pmp preparatory material
TRANSCRIPT
1Project Management Framework Version 1.0 Project Management Framework
“Building Professionalism in Project Management”
2Project Management Framework Version 1.0 Project Management Framework
Course Objective
To familiarize participants with Project Management Body of Knowledge Guide (Fourth Edition) by explaining the concepts, processes, and techniques of Project Management.
3Project Management Framework Version 1.0 Project Management Framework
What the exam will test? Your knowledge about PMI’s processes and your ability to
apply these processes in a variety of situation.
Your understanding of the many terms that are used to describe the process.
Your understanding of professional responsibility as it applies to project management.
4Project Management Framework Version 1.0 Project Management Framework
Learning Strategies
20 / 80 approach
Learn PMPism
Emphasis on learning exercise
Gaining understanding through review exercise and class discussions
Remove friction in reading PMBOK® Guide
PMBOK is a registered mark of the Project Management Institute, Inc
5Project Management Framework Version 1.0 Project Management Framework
PROJECT MANAGEMENT FRAMEWORKPROJECT MANAGEMENT FRAMEWORK
The PMI Registered Education Provider logo and PMP are registered marks of the Project Management Institute, Inc
6Project Management Framework Version 1.0 Project Management Framework
Course Structure
Project Management Framework
Introduction
PMBOK® Guide
Role of a Project Manager
Define a Project
Define Project Management
Correlation among Project, Program, and Portfolio Management
Enterprise Environmental Factors
Project and Operations Management
Project Management Office (PMO)
Project Life Cycle and OrganizationProject Life Cycle - Introduction
Projects Life Cycle - Characteristics
Product vs. Project Life Cycle Relationship
7Project Management Framework Version 1.0 Project Management Framework
Course Structure
Phase-to-Phase Relationship
Relationship between Stakeholders and the Project
Types of Stakeholders
Organizational Influences on Project Management
Projects Phases
Project Governance
Project Management Processes for a ProjectProject Process - Introduction
Common Project Management Process Interaction
Project Management Process Group - Flow
8Project Management Framework Version 1.0 Project Management Framework
Project Management Framework - Project Management Framework - IntroductionIntroduction
9Project Management Framework Version 1.0 Project Management Framework
Project Management Body of Knowledge Project Management Body of Knowledge (PMBOK)(PMBOK)®® - Introduction - Introduction
Sum of knowledge within the profession of Project Management.
Practitioners & Academicians apply and advance it.
Includes proven traditional practices, as well as innovative and advanced practices.
Is constantly evolving.
PMBOK is a registered mark of the Project Management Institute, Inc
10Project Management Framework Version 1.0 Project Management Framework
PMBOKPMBOK®® Guide Guide PMBOK®® Guide is a recognized standard for the project management
profession.
Project Management Institute (PMI) views these standards as a foundation reference.
PMBOK®® Guide identifies (provides a general overview) the subset of Body of Knowledge that is generally recognized as good practices and promotes a common lexicon.
PMBOK is a registered mark of the Project Management Institute, Inc
11Project Management Framework Version 1.0 Project Management Framework
Code of Ethics and Professional ConductCode of Ethics and Professional Conduct PMI Code of Ethics and Professional Conduct:
Guides practitioners of the Project Management Profession Describes expectations practitioners have of themselves and others
Code of Ethics and Professional Conduct is specific about:
Obligation of Responsibility – to comply with laws, regulations and organizational and professional policies
Respect, fairness, and honesty – to deal with the stakeholders
Acceptance of the code is a requirement for the PMP®
certification by PMI.
12Project Management Framework Version 1.0 Project Management Framework
ProjectProject
A project is a temporary endeavor undertaken to create a unique product, service, or result.
Every project has a definite beginning and a definite end.
A project creates unique deliverables in the form of products, services, or results.
(Repetitive elements may be present in some project deliverables, which does
not change the fundamental uniqueness of the project work.)
Uniqueness is an important characteristic of
project’s deliverables.
A project ends as a result of one of the following: Project objectives have been achieved. It becomes clear that the project objectives
cannot be met. The need for the project no more exists.
Continue…
13Project Management Framework Version 1.0 Project Management Framework
Project Continue…Project Continue…
A single person A single Organization Multiple Organizational Units
A project can involve:
A project can create:
A product that can be either a component of another item or an end item in itself A capability to perform a service A result such as a outcome or document
14Project Management Framework Version 1.0 Project Management Framework
1. Project Management is the application of knowledge, skills, tools, and techniques to project activities to meet project requirements.
2. Project Management is accomplished through the application and integration of project management processes in 5 process groups - Initiating, Planning, Executing, Monitoring and Controlling, and Closing.
3. The project manager is the person responsible for accomplishing the project objectives.
4. Project managers often talk of “Project Constraints” which includes: project scope, quality, time, cost, resources, and risk in managing competing project requirements.
Project ManagementProject Management
Continue…
15Project Management Framework Version 1.0 Project Management Framework
Project Management Continues…Project Management Continues…
Progressive Elaboration means developing and continuing by increments.
Project objectives, scope and deliverables are progressively elaborated.
Progressive Elaboration should not be confused with scope creep.
Progressive ElaborationProgressive Elaboration
16Project Management Framework Version 1.0 Project Management Framework
Project, Program, and Portfolio Management
Portfolio Management
Program Management
Project Management
Project management exists in a broader context that includes:
Project prioritization is
based on:
Risk
Funding
Organizational Strategic
Plan
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 1-1. Page 8.
17Project Management Framework Version 1.0 Project Management Framework
Program ManagementProgram Management
Program:
A project may or may not be a part of a program but a program will always have projects.
A group of related projects Individual project management is not available Includes elements of related work outside the scope
Program Management focuses on:
Project Interdependencies Optimal approach for managing them
Projects within programs are related through common outcome or collective capability
18Project Management Framework Version 1.0 Project Management Framework
Portfolio ManagementPortfolio Management
Portfolio:
Collection of projects or programs Facilitate effective management to meet business objectives Not interdependent or directly related to projects or programs
Portfolio Management being a centralized management includes :
Identifying Prioritizing Authorizing Managing and Controlling all programs and projects
Project, Program, and Portfolio Management on certain parameters
Senior managers or senior management teams typically take on the responsibility of portfolio management for an organization.
20Project Management Framework Version 1.0 Project Management Framework
Project and Strategic PlanningProject and Strategic Planning
Projects are:
Strategic Considerations:
Market Demand Business Need Customer Request Technological Advance Legal Requirement
An organization’s strategic plan becomes the primary factor guiding investments in projects.
Means of achieving an organization’s strategic plan Authorized to follow strategic considerations
21Project Management Framework Version 1.0 Project Management Framework
Project Management Office (PMO)Project Management Office (PMO)
PMO is an organizational unit to centralize and coordinate the management of projects under its domain.
PMO: Acts as an integral stakeholder A key decision maker Involved in selection, management, and
deployment of resources
PMO supports Project Managers in:
Identifying and developing project management standards Coaching, mentoring, and training Managing shared resources Developing, managing, and monitoring project policies and procedures Coordinating across projects
22Project Management Framework Version 1.0 Project Management Framework
PMO and Project Manager PMO and Project Manager
PMOs and Project Managers follow different objectives but the final aim is to achieve the strategic needs of the organization.
