pmp 11 project integration
TRANSCRIPT
![Page 1: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/1.jpg)
Project Integration ManagementBased on PMBOK 5th Edition
Abdelrahman Sheta, PMP,ITIL
PMP - Project Management Framework 1facebook.com/Sheta.Page
![Page 2: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/2.jpg)
What is Project Integration 4.1 Develop Project Charter 4.2 Develop Project Management
Plan 4.3 Direct and Manage Project
Work 4.4 Monitor and Control Project
Work 4.5 Perform Integrated Change
Control 4.6 Close Project
PMP - Project Management Framework 2
Agenda
facebook.com/Sheta.Page
![Page 3: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/3.jpg)
Project Integration Management
PMP - Project Management Framework 3
Includes the processes and activities
needed to identify, define, combine, unify,
& coordinate the various processes &
project management activities within
the project management process groups.
Includes characteristics of
unification, consolidation, articulation &
integrative actions that are crucial to
project successful completionfacebook.com/Sheta.Page
![Page 4: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/4.jpg)
Project Integration Management
PMP - Project Management Framework 4
Primarily concerned with effectively
integrating the processes among the
project management process groups
that are required to accomplish project
objectives within an organization’s
defined procedures.
facebook.com/Sheta.Page
![Page 5: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/5.jpg)
Project Integration Management
PMP - Project Management Framework 5
Primaril
y
effective
ly
concerned
with
integrating
the
processes among the
project management
process groups that
are required to
accomplish project
objectives within an
organization’s defined
procedures.facebook.com/Sheta.Page
![Page 6: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/6.jpg)
Project
Integration
Manageme
nt
Overview
PMP - Project Management Framework 6facebook.com/Sheta.Page
![Page 7: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/7.jpg)
4.1 Develop Project Charter
PMP - Project Management Framework 7
The project charter is the document that
formally authorizes a project, and
provide the project manager with the
authority to apply organizational resources
to the project activities.
The key benefit is a well-defined project
start and project boundaries, creation of
a formal record of the project & a direct
way for senior management to formally
accept and commit to the project.facebook.com/Sheta.Page
![Page 8: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/8.jpg)
PMP - Project Management Framework 8facebook.com/Sheta.Page
![Page 9: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/9.jpg)
Develo
p
Project
Charte
r Data
FlowPMP - Project Management Framework 9facebook.com/Sheta.Page
![Page 10: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/10.jpg)
Develop Project Charter: Inputs
1. Project Statement of Work
(SOW): A written description of the
deliverables supplied by the
PMP - Project Management Framework
project. It references the following:
Business Need
Product Scope Description
Strategic Plan10facebook.com/Sheta.Page
![Page 11: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/11.jpg)
Develop Project Charter: Inputs
PMP - Project Management Framework 11
2. Business Case, describes the necessary
information from a business standpoint to
determine whether or not the project is
worth investment. It’s usually a result of
one of the following: Market Demand
Organizational Need
Customer Request
Technological Advance
Legal Requirement
Ecological
(Environmental)
Impact
Social Needfacebook.com/Sheta.Page
![Page 12: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/12.jpg)
Develop Project Charter: Inputs
3. Agreements: contracts, Service Level Agreements
• (SLA), letter of agreements, letter of intents, etc.
4. Enterprise Environmental Factors
5. Organizational Process Assets
PMP - Project Management Framework 12facebook.com/Sheta.Page
![Page 13: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/13.jpg)
Develop Project Charter: T & T1. Expert Judgment, knowledgeable and experiences persons
(groups) from many sources including: Other units within the organization Consultants Different Stakeholders (including the
customer) Professional and technical associations Industry groups Subject Matter Experts Project Management Office
2. Facilitation TechniquesPMP - Project Management Framework 13facebook.com/Sheta.Page
![Page 14: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/14.jpg)
Develop Project Charter: Outputs
PMP - Project Management Framework 14
1. Project Charter, usually includes Project Purpose/Justification Measurable Project Objectives High-level requirements Assumptions and Constraints High level project description and
boundaries High level Risks Summary budget & milestones Initial Stakeholder List Project Approval Requirements Assigned Project Manager Name and Authority of the sponsor
facebook.com/Sheta.Page
![Page 15: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/15.jpg)
Sample Project Charter
PMP - Project Management Framework 15facebook.com/Sheta.Page
![Page 16: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/16.jpg)
4.2 Develop Project Management Plan
PMP - Project Management Framework 16
The process of defining, preparing,
coordinating and integrating all
subsidiary plans. Th
ekey benefit is a central documentthat
defines the basis of all project work. Project
Plan defines how the project willbe
executed, monitored and controlled, and closed.
