

  • 7/29/2019 Plant Assessments

    5/10

    Emerson Process Management - CSI

    are prescribed based upon vendor recommendations. However, coupled with

    PdM and Proactive maintenance it is highly effective.

    s Proactive Maintenance - The philosophy of Proactive Maintenance is that

    failures are never accepted as the norm. Proactive plants strive to eliminate

    the need for maintenance. This utopian state-of-affairs is never reached but

    many benchmark plants have eliminated 75% or more of their previous

    reactive maintenance activities. The foundation for Proactive Maintenance is

    a disciplined, formal Root Cause Failure Analysis (RCFA) Program.s System/Equipment Reliability Prioritization (RCM/SERP) - A fundamental

    precept in RBMTM is to ensure that the right equipment is getting the

    attention. Most plants simply take vendor's recommendations and apply them

    as PM tasks. This is highly ineffective and a vast waste of resources. A SERP

    will provide a prioritized list of "critical" equipment; i.e., that equipment

    responsible for plant availability, safety, environmental impact, and high

    maintenance costs. This assists the plant in creating "Equipment Reliability

    Plans" to reach benchmark status.

    s Plant Material Condition - Current plant condition and recommendations forimmediate, as appropriate.

    EXCERPT:

    PREVENTIVE PROGRAMS

    a. STRENGTHS

    (1) Preventive Maintenance activities have been proceduralized. The procedures have been

    reviewed by the work group to insure they are practical and effective.

    (2) New personnel were involved in the development of the procedures -increasing their

    knowledge of the equipment, and involving them in the work process.

    (3) Essential PM activities are placed in a monthly chart, by their due date. The chart is

    followed by the group leads.

    b. OPPORTUNITIES FOR IMPROVEMENT:

    (1) The quality and applicability of PM's need to be reviewed. Many were evolved from

    vendor manuals, and may not have incorporated plant experience on the equipment. Their

    relationship to equipment reliability and failure is unclear.

    Recommendation: Perform an equipment prioritization and task selection based on failure

    prevention and mitigation. CSI refers to this process as System and Equipment Reliability

    Prioritization, or SERP.

    Based on the SERP, starting with the highest rated equipment, evaluate all PM activities.

    http://www.compsys.com/DRKNOW/APLPAPR.NSF/ap...3D232D9B83FEB3D852565A2005F12FB?OpenDocument (5 de 10)05/07/2010 16:41:14

  • 7/29/2019 Plant Assessments

    6/10

    Emerson Process Management - CSI

    Ask why the task is being performed - is it defending against a failure, or prolonging

    equipment life ? Can Predictive techniques be used to direct performance, or avoid the PM

    entirely? Can multiple activities be combined? Is the PM cost effective ?

    (2) Many PM's on Line A are not being performed in a timely manner. They get delayed or

    prolonged, which forces a backing up of tasks, and puts the machines out of commission for

    an extensive period. (Quartz cleaning is delayed, resulting in the quarterly and semiannual

    PM backing up.) The PM program lacks direction and control.

    Recommendation: Place all PM's into the monthly schedule and track compliance. Do not

    allow tasks to be deferred or extended without management review.

    (2) Work Management - Determining the "right work to do" is of little value if it is not

    properly planned and executed. All CSI recommendations are focused on improving the

    maintenance/reliability function with a target of less then 2070 reactive. The skills are

    evaluated in the following areas with specific recommendations for improvements, as

    appropriate:

    Management involvement, support and culture

    Organization

    Planning and Scheduling

    Use of Management Information Systems

    Effectiveness of Work Control (Screening &authorization of work; use of Work

    Requests

    EXCERPT:

    WORK CONTROL

    a. STRENGTHS

    (1) The maintenance director's staff is fully capable and eager to enhance this process.

    b. OPPORTUNITIES FOR IMPROVEMENT

    (1) The work order "Failure Cause Codes "are routinely not filled out. This makes it very difficult

    to assess past equipment failures and hampers the continuous improvement process. In addition, in

    order to facilitate a computerized equipment "failure trending "process, the Cause Codes need to be

    revised to include the degree of equipment failure; i.e., partial or total.

