pm_mba_15_risk
DESCRIPTION
NotesTRANSCRIPT
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
1
MANAGING MANAGING PROJECT PROJECT
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
2
In a project life cycle, several questions will arise:• What can go wrong?• What are the probabilities for mistakes
happening?• What are the consequences?• When and how can it be stopped or mitigated?• To what extent can it be tolerated or accepted?• How is it measured, reduced, and managed?
RISKS AND OPPORTUNITIESRISKS AND OPPORTUNITIES
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
3
• Risk is defined as the probability an injury, breakage, loss or other negative outcomes. In the context of project management, it is the probability of not getting results as planned.
• Opportunity is defined as the possibility to achieve advancement or progress. In project management, it is the possibility of increasing project results.
In project management, risk and opportunity can each be divided into 2 categories:
Opportunity
1. Strategic
2. Tactical
Risk
1. Operational
2. Product
Definitions:
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
4
A risk occurs with emergence of 2 factors:
• An unknown OUTCOME
• A negative or uneasy IMPACT
RISK = PROBABILITY x IMPACT
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
5
LOW RISK
MEDIUM RISK
HIGH RISK
IMPACT
PR
OB
AB
ILIT
Y
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
6
PROJECT OPPORTUNITIES
PROJECT CYCLE PHASES
STRATEGIC OPPORTUNITIES
TACTICAL OPPORTUNITIES
NEW MARKET
NEW PRODUCT
NEW APPROACH
RE-ORGANISATION
SHORTEN THE SCHEDULE
COST REDUCTION
PROCESS IMPROVEMENT
REMOVAL OFUNECESSARY ACTIVITIES
STRENGTH OF P&P
PROJECT OPPORTUNITY CATEGORIES
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
7
PROJECTRISK
OPERATIONALRISK
PRODUCT RISK
PROJECT LIFE CYCLE PHASE
EXTERNALRISK
INTERNALRISK
FAILURERISK
DANGEROUSRISK
PAYMENT
POLITICAL SUPPORT
TECHNOLOGY SHARING
PERFORMANCE
PLANNING
RESOURCE
TOOLS
SKILLS
SUB-CONTRACTOR PERFORMANCE
MODE OF FAILURE
TEST FAILURE
INVENTORY EXPIRY DATE
OUT OF STOCK
PROCESS SENSITIVITY
RADIATION
EXPLOSIVES
POTENTIAL ENERGY
HIGH VOLTAGE
TOXIC
PROJECT RISK CATEGORIES
This leads to project cancellation/liquidation This leads to injury
and project failure
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
8
Risk management involves risk reducing techniques like:• Identifying the potential risks• Evaluating the probabilities of occurring and the
impact/consequence if it does occur.• Making a decision to ‘do nothing’ OR take ‘preventative’
action OR take contingency action.
Risk ManagementThis is a systematic process to identify, analyse, and take action towards a project risk, which includes the maximisation of the probabilities of positive outcomes while at the same time the minimisation of the probabilities of negative outcomes in the project life.
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
9
1. Identifying risks
2. Assess risks (qualitative and qualitative analysis)
3. Risks plan response
4. Risk control and investigation/ monitoring
MAIN PROCESSES OF RISK MANAGEMENT
Identify Risks
Can jeopardize accomplishing the project objective
Brainstorm sources of risks
Establish categories for risks and evaluate
Use historical information
Progressively elaborate and identify new risks as more information becomes available
Assess Risks
Determine the likelihood the risk event will occur
Evaluate degree of impact on the project objective
Prioritize – Likelihood of occurrence and degree of impact
– Position relative to the critical path
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
12
Risk Evaluation/Analysis
• Identify risk – Use the ‘cause and effect’ diagram (fishbone).
• Evaluate risk probability and impact (consequences) – Two (2) ways:(i) Qualitative analysis(ii) Quantitative analysis
Difficulty in calculating the probability of a risk happening, usually done from experience or research. The ‘decision tree’ can be used.
