please comply with the lean construction institute’s usage ... · lean / vdc for fast track...
TRANSCRIPT
Please comply with the Lean Construction Institute’s Usage Policies and Attribution Guidelines at http://www.leanconstruction.org/usage.pdf
when using this file. Thank you.
1
Digital Design and FabricationOpportunities of improving project design and delivery using Lean and VDC
Samir Emdanat, Director of Virtual Design and ConstructionGHAFARI Associates
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
Elements of Lean
People -> Process -> VDC
In other wordsStep 1: Build a team that believes in Step 2 and Step 3 and a culture of continuous improvement
Step 2: Use Value Stream Mapping to develop a deep and shared understanding of the current processes, (especially the information exchanges between processes) - create a shared vision of target ideal state.
Step 3: Implement process changes and appropriate VDC/automation to eliminate waste in internal processes and at handoffs and keep improving.
Automating an inefficient process accelerates the production of waste.
ALean
System
Peop
le
Technology
Process
2
Lean / VDC for Fast Track ProjectsAccelerated Schedule & 2D Paper Based Approach
Kick-offKick-off
DesignValidationafter Launch
Owner
Contractor
Fabricator
AE
Typical ProcessChangesRe-WorkChanges
Increased Rework
ProductionDelays
Virtual Build
Potential Time Savings
Lean / VDC Approach
Kick-offKick-off Production
Owner
Contractors
Fabricator
AE
Cost of FieldChanges
Design Construction
Design Construction
Manufacturing – 11 completed projects
3
Example: Lean / VDC Process (Steel)
Material Ordered
Material Delivered
CertaintyAbout Design
Certainty about
DetailingDetailing
Fabrication and Pre-
AssemblyJIT
Installation
Ideal State – Lean / Fully Automated Design to Fabrication Process
Steel is one of few building systems where a complete digital workflow from early design to completed fabrication is possible and through available industry standards and technologies.
Yet most projects are delivered using paper drawings.
Example: Lean / VDC Process (Steel)
Manual Material Take offs
Not enough time to
complete design
Detailing done before trade coordination
Late changes
Field changes
Handoff
Paper
Handoff
Paper
Handoff
Paper
Design DetailingShop
Drawing Review
Not enough time for
detailed shop drawing review
Fabrication Installation
4
Example: Lean / VDC Process (Steel)
Why it takes months to prepare and approve shop drawingsFA
BR
ICA
TOR
GC
/CM
ARC
HITEC
T
EN
GIN
EE
R
ARC
HITEC
T
GC
/CM
FAB
RIC
ATO
R
DETAILER
FAB
RIC
ATO
R
DETAILER
~20 days -hand offs
ReviewSubmittal ~15 days -hand offs
Corrections
5
Collision-Free
Target for 80% Clash-FreeProcess Systems Added Steel Detailer’s Model
Certainty: Other Disciplines Design to Fab Workflow
Start 3D Detailing as soon as possible but not before main member design has
completed
Complete all discipline coordination before
steel detailing is completed.
Lean & VDC Results (Manufacturing)
Mill order from 8-14 weeks down to 3 weeks on first project (8 days on later project ~4000 tons).
Shop drawing review time from 10 days to 1 Day (fully in 3D – no paper)
No changes during construction
Early finish (35 Days early) for steel erection
Early finish 27% overall schedule
Steel DetailingBidding – Steel FabricatorDesign/Analysis
A/E Phase
Steel Fabrication, Erection
Shop Drawing Review
Drawings / CDs
Steel Detailing, Fabrication, Erection
Mill Order 8-14 Weeks (Typical)
Steel Mill Order within 3 Weeks (breakthrough using VDC on top of a lean process)
6
Healthcare Integrated Project Delivery
Key project stake holders sign a single contract.
The contract requires:Early commitment to cost and schedule.Shared profit and shared riskUse of leanUse of VDC technologies
The contract does not specify how to get there.
Value Stream Mapping
7
Multi-Discipline Models to Inform Structural Pkg
Real-time Information Access from Multiple Locations
8
Some Early Results 230,000 sqft hospital
Avoided major late changes to early steel/foundation package (e.g. stairs, elevators, corridor widths)
Completed structural design in 8 months
Reduced overall time from start of design to OSHPD approval on first package by 50%
Resolved hundreds of multi-discipline coordination issues early in design.
On track for 3D model based steel shop drawing reviews (no paper).
On track to eliminate MEP submittals.
Made significant progress on model-based estimating
Overall PRE con costs did not increase (tracking less than original baseline).