facebook.com/Sheta.Page
![Page 17: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/17.jpg)
PMP - Project Management Framework 17facebook.com/Sheta.Page
![Page 18: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/18.jpg)
Develop Project
Manageme
nt Data
Flow PMP - Project Management Framework 18facebook.com/Sheta.Page
![Page 19: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/19.jpg)
Develop Project Management Plan: Inputs
PMP - Project Management Framework 19
1. Project Charter
2. Outputs from other planning processes
3. Enterprise Environmental Factors
4. Organization Process Assets
facebook.com/Sheta.Page
![Page 20: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/20.jpg)
Develop Project Management Plan: T & T
1. Expert Judgment, knowledgeable and experiences
• persons (groups).
2. Facilitation Techniques
PMP - Project Management Framework 20facebook.com/Sheta.Page
![Page 21: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/21.jpg)
1. Project Management Plan, includes:
PMP - Project Management Framework 21
Scope Baseline
Schedule
baseline Cost
Baseline
Scope Management Plan
Requirements Management Plan
Cost Management Plan
Quality Management Plan
HR management Plan
Communication Plan
StakeholderManagementPlan Risk Management Plan
Procurement Plan
Process Improvement Plan
Develop Project Management Plan: Output
facebook.com/Sheta.Page
![Page 22: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/22.jpg)
4.3 Direct and Manage Project Work
PMP - Project Management Framework 22
The process of performing thework defined in the
project plan to achieve the project's objectives.
It includes but are not limited to: Activities to accomplish requirements Create project deliverables Staff, train & manage project team members Establish and manage project communication
channels Generate project data (e.g. cost, schedule,
technical andquality progress)
Issue change requests Manage risks Manage sellers and suppliers
facebook.com/Sheta.Page
![Page 23: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/23.jpg)
Direct and Manage Project Work (2)
PMP - Project Management Framework 23
Direct and Manage Project Work also
required review of the impact of all project
changes and the implementation of
approved changes:
Correct action: to realign the performanceof the
project work to the project plan
Preventive action: to ensurefutureperformance to
align with project plan
Defect repair: to modify a non-conforming deliverable
facebook.com/Sheta.Page
![Page 24: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/24.jpg)
Direct and Manage Project Work: Data Flow Diagram
PMP - Project Management Framework 24facebook.com/Sheta.Page
![Page 25: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/25.jpg)
1. Project Management Plan
2. Approved Change Requests
3. Enterprise Environmental Factors
4. Organization Process Assets
PMP - Project Management Framework 25
Direct & Manage Project Work: Inputs
facebook.com/Sheta.Page
![Page 26: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/26.jpg)
1. Expert Judgment
2. Project Management Information Systems
3. Meetings
Direct & Manage Project Work: T & T
PMP - Project Management Framework 26facebook.com/Sheta.Page
![Page 27: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/27.jpg)
1. Deliverables
2. Change Requests (corrective actions, preventive
actions, defect repair, Updates)
3. Project Management Plan updates
4. Project Documents Updates
(Requirements document, project logs,
risk register, stakeholder register, etc.)
PMP - Project Management Framework 27
Direct & Manage Project Work: Output
facebook.com/Sheta.Page
![Page 28: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/28.jpg)
5. Work Performance Data, includes
Schedule progress showing status
information (SPI, CPI, ETC, etc.)
Which Deliverables are completed and which are not.
Extent to which quality standard are met.
Costs authorized and incurred.
Lessons learned.
Resource utilization detail.
PMP - Project Management Framework 28
Direct & Manage Project Work: Output
facebook.com/Sheta.Page
![Page 29: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/29.jpg)
4.4 Monitor and Control Project Work
PMP - Project Management Framework 29
Tracking, reviewing, and reporting the progress to
meet the performance objectives.
Corrective and preventive actions are taken
to control the project performance to
resolve/prevent deviation between project
results and project plan.
What you can not measure, you can not
manage
facebook.com/Sheta.Page
![Page 30: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/30.jpg)
PMP - Project Management Framework 30facebook.com/Sheta.Page
![Page 31: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/31.jpg)
Compares actual project performance against theproject management plan.
Assesses performance to decide whether anycorrective or preventive actions are needed
Analyzes, tracks, and monitors project risk.
Maintains an accurate and timely information on the project’s deliverables(s).
Provides cost and schedule forecasts.
Monitors the implementation of approved changeswhen and as they occur.