Difference between the role of PMO and Project Manager:
PMO Project Manager
Focuses on achieving potential business objectives.
Focuses on achieving specified project objectives.
Optimizes the use of shared resources across all projects.
Controls the assigned project resources.
Manages methodologies, standards, risk/opportunity, and interdependencies among projects at enterprise level.
Manages project constraints such as scope, schedule, cost, etc. of an individual project.
23Project Management Framework Version 1.0 Project Management Framework
Operations are ongoing and repetitive while projects are temporary and unique.
The purpose of a project is to attain its objectives (and then terminate).
The objective of an ongoing operation is to sustain the business.
Project and Operations ManagementProject and Operations Management
Project intersect with operations during project life
cycle at various points: Each closeout phase Developing a new product Upgrading a product Improvements in operations Divestment of the operations at the end of the product life cycle
24Project Management Framework Version 1.0 Project Management Framework
Characteristics a Project Manager :
Role of a Project ManagerRole of a Project Manager
Knowledge – What the project manager knows Performance – How the project manager applies the knowledge Personal – How the project manager behaves while performing the project
A Project Manager is the person assigned by an organization to achieve objectives of the project.
25Project Management Framework Version 1.0 Project Management Framework
Project Life Cycle and OrganizationProject Life Cycle and Organization
26Project Management Framework Version 1.0 Project Management Framework
Project Life Cycle - IntroductionProject Life Cycle - Introduction
A project life cycle is a collection of generally sequential and sometime overlapping project phases.
Project managers or the organization can divide projects into phases to provide better management control with appropriate links to the ongoing operations of the performing organization and these phases are known as the Project Life Cycle.
Many organizations identify a specific set of life cycles for use on all their projects.
27Project Management Framework Version 1.0 Project Management Framework
Project Life Cycle - Characteristics Project Life Cycle - Characteristics
1. Phases are generally sequential.
Most Project Life Cycles share a number of common characteristics:
2. Cost and staffing levels are low at the start, peak during the intermediate phases, and drop rapidly as the project draws to a conclusion.
Continue…Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 2-1. Page 16.
28Project Management Framework Version 1.0 Project Management Framework
Project Life Cycle - Characteristics Project Life Cycle - Characteristics
3. The ability of stakeholders to influence the project outcome and cost is highest at the start and gets progressively lower as the project continues.
4. Risk is greatest at the start of the project and gets progressively lower as the project continues.
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 2-2. Page 17.
29Project Management Framework Version 1.0 Project Management Framework
Product vs. Project Life Cycle Relationships (As per (As per PMBOKPMBOK®® Guide Guide))
PMBOK is a registered mark of the Project Management Institute, Inc
30Project Management Framework Version 1.0 Project Management Framework
Project PhasesProject Phases are:
Divisions within a project for extra control to manage the completion of a deliverable effectively Typically sequential but can overlap in some projects Elements of the project life cycle Segmented into logical subsets for easy management
Characteristics of Phases:
The close of a phase ends with some form of transfer, usually when phases are sequential
Primary objective of the phase requires an extra degree of control to be successful
No single way to define the ideal structure for a project
Continue…
31Project Management Framework Version 1.0 Project Management Framework
Phase starts once the earlier phase is complete
Phase starts prior to the completion of the previous phase
Planning of the next phase depends on the planning of the current phase
Project Phases
Single Phase Multiple Phases
Sequential Overlapping Iterative
Projects having only one phase
32Project Management Framework Version 1.0 Project Management Framework
Project Governance
Project Governance:
A comprehensive, consistent method of controlling the project Should be included in the project management plan Must fit within the larger context of the program
Project Governance is facilitated by:
Phase structure which provides a formal basis for control Review of the deliverables to determine completeness and acceptance A natural point to reassess the effort underway to change or terminate the project Formal phase completion which does not include authorizing the subsequent phase
33Project Management Framework Version 1.0 Project Management Framework
Project StakeholdersProject Stakeholders
1. Project stakeholders are individuals and organizations that are : actively involved in the project or whose interests may be affected as a result of project execution or
completion or may exert influence over the project’s objectives and outcomes.
2. The project management team must identify the stakeholders and manage their
influence in relation to the requirements to ensure a successful project.
Continue…
34Project Management Framework Version 1.0 Project Management Framework
The Relationship Between Stakeholders andThe Relationship Between Stakeholders and the Project the Project
Continue…Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 2-6. Page 24.
35Project Management Framework Version 1.0 Project Management Framework
Organizational InfluencesOrganizational Influences
Organizational Influences on Project Management:
Culture, Style, and Structure Degree of project management maturity Involvement of external entitles as a part of a joint venture
Continue…
36Project Management Framework Version 1.0 Project Management Framework
Organizational Culture and StyleOrganizational Culture and Style
Organizational cultures and styles may have a strong influence on a project’s ability to meet its objectives.
The cultures are reflected in numerous factors including:
1. Shared values, norms, beliefs, and expectations
2. Policies and procedures
3. View of authority relationships
4. Work ethics and work hours
Continue…
37Project Management Framework Version 1.0 Project Management Framework
Organizational StructureOrganizational Structure The structure of the performing organization often constraints the availability of resources in a spectrum from functional to projectized, with a variety of matrix structures in between.
Continue…
38Project Management Framework Version 1.0 Project Management Framework
For conducting organization’s work, whichincludes but not limited to:
Organizational standard processes Standardized guidelines, work instructions, etc. Guidelines and criteria for tailoring set of standard processes Organization communication requirement Project closure requirements Financial, Change, and risk control procedures
Organizational Process Assets
Processes & Procedures Corporate Knowledge Base
For storing and retrieving organizational information, which includes but not limited to: Process measurement databases Project files Historical information and lessons learned knowledge base Issue and defect management databases Configuration management knowledge databases Financial databases
39Project Management Framework Version 1.0 Project Management Framework
Enterprise Environment Factors:
40Project Management Framework Version 1.0 Project Management Framework
Project Management ProcessesProject Management ProcessesFor a Project For a Project
41Project Management Framework Version 1.0 Project Management Framework
Project Process - IntroductionProject Process - Introduction
A Process is a set of interrelated actions and activities that are performed to achieve a pre-specified set of products, results, or services.
Project processes are performed by Project Team.
Ensure effective flow throughout the project
Includes tools and techniques in applying skills and capabilities
Specify and create the project products
Defined by the project life cycle
Vary by application area
42Project Management Framework Version 1.0 Project Management Framework
Project Management Process GroupsProject Management Process Groups
These process groups are:
Project management processes are grouped into five categories known as project management process groups or process groups.
1. Initiating Process Group:
– To define a new project or a new phase of an existing project
– Obtains authorization
2. Planning Process Group:
– To establish the scope of the project
– Refine the objectives
– Define the course of action
Continue…
43Project Management Framework Version 1.0 Project Management Framework
Project Management Process GroupsProject Management Process Groups
3. Executing Process Group:
– To complete the defined work in the project
– Satisfy the project specifications in the project management plan
4. Monitoring and Controlling Process Group:
– To track, review, and regulate project’s progress and performance
– Identifies the areas where changes are required
– Initiates the required changes
5. Closing Process Group:
– To finalize all activities to formally close the project or phase
44Project Management Framework Version 1.0 Project Management Framework
Common Project Management Process Interactions
Following figure shows the integrative nature of project management that requires
the Monitoring and Controlling Process Group to interact with the other process groups.