• Identifying the relations/ties of one risk to another using the ‘influence’ diagram.
• Organise a list of priorities
• Action towards risk – avoid, reduce, move, accept, contigency.
The procedures and processes to identify, detail, quantify, and evaluate each risk and its respective significance.
The following title shows a qualitative approach in risk analysis.
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
13
Enough information about...?
PROBLEM FIELD
OTHER PROBLEM
FIELD
Project & Scope Objective Statement
Identify Risk (cause and effect)
CAUSES
What, when, where, who,
why?
Dependencies & Relations/
TiesProbability Impact
Priority List
ACTION GENERATION
Choose Plan of Action:
Avoid, reduce, move, accept, contingency
Evaluate Secondary Risk
Impact Re-evaluation
Choose Starting Action
Is the outcome within the
allowed criteria?
OTHER PROBLEM
FIELD
REVIEW AGAIN
BASIC PROCESS OF BASIC PROCESS OF RISK ANALYSISRISK ANALYSIS
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
14
CONSEQUENCELate Delivery
HARDWARE WORKER
FUNCTION FINANCE
Bought itemsreceived late
Poor welding
Items not according to specification
Item is not manufactured according to design
Main staff sick/on leave
Low worker productivity
External agency lags schedule
Procurement procedure not neat
Design needs to be re-engineered
Design specification may change
Design not according to standards
Import tax may increase
Fabricator may bankrupt
Cash flow not sufficient to pay bills
IDENTIFYING RISKS: ‘CAUSE AND EFFECT’ DIAGRAM FOR B-8 PROTON COMPONENT
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
15
F1Design does not meet standards
F2Design
Specification may change
F3Design needs to be re-engineered
F4
H2Poor welding
H3Items do not
meet specifications
H4
Manufacture differs from design
P1Main staff
sick/on leave
P2Low worker productivity
P3External agency lags scheduling
M1Fabricator may
bankrupt
M2Cash flow not sufficient to
pay bills
M3Import tax may
increase
‘INFLUENCE’ CHART
H1
Procurement Procedure untidy
Bought items received late
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
16
RATINGS FOR MAIN ORDER OF RISKS
PROBABILITY OF OCCURRING
IMPACT
R = 0-10% R = 1-5 DAYS
S = 11-20% S = 6-15 DAYS
T > 20% T > 15 DAYS
An illustration on how qualitative estimations can be quantified to show relative importance.
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
17
B-8 Component: Consequences – Late Delivery
1.55R30TM3
M2
M1
P3
P2
P1
H4
H3
H2
H1
220T10RF4
120T5RF3
1.55R30TF2
210S20SUntidy procurement procedureF1
Consequences
Impact
Level %
Chances
Level % Function
This method shows main order but does not give a cut-off point on which action should be taken and
which should not. The cut-off point can be defined if required.
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
18
Decision Tree MethodMechanical Approach
-120000 80000
0.5Success
0.5 Electrical Approach 0 150000Win Contract
2 -50000 90000 0.5250000 90000 Fail-Change to mechanical
-120000 30000
0.7Success
Prepare ProposalMagnetisc Approach 0 120000
-50,000 20000-80000 84000 0.3
Fail-Change to mechanical
-120000 0
1 0.520,000 No Contract
0 -50000
No Proposal
0 0
Plan Risk Responses
Set of actions – Prevent or reduce the likelihood of occurrence or the impact of a risk
– Implement if the risk event occurs
Establishes a trigger point for implementing an action
Assigns responsibility for implementation
Avoid, mitigate, or accept the risk
Include a contingency fund to cover implementation cost
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
21
RESPONSE TOWARDS RISKS
Techniques/Categories of response towards risks are:
• Avoid – Change the project plan to remove the risk or situation, to protect the project from the impact to the said risk. This involves redefining the requirements, gathering more information, improving communications, or using an expert.
• Mitigate – through design, suitable materials choice, using certain procedures, training, and others.
• Move – Shift to a third party through a contract agreement, insurance, warranty, guarantee, performance bond, and others.