Monitor and Control Project Work (2)
PMP - Project Management Framework 31facebook.com/Sheta.Page
![Page 32: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/32.jpg)
1. Project Management Plan
2. Schedule Forecasts (ETC)
3. Cost Forecasts (ETC, BA)
4. Validated Change Requests (including corrective
and/or preventive actions and defect repair)
5. Work Performance Information (SPI,
CPI, CV, SV, etc.)
Monitor & Control Project Work: Inputs
PMP - Project Management Framework 32facebook.com/Sheta.Page
![Page 33: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/33.jpg)
6. Enterprise Environmental Factors (Government
or industry standards, work authorization
system, stakeholder risk tolerances, etc.)
7. Organizational Process Assets
Monitor & Control Project Work: Inputs
PMP - Project Management Framework 33facebook.com/Sheta.Page
![Page 34: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/34.jpg)
1. Analytical Techniques Regression Causal Analysis Root Cause Analysis Forecasting methods (time series, scenario
building, etc.) Fault tree analysis (FTA) Reserve Analysis Failure mode and effect analysis (FMEA) Trend Analysis Earned Value Management Variance Analysis Forecasting methods
Monitor & Control Project Work: T & T
PMP - Project Management Framework 34facebook.com/Sheta.Page
![Page 35: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/35.jpg)
2. Expert Judgment
3. Project Management Information Systems
4. Meetings
Monitor & Control Project Work: T & T (2)
PMP - Project Management Framework 35facebook.com/Sheta.Page
![Page 36: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/36.jpg)
1. Change Requests
2. Work Performance Reports
3. Project Management Plan Updates
4. Project Documents Updates
PMP - Project Management Framework 36
Monitor & Control Project Work: Output
facebook.com/Sheta.Page
![Page 37: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/37.jpg)
The process of reviewing all change requests,
approving changes & managing changes to: the
deliverables, organizational process assets,
project documents & the project management
plan.
Change Control Board (CCB) is responsible for approving
or rejecting change requests
Roles and responsibilities of CCB are defined within
configuration control and change control procedure
4.5 Perform Integrated Change Control
PMP - Project Management Framework 37facebook.com/Sheta.Page
![Page 38: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/38.jpg)
PMP - Project Management Framework 38facebook.com/Sheta.Page
![Page 39: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/39.jpg)
1. Project Management Plan
2. Work Performance Reports
3. Change Requests
4. Enterprise Environmental Factors
5. Organizational Process Assets
PMP - Project Management Framework 39
Perform Integrated Change Control: Input
facebook.com/Sheta.Page
![Page 40: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/40.jpg)
PMP - Project Management Framework 40facebook.com/Sheta.Page
![Page 41: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/41.jpg)
1. Expert Judgment
2. Meetings
3. Change Control Tools
Perform Integrated Change Control: T & T
PMP - Project Management Framework 41facebook.com/Sheta.Page
![Page 42: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/42.jpg)
1. Approved/Rejected Change Requests
2. Change Log
3. Project Management Plan Updates
4. Project Documents Updates
Perform Integrated Change Control: Output
PMP - Project Management Framework 42facebook.com/Sheta.Page
![Page 43: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/43.jpg)
Which of the following is NOT part of
change control system:
A. Approval
B. Change control board
C. Project Management Information System
D. Stakeholder analysis
Quiz:
PMP - Project Management Framework 43facebook.com/Sheta.Page
![Page 44: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/44.jpg)
1. The process of finalizing al activities
across all of the project management
process groups to formally close the
project or phase
2. Provide lessons learned, formal
ending of project work and release
of organization resources to pursue
new endeavors.
4.6 Close Project
PMP - Project Management Framework 44facebook.com/Sheta.Page
![Page 45: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/45.jpg)
Close Project Data Flow
PMP - Project Management Framework 45facebook.com/Sheta.Page
![Page 46: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/46.jpg)
1. Project Management Plan
2. Accepted Deliverables
3. Organizational Process Assets (lessons
learned, project documents, Acceptance
records, etc ).
Close Project: Inputs
PMP - Project Management Framework 46facebook.com/Sheta.Page
![Page 47: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/47.jpg)
1. Expert Judgment
2. Analytical Techniques
3. Meetings
Close Project: T & T
PMP - Project Management Framework 47facebook.com/Sheta.Page
![Page 48: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/48.jpg)
1. Final Product, Service, or Result Transition
2. Organizational Process Assets Updates
(Project files, closure documents,
historical information, etc.)
Close Project: Outputs
PMP - Project Management Framework 48facebook.com/Sheta.Page
![Page 49: PMP 11 Project Integration](https://reader036.vdocument.in/reader036/viewer/2022062320/55d576c7bb61eba40d8b4622/html5/thumbnails/49.jpg)
49PMP - Project Management Frameworkfacebook.com/Sheta.Page