    Recommendation: Revise the Cause Codes as described in Appendix C. This should not be

    difficult to do. All mechanics need to be told the importance of providing this information to the

    ERIG/group responsible for assessing program performance.

    (2) Work orders are not:

    http://www.compsys.com/DRKNOW/APLPAPR.NSF/ap...3D232D9B83FEB3D852565A2005F12FB?OpenDocument (6 de 10)05/07/2010 16:41:14

  • 7/29/2019 Plant Assessments

    7/10

    Emerson Process Management - CSI

    sorted by equipment (1470 &PM's) o screened to determine if RCFA is appropriate o

    screened for adequacy of current PM's o scheduled o assessed for feedback to the

    PdM program (how good was the call to take equipment down for maintenance ?)

    Recommendation: Prioritize systems and equipment as earlier described in the SERP process. Take

    the top 20%, based on the MPI (Maintenance Priority Index), and perform condition assessments.

    Address the Root Cause. Provide training (as described in Section 5 - Training) on both RCFA andprocedural compliance. The new CMMS will help immensely on the planning and scheduling

    aspects.

    (3) Operations keeps informal lists (white boards, etc) of work to be done. When equipment

    outages are ordered, maintenance is sometimes not prepared to do the work (lack of spares, etc).

    Recommendation: It is strongly recommended that operations fill out work requests on all known

    deficiencies all the time (culture). Management will not be able to fully assess plant reliability

    unless all problems are known. Once this is done, a computer generated report will be available tomanagement. This report can be sorted by process, by equipment or by area.

    (4) Too much work is being initiated over the telephone.

    Recommendation: Consider implementing a central dispatch system. Limit all calls to true

    emergencies.

    (5) Too much emphasis on maintenance cost. There are entirely too many sign-offs required to

    implement the maintenance process. This wastes valuable management time as well asmaintenance staff time in insuring all forms/signatures are obtained. For example, a work request

    needs multiple signatures to be authorized (should be just the originator plus applicable foreman

    unless job to be done as a project). Once it becomes a Work order, multiple signatures are again

    required, including:

    o if cost of W.O. exceeds 10% of estimate, additional sign-offs required. o if a requisition exceeds

    $3000, additional sign-offs required. o if cost of W. O. less than $5000, 4 sign-offs required o if

    cost of W.O. $5000-$10000, add Department head o if cost of W. O. greater than 1O, 000 add

    Director O&M, etc...

    Recommendation: Management should ask 'How many times has specific action been taken based

    on these reviews and sign-offs ? If the answer is, "seldom, "recommend scaling back substantially.

    As equipment reliability improves, costs will improve as well!

    REMAINING ASSESSMENT AREAS:

    (3) Work Execution - Benchmark plants ensure that their mechanics provide feedback to

    Reliability and Task planners so that the quality of all tasks is continually improved. CSI reviews:

    Work practices including Emergency Work Procedures

    Procedures (Adequacy/compliance)

    http://www.compsys.com/DRKNOW/APLPAPR.NSF/ap...3D232D9B83FEB3D852565A2005F12FB?OpenDocument (7 de 10)05/07/2010 16:41:14

  • 7/29/2019 Plant Assessments

    8/10

    Emerson Process Management - CSI

    Contract Maintenance

    Document control

    Material control

    (4) Training - The average age of America's workforce is in the 50's. Within 10 to 15 years, these

    highly skilled workers will be leaving the workforce. The training program is evaluated and the

    recommendations provide ways to transfer critical skills to the younger generation as well as

    upgrades to your existing program:

    Skills assessment & development

    Job descriptions

    Awareness training needs

    Training facilities

    (5) Performance Monitoring & Assessment - Management at benchmark plants realizes the value

    of solid programs as described above. However, the key to retaining "benchmark" status is throughContinuous Improvement. CSI provides the vital information on how to implement a topnotch

    Performance Monitoring & Assessment Program. This generally requires a "Paradigm" shift in

    culture and it takes several years to reach the top. The good news is, "it's worth every penny

    invested."

