pmi bluegrass may 2012 lunch presentation: commissioning building systems commissioning for project...

73
PMI Bluegrass May 2012 Lunch Presentation: Building Systems Commissioning for Project Managers

Upload: rachel-darleen-thornton

Post on 25-Dec-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Building Systems Commissioning for

Project Managers

Page 2: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning Process

Page 3: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

What is Commissioning?What is Commissioning?

A process of documentation, adjustment, testing, verification, and training, performed specifically to ensure that the finished facility operates in accordance with the owner’s documented project requirements and the construction documents.

It begins in pre-design and continues through design, construction, and the life of the facility.

(BCA draft document, 2004.)

Page 4: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

What is Commissioning?What is Commissioning?

The commissioning process provides the framework to verify that a facility and its systems will function to meet the design intent and the owner's needs and to coincide with the phases of a construction project.

(Applying the PMBOK® Guide Will Enhance the Commissioning Process and Result in Greater Project Success - by Aaron Pankonin, CBCP, CAPM)

Page 5: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

What is Commissioning?What is Commissioning?

Owner’s Project Requirements

– Details functional requirements and Owner’s expectations of how a building will be used and operated – DESIGN INTENT DOCUMENT

– Basis for building commissioning

Basis of Design

– The concepts, calculations, decisions, and product selections used to meet the OWNER’S PROJECT REQUIREMENTS

Page 6: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

What Commissioning is NOT?What Commissioning is NOT?

– Completing Standard Forms

– Contractors’ QA/QC Program

– Verification of the Contractors’ QA/QC Program

– Construction Inspection

– Construction Management Substitute

Page 7: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Page 8: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

DesignIntent

Commissioning validates the design!

That the design works and

meets the “design intent”

Commissioning

“retro” ; “re”; or

“ongoing” Cx

Design Construction O & M

“Inspections” validate

construction

That the construction is installed

correctly per the “design”

Changing Needs

What is Commissioning?(validates the “design”!)

This is not commissioning!

Page 9: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Elements of CommissioningElements of Commissioning

Design Intent Documents (DID or OPR)Design Intent Documents (DID or OPR)Design ReviewsDesign ReviewsSubmittal ReviewsSubmittal ReviewsSite Observations and Site MeetingsSite Observations and Site MeetingsResolution Tracking Forms (RTF’s)Resolution Tracking Forms (RTF’s)System Verification Checklists (SVC’s)System Verification Checklists (SVC’s)Organized Systems Start-UpsOrganized Systems Start-UpsFunctional Performance Tests (FPT's)Functional Performance Tests (FPT's)Operation and Maintenance (O&M) trainingOperation and Maintenance (O&M) trainingO&M DocumentationO&M DocumentationCommissioning ReportCommissioning ReportWarranty Review of Building OperationWarranty Review of Building Operation

Page 10: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Approaches to CommissioningApproaches to Commissioning

– Comprehensive Commissioning

– Construction Phase Commissioning

Page 11: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Page 12: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Phases of CommissioningPhases of Commissioning

Pre-Design PhasePre-Design Phase

Design PhaseDesign Phase

Construction PhaseConstruction Phase

Acceptance PhaseAcceptance Phase

Post-Acceptance PhasePost-Acceptance Phase

Page 13: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Pre-Design PhasePre-Design Phase

Establish commissioning Establish commissioning

Select a Commissioning Agency (CxA)Select a Commissioning Agency (CxA)

Develop commissioning scopeDevelop commissioning scope

CxA review of DID or OPRCxA review of DID or OPR

Page 14: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Pre-Design Phase is CRITICAL!

