please note that this entire project was a ... - civil · project was a completely academic...
TRANSCRIPT
PLEASE NOTE THAT THIS ENTIRE PROJECT WAS A COMPLETELY
ACADEMIC EXERCISE.
THIS PROJECT IN NO WAY REPRESENTS THE OPINIONS OF
ITRANS OR THE MTO
PREAMBLE1
P R O J E C T S P O N S O R : I T R A N S C O N S U LT I N G I N C
J O S E P H A R C A R O , P. E N G , A V S
F A C U LT Y A D V I S O R : R Y E R S O N U N I V E R S I T Y
D R . S A I D E A S A , P. E N G
C A P S T O N E P R O J E C T T E A M :
P O O R YA B A YA N I
B E R N A R D J A M E S
S A A D S Y E D
J A N U A R Y 1 4 , 2 0 1 0
HIGHWAY 404 AND16TH AVENUE INTERCHANGE
RECONSTRUCTION2
PRESENTATION SUMMARY
A) Proposal Writing and Winning the Project
B) Preliminary Study Report
C) Preferred Alternatives Report
D) Preliminary Design Report and Drawings
E) Conclusions
F) Lessons and Thoughts
3
PRESENTATION SUMMARY
A) Proposal Writing and Winning the Project
B) Preliminary Study Report
C) Preferred Alternatives Report
D) Preliminary Design Report and Drawings
E) Conclusions
F) Lessons and Thoughts
4
PROBLEM DEFINITION
Existing Traffic Congestion Minimal Pedestrian options
and no Cyclist Options on 16th Avenue
No current use of HOV Lanes to Encourage Carpooling
Assumed Year of Construction 2022
Assumed End of Life Cycle for Highway Pavements
PROJECT SCOPE6
PROJECT OBJECTIVES
Assess the need for change Determine the preferred
Interchange configuration to accommodate 10 lanes of traffic on Highway 404 and 6 lanes of traffic along 16th
Avenue Design the preferred
alternative Construction processes
including staging, cost and working days estimates
PROJECT SCOPE7
PROPOSAL REQUIREMENTS
Resources Available
Required
Software
Work Plan Work Breakdown Structure
Overall Time Budget
Project Schedule
Project Deliverables Technical
Physical
8
PROJECT OUTLINE
CREATION OF FIRM
SELECTION OF PROJECT
DEVELOPMENT OF PROJECT SCOPE
REVIEW OF BACKGROUND
REPORTS
IDENTIFICATION OF EXISTING
GEOMETRIC CONDITIONS
ANALYSIS OF EXISTING AND
FUTURE TRAFFIC CONDITIONS
JUSTIFICATION OF IMPROVEMENTS
GEOMETRIC DESIGN PARAMETERSESTABLISHMENT OF EVALUATION
CRITERIA
DEVELOPMENT OF ALTERNATIVE
SOLUTIONS
EVALUATION OF ALTERNATIVE
SOLUTIONS
SELECTION OF PREFERRED
ALTERNATIVE
DESIGN OF PREFERRED
ALTERNATIVE
CREATION OF PLAN AND PROFILE
DRAWINGS
DEVELOPMENT PRELIMINARY
COST ESTIMATE
CREATION OF TYPICAL SECTION
DRAWINGS
DEVELOPMENT OF WORKING
DAYS ESTIMATE
CREATION OF CONSTRUCTION
STAGING PLAN AND SECTIONS
CREATION OF GENERAL
ARRANGEMENT DRAWING
COMPILATION OF DRAWINGS
DEVELOPMENT PRELIMINARY
DESIGN REPORT
ADJUSTMENT OF PREFERRED
ALTERNATIVE
DEVELOPMENT OF PRELIMINARY
STUDY REPORT
ACCUMULATION OF GUIDELINES
AND MANUALS
GEOMETRIC DESIGN PARAMETERS
REVIEW OF LITERATURE
ESTABLISHMENT OF GEOMETRIC
DESIGN PARAMETERS
PROJECT START UP MEETING
9
PRESENTATION SUMMARY
B) Preliminary Study Report
Background Information
Creation and Evaluation of Alternative Solutions
11
BACKGROUND INFORMATION
Project Location
Project Constraints
Software Packages
Design Manuals
Existing Conditions
Traffic Analysis
12
BACKGROUND INFORMATION
PROJECT LOCATION
16th Avenue and Highway 404 Interchange
• Ontario
• York Region
• Boundary of Markham
• Boundary of Richmond Hill
PROJECT LOCATION
13
BACKGROUND INFORMATION
PROJECT CONSTRAINTS
• Commercial Property
• Rouge River Watershed
• Buttonville Airport
14
BACKGROUND INFORMATION
Autodesk Civil 3D 2008
Autodesk AutoCAD 2008
Microsoft Excel 2007
Microsoft Word 2007
Microsoft Power Point 2007
Microsoft Publisher 2007
Microsoft Project 2007
Highway Capacity Software 5.2
Google Earth 4.2
Adobe Acrobat CS3
SOFTWARE PACKAGES
15
BACKGROUND INFORMATION
MTO Geometric Design Standards for Ontario Highways (1985)
MTO Road Side Safety Manual (1993)
Ontario Bikeways Planning and Design Guidelines (1996)
