pmo2000™ 1 improved reliability through pm optimisation project team: electrician planner...
TRANSCRIPT
1 PMO2000™ www.reliabilityassurance.com
Improved Improved Reliability Reliability through through PM OptimisationPM Optimisation
Project Team:
Electrician
Planner
Mechanic
Operator
Reliability EngineerFacilitator: Steve Turner
PMO2000™
Why investigate the Residue Cell C’sWhy investigate the Residue Cell C’s
PM Optimisation will fall in line with the business plan for the Site.
The only cost centre in the plant consistently over budget.
Opportunity to improve reliability as Cell C’s have highest failure rate in the area.
Opportunity for more consistent performance to meet plant expansion plans.
The experience is that there is more work in the area than there are people assigned.
PMO2000™
ObjectivesObjectives
Better focus of PM schedules. Increase the quality of maintenance. Understand the rationale behind each PM task. To better manage the Cell C operation and maintenance. Exchange information and increase understanding of
each role ie mech ,elect, process.
Understand equipment failure history. Improve detection and rectification of failures. Communicate findings.
PMO2000™
Objectives…Objectives…contcont
All of the previous will result in greater abilityfor us to meet the business plan.
PMO2000™
How we went about itHow we went about it
Started with the existing PM lists Applied the process to the all schedules including:
SAP schedules Maintenance and Process task lists Check sheets
Created a new daily schedule for both operator and maintenance technicians.
Review failure modes and the PM’s which addressed these.
PMO2000™
How we went about it….How we went about it….con’tcon’t
Review operating logsheets Determined the most appropriate maintenance
strategy. What task (preventive, predictive or
corrective) Who does it How often.
Develop implementation list/plan for approval.
PMO2000™
Opportunities identifiedOpportunities identified
Numerous new PM tasks that should be done. Task frequency could be more effective
particularly in the mechanical area. Some job descriptions were not specific or
reflective of actual work. Identified a opportunities for reliability
engineering.
PMO2000™
Opportunities Identified…Opportunities Identified…contcont
Better utilisation of maintenance and operations resources by eliminating task duplication.
The maintenance strategy needs to be better documented so that it can more easily be reviewed and communicated.
There is an opportunity to transfer some of the knowledge to other processes and sites.
PMO2000™
Outcome PM Optimisation AnalysisOutcome PM Optimisation Analysis
Overall Breakdown Of 110 Maintenance Tasks
Delete13%
Extend Interval11%
New Task7%
Reduce Interval9%
Use As Is60%
PMO2000™
Outcome PM Optimisation AnalysisOutcome PM Optimisation Analysis
Analysis of Mechanical Changes
Delete19%
Extend Interval30%
New Task13%
Reduce Interval25%
Use As Is13%
PMO2000™
Table of Overall Downtime for PM on Unit
Sum of Hours Proposed Program Previous Program
Interval Total Lab D/timePer Year Total Lab D/time
Per Year Total
2 Monthly 0.3 1 0.3 6 2
Monthly 5.17 2 3 12 36Two Weeks 2.25 1 2.25 26 59 1 8 26 208
Weekly 1.92 1 2 52 104Grand Total 9.64 200 208
Downtime Analysis-MechanicalDowntime Analysis-Mechanical
PMO2000™
Downtime ScheduleDowntime Schedule
0
2
4
6
8
10
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
Do
wn
tim
e H
ou
rs
Original Total 32hrs
Revised Total 30hrs
PMO2000™
Some interesting issuesSome interesting issues
Some valve failures could possibly be managed by condition monitoring rather than in breakdown.
Breakdown history was recorded incorrectly. This precludes any efficient analysis.
Some task were carried out too often…others not often enough.
The existing mechanical PM were difficult to complete but now broken into three PM’s.
Not all process tech inspections are recorded.
PMO2000™
Some interesting issues….Some interesting issues….contcont
Greater involvement of process tech’s in fault finding is possible for maintenance and operations problems.
The justification for each maintenance task is now documented.
The existing PMs are not all being completed. Pizza Hut do not deliver on public holidays.
PMO2000™
Other benefits... Other benefits...
More knowledgeable and empathetic workforce. More descriptive tasks with acceptable limits. Improved team work. Greater sense of ownership in the maintenance and
equipment performance. Better understanding of failure modes and objective of
tasks Planned downtime reduced (1hr per fortnight per unit).
Unplanned downtime will add to this.
PMO2000™
Benefits..con’t Benefits..con’t
Move to a less reactive environment by adopting more frequent inspections where warranted.
The PM program can now be achieved.
PMO2000™
What needs to happen nowWhat needs to happen now
Input changes to SAP (already started). Implement the Process Tech check procedure. Modify Elect Maintenance Tech check sheets. Develop Mech Maintenance Tech check sheet. Improve failure reporting in SAP. Carry out some minor plant modifications. Implement new tasks ie NDT and Structural
inspections .
18 PMO2000™ www.reliabilityassurance.com
Improved Reliability Improved Reliability through through PM OptimisationPM Optimisation
Project Team:
• Electrician
• Planner
• Mechanic
• Operator
• Reliability EngineerFacilitator: Steve Turner