Page 15: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Design PhaseDesign Phase

Review design for commissioning, testing and O&M access and provisions

Prepare commissioning specificationWrite the commissioning planEstablish commissioning in the project

schedule

Page 16: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Construction PhaseConstruction Phase– Review submittals

– Update commissioning plan

– Coordination including site observation, Cx Meetings, Resolution Tracking Forms (RTF’s), and System Verification Checklists (SVC’s)

– Equipment and systems start-ups

– TAB HVAC systems

– Verify Building Automation System (BAS) installation and start-up

Page 17: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Acceptance PhaseAcceptance Phase

Review TAB Report

Functional Performance Tests (FPT’s)

O&M Training and Documentation

Commissioning Report

Page 18: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Post Acceptance PhasePost Acceptance Phase

Correct unresolved deficiencies and conduct required re-tests

Carry out specified off-season testingPerform specified post-occupancy

monitoringReview usage changesUpdate commissioning documentation

Page 19: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Why Commission?Why Commission?Better Buildings

Building owners are finding that the energy, water, and productivity savings achieved by commissioned buildings can offset the cost of the commissioning process. Studies indicate 8 to 20 percent savings in building operating costs over those in a non-commissioned building.

(Building Commissioning Guide, Version 2.2, GSA/DOE, dated July 30, 1998)

Page 20: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Why Commission?Why Commission?Better PeopleBetter People

Aside from achieving documented cost savings and cost avoidance, commissioning enhances customer satisfaction by promoting proper training of the owner’s Operations & Maintenance staff, which increases the longevity and efficient operation of building systems.

Page 21: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Page 22: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Page 23: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Page 24: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Page 25: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Page 26: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Page 27: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

What is cost and value of commissioning?

Page 28: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning (Cx)Commissioning (Cx)(New Construction)

0.5 to 1.5 Percent of Total Construction Cost

Retrocommissioning (RetroCx)Retrocommissioning (RetroCx)(Existing Construction)

3.0 to 5.0 Percent of Total Operating Cost

Source: Building Commissioning Guide, Version 2.2, DOE/GSA, July 30, 1998

W

hat D

oes

Com

mis

sion

ing

Cos

t?

Page 29: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning CostsCommissioning Costs

Commissioning New ConstructionCommissioning New Construction

Approximately 2%-3% of Mechanical System Construction Cost – (BCA Case Studies)

Approximately 1%-2% of Electrical System Construction Cost – (BCA Case Studies)

Approximately 2%-5% of Comprehensive HVAC Construction Cost – (ACG Commissioning Guideline)

Page 30: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

The Economics of CommissioningThe Economics of Commissioning

* Based on research findings from University of Wisconsin, ASERTTI Training Module, 1998

If planned correctly and implemented early enough in the design process, commissioning can be included with little or no cost impact*.

Without Commissioning

With CommissioningDesign Phase

Costs

Construction Phase Costs First Year Warranty Period Costs

Design Phase

Costs

Construction Phase CostsFirst Year Warranty Period Costs

Wha

t Doe

s C

omm

issi

onin

g C

ost?

Page 31: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Page 32: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Page 33: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

BenefitsBenefits

– Better bid documents– More accurate budgets– More “control” of project– Projects delivered on time– Fewer change orders– Fewer warranty issues– Satisfied Client

Page 34: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

TITLE SLIDECommissioning of a project is a term that has different interpretations depending on who is using it.

Page 35: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

AssociationsAssociations– AABC Commissioning Group (ACG)– ASHRAE– Building Commissioning Association (BCxA)– Institute of Electrical & Electronic Engineers (IEEE)– International Society For Pharmaceutical Engineering

(ISPE)– National Environmental Balancing Bureau (NEBB)– Sheet Metal and Air Conditioning Contractors' National

Association / Testing Adjusting and Balancing Bureau (SMACNA / TABB)

– University of Wisconsin– Association of Energy Engineers (AEE)

Page 36: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

CertificationsCertifications– AABC Commissioning Group (ACG)– ASHRAE (Process Management Certification)– Building Commissioning Association (BCxA)– Institute of Electrical & Electronic Engineers (IEEE)– International Society For Pharmaceutical Engineering

(ISPE)– National Environmental Balancing Bureau (NEBB)– Sheet Metal and Air Conditioning Contractors' National

Association / Testing Adjusting and Balancing Bureau (SMACNA / TABB)

– University of Wisconsin– Association of Energy Engineers (AEE)

