pmp 4ed input toolstechnique and output (itto)

Upload: sulfar100

Post on 03-Apr-2018

235 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 PMP 4ed Input ToolsTechnique and Output (ITTO)

    1/15

    Process Name Input Tools and techniques

    Develop project charter [init]

    Project statement of work

    Business case

    Contract

    Enterprise Environmental Factors

    Organization Process Assets

    Expert Judgment Projec

    Develop project management

    plan [plan]

    Project Charter

    Output from Planning Processes

    Enterprise Environmental Factors

    Organization Process Assets

    Expert Judgment Projec

    Direct and manage project

    execution [exec]

    Project management plan

    Approved change requests

    Enterprise environmental factorsOrganizational process assets

    Expert judgment

    Project management info system

    Delive

    Work

    Chang

    Projec

    Projec

    Monitor and control project

    work [moco]

    Project management plan

    Performance reports

    Enterprise environmental factors

    Organizational process assets

    Expert Judgment

    Chang

    Projec

    Projec

    Perform integrated change

    control [moco]

    Project management plan

    Work performance information

    Change requests

    Enterprise environmental factors

    Organizational process assets

    Expert Judgment

    Change control meetings

    Chang

    Projec

    Projec

    Close project or phase [close]

    Project management plan

    Accepted Deliverables

    Organizational Process Assets

    Expert JudgmentFinal P

    Organ4.

    Integrationmanagement(6)

  • 7/28/2019 PMP 4ed Input ToolsTechnique and Output (ITTO)

    2/15

    Process Name Input Tools and techniques

    Collect Requirements [plan]Project Charter

    Stakeholder Register

    Interviews

    Focus groups

    Facilitated Workshops

    Group creativity techniques

    Group decision making techniques

    Questionnaires and Surveys

    Observation

    Prototypes

    Requi

    Requi

    Requi

    Define scope [plan]

    Project Charter

    Requirements Documentation

    Organizational Process Assets

    Expert judgment

    Product Analysis

    Alternatives identification

    Facilitated Workshops

    Projec

    Projec

    Create WBS [plan]

    Project scope statement

    Requirements documentation

    Organizational Process Assets

    Decomposition

    WBS

    WBS

    Scope

    Projec

    Verify scope [moco]

    Project Management Plan

    Requirements Documentation

    Requirements traceability matrix

    Validated Deliverables

    Inspection

    Accep

    Chang

    Projec

    Control scope [moco]

    Project Mgmt Plan

    Work performance info

    Requirements documentation

    Requirements traceability matrix

    Organizational process Assets

    Variance Analysis

    Work

    Organ

    Chang

    Projec

    Projec

    5.

    ScopeManag

    ement(5)

  • 7/28/2019 PMP 4ed Input ToolsTechnique and Output (ITTO)

    3/15

    Process Name Input Tools and techniques

    Define activities [plan]

    Scope Baseline

    Enterprise Environmental factorsOrganizational Process Assets

    Decomposition

    Rolling wave planning

    Templates

    Expert judgment

    Activ

    ActivMile

    Sequence activities [plan]

    Activity List

    Activity attributes

    Milestone list

    Project scope statement

    Organizational process assets

    Precedence Diagramming Method (PDM)

    Dependency Determination

    Applying leads and lags

    Schedule network templates

    Proj

    Proj

    Estimate activity resources

    [plan]

    Activity List

    Activity attributes

    Resource Calendars

    Enterprise Environmental factors

    Organizational process assets

    Expert Judgment

    Alternatives analysis

    Published estimating data

    Bottom-up estimating

    Project management software

    Activ

    Res

    Proj

    Estimate activity durations[plan]

    Activity List

    Activity attributes

    Activity resource requirements

    Resource calendarsProject scope statement

    Enterprise environmental factors

    Organizational process asset

    Expert judgment

    Analogous estimating

    Parametric estimatingThree-point estimates

    Reserve analysis

    ActivProj

    Develop schedule [plan]

    Activity List

    Activity attributes

    Project Schedule network diagrams

    Activity resource requirements

    Resource Calendars

    Activity Duration Estimates

    Project scope statement

    Enterprise environmental factors

    Organizational process assets

    Schedule network analysis

    Critical path method

    Critical chain method

    Resource leveling

    What-if scenario analysis

    Applying Lead and Lags

    Schedule compression

    Scheduling tool

    Proj

    Sch

    Sch

    Proj

    Control schedule [moco]

    Project Management PlanProject Schedule

    Work Performance information

    Organizational process assets

    Performance reviews

    Variance analysis

    Project management softwareResource leveling

    What-if scenario analysis

    Adjusting leads and lags

    Schedule compression

    Scheduling tool

    Wor

    Org

    Cha

    Proj

    Proj

    6.