• Accept – examples include the readiness to accept losses, sales of assets, increased loans, or buying more internal insurance.
• Contingency Plan – used when the project is in operation like increased cost, time, before and after the event.
This is all the responses that are taken regarding the risk or combination of risks.
Managing Risks for Information Systems Development
Risks can be categorized into seven types – Technological risk
– Human risk
– Usability risk
– Project team risk
– Project risk
– Organizational risk
– Strategic and political risk
Critical Success Factors
Identify risks and their potential impacts before the project starts.
Involve the project team or experts in assessing risks.
Assign high priority to managing risks that have a high likelihood of occurrence and a high potential impact on the project outcome.
Develop response plans for addressing high priority risks.
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
25
RISK DECISION MATRIX EXAMPLE
Establish Contingency
Plans
Status Regularly
Establish Contingency
PlansAct
Immediately if Cost Effective
Unacceptable
Take Immediate Action
Acceptable,Do nothing
Status Regularly
Establish Contingency
Plans
Status Frequently
Establish Contingency
PlansAct
Immediately if Cost Effective
Acceptable,Do nothing
Status Occasionally
Establish Contingency
Plans
Status Regularly
Establish Contingency
PlansAct
Immediately if Cost Effective
High
Medium
Low
Low
Medium
High
PR
OB
AB
ILIT
Y O
F F
AIL
UR
E
UNWANTED CONSEQUENCES
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
26
Choosing a Response
Choosing a suitable response involves the appraisal of its effect on the original risk. One of the approaches is evaluating the cost/benefit. A choice can be made as follows:
• Prepare the baseline
• Consider each response and estimate the operational cost including the respective effects towards the original probability ratings.
• Re-evaluate the risk impact with the assumption that it occurred and the response taken.
Strategy forming in Risk Management
In risk management, the assessment of risk methods need to be studied. This includes the method for documentation. In the larger projects, a staff member should be appointed to manage this.
A good way is to hold risk workshops so that all that are involved will understand and will be unified in overcoming the associated risks.
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
27
Identifying Risks
Identifying and categorising risks can follow:• WBS
– hardware, function, resource (finance, human, material), responsibilities (identify the parties responsible for the risk, contract).
• The field of work most exposed to risks.– Scheduling, capital costs, economics, contract.
• Financer’s classifications in the project.– Pre-completion risks (sponsors, shareholders, contractors, technical,
environment), during completion (operation and maintenance, raw material supply, product marketing), finance (cost overrun, foreign exchange, interest rates, inflation), country (political & socio-culture), miscellaneous (force major, operational bond).
Risk decision effectiveness
• Information quality
• Quality of Method/Rules
• The process of acceptance
Currently, the perception of the public towards risks
influences the company’s risk strategy very much
Summary
• Risk is an uncertain event that, if it occurs, can jeopardize accomplishing the project objective.
• Risk management involves identifying, assessing, and responding to project risks in order to minimize the likelihood of occurrence and/or potential impact of adverse events on the accomplishment of the project objective.
• Risk identification includes determining which risks may adversely affect the project objective and estimating what the potential impacts of each risk might be if it occurs.
• Assessing each risk involves determining the likelihood that the risk event will occur and the degree of impact the event will have on the project objective, and then prioritizing the risks.
• A risk response plan is a defined set of actions to prevent or reduce the likelihood of occurrence or the impact of a risk, or to implement if the risk event occurs.
• Regularly review and evaluate all risks to determine if there are any changes to the likelihood of occurrence or the potential impact of any of the risks, or if any new risks have been identified.
Assignment/Exercise(individual)
1. Base on the Assignment 5 project, list and categorize three risks that could jeopardize the project.
2. Create a risk assessment matrix including a response plan for each of the risks.
3. What risks for the project have the highest priority? Does the priority for a risk change as the project progresses?
4. What changes are made to the risk assessment matrix as the changes occur?
PM
Ele
men
ts 5
- Ris
ks a
nd
Op
portu
nitie
s
29