Page 37: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

The Need for GuidelinesThe Need for Guidelines

– Uniform delivery of services– Cx adoption as standard practice– Owner procurement / selection of providers– Continuing education – Benchmarking of Cx Benefits– Training competent Cx service providers– Client education and cooperation– Efficient Cx interface with designers, contractors,

vendors, etc

Page 38: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

GuidelinesGuidelines– ACG Commissioning Guideline – 2005– ASHRAE Guideline 1 –1996: The HVAC

Commissioning Process– ASHRAE Guideline 1.1 – 2007: HVAC&R Technical

Requirements for the Commissioning Process – ASHRAE Guideline 0-2005: The Commissioning

Process– NECA90-2004: Recommended Practices for

Commissioning Building Electrical Systems– ISPE Pharmaceutical Engineering Guide Volume

5: Commissioning and Qualification

Page 39: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Guideline 0:1.1. Cx responsibilities statement in request for A/E design Cx responsibilities statement in request for A/E design

services.services.

2.2. Develop and commit to Owner’s Project Requirements.Develop and commit to Owner’s Project Requirements.

3.3. Assign O&M personnel to the commissioning process.Assign O&M personnel to the commissioning process.

4.4. Review and approve changes made in the Owner’s Project Review and approve changes made in the Owner’s Project Requirements.Requirements.

5.5. Review and approve the Construction Documents.Review and approve the Construction Documents.

6.6. Provide competent documenting of training sessions (video, Provide competent documenting of training sessions (video, etc.)etc.)

7.7. Review and comment on the Cx Process Progress Reports.Review and comment on the Cx Process Progress Reports.

8.8. Review and comment on the Cx Authority’s verification Review and comment on the Cx Authority’s verification reports.reports.

Page 40: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

ASHRAE Guideline 1.11. Aligns Guideline 1.1 with Guideline 0 terminology

2. Greater emphasis on Owners Project Requirements (OPR)

3. Eliminate DID terminology

4. Suggests challenging design for achieving OPR

5. Promotes sampling over 100% verification and testing

6. Includes more technical process details (specific tasks)

7. Enhanced appendix of sample forms and procedures

8. Advocates extensive training for owner personnel

9. Promotes team building to accomplish commissioning

Page 41: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

StandardsStandards– ASHRAE Standard 202

– SPC 202 Committee

– Complete at San Antonio AHSRAE Meeting in June

– 1st Public Review this Summer

– Release before or at AHR Expo January 2013

Page 42: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Who manages for everything?

Page 43: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Owner’s Project Requirements Program requirements Community context Codes and regulations Site and climate Facility context and function Facility technology Sustainability Cost Schedule Client’s needs and capabilities

Page 44: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning DefinitionsCommissioning Definitions

Commissioning Authority (CxA):Commissioning Authority (CxA):

A person (or firm) representing the facility owner

Leader of the Commissioning Team

Authority of Cx Process – not design or means and methods

CxA not in chain of command – preserves objectivity

Page 45: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning DefinitionsCommissioning DefinitionsEXISTING BUILDING COMMISSIONINGEXISTING BUILDING COMMISSIONING

Retro-Commissioning (RetroCx):Retro-Commissioning (RetroCx):

Commissioning an existing building that has never been commissioned

Re-Commissioning (ReCx):Re-Commissioning (ReCx):

Commissioning a building that has been previously commissioned

Continuous Commissioning (CCx):Continuous Commissioning (CCx):

Owner continues to collect and compare baseline data on selected building systems to ensure that the building functions optimally throughout its operating life

Page 46: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning DefinitionsCommissioning Definitions

Total Building Commissioning (TBCx)Total Building Commissioning (TBCx)

Emphasizes that Commissioning is NOT only for the Mechanical and HVAC system, or any single system

Commissioning TeamCommissioning Team

Experts who, through coordinated actions, are responsible for carrying out the Commissioning Process

Commissioning PlanCommissioning Plan

A strategy overseen by the Commissioning Authority and prepared by the Commissioning Team

Page 47: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning DefinitionsCommissioning Definitions

Commissioning Provider (CP):Commissioning Provider (CP):