    TimeManagement(6)

  • 7/28/2019 PMP 4ed Input ToolsTechnique and Output (ITTO)

    4/15

    Process Name Input Tools and techniques

    Estimate cost [Plan]

    Scope Baseline

    Project Schedule

    Human resource plan

    Risk register

    Enterprise Environmental factors

    Organizational process assets

    Expert judgment

    Analogous estimating

    Parametric estimating

    Bottom-up estimating

    Three-point estimates

    Reserve analysis

    Cost of quality

    Project management estimating software

    Vendor Bid analysis

    Activit

    Basis

    Projec

    Determine budget [Plan]

    Activity cost estimatesBasis of estimates

    Scope baseline

    Project schedule

    Resource calendars

    Contracts

    Organizational process assets

    Cost aggregation

    Reserve analysis

    Expert judgment

    Historical relationships

    Funding limit reconciliation

    Cost p

    Projec

    Projec

    Control cost [moco]

    Project management plan

    Project funding requirements

    Work performance information

    Organizational Process Assets

    Earned value management

    Forecasting

    To-complete performance index (TCPI)

    Performance reviews

    Variance analysis

    Project management software

    Work

    Budge

    Organ

    Chang

    Projec

    Projec

    7.

    Costmanag

    ement(3)

  • 7/28/2019 PMP 4ed Input ToolsTechnique and Output (ITTO)

    5/15

    Process Name Input Tools and techniques

    Plan Quality [plan]

    Scope baseline

    Stake holder register

    Cost performance baseline

    Schedule baseline

    Risk register

    Enterprise Environmental Factors

    Organizational Process Assets

    Cost benefit analysis

    Cost of Quality

    Control charts

    Benchmarking

    Design of experiments

    Statistical sampling

    Flowcharting

    Proprietary Quality Mgmt methodologies

    Additional Quality planning tools

    Qualit

    Qualit

    Qualit

    Proce

    Projec

    Perform quality assurance

    [exec]

    Project Management Plan

    Quality Metrics

    Work performance information

    Quality Control measurements

    Plan quality and perform quality control

    tools and techniques

    Quality audits

    Process analysis

    Organ

    Chang

    Projec

    Projec

    Perform quality control [moco]

    Project Management Plan

    Quality Metrics

    Quality checklist

    Work performance measurements

    Approved change requests

    Deliverables

    Organizational Process Assets

    Cause and effect diagrams

    Control charts

    Flowcharting

    Histogram

    Pareto Chart

    Run chart

    Scatter Diagram

    Statistical sampling

    Inspection

    Approved change requests review

    Qualit

    Valida

    Valida

    Organ

    Projec

    Projec

    Develop human resource plan

    [plan]

    Activity resource requirements

    Enterprise environmental factors

    Organizational Process Assets

    Organization charts and positiondescriptions

    Networking

    Organization theory

    Huma

    Acquire project team [exec]

    Project management plan

    Enterprise environmental factors

    Organizational Process Assets

    Pre-assignments

    Negotiation

    Acquisition

    Virtual team

    Projec

    resour

    Projec

    Develop project team [exec]

    Project staff assignments

    Project management plan

    Resource calendars

    Interpersonal skills

    Training

    Team-building activities

    Ground rules

    Co-location

    Recognition and rewards

    Team

    Enterp

    Manage project team [exec]

    Project staff assignments

    Project management plan

    Team performance assessmentsPerformance reports

    Organizational Process Assets

    Observation and conversation

    Project performance appraisals

    Conflict managementIssue log

    Interpersonal Skills

    Enterp

    OrganChang

    Projec

    Identify stakeholder [init]

    Project charter

    Project documents

    Enterprise environmental factors

    Organizational Process Assets

    Stakeholder analysis

    Expert judgment

    Stakeh

    Stakeh

    Plan communication [plan]

    Stakeholder register

    Stakeholder management strategy

    Enterprise environmental factors

    Organizational Process Assets

    Communication requirement analysis

    Communication technology

    Communication models

    Communication methods

    Comm

    Projec

    8.