Continue…Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 3-1. Page 40.
45Project Management Framework Version 1.0 Project Management Framework
Common Project Management Process Interactions
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 3-2. Page 41.
46Project Management Framework Version 1.0 Project Management Framework
DefinitionsDefinitions
Input: Any item, whether internal or external to the project that is required by a process before that process proceeds. May be an output from a predecessor process.
Output: A product, result, or service generated by a process. May be an input to a successor process.
Tool: Something tangible, such as a template or software program, used in performing an activity to produce a product or result.
Technique: A defined systematic procedure employed by a humanresource to perform an activity to produce a product or result or deliver a service, and that may employ one or more tools.
(As per (As per PMBOKPMBOK®® Guide Guide))
PMBOK is a registered mark of the Project Management Institute, Inc
47Project Management Framework Version 1.0 Project Management FrameworkThe PMI Registered Education Provider logo and PMP are registered marks of the Project Management Institute, Inc
48Project Management Framework Version 1.0 Project Management Framework
Before we begin…
49Project Management Framework Version 1.0 Project Management Framework
Everyone respects your time, do you?
Come on time, Promptly return from the breaks
50Project Management Framework Version 1.0 Project Management Framework
Age and experience maketh a good manager
sometimes...not always
51Project Management Framework Version 1.0 Project Management Frameworkwhen switched off or silent
Your phone looks better…
52Project Management Framework Version 1.0 Project Management Framework
Involvement is the key
not mere enrolment…
53Project Management Framework Version 1.0 Project Management Framework
Be here…
…and only here
54Project Management Framework Version 1.0 Project Management Framework
Listen to others…
…before you start correcting them
55Project Management Framework Version 1.0 Project Management FrameworkThank you!!!
56Project Management Framework Version 1.0 Project Management Framework
PROJECT INTEGRATION MANAGEMENTPROJECT INTEGRATION MANAGEMENT
The PMI Registered Education Provider logo and PMP are registered marks of the Project Management Institute, Inc
57Project Management Framework Version 1.0 Project Management Framework
Course StructureProject Integration Management
Introduction
Integration Management – Introduction
Develop Project Charter : Inputs, Tools, and Outputs
Develop Project Charter
Monitor and Control Project Work : Inputs, Tools, and Outputs
Monitor and Control Project Work
Direct and Manage Project Execution
Perform Integrated Change Control
Perform Integrated Change Control : Inputs, Tools, and Outputs
Develop and Manage Project Execution : Inputs, Tools, and Outputs
Develop Project Management Plan
Develop Project Management Plan : Inputs, Tools, and Outputs
Close Project
Close Project : Inputs, Tools, and Outputs
58Project Management Framework Version 1.0 Project Management Framework
IntroductionIntroduction
59Project Management Framework Version 1.0 Project Management Framework
Project Integration Management – IntroductionProject Integration Management – Introduction
What is Integration?
It is the processes required to ensure that the various elements (people, It is the processes required to ensure that the various elements (people, product, etc.) of the project are appropriately coordinated with each product, etc.) of the project are appropriately coordinated with each
other. other.
60Project Management Framework Version 1.0 Project Management Framework
Project Integration Management – IntroductionProject Integration Management – Introduction
It is a unique knowledge area and it is the core of project management.
It includes processes and activities needed to identify, define, combine, unify, and coordinate between the various processes and project management activities within the project management process group.
It involves putting the pieces of the project together into a cohesive whole, while managing trade offs among the different project objectives and alternatives to meet or exceed stakeholders needs and expectations.
It involves selection about: Resource Allocation Balancing among competing objectives
and alternatives Managing interdependencies among
project management knowledge areas
61Project Management Framework Version 1.0 Project Management Framework
Project Integration Management – Processes Management – Processes
Develop Project Charter (Initiating) – process of developing a document that formally authorizes a project or a phase and documenting initial requirements that satisfy the stakeholder's needs and expectations.
Develop Project Management Plan (Planning) – process of documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans.
Direct and Manage Project Execution (Executing) – process of performing the work defined in the project management plan to achieve the project’s objectives.
Monitor and Control Project Work (Monitoring & Controlling) – process of tracking, reviewing, and regulating the progress to meet the performance objectives defined in the project management plan.
(As per (As per PMBOK® GuidePMBOK® Guide))
Continue…PMBOK is a registered mark of the Project Management Institute, Inc
62Project Management Framework Version 1.0 Project Management Framework
Project Integration Management – ProcessesProject Integration Management – Processes
Perform Integrated Change Control (Monitoring & Controlling) – process of reviewing all change requests, approving changes, and managing changes to the deliverables, organizational process assets, project documents, and the project management plan.
Close Project or Phase (Closing) – process of finalizing all activities across all of the project management process groups to formally complete the project or phase.
(As per (As per PMBOK® GuidePMBOK® Guide))
These processes:
Interact with each other and with the processes in the other Knowledge Areas Occur at least once in every project or project phases
Continue…PMBOK is a registered mark of the Project Management Institute, Inc
63Project Management Framework Version 1.0 Project Management Framework
Project ManagementProject ManagementPlanPlan
ChangesChanges
Project Integration Management – ProcessesProject Integration Management – Processes
Planning process group provides the Executing process group with a documented project management plan during the early stage of the project.
Later, it facilitates updates to the project management plan if changes occur during the progress of the project.
PlanningPlanning ExecutingExecuting
65Project Management Framework Version 1.0 Project Management Framework
Develop Project CharterDevelop Project Charter
Project charter is the process of developing a document that:Formally authorizes a project or a phase. Jot downs initial requirements.Establishes a partnership between the
performing organization and the requesting organization (Internal Project) and performing organization and Customer (External Project).
Who can authorize Projects?
Projects are authorized by someone external to the project:
A sponsorPMOPortfolio steering committee
Continue…
66Project Management Framework Version 1.0 Project Management Framework
Process Process - Develop Project Charter- Develop Project Charter
The project initiator or sponsor should be at a level that is appropriate to funding the project.
Chartering a project links the project to the strategy and ongoing work of the organization. (Internal)
The Project Manager is identified and assigned to the project as early as possible, but always prior to the start of planning, and preferably while Project Charter is being developed.
Project charter provides the project manager with the authority to apply resources to project activities.
67Project Management Framework Version 1.0 Project Management Framework
Develop Project Charter – Inputs, Tools, and OutputsDevelop Project Charter – Inputs, Tools, and Outputs
Project statement of work- Business need- Product scope description- Strategic plan
Business case Contracts Enterprise environmental factors Organizational process assets
Expert judgment Project charter
68Project Management Framework Version 1.0 Project Management Framework
Develop Project Charter Data Flow DiagramDevelop Project Charter Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 4-3 Page 74.