Independent Third-Party Commissioning Firm

A/E Firm

General Contractor

Construction Manager

Owner's Personnel

Page 48: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Systems Typically CommissionedSystems Typically Commissioned

Mechanical SystemsMechanical Systems Heating, Ventilation and Air Conditioning (HVAC) Building Automation Systems (BAS) Fire Protection

Electrical SystemsElectrical Systems Switchgear and Transformers Grounding/Bonding, Circuitry Generators and UPS Systems Lighting and Lighting Controls

Specialty SystemsSpecialty Systems Security Systems and Fire Alarm Voice/Data Systems

Page 49: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Future Commissioned SystemsFuture Commissioned SystemsThe National Institute for Building Sciences (NIBS)

is currently developing commissioning requirements for the following systems:

– Exterior Envelope – Roofing Systems– Structural Systems– Interior Systems– Elevator Systems– Plumbing Systems– Lighting Systems– Electrical Systems– Fire Protection Systems– Telecommunication Systems

Page 50: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

LEED EA Prerequisite 1LEED EA Prerequisite 1

Experienced, independent, CxA to ownerReview OPR and DIDIncorporate Cx requirements into CD’sCreate/execute Cx PlanVerify installation and performance of

Systems to be CommissionedComplete and submit a Cx Report

Page 51: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

EA Credit 3 Enhanced CommissioningEA Credit 3 Enhanced CommissioningIndependent 3rd Party CxA

Review OPR, BOD and Design by mid-CD’s

Independent submittal review

Systems Manual

O&M and Occupant Training Verification

10th Month Review of Building Operation

Page 52: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

PROJECT MANAGEMENT IS RESPONSIBLE

Page 53: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Team EffortTeam Effort

Commissioning succeeds when…Commissioning succeeds when…Team members understand and carry out

their responsibilitiesTeam members cooperate and coordinate

with each other and third-party agencies

Communication and accountability essential for effective teamwork – and they are the responsibility of the commissioning agent.

Page 54: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning Team MembersCommissioning Team MembersOwner / OperatorOwner / OperatorArchitectArchitectDesign ConsultantsDesign ConsultantsCommissioning AgentCommissioning AgentConstruction Manager (or General Contractor)Construction Manager (or General Contractor)Mechanical ContractorMechanical ContractorElectrical ContractorElectrical ContractorTemperature Controls ContractorTemperature Controls ContractorTest and Balance ContractorTest and Balance Contractor

Page 55: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning Team MembersCommissioning Team Members

Potential Team Members:Potential Team Members:Equipment VendorsSpecialty TradesSpecialty ConsultantsProgram ManagerService Contract ProvidersBAS SpecialistsIT Support Groups

Page 56: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning Team RolesCommissioning Team Roles

Owner / OperatorOwner / Operator

Assign Cx Team Member and attend meetingsAssign Cx Team Member and attend meetingsRetain a commissioning agentRetain a commissioning agentCommunicate project requirements to the design Communicate project requirements to the design

teamteamCoordinate facilities and staff participationCoordinate facilities and staff participationConduct regular site observationConduct regular site observation

Page 57: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning Team RolesCommissioning Team Roles

ArchitectArchitect

Assign Cx Team Member and attend meetingsCoordinate work of design consultantsConsider spatial requirementsConsider room naming conventionConduct regular site observationCoordinate design and changes with owner and

end-users

Page 58: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning Team RolesCommissioning Team Roles

Design ConsultantsDesign Consultants

Assign Cx Team Members and attend meetingsProvide Basis of Design and Design IntentRespond to RFI’s and CO’sConduct regular site observationCoordinate design and changes with owner and

end-usersReview O&M manuals, as-built drawings and

other specified documentationProvide HVAC training on the design intent

Page 59: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning Team RolesCommissioning Team Roles

Commissioning AgentCommissioning Agent

Assign Cx Team Leader and attend meetingsReview DesignProvide Commissioning Plan and SpecificationConduct regular site observation visitsProvide System Verification ChecklistsMonitor system start-upsConduct Functional Performance TestsReview O&M documentation and training

Page 60: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning Team RolesCommissioning Team Roles