Transportation Association of Canada: Geometric Design Guide for Canadian Roads (1999)
Highway Capacity Manual (2000)
Ontario Traffic Manual Book 7–Temporary Conditions (2001)
MTO Production Rates (2002)
MTO Working Days Estimating Guide (2002)
MTO Structural Manual (2003)
MTO Parametric Costs Estimating Guide (2006)
DESIGN MANUALS
16
BACKGROUND INFORMATION
TRAFFIC DATA AND ANALYSIS
• Existing conditions and LOS
• 2% growth rate (future volumes 2022)
• Justification of improvements for Future conditions
AM Peak Period PM Peak Period
18
BACKGROUND INFORMATION
TRAFFIC DATA AND ANALYSIS
• Highway Capacity Software Results
(Level of Service C or better for 2022 volumes)
Intersection Ramp Level Of
Capacity Service
19
CREATION AND EVALUATION ALTERNATIVE SOLUTIONS
Identified the design parameters for each component of the interchange
Defined individual alternative solutions for each construction component
Compiled Preliminary Study Report with project scope, background information, and alternative solutions
20
CREATION AND EVALUATION OF
ALTERNATIVE SOLUTIONS
DESIGN PARAMETERS
• Ramp Configuration
• Bike Lane Crossings
• Highway Widening Options
• Structural components
Hwy 404 is a Rural Freeway Divided designed @120kph (RFD120) with a posted speed of 100kph
16th avenue is an urban cross section designed @80kph (UAD80) with a posted of 60kph
Other relevant Information used was received directly from iTrans or was gathered from design guidelines such as MTO publications
Each alternative was evaluated against each other and the existing condition
21
CREATION AND EVALUATION OF
ALTERNATIVE SOLUTIONS
RAMP CONFIGURATIONS
• Alternate 1
• Alternate 2
• Alternate 3
• Alternate 4
• Alternate 5
#5: Modified Parclo B-2 and A-4#4: Parclo B-4
#1: Parclo B-2 (existing) #2: Full Cloverleaf #3: Parclo A-4
22
CREATION AND EVALUATION OF
ALTERNATIVE SOLUTIONS
BIKE LANE CROSSINGS
• Alternate 1
• Alternate 2
#2: Bike Lanes cross perpendicularly#1: Bike Lanes cross parallel
• Important to safely account all modes of transportation
• Much debate over cyclist safety at ramp terminals
23
CREATION AND EVALUATION OF
ALTERNATIVE SOLUTIONS
HIGHWAY WIDENING OPTIONS
• Alternate 1
• Alternate 2
• Alternate 3
• Alternate 4
• Alternate 5
#5: Widen in the Median and Outwards#4: Widen in the Median
#1: Widen to the east #2: Widen to the west #3: Widen Outwards
24
CREATION AND EVALUATION OF
ALTERNATIVE SOLUTIONS
STRUCTURAL COMPONENTS
• Structure Span Options
• Deck Pour Options
• Abutment Type Options
25
PRESENTATION SUMMARY
A) Proposal Writing and Winning the Project
B) Preliminary Study Report
C) Preferred Alternatives Report
D) Preliminary Design Report and Drawings
E) Conclusions
F) Lessons and Thoughts
26
PREFERRED ALTERNATIVES REPORT
Analysis of Alternative Solutions
Selection of Preferred Alternative Solution
Refined Preferred Alternative Solution
Compiled Preferred Alternative Report
27
PREFERRED ALTERNATIVE
HIGHWAY 404 & 16th
AVENUE INTERCHANGE CONFIGURATION
• Parclo A-4
• Bike Lanes Perpendicular
• Widen Highway in the Median
•Assumed Buttonville Airport will be up for redevelopment in 2022
Parclo A-4
Bike Lanes cross perpendicularly (but the final decision will be
made at a policy level)Widen in the Median
28
PRESENTATION SUMMARY
A) Proposal Writing and Winning the Project
B) Preliminary Study Report
C) Preferred Alternatives Report
D) Preliminary Design Report and Drawings
E) Conclusions
F) Lessons and Thoughts
29
PRELIMINARY DESIGN
Design Report
Drawings Plan Drawings
Profile Drawings
Typical Sections Drawings
General Arrangement Drawing
Construction Process
30
PRELIMINARY DESIGN
DESIGN REPORT
Documents methodology and rationale for selection of the preferred alternative