    Qualitymanagement(3)

    9

    .Humanresource

    management(4)

    ation

    t(5)

  • 7/28/2019 PMP 4ed Input ToolsTechnique and Output (ITTO)

    6/15

    Process Name Input Tools and techniques

    Distribute information [exec]

    Project Management Plan

    Performance reports

    Organizational Process Assets

    Communication methods

    Information distribution toolsOrganiza

    Manage stakeholders

    expectation [exec]

    Stakeholder register

    Stakeholder management strategy

    Project mgmt plan

    Issue logChange log

    Organizational Process Assets

    Communication methods

    Interpersonal SkillsManagement skills

    Organiza

    Change r

    Project mProject do

    Report performance [moco]

    Project management plan

    Work performance information

    Work performance measurements

    Budget forecasts

    Organizational process assets

    Variance analysis

    Forecasting methods

    Communication methods

    Reporting systems

    Performa

    Organiza

    Change r

    10.

    Communi

    man

    agemen

  • 7/28/2019 PMP 4ed Input ToolsTechnique and Output (ITTO)

    7/15

    Process Name Input Tools and techniques

    Plan risk management [plan]

    Project scope statement

    Cost management plan

    Schedule management plan

    Communications management planEnterprise environmental factors

    Organizational process assets

    Planning meetings and analysis Risk

    Identify risks [plan]

    Risk management plan

    Activity cost estimates

    Activity duration estimates

    Scope baseline

    Stakeholder register

    Cost management plan

    Schedule management plan

    Quality management plan

    Project documents

    Enterprise environmental factors

    Organizational process assets

    Documentation reviews

    Information gathering techniques

    Checklist analysis

    Assumptions analysis

    Diagramming techniques

    SWOT analysis

    Expert judgment

    Risk

    Perform Qualitative analysis

    [plan]

    Risk register

    Risk management plan

    Project scope statement

    Organizational process assets

    Risk Probability and impact assessmentProbability and impact matrix

    Risk data quality Assessment

    Risk Categorization

    Risk urgency assessment

    Expert Judgment

    Risk

    Perform Quantitative analysis

    [plan]

    Risk register

    Risk management plan

    Cost management plan

    Schedule management plan

    Organizational process assets

    Data gathering and representation

    techniques

    Quantitative risk analysis and modeling

    techniques

    Expert judgment

    Risk

    Plan risk responses [plan]Risk register

    Risk management plan

    Strategies for negative risks or threats

    Strategies for positive risks or

    opportunities

    Contingent response strategies

    Expert judgment

    Risk

    Risk

    Proje

    Proje

    Monitor and control risks

    [moco]

    Risk Register

    Project management plan

    Work performance information

    Performance reports

    Risk Reassessment

    Risk Audits

    Variance and Trend Analysis

    Technical performance measurements

    Reserve analysis

    Status meetings

    Risk

    Orga

    Cha

    Proje

    Proje

    11.

    Riskmanag

    ement(6)

  • 7/28/2019 PMP 4ed Input ToolsTechnique and Output (ITTO)

    8/15

    Process Name Input Tools and techniques

    Plan procurement [plan]

    Scope Baseline

    Requirement documentation

    Teaming agreements

    Risk register

    Risk related contract decision

    Activity resource requirements

    Project schedule

    Activity cost estimates

    Cost performance baseline

    Enterprise environmental factors

    Organizational process asset

    Make-or-buy analysis

    Expert judgment

    Contract types

    Procu

    Procu

    Make

    Procu

    Sourc

    Chan

    Conduct procurement [exec]

    Procurement management plan

    Procurement documents

    Source selection criteria

    Qualified seller list

    Seller proposals

    Project documents

    Make-or-buy decision

    Teaming agreements

    Organizational process assets

    Bidder conferences

    Proposal evaluation techniques

    Independent estimates

    Expert judgment

    Advertising

    Internet search

    Procurement negotiations

    Selec

    ProcuReso

    Chan

    Proje

    Proje

    Administer procurement

    [moco]

    Procurement documents

    Project management plan

    Contract

    Performance reports

    Approved change requests

    Work performance information

    Contract change control system

    Procurement performance reviews

    Inspection and audits

    Performance reporting

    Payment systems

    Claims Administration

    Record management system

    Procu

    Organ

    Chan

    Proje

    Close procurement [close]Project Management Plan

    Procurement documentation

    Procurement audit

    Negotiation settlement

    Record management system

    Close

    Organ

    12.