Construction ManagerConstruction Manager

Assign Cx Team Member and attend meetingsProject SchedulingManage overall completion of workManage project documentationCoordination of contractorsMaintaining specified building conditions

Page 61: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning Team RolesCommissioning Team RolesMechanical ContractorMechanical Contractor

Assign Cx Team Member and attend meetingsManage subcontractors and vendorsDocument Progress (SVC’s)Coordinate equipment start-upOperate systems as required for Functional

Performance TestsPlan and deliver O&M staff trainingProvide O&M manuals, as-built drawings and

other specified documentation

Page 62: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning Team RolesCommissioning Team RolesElectrical ContractorElectrical Contractor

Assign Cx Team Member and attend meetingsAssign Cx Team Member and attend meetings Coordinate electrical installation with mechanical Coordinate electrical installation with mechanical

workwork Attend meetingsAttend meetings Document Progress (SVC’s)Document Progress (SVC’s) Operate systems as required for Functional Operate systems as required for Functional

Performance TestsPerformance Tests Plan and deliver O&M staff trainingPlan and deliver O&M staff training Provide O&M manuals, as-built drawings and other Provide O&M manuals, as-built drawings and other

specified documentationspecified documentation

Page 63: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning Team RolesCommissioning Team RolesTemperature Controls ContractorTemperature Controls Contractor

– Assign Cx Team member and attend meetings– Design and complete controls installation as

required by DID/OPR– Document Progress (SVC’s)– Coordinate with TAB agency– Operate systems as required for Functional

Performance Tests– Plan and deliver O&M staff training– Provide O&M manuals, as-built drawings and

other specified documentation

Page 64: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Commissioning Team RolesCommissioning Team Roles

Test and Balance ContractorTest and Balance Contractor

Assign Cx team member and attend meetingsAssign Cx team member and attend meetingsReview design for adequate testing provisionsReview design for adequate testing provisionsSubmit TAB data sheets for approvalSubmit TAB data sheets for approvalCoordinate work with master scheduleCoordinate work with master scheduleReview site conditions prior to field workReview site conditions prior to field workSubmit complete and accurate TAB ReportSubmit complete and accurate TAB ReportParticipate in verification of TAB ReportParticipate in verification of TAB Report

Page 65: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

REFERENCES

Page 66: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

ResourcesResources

www.commissioning.org for AABC Commissioning Group www.ashrae.org for American Society of Heating,

Refrigerating, and Air-Conditioning Engineers www.bcxa.org for Building Commissioning Association www.buildingamerica.gov for U. S. Dept. of Energy

Building America Program www.facomgrp.com for Facility Commissioning Group

Page 67: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

ResourcesResources www.ieee.org for Institute of Electrical & Electronic

Engineers www.ispe.org for International Society For Pharmaceutical

Engineering www.nebb.org for National Environmental Balancing

Bureau www.peci.org for Portland Energy Conservation, Inc. www.smacna.org for Sheet Metal and Air Conditioning

Contractors' National Balancing Bureau

Page 68: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Project Management Drives

Commissioning Process

Page 69: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

PMBOK

PMBOK recognizes 5 basic process groups and 9 knowledge areas typical of almost all projects. The basic concepts are applicable to projects, programs and operations. The five basic process groups are:

InitiatingPlanning Executing Controlling and Monitoring Closing.

Processes overlap and interact throughout a project or phase. Processes are described in terms of:Inputs (documents, plans, designs, etc.) Tools and Techniques (mechanisms applied to inputs) Outputs (documents, products, etc.)

Page 70: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Page 71: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Page 72: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Project Management/Commissioning Project Management/Commissioning PrerogativesPrerogatives

– Project Integration Management– Project Scope Management– Project Time Management– Project Cost Management– Project Quality Control– Project Human Resource Management– Project Communications Management– Project Risk Management

Page 73: PMI Bluegrass May 2012 Lunch Presentation: Commissioning Building Systems Commissioning for Project Managers

PMI Bluegrass May 2012 Lunch Presentation: Commissioning

Questions, Comments, Discussion