    TOWER QC 2, GIFT CITY

    Balance work/Snag list Snag Date:26.09.13

    10th Floor DE SNAGS

    4Installation of Supply air duct up to the room wall with VCD

    and Fire Damper.In Progress

    5 Installation of return air duct up to the room wall with VCDand Fire Damper. In Progress

    6 Painting of Chilled water pipe line with flow direction. Balance

    7 Commissioning of AHU is balance. Balance

    8 Integration of DDC with BMS is balance. Balance

    9 Integration of LCP with BMS is balance. Balance

    10 Water connection for filter washing is balance. Balance

    11 Installation of Fire Extinguisher is balance. Balance

    12 Cleaning is required. In Progress

    No. AHU room 4

    1 Room Acoustic Insulation is balance. Balance

    2 Installation and Termination of LCP for AHU is balance. In Progress

    3 Installation of AHU drain pipe is balance. Done

    4Installation of Supply air duct up to the room wall with VCD

    and Fire Damper.In Progress

    5Installation of return air duct up to the room wall with VCD

    and Fire Damper.In Progress

    6 Painting of Chilled water pipe line with flow direction. Balance

    7 Commissioning of AHU is balance. Balance

    8 Integration of DDC with BMS is balance. Balance

    9 Integration of LCP with BMS is balance. Balance

    10 Water connection for filter washing is balance. Balance

    11 Installation of Fire Extinguisher is balance. Balance

    12 Cleaning is required. In Progress

    Electrical Room

    1 Integration of LDB with BMS is balance. Done

    2 labelling of Switch Board/Power Plug is balance. Done

    3 Installation of Rubber Mat is balance. Done

    4 Pasting of SLD for Panel and DBs is balance. Done

    5 Installation of Fire Extinguisher is balance. Done

    6 Continuity of cable tray to be maintained. Done

    7Proper fixing of card reader and door lock position sensor is

    to be done.Done

  • 8/12/2019 Pmc de Snags-10 Th Floor

    3/6

    TOWER QC 2, GIFT CITY

    Balance work/Snag list Snag Date:26.09.13

    10th Floor DE SNAGS

    12 Cleaning is required. Balance

    No. Male Toilet 1

    1 labelling of Switch Board/Power Plug is balance. Done

    2 Installation of Soap dispensor holder is balance. Balance

    3 Installation of Toilet paper holder is balance. Balance

    4 Installation of paper dispenser is balance. Balance

    5 Installation of waste paper bin is balance. Balance

    6 Installation of Hand dryer is balance. Balance

    7 Switch board plate to be fixed properly in passage. Done

    No. Female Toilet 1

    1 labelling of Switch Board/Power Plug is balance. Done

    2 Installation of Soap dispensor holder is balance. Balance

    3 Installation of Toilet paper holder is balance. Balance

    4 Installation of paper dispenser is balance. Balance

    5 Installation of waste paper bin is balance. Balance

    6 Installation of Hand dryer is balance. Balance

    No. Male Toilet 2

    1 labelling of Switch Board/Power Plug is balance. Done

    2 Installation of Soap dispensor holder is balance. Balance

    3 Installation of Toilet paper holder is balance. Balance

    4 Installation of paper dispenser is balance. Balance

    5 Installation of waste paper bin is balance. Balance

    6 Installation of Hand dryer is balance. Balance

    7 Switch board plate to be fixed properly in passage. Done

    No. Female Toilet 2

    1 labelling of Switch Board/Power Plug is balance. Done

    2 Installation of Soap dispensor holder is balance. Balance

    3 Installation of Toilet paper holder is balance. Balance

    4 Installation of paper dispenser is balance. Balance

    5 Installation of waste paper bin is balance. Balance

    6 Installation of Hand dryer is balance. Balance

    No. Male Toilet 3

  • 8/12/2019 Pmc de Snags-10 Th Floor

    4/6

    TOWER QC 2, GIFT CITY

    Balance work/Snag list Snag Date:26.09.13

    10th Floor DE SNAGS

    1 labelling of Switch Board/Power Plug is balance. Done