69Project Management Framework Version 1.0 Project Management Framework
Develop Project Charter: OutputsDevelop Project Charter: Outputs
Project CharterProject charter documents:
Business needs Current understanding of customer’s needs New product, service, or result
Project purpose Measurable project objectives and related success criteria High-level requirements High-level project description High-level risks Summary milestone schedule Summary budget Project approval requirements Responsibility and authority level of project manager, sponsor, or other
persons
71Project Management Framework Version 1.0 Project Management Framework
Process Process - Develop Project Management Plan- Develop Project Management Plan It defines how the project is executed, monitored and controlled, and
closed.
It’s content will differ depending upon the application area and complexity of the project.
Project management processes selected by the project management team
Level of implementation of each selected process Description of the tools and techniques to be used How the selected processes will manage the
dependencies, interactions, inputs, and outputs among processes
It is updated, controlled, and approved through the
Perform Integrated Change Control process.
72Project Management Framework Version 1.0 Project Management Framework
Develop Project Management Plan – Inputs, Tools, Develop Project Management Plan – Inputs, Tools, and Outputsand Outputs
Project charter Outputs from planning
processes Enterprise environmental f
actors Organizational process as
sets
Expert judgment Project management plan
73Project Management Framework Version 1.0 Project Management Framework
Develop Project Management PlanDevelop Project Management Plan
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 4-5 Page 79.
74Project Management Framework Version 1.0 Project Management Framework
Integrates and consolidates all of the subsidiary management plans
and baselines from the planning processes.
Project Life cycle Project management
processes
tailored to that project Subsidiary Plans Other baselines
It includes:
Develop Project Management Plan: OutputsDevelop Project Management Plan: Outputs
Project Management Plan
Continue…
75Project Management Framework Version 1.0 Project Management Framework
Develop Project Management Plan: OutputsDevelop Project Management Plan: Outputs
What is performance measurement baseline?
A performance measurement baseline is the combination of: Schedule baseline Cost performance baselines Scope baseline
These baselines are used as an overall project baseline against which integrated performance can be measured.
Can you think of other baselines?
Quality
The performance measurement baseline is used for earned value measurement.
77Project Management Framework Version 1.0 Project Management Framework
Process Process - Direct and Manage Project Execution - Direct and Manage Project Execution The process of performing the work defined in the project management plan
to achieve the project’s objectives.
What type of different activities could be included?
Perform activities to accomplish project requirements Create project deliverables Staff, train, and manage the team members Obtain, manage, and use resources (material, tools, etc.) Implement the planned methods and standards Establish and manage project communication channels (Internal and External) Generate project data (Cost, schedule, technical and quality progress, status to facilitate forecasting) Issue change request and adapt approved changes Manage risk and implement risk response activities Manage sellers and suppliers Collect and document lessons learned, and implement approved process improvement activities
78Project Management Framework Version 1.0 Project Management Framework
Direct and Manage Project Execution Direct and Manage Project Execution
Corrective actions that will bring anticipated project performance into compliance with Project Management Plan.
Preventive actions to reduce the probability of potential negative consequences.
Defect repair request to correct product defects found by quality process with a recommendation to repair or replace the component.
It is directly affected by the project application area.
It requires implementation of approved changes covering:
79Project Management Framework Version 1.0 Project Management Framework
Direct and Manage Project Execution– Inputs, Direct and Manage Project Execution– Inputs, Tools, and OutputsTools, and Outputs
Project management plan Approved change requests
– The documented, authorized changes to expand or reduce project scope which may require implementation of preventive or corrective actions.
Enterprise environmental factors
Organizational process assets
Expert judgment Project management
information system
Deliverables Work performance
information Change requests Project management plan
updates Project document update
s
80Project Management Framework Version 1.0 Project Management Framework
Direct and Manage Project Execution Direct and Manage Project Execution
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 4-7 Page 84.
81Project Management Framework Version 1.0 Project Management Framework
Direct and Manage Project Execution:Direct and Manage Project Execution:Tools and TechniquesTools and Techniques
Who can be the experts?
Consultants, Stakeholders, Professional and technical associations and other units within the organization.
Project management information system is a part of the enterprise environmental factors.
It provides access to an automated tools, such as: A scheduling software tool A configuration management system An information collection and distribution system
Web interfaces to other online automated systems
82Project Management Framework Version 1.0 Project Management Framework
Direct and Manage Project Execution: OutputsDirect and Manage Project Execution: Outputs
Deliverables: An approved deliverable is any unique and verifiable product to perform a service to complete a process, phase, or project.
Work Performance Information: Collective information as the project progresses. This includes:
Deliverables status Schedule progress Costs incurred
Continue…
Change Requests: Issues found during the project work. These issues may modify Project's: Policies or procedures, scope, cost, schedule or quality.
Requests for a change can include:
Corrective action Preventive action Defect repair
83Project Management Framework Version 1.0 Project Management Framework
Direct and Manage Project Execution: OutputsDirect and Manage Project Execution: Outputs
Project management plan that may be updated include:
Requirement, Schedule, Cost, Quality, Human, Communications, Risk, Procurement Management Plans
Project Baselines
Project documents that may be updated include:
Requirement documents Project logs (issue, assumption, etc.) Risk register Stakeholder register
85Project Management Framework Version 1.0 Project Management Framework
Process Process - Monitor and Control Project Work- Monitor and Control Project Work
The process of tracking, reviewing, and regulating the progress to meet the performance objectives defined in the project management plan.
Monitoring includes:
Collecting Measuring Distributing performance information, and Assessing measurements and trends to improve processes
Controlling includes:
Determining corrective or preventive actions Replanning and following up on action plans
Continue…
86Project Management Framework Version 1.0 Project Management Framework
Monitor and Control Project WorkMonitor and Control Project Work
Comparing actual project performance against the project management plan.
Assessing performance to determine whether any corrective or preventive actions are indicated, and recommending those actions as necessary.
Identifying new risks and analyzing, tracking, and monitoring existing project risks.
Maintaining an accurate, timely information base concerning the project's product(s) and their associated documentation through project completion.
Providing information to support status reporting, progress measurement, and forecasting.
Providing forecasts to update current cost and current schedule information.
Monitoring implementation of approved changes as per their occurrence.
What type of different activities could be included?
87Project Management Framework Version 1.0 Project Management Framework
Monitor and Control Project Work– Inputs, Tools, Monitor and Control Project Work– Inputs, Tools, and Outputsand Outputs
Project management plan Performance reports Enterprise environmental
factors Organizational process as
sets
Expert judgment Change requests Project
management plan Project document u
pdates
88Project Management Framework Version 1.0 Project Management Framework
Monitor and Control Project WorkMonitor and Control Project Work
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 4-9 Page 90.
89Project Management Framework Version 1.0 Project Management Framework
Monitor and Control Project Work– OutputsMonitor and Control Project Work– Outputs
Change requests Project management plan Project document updates
Project Management Plan Project Document
91Project Management Framework Version 1.0 Project Management Framework
Process Process - Perform Integrated Change Control - Perform Integrated Change Control
It is performed from project inception through completion.
The project management plan, scope statement, and other deliverables must be maintained by carefully and continuously managing changes by:
Rejecting changes OR Approving changes
Incorporate approved changes
into revised baseline.
Continue…
92Project Management Framework Version 1.0 Project Management Framework
Influencing the factors that circumvent change control so that only approved changes are implemented.
Reviewing, analyzing, and approving change requests promptly (slow decision may negatively affect time, cost, or the feasibility of a change)
Managing approved changes.