    At the plant, system & component level

    Goals & Objectives

    Selection & use of Indices

    Reports, Tracking & Trending

    Overall Effectiveness

    EXCERPT:

    GOALS AND OBJECTIVES

    a. STRENGTHS

    (1) Goals and objectives are defined and

    prominently displayed. Key indicators are

    customer delivery cycles and yield.

    b. OPPORTUNITIES FOR IMPROVEMENT

    (1) Additional key parameters should be monitored and

    tracked.

    Recommendation: Set up tracking and goals for

    maintenance cost per unit output, overtime, availability

    http://www.compsys.com/DRKNOW/APLPAPR.NSF/ap...3D232D9B83FEB3D852565A2005F12FB?OpenDocument (8 de 10)05/07/2010 16:41:14

  • 7/29/2019 Plant Assessments

    9/10

    Emerson Process Management - CSI

    (traceable to machine), percent of planned work, failure

    analysis, scheduling performance, and budget

    performance. Refer to Appendix E for specific

    calculations.

    III. IMMEDIATE ACTION PLAN

    The recommendations provide the specific steps for initial improvements. The plan is designed for

    long term improvements within a workable time frame.

    EXCERPT:

    Note: These have been placed into Gant chart form. See attachment. The sequencing and timing

    may have to be reviewed and "fine-tuned 'by your organization.

    1. Take away radios from technicians and have the shift lead carry the radio. This will forcerequests to be channeled through a single source. It will also allow the technicians to work the

    priority jobs uninterruptedly. (Eventually, the Work Order will become the only way to initiate

    work.) This should take place immediately, and about a month to totally implement.

    2. Initiate the Work Order Program. Continue with the Data Stream project to implement

    equipment codes. This project should complete by the fourth quarter. Write the Work Order

    process into a master plant procedure and train Maintenance and Production on it. The procedure

    should be completed by third quarter, with training complete early in the fourth quarter.

    3. Expand on the monthly schedule to include all PM's. Track adherence and ratio of planned to

    reactive work. Do this immediately, as the PM 's are known. Set up achievable goals for adherence

    - 40-50% at first, and keep improving. Eventually, adherence should be in the 90% range. The first

    goal should be achievable in the third quarter.

    4. Perform a SERP to obtain prioritization, then analyze for appropriate tasks. Begin this after the

    Work Order program has been implemented. (The end of the fourth quarter.) First develop a

    process procedure and train performers to it. You should be ready to begin prioritization of

    equipment in the first quarter of 1997. Two more quarters will be required to designate appropriate

    tasks. Additional time may be required if many new tasks are needed, or an extensive rework is

    needed on existing ones.

    5. Begin improving equipment reliability immediately. Get Operators, Maintenance, and

    Engineering trained on Root Cause Failure Analysis right away, through the end of the year. After

    equipment has been prioritized, identify the worst plant problems, prioritize them, and perform

    Root Cause Failure Analysis on the most pressing plant programs. This would take place the first

    quarter of 1997. The first action plan should be complete in the second quarter of 1997.

    IV. APPENDICES

    The appendices contain information that support the recommendations. Depending on the

    particular needs of the customer, the appendices may contain job descriptions, organizational

    http://www.compsys.com/DRKNOW/APLPAPR.NSF/ap...3D232D9B83FEB3D852565A2005F12FB?OpenDocument (9 de 10)05/07/2010 16:41:14

  • 7/29/2019 Plant Assessments

    10/10

    Emerson Process Management - CSI

    charts, detailed implementation schedules, specific performance calculations, example procedures,

    process flows, recommended training, and reference sources.