Includes Preliminary Design of the entire project to capture major aspects and decision making
Used to produced the Detailed Design for construction drawings where no design changes should be needed
31
PRELIMINARY DESIGN
•TYPICAL SECTIONS DRAWINGS
• Highway 404 Section
• 16th Avenue Section
• Ramp Section
34
CONSTRUCTION PROCESS
Preliminary Construction Staging
Preliminary Cost Estimate
Preliminary Working Days Estimate
36
Preliminary Construction Staging
Construction requires stages to arrive at the ultimate condition
A staging plan shows the sequence of construction for the project
Shows effect on Traffic during construction
This project requires 8 Stages
CONSTRUCTION PROCESS37
Preliminary Cost Estimate
Structure Demolition
Road and Ramp Removal
Structure Reconstruction
Road Reconstruction: Highway 404 Widening
16th Avenue Widening
Ramp Construction
CONSTRUCTION PROCESS46
Preliminary Cost Estimate
Description Cost (millions)
Demolition and Removals $1.1
HWY 404 Reconstruction and Widening
$5.8
16th Ave Reconstruction and Widening
$1.4
Ramp Reconstruction $5.3
Structure Reconstruction $6.5
Total $20.1
CONSTRUCTION PROCESS47
Preliminary Working Days Estimate
Total Tasks
Total Crew Hours Road Crews
Structure Crews
Number of Crews
Number of Total Working Days
CONSTRUCTION PROCESS48
Preliminary Working Days Estimate
Description Number of Days
Roads and Ramps Removal 124
Structure Construction 182
Roads and Ramp Construction
267
Total Preliminary
Estimate573
Total Concrete Crew Work 182
Total Road Crew Work 391
Effective Working Days 391
CONSTRUCTION PROCESS49
PRESENTATION SUMMARY
A) Proposal Writing and Winning the Project
B) Preliminary Study Report
C) Preferred Alternatives Report
D) Preliminary Design Report and Drawings
E) Conclusions
F) Lessons and Thoughts
50
CONCLUSIONS
Based on preliminary study results, it was deemed necessary to redesign the existing interchange
This project looked at multiple alternatives and selected the preferred alternative based on prescribed criteria
The final deliverables of a PDR, Plan and Profile Drawings, GA drawing, Typical Sections Drawings, Staging Plan, and Working Days Estimate have been completed
51
FUTURE STUDY
Future studies related to this project specifically can include:
Environmental Assessment with Public Involvement
Detailed Design
Stormwater Management Plan
Structural Design
52
PRESENTATION SUMMARY
A) Proposal Writing and Winning the Project
B) Preliminary Study Report
C) Preferred Alternatives Report
D) Preliminary Design Report and Drawings
E) Conclusions
F) Lessons and Thoughts
53
Lessons Learned
Projects like this Take a LOT of Time!
When looking for specific software for your project, ask the IT guy!
54
Things We Did Well
Bi-Weekly Meetings with Client (alternating)
Bi-Weekly Meetings with Faculty Advisor
Use of Conference Calling for Meetings with Client (time saver for all)
Mini Team Pre-Meetings Prior to External Meetings
Rotating Responsibilities Within Meetings (i.e. note taker, meeting leader, etc)
Meticulous Note Taking During Meetings, Minutes of Meetings
55
Things We Did Well
Updating Client of all Major Events (via e-mail)
Standardizing all Communications (i.e. Forms, using single e-mail address setup specifically for the job, etc)
Tracking Project Completion Using Gantt Chart and Scheduling Software (Milestones)
Seeking expert advice from specialists rather than making assumptions
56
QUESTIONS?
ACKNOWLEDGEMENTS
Joseph Arcaro, P.Eng, AVS (iTrans)
Greg Perry (iTrans)
Nathalie Baudais P.Eng, P.E (iTrans)
Jonathan Chai (iTrans)
Imelda Valdivieso (iTrans)
Dr. Said Easa, P.Eng (Ryerson)
Dr. Khaled Sennah, P.Eng (Ryerson)
Dr. Medhat Shehata, P.Eng (Ryerson)
Dianne Mendonca (Ryerson)
Kim Kritzer (Ryerson)
Des Rogan (Ryerson)
Poorya Bayani, BEngSaad Syed, EIT
Bernard James, EIT
57