Releasing approved changes for incorporation into the project management plan and project documents.
Reviewing, approving, or denying all recommended corrective and preventive actions.
Coordinating changes across the entire project.
Documenting the complete impact of change requests.
Perform Integrated Change ControlPerform Integrated Change ControlWhat type of different activities could be included?
Continue…
93Project Management Framework Version 1.0 Project Management Framework
Perform Integrated Change ControlPerform Integrated Change Control
Every (documented) change must be either accepted or rejected by some authority.
Within the project management team OR External organization
Many times, change control system includes a change control board (CCB) responsible for approving o rejecting change requests.
If the project is being provided under a contract, then some proposed changes need to be approved by the customer.
94Project Management Framework Version 1.0 Project Management Framework
Note Note
Do not consider yourself an opponent of changes by default, but you do need to manage changes and make sure each change goes through the change control system and that changes do not make their way through the backdoor. So, when it comes to changes, the keyword is control, not oppose.
95Project Management Framework Version 1.0 Project Management Framework
Configuration Management System Configuration Management System
A configuration management system with integrated change control provides, a standardized, effective, and efficient way to manage approved changes and baselines within a project.
Configuration control focuses on
Specifications of deliverables and processes
Identifying, documenting and controlling changes to the project and the product baselines
Change control focuses on
While
Continue…
96Project Management Framework Version 1.0 Project Management Framework
Configuration Management System Configuration Management System Configuration management system, including change control
processes, accomplishes three objectives:
Establish an evolutionary method to consistently identify and request changes to established baselines, and assess the value and effectiveness of those changes.
Provides opportunities to continuously validate and improve the project by considering the impact of each change.
Provides mechanism for the project management team to consistently communicate all approved and rejected changes to the stakeholders.
Continue…
97Project Management Framework Version 1.0 Project Management Framework
Configuration Management System Configuration Management System
Configuration management activities included in the integrated change control processes are:
Configuration Identification
Configuration status accounting
Configuration verification and audit
98Project Management Framework Version 1.0 Project Management Framework
Perform Integrated Change Control– Inputs, Tools, Perform Integrated Change Control– Inputs, Tools, and Outputsand Outputs
Project management plan
Work performance information
Change requests Enterprise environment
al factors Organizational process
assets
Expert judgment Change control
meetings
Change request status updates
Project management plan updates
Project document updates
99Project Management Framework Version 1.0 Project Management Framework
Perform Integrated Change ControlPerform Integrated Change Control
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 4-11. Page 96.
100Project Management Framework Version 1.0 Project Management Framework
Perform Integrated Change Control – OutputsPerform Integrated Change Control – Outputs
Change request status updates Project management plan updates Project document updates
102Project Management Framework Version 1.0 Project Management Framework
The process of finalizing all activities across all the Project Management Process Groups to formally complete the project or phase.
Includes activities to investigate and document the reasons if a project is terminated before completion.
Process Process - Close Project or Phase- Close Project or Phase
Activities for administrative closure of the project or phase: Satisfy completion or exit criteria for the phase or
project
Transfer the project’s products, services, or results to the next phase or production or operations
Collect project or phase records, audit project success or failure, gather lessons learned and archive project information for future use.
103Project Management Framework Version 1.0 Project Management Framework
Close Project or phase – Inputs, Tools, and Close Project or phase – Inputs, Tools, and OutputsOutputs
Project management plan
Accepted deliverables Organizational proces
s assets
Expert judgment Final product, service, or result transition
Organizational process assets updates
104Project Management Framework Version 1.0 Project Management Framework
Close Project or PhaseClose Project or Phase
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 4-13. Page 100.
105Project Management Framework Version 1.0 Project Management Framework
Close Project or Phase - OutputsClose Project or Phase - Outputs
Final product, service, or result transition:
- refers to the transition of the final product, service, or result that the project was authorized to produce. (based on transition criteria)
Organizational Process Assets Updates:
- includes project files, project or phase closure documents, and historical information, etc.
106Project Management Framework Version 1.0 Project Management FrameworkThe PMI Registered Education Provider logo and PMP are registered marks of the Project Management Institute, Inc
107Project Management Framework Version 1.0 Project Management Framework
PROJECT SCOPE MANAGEMENTPROJECT SCOPE MANAGEMENT
The PMI Registered Education Provider logo and PMP are registered marks of the Project Management Institute, Inc
108Project Management Framework Version 1.0 Project Management Framework
Course Structure
Project Scope Management
Introduction
Project Scope Management - Introduction
Collect Requirements: Inputs, Tools, and Outputs
Collect Requirements
Verify Scope: Inputs, Tools, and Outputs
Verify Scope
Create WBS
Control Scope
Control Scope: Inputs, Tools, and Outputs
Create WBS: Inputs, Tools, and Outputs
Define Scope
Define Scope: Inputs, Tools, and Outputs
109Project Management Framework Version 1.0 Project Management Framework
IntroductionIntroduction
110Project Management Framework Version 1.0 Project Management Framework
Project Scope ManagementProject Scope Management
The processes required to ensure that the project includes all the work required, and only the work required to complete the project successfully.
It is primarily concerned with defining and controlling ‘what is’ and ‘what is not’ included in the project.
111Project Management Framework Version 1.0 Project Management Framework
Project Scope Management - ProcessesProject Scope Management - Processes
Collect Requirements: process of defining and documenting stakeholders’ needs to meet the project objectives.
Define Scope: process of developing a detailed description of the project and product.
Create WBS: process of subdividing project deliverables and project work into smaller, more manageable components.
Verify Scope: process of formalizing acceptance of the completed project deliverables.
Control Scope: process of monitoring the status of the project and product scope and managing changes to the scope baseline.
112Project Management Framework Version 1.0 Project Management Framework
Product Scope vs. Project ScopeProduct Scope vs. Project Scope
Product Scope: The features and functions that characterize a product, service, or result. Completion of the “product scope” is measured against the product requirements.
Project Scope: The work that needs to be accomplished to deliver a product, service, or result with the specified features and functions. Completion of the “project scope” is measured against the project management plan.
113Project Management Framework Version 1.0 Project Management Framework
Project Scope ManagementProject Scope Management The work involved in performing the five processes of Project Scope Management is
preceded by a planning effort by the project management team.
This planning effort is part of the Develop Project Management Plan process, This includes:
Time, Cost, and Scope management
Scope Management Plan process provides guidance on how project scope will be:
Defined Documented Verified Managed, and Controlled
114Project Management Framework Version 1.0 Project Management Framework
Collect RequirementsCollect Requirements
115Project Management Framework Version 1.0 Project Management Framework
Collect RequirementsCollect Requirements The process of defining and documenting stakeholders’ needs to meet the project
objectives.
Continue…
Categories of Requirements
Project Requirements Product Requirements
Business Requirements
Project management Requirements
Delivery Requirements
Technical Requirements
Security Requirements
Performance Requirements
116Project Management Framework Version 1.0 Project Management Framework
Collect RequirementsCollect Requirements
Requirements become the foundation of Scope definition.
The development of requirements begins with an analysis of the information contained in:
The project charter The stakeholder register
Cost, schedule, and quality planning are built on these requirements.