    2 Installation of Soap dispensor holder is balance. Balance

    3 Installation of Toilet paper holder is balance. Balance

    4 Installation of paper dispenser is balance. Balance

    5 Installation of waste paper bin is balance. Balance

    6 Installation of Hand dryer is balance. Balance

    No. Female Toilet 3

    1 labelling of Switch Board/Power Plug is balance. Done

    2 Installation of Soap dispensor holder is balance. Balance

    3 Installation of Toilet paper holder is balance. Balance

    4 Installation of paper dispenser is balance. Balance

    5 Installation of waste paper bin is balance. Balance

    6 Installation of Hand dryer is balance. Balance

    No. Male Toilet 4

    1 labelling of Switch Board/Power Plug is balance. Done

    2 Installation of Soap dispensor holder is balance. Balance

    3 Installation of Toilet paper holder is balance. Balance

    4 Installation of paper dispenser is balance. Balance

    5 Installation of waste paper bin is balance. Balance

    6 Installation of Hand dryer is balance. Balance

    7 Switch board plate to be fixed properly in passage. Done

    No. Female Toilet 4

    1 labelling of Switch Board/Power Plug is balance. Done

    2 Installation of Soap dispensor holder is balance. Balance

    3 Installation of Toilet paper holder is balance. Balance

    4 Installation of paper dispenser is balance. Balance

    5 Installation of waste paper bin is balance. Balance

    6 Installation of Hand dryer is balance. Balance

    No. Handicap Toilet

    1 labelling of Switch Board/Power Plug is balance. Done

    2 Installation of Soap dispensor holder is balance. Balance

    3 Installation of Toilet paper holder is balance. Balance

  • 8/12/2019 Pmc de Snags-10 Th Floor

    5/6

    TOWER QC 2, GIFT CITY

    Balance work/Snag list Snag Date:26.09.13

    10th Floor DE SNAGS

    4 Installation of paper dispenser is balance. Balance

    5 Installation of waste paper bin is balance. Balance

    6 Installation of Hand dryer is balance. Balance

    7 Installation of Grab rail is balance. Done

    Lift lobbies and corridors

    1 Fire exit signages and evacuation plan to be installed. In Progress

    2 labelling of Switch Boards/Power Plugs. Done

    Service Lift lobby

    1 Labelling for intake hopper of garbage chute is balance. Done

    2 labelling of Switch Board/Power Plug is balance. Done

    3 Plate of switch board to be installed. Done

    4 Intake hopper of chute not open/close. Balance

    Tel.closet room

    1 Cables are to be laid properly. Done

    Office area

    1 Paint touch up of fire fighting pipes wherever balance. Done

    2Proper connection of cable trays near SMDB to maintain

    continuity of cable trays.Done

    3 Extra rods to be removed. In Progress

    No. Fire Shafts1 Supports to be painted wherever pending. Done

    2 Red push button is missing in FHC near electrical room. Balance

    3 Rubber grip to be placed at hose of fire extinguishers. Done

    4 Cleaning is required. Done

    5 63 mm dia. Hose reel of 30 mt. length to be provided. Done

    No. ELV

    1 Commissioning of HVAC System is balance. In Progress

    2 Commissioning of Fire Alarm System is balance. In Progress

    3 Commissioning of Access Control System is balance. Done

    4 Commissioning of CCTV System is balance. Done

    5 Integration of various services with BMS is balance. In Progress

    No. Shafts

    1Identification tags with flow direction on the pipes is to be

    provided.In Progress

    2Tapping for RO water at easily access location for each

    office.Balance

    3 Flooring not done at ELV shafts. In Progress

    4 Cleaning is required. Done

  • 8/12/2019 Pmc de Snags-10 Th Floor

    6/6

    TOWER QC 2, GIFT CITY

    Balance work/Snag list Snag Date:26.09.13

    10th Floor DE SNAGS

    Remarks

    De Snag Date 28.01.2014

    ANC Representative: Praful

    PMC Representative: Vanraj