    Procurementm

    anagement(4)

  • 7/28/2019 PMP 4ed Input ToolsTechnique and Output (ITTO)

    9/15

    4. Integration management (6) I

    5. Scope Management (5) S

    6. Time Management (6)T

    7. Cost management (3) C

    8. Quality management (3) Q

    9. Human resource management (4) H

    10. Communication management (5) C

    11. Risk management (6) R

    12. Procurement management (4) P

  • 7/28/2019 PMP 4ed Input ToolsTechnique and Output (ITTO)

    10/15

    http://mypmpexamprep.blogspot.com

    DPC > PMP > EPMP > MC > ICC > Close

    Co Req > Define scope > WBS > Verify > Control

    Activity > Sequence > Resource > Duration > Dev Schedule > Control

    Estimate > Budget > Control budget

    Plan Quality > QA > QC

    Plan HR > Acquire > Develop > Manage

    Ide SH > Plan commu > Distribute > MSH Ex > Reports

    Plan risk > Idendity Risk > Qal > Qty > Plan risk response > control

    Plan Proc > Conduct > Admin > Close

  • 7/28/2019 PMP 4ed Input ToolsTechnique and Output (ITTO)

    11/15

    INIT 4. Integration management (6) Develop project charter [init]

    10. Communication management (5) Identify stakeholder [init]

    PLAN 4. Integration management (6) Develop project plan [plan]

    5. Scope Management (5) Collect Requirements [plan]5. Scope Management (5) Define scope [plan]

    5. Scope Management (5) Create WBS [plan]

    6. Time Management (6) Define activities [plan]

    6. Time Management (6) Sequence activities [plan]

    6. Time Management (6) Estimate activity resources [plan]

    6. Time Management (6) Estimate activity durations [plan]

    6. Time Management (6) Develop schedule [plan]

    7. Cost management (3) Estimate cost [Plan]

    7. Cost management (3) Determine budget [Plan]

    8. Quality management (3) Plan Quality [plan]

    9. Human resource management (4) Develop human resource plan [plan]

    10. Communication management (5) Plan communication [plan]

    11. Risk management (6) Plan risk management [plan]

    11. Risk management (6) Identify risks [plan]

    11. Risk management (6) Perform Qualitative analysis [plan]

    11. Risk management (6) Perform Quantitative analysis [plan]

    11. Risk management (6) Plan risk responses [plan]

    12. Procurement management (4) Plan procurement [plan]

    EXEC 4. Integration management (6) Direct and manage project execution [exec]

    8. Quality management (3) Perform quality assurance [exec]9. Human resource management (4) Acquire project team [exec]

    9. Human resource management (4) Develop project team [exec]

    9. Human resource management (4) Manage project team [exec]

    10. Communication management (5) Distribute information [exec]

    10. Communication management (5) Manage stakeholders expectation [exec]

    12. Procurement management (4) Conduct procurement [exec]

    MOCO 4. Integration management (6) Monitor and control project work [moco]

    4. Integration management (6) Perform integrated change control [moco]

    5. Scope Management (5) Verify scope [moco]

    5. Scope Management (5) Control scope [moco]

    6. Time Management (6) Control schedule [moco]

    7. Cost management (3) Control cost [moco]

    8. Quality management (3) Perform quality control [moco]

    10. Communication management (5) Report performance [moco]

    11. Risk management (6) Monitor and control risks [moco]

    12. Procurement management (4) Administer procurement [moco]

    http://mypmpexamprep.blogspot.com

    Total 42 Processes

  • 7/28/2019 PMP 4ed Input ToolsTechnique and Output (ITTO)

    12/15

    CLOSE 4. Integration management (6) Close project or phase [close]

    12. Procurement management (4) Close procurement [close]

  • 7/28/2019 PMP 4ed Input ToolsTechnique and Output (ITTO)

    13/15

  • 7/28/2019 PMP 4ed Input ToolsTechnique and Output (ITTO)

    14/15

  • 7/28/2019 PMP 4ed Input ToolsTechnique and Output (ITTO)

    15/15