117Project Management Framework Version 1.0 Project Management Framework
Collect Requirements – Inputs, Tools, and OutputsCollect Requirements – Inputs, Tools, and Outputs
Project Charter Stakeholder register
Interviews Focus groups Facilitated workshops Group creativity techniques Group decision making techniques Questionnaires and surveys Observations Prototypes
Requirements documentation Requirements management
plan Requirements traceability
matrix
118Project Management Framework Version 1.0 Project Management Framework
Collect Requirements – Tools and TechniquesCollect Requirements – Tools and Techniques
Technique Key Characteristics Limitations
Interview A formal or informal method to find out information by talking to the stakeholders directly
Often conducted “one-on one”
Analysis of the data becomes difficult
Expensive and time consuming
Interviewer can be biased
Focus groups Bring stakeholders and subject matter experts together to learn about their expectations and attitudes towards a proposed product, service, or result
Trained moderator guides through an interactive discussion
More conversational than a one-on-one interview
Cost of finding a moderator with good facilitative skills and venue
May be dominated by one or two participants only
Analysis of the data becomes difficult and time consuming
Continue…
119Project Management Framework Version 1.0 Project Management Framework
Collect Requirements – Tools and TechniquesCollect Requirements – Tools and Techniques
Technique Key Characteristics Limitations
Facilitated
Workshops
Sessions to bring key cross-functional stakeholders together to define product requirements
A primary technique for quickly defining cross-functional requirements and reconciling stakeholder differences
Issues can be discovered and resolved more quickly than in individual sessions
Difficult to keep focused, clear purpose and desired outcome
May be dominated by powerful individuals
Group Creativity Technique
Brainstorming Nominal group technique The Delphi technique Idea/mind mapping Affinity diagram
Analysis of the data becomes difficult and time consuming
May loose the focus of the discussion
Continue…
120Project Management Framework Version 1.0 Project Management Framework
Collect Requirements – Tools and TechniquesCollect Requirements – Tools and Techniques
Technique Key Characteristics
Limitations
Group Decision
MakingTechniques
An assessment process of multiple alternatives with an expected outcome for future actions
Used to generate, classify, and prioritize product requirements
Multiple methods such as, Unanimity, Majority, Plurality, and Dictatorship
Time consuming May be dominated by
powerful people Problems and conflicts
occur due to non acceptance of some decisions
Questionnairesand Surveys
Written sets of questions designed to quickly gather information from wide number of audiences
Statistical analysis is appropriate
No response for selective items
Time consuming
Continue…
121Project Management Framework Version 1.0 Project Management Framework
Collect Requirements – Tools and TechniquesCollect Requirements – Tools and Techniques
Technique Key Characteristics Limitations
Observations A direct way of viewing individuals in their environment and how they perform their jobs or tasks
Can also be done by a “participant observer” who actually performs a process or procedure to experience how it is done
May land up collecting unimportant material
Unable to observe large population
Data analysis can be time consuming
Prototypes A method of providing a working model of the expected product before actually building it
Allows stakeholders to experiment with a model rather than only discussing abstract representations
Too slow process Time consuming and
expensive
122Project Management Framework Version 1.0 Project Management Framework
Collect Requirements – OutputsCollect Requirements – Outputs
Requirements Documentation: describes how individual requirements meet the business need for the project.
Format of a requirements documents may be,
Continue…
A simple document listing all the requirements categorized by stakeholder and priority
Elaborate forms containing executive summary, detailed descriptions, and attachments
123Project Management Framework Version 1.0 Project Management Framework
Collect Requirements – OutputsCollect Requirements – Outputs Requirements documentation include:
Business need or opportunity to be seized, describing the limitations of the current situation and what the project has been undertaken
Business and project objectives for traceability Functional requirements, describing business processes, information,
and interaction with the product, as appropriate which can be documented textually in a requirements list, in models, or both
Non-functional requirements, such as level of service, performance, safety, security, compliance, supportability, retention/purge, etc
Quality requirements Acceptance criteria Business rules stating the guiding principles of the organization Impacts to other organizational areas, such as the call center, sales force,
technology groups Impacts to other entities inside or outside the performing organization Support and training requirements Requirements assumptions and constraints
Continue…
124Project Management Framework Version 1.0 Project Management Framework
Collect Requirements – OutputsCollect Requirements – Outputs Requirements Management Plan: documents how requirements will
be analyzed, documented, and managed throughout the project.
How requirements activities will be planned, tracked, and reported Configuration management activities such as:
how changes to the product, service, or result requirements will be initiated,
how impacts will be analyzed, how they will be traced, tracked, and reported, as well as the authorization
levels required to approve these changes
Requirements prioritization process Product metrics that will be used and the rationale for using them Traceability structure, that is, which requirements attributes will be captured on the traceability matrix and to which other project documents requirements will be traced.
Requirements Management Plan includes:
Continue…
125Project Management Framework Version 1.0 Project Management Framework
Collect Requirements – OutputsCollect Requirements – Outputs
Requirements Traceability Matrix: Is a table that links requirements to their origin and
traces them throughout the project life cycle. Ensures that each requirement adds business value
by linking it to the business and project objectives. Provides a structure for managing changes to the
product scope.
This process includes tracing requirements to: Business needs, opportunities, goals, and objectives Project objectives Project scope/WBS deliverables Product design and development Test strategy and test scenarios, and More detailed requirements from high-level requirements
Sample RTM
126Project Management Framework Version 1.0 Project Management Framework
Collect RequirementsCollect Requirements
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 5-3. Page 106.
127Project Management Framework Version 1.0 Project Management Framework
Define Scope Define Scope
128Project Management Framework Version 1.0 Project Management Framework
Define Scope
The process of developing a detailed description of the project and product.
A detailed project scope statement is critical to project success and builds upon the major deliverables, assumptions, and constraints that are documented during project initiation.
During planning, the project scope is defined and described with greater specificity as more information about the project is known.
129Project Management Framework Version 1.0 Project Management Framework
Define Scope – Inputs, Tools, and OutputsDefine Scope – Inputs, Tools, and Outputs
Project Charter - If in the performing
organization, project charter is not used then comparable information needs to be acquired and used as a basis for the detailed project scope statement.
Requirements documentation
Organizational process assets
Expert judgment Product analysis Alternatives
identification Facilitated workshops
Project scope statement
Project document updates
130Project Management Framework Version 1.0 Project Management Framework
Define Scope – OutputsDefine Scope – Outputs
Project Document Updates:
Stakeholder register Requirements documentation, and Requirements traceability matrix
The detailed project scope statement includes:
Product scope description Product acceptance criteria
Project deliverables Project exclusions Project constraints Project assumptions
131Project Management Framework Version 1.0 Project Management Framework
Define Scope Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 5-5. Page 113.
132Project Management Framework Version 1.0 Project Management Framework
Create WBSCreate WBS
133Project Management Framework Version 1.0 Project Management Framework
Create WBSCreate WBS
Create Work Breakdown Structure (WBS) is the process of subdividing project deliverables and project wok into smaller, more manageable components.
Requirements become the foundation of WBS.
The WBS is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to: Accomplish project objectives and Create required deliverables
The lowest level of WBS component are called work packages and it can be:
Scheduled Cost Estimated Monitored Controlled
134Project Management Framework Version 1.0 Project Management Framework
Create WBS – Inputs, Tools, and OutputsCreate WBS – Inputs, Tools, and Outputs
Project scope statement Requirements
documentation Organizational process a
ssets
Decomposition
WBS WBS dictionary Scope baseline Project document upd
ates
135Project Management Framework Version 1.0 Project Management Framework
Create WBS – OutputsCreate WBS – Outputs
WBS
WBS dictionary A document generated by the Create
WBS process that supports the WBS.
Scope baseline Project scope statement WBS WBS dictionary
Project document updates
Project Scope Statement
136Project Management Framework Version 1.0 Project Management Framework
Work Breakdown StructureWork Breakdown Structure
137Project Management Framework Version 1.0 Project Management Framework
Work Breakdown Structure - ExampleWork Breakdown Structure - Example
RSD – Requirement Specification Design
RTM – Requirement Traceability Matrix
138Project Management Framework Version 1.0 Project Management Framework
Create WBS Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 5-7. Page 117.
139Project Management Framework Version 1.0 Project Management Framework
Verify ScopeVerify Scope
140Project Management Framework Version 1.0 Project Management Framework
Verify ScopeVerify Scope The process of formalizing acceptance of the completed project deliverables.
Verify Scope includes:
Reviewing deliverables to ensure satisfactory completion
Obtaining formal acceptance of deliverables
141Project Management Framework Version 1.0 Project Management Framework
Scope Verification vs. Quality Control Scope Verification vs. Quality Control
Scope verification is primarily concerned with the acceptance of deliverables, while quality control is primarily concerned with meeting quality requirements specified for the deliverables.
If the project is terminated early, the project scope verification process should establish and document the extent of completion.
142Project Management Framework Version 1.0 Project Management Framework
Verify Scope – Inputs, Tools, and OutputsVerify Scope – Inputs, Tools, and Outputs
Project management plan Requirements documentation Requirements traceability
matrix Validated deliverables
- Completed and checked for correctness by the Perform Quality Control process.
Inspection Accepted deliverables Change requests Project document updates
143Project Management Framework Version 1.0 Project Management Framework
Verify Scope – OutputsVerify Scope – Outputs
Accepted deliverables: Formal documentation received from the customer or sponsor acknowledging stakeholder acceptance of the project’s deliverables is forwarded to the Close project or Phase process.
Project Document Updates: Include any documents that define the product or report status on product completion.
Change requests
144Project Management Framework Version 1.0 Project Management Framework
Verify Scope – OutputsVerify Scope – Outputs
IntegratedChangeControl
Deliverable
Accepted
Close Documented forNon-acceptance
Not Accepted
Yes NoChange Request
Defect Repair
145Project Management Framework Version 1.0 Project Management Framework
Verify Scope Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 5-12. Page 123.
146Project Management Framework Version 1.0 Project Management Framework
Control ScopeControl Scope
147Project Management Framework Version 1.0 Project Management Framework
Control Scope
The process of: Monitoring the status of the project and product scope Managing changes to the scope baseline
It ensures that all requested changes and recommended corrective actions are processed through the Perform Integrated Change Control process.
It is also used to manage the actual changes when they occur and integrated with other control processes.
Uncontrolled changes are often referred to as project scope creep.
148Project Management Framework Version 1.0 Project Management Framework
Control Scope – Inputs, Tools, and OutputsControl Scope – Inputs, Tools, and Outputs
Project management plan - Contains: Scope baseline,
Scope management plan, Change management plan, Configuration management plan, and Requirements management plan.
Work performance information
Requirements documentation
Requirements traceability matrix
Organizational process assets
Variance analysis- Determining the cause and degree of variance relative to the scope baseline- Deciding whether corrective or preventive action is required.
Work performance measurement
Organizational process assets updates
Change requests Project management plan
updates Project document updates
149Project Management Framework Version 1.0 Project Management Framework
Control Scope – OutputsControl Scope – Outputs
Work performance measurement
Organizational process assets updates
Change requests
Project management plan updates Scope Baseline Updates Other Baseline Updates
Project document updates
150Project Management Framework Version 1.0 Project Management Framework
Control Scope Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 5-14. Page 126.
151Project Management Framework Version 1.0 Project Management FrameworkThe PMI Registered Education Provider logo and PMP are registered marks of the Project Management Institute, Inc
152Project Management Framework Version 1.0 Project Management Framework
PROJECT TIME MANAGEMENTPROJECT TIME MANAGEMENT
The PMI Registered Education Provider logo and PMP are registered marks of the Project Management Institute, Inc
153Project Management Framework Version 1.0 Project Management Framework
Course StructureProject Time Management
Introduction
Project Time Management – Introduction
Define Activities : Inputs, Tools, and Outputs
Define Activities
Estimate Activity Duration : Inputs, Tools, and Outputs
Estimate Activity Duration
Estimate Activity Resources
Develop Schedule
Develop Schedule : Inputs, Tools, and Outputs
Estimate Activity Resources : Inputs, Tools, and Outputs
Sequence Activities
Sequence Activities : Inputs, Tools, and Outputs
Control Schedule
Control Schedule : Inputs, Tools, and Outputs
154Project Management Framework Version 1.0 Project Management Framework
Project Time Management – IntroductionProject Time Management – Introduction
155Project Management Framework Version 1.0 Project Management Framework
Project Time Management – IntroductionProject Time Management – Introduction The processes required to manage timely completion of the project.
They include the following:
Define Activities - process of identifying the specific actions to be performed to produce the project deliverables.
Sequence Activities - process of identifying and documenting relationships among the project activities.
Estimate Activity Resources - process of estimating the type and quantities of material, people, equipment, or supplies required to perform each activity.
Estimate Activity Durations - process of approximating the number of work periods needed to complete individual activities with estimated resources.
Continue…
156Project Management Framework Version 1.0 Project Management Framework
Project Time Management – IntroductionProject Time Management – Introduction
Develop Schedule - process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
Control Schedule - process of monitoring the status of the project to update project progress and managing changes to the schedule baseline.
*Note: Majority of effort in the Project Time Management is incurred in the Control Schedule process to ensure completion of project work on time.
157Project Management Framework Version 1.0 Project Management Framework
Project Time Management – IntroductionProject Time Management – Introduction
158Project Management Framework Version 1.0 Project Management Framework
Scheduling OverviewScheduling Overview
159Project Management Framework Version 1.0 Project Management Framework
Define ActivitiesDefine Activities
160Project Management Framework Version 1.0 Project Management Framework
Define ActivitiesDefine Activities The process of identifying the specific actions to be performed to produce the
project deliverables.
Project work packages that are decomposed into smaller components called activities to provide basis for:
Estimating Scheduling Executing Monitoring and Controlling the project work
161Project Management Framework Version 1.0 Project Management Framework
Define Activities – Inputs, Tools, and OutputsDefine Activities – Inputs, Tools, and Outputs
Scope baseline
Enterprise environmental factors
Organizational process assets
Decomposition- Involving team members in the decomposition can lead to better and more accurate results.
Rolling wave planning
Templates
Expert judgment
Activity list
Activity attributes
Milestone list
162Project Management Framework Version 1.0 Project Management Framework
Rolling Wave PlanningRolling Wave Planning
A form of progressive elaboration planning where, - the work to be accomplished in the near term is planned in detail and
- future work is planned at a higher level of the WBS.
Work can exist at various levels of detail depending on where it is in the project life cycle.
163Project Management Framework Version 1.0 Project Management Framework
Define Activities Data Flow DiagramDefine Activities Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 6-4. Page 133.
164Project Management Framework Version 1.0 Project Management Framework
Define Activities – OutputsDefine Activities – Outputs
Activity list- It is a comprehensive list including all schedule activities required on the project.
Activity attributes- Extend the description of the activity by identifying the multiple components associated with each activity.
Milestone list- A milestone is a significant point or event in the project.
Mandatory (Such as those required by contract) - Milestone List
Optional (Such as those based upon historical information)
165Project Management Framework Version 1.0 Project Management Framework
Sequence ActivitiesSequence Activities
166Project Management Framework Version 1.0 Project Management Framework
Sequence ActivitiesSequence Activities The process of identifying and documenting relationships among project
activities. Activities are sequences using logical relationships.
Every activity and milestone except the first and last are connected to at least one predecessor and one successor.
It may be necessary to use lead and lag time between activities to support a realistic and achievable project schedule.
Sequencing can be performed by using:- project management software or- manual or automated techniques
167Project Management Framework Version 1.0 Project Management Framework
Sequence Activities – Inputs, Tools, and OutputsSequence Activities – Inputs, Tools, and Outputs
Activity list Activity attributes Milestone list Project scope
statement Organizational proc
ess assets
Precedence Diagramming Method (PDM)
Dependency determination Applying leads and lags Schedule network templates
Project schedule network diagrams
Project document updates
168Project Management Framework Version 1.0 Project Management Framework
Sequence Activities Data Flow DiagramSequence Activities Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 6-6. Page 137.
169Project Management Framework Version 1.0 Project Management Framework
Precedence Diagramming Method (PDM)Precedence Diagramming Method (PDM) PDM is a method used in Critical Path Method (CPM) for constructing a project schedule network diagram.
It uses boxes or rectangles, referred to as nodes, to represent activities, and connects them with arrows that show the logical relationships that exist between them. Also known as Activity On Node (AON)
Four types of dependences included in PDM:
Finish-to-start (FS)
Finish-to-finish (FF)
Start-to-start (SS)
Start-to-finish (SF)
170Project Management Framework Version 1.0 Project Management Framework
Types of DependenciesTypes of Dependencies
FINISH START
F Completion of successor depends on completion of predecessor
Initiation of the successor depends on completion of the predecessor
S
Completion of the successor depends upon the initiation of predecessor
Initiation of the successor activity depends on the initiation of predecessor
171Project Management Framework Version 1.0 Project Management Framework
Types of DependenciesTypes of Dependencies
Finish to Finish
Start to Start
Finish to start
172Project Management Framework Version 1.0 Project Management Framework
Dependency DeterminationDependency DeterminationFollowing types of dependencies are used to define the sequence among the activities:
Mandatory dependencies – Those that are contractually required or inherent in the nature of the work being done (referred to as “Hard logic”).
Discretionary dependencies – Established based on - knowledge of best practices and unusual aspect of the project. (referred to as “preferred logic, preferential logic, or soft logic”)
Discretionary dependencies should be fully documented since they can create arbitrary total float values and can limit later scheduling options.
When fast tracking techniques are employed, these discretionary dependencies should be reviewed and considered for modification of removal.
Continue…
173Project Management Framework Version 1.0 Project Management Framework
Dependency DeterminationDependency Determination External dependencies – The project management team determines which
dependencies are external dung the process of sequencing the activities. Involves relationship between project activities and non-project activities (sub
contractors). These dependencies are usually outside the project team’s control.
174Project Management Framework Version 1.0 Project Management Framework
Estimate Activity ResourcesEstimate Activity Resources
175Project Management Framework Version 1.0 Project Management Framework
Estimate Activity ResourcesEstimate Activity Resources
The process of estimating the type and quantities of: Material People Equipment Supplies required to perform each activity.
It is closely coordinated with the Estimate Costs process.
176Project Management Framework Version 1.0 Project Management Framework
Estimate Activity Resources – Inputs, Tools, and Estimate Activity Resources – Inputs, Tools, and OutputsOutputs
Activity list Activity attributes Resource calendars Enterprise environment
al factors Organizational process
assets
Expert judgment Alternatives analysis Published estimating
data Bottom-up estimating
- When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail
Project management software
Activity resource requirements
Resource breakdown structure
Project document updates
177Project Management Framework Version 1.0 Project Management Framework
Estimate Activity Resources Data Flow DiagramEstimate Activity Resources Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 6-89 Page 142.
178Project Management Framework Version 1.0 Project Management Framework
Estimate Activity Resources – OutputsEstimate Activity Resources – Outputs
Resource breakdown structure
- It is a hierarchical structure of the identified resources by resource category and resource type.
- Examples of resource categories include: Labour Material Equipment Supplies
- Resource types can include: Skill level Grade level Other information as appropriate to the project.
- It is useful for organizing and reporting project schedule data with recourse utilization information.
179Project Management Framework Version 1.0 Project Management Framework
Estimate Activity DurationsEstimate Activity Durations
180Project Management Framework Version 1.0 Project Management Framework
Estimate Activity DurationsEstimate Activity Durations
The process of approximating the number of work period needed to complete individual activities with estimated resources.
The duration estimate is progressively elaborated, based on quality and availability of the input data and results in better and accurate estimates.
Continue…
181Project Management Framework Version 1.0 Project Management Framework
Estimate Activity DurationsEstimate Activity Durations
Using Project Calendar & Resource Calendar
Number of Work Periodsneeded (Activity Duration)
Amount of work effort required &Resources to be applied
182Project Management Framework Version 1.0 Project Management Framework
Estimate Activity Duration – Inputs, Tools, and Estimate Activity Duration – Inputs, Tools, and OutputsOutputs
Activity list Activity attributes Activity resource requirements Resource calendar Project scope statement Enterprise environmental factors Organizational process assets
Expert judgment Analogous estimating Parametric estimating Three-point estimates Reserve analysis
Activity duration estimates
Project document updates
183Project Management Framework Version 1.0 Project Management Framework
Estimate Activity Duration Data Flow DiagramEstimate Activity Duration Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 6-13. Page 153.
184Project Management Framework Version 1.0 Project Management Framework
Estimation MethodsEstimation Methods
1. Analogous Estimating:
Analogous duration estimating is frequently used to estimate project duration when there is a limited information
Uses parameters such as duration, budgets, size, weight, and complexity, from a previous, similar project, as the basis for estimation
Uses historical information and expert judgment. Is generally less costly and time consuming but also less accurate. Is most reliable when the previous activities are similar in fact and not just in
appearance, and the project team members preparing the estimates have the needed expertise.
Continue…
185Project Management Framework Version 1.0 Project Management Framework
Estimation MethodsEstimation Methods
2. Parametric Estimating:
Uses a statistical relationship between historical data and other variables (e.g. square feet in construction) to calculate an estimate for activity parameters, such as: cost. budget, and duration.
It can produce higher levels of accuracy depending upon the sophistication and underlying data built into the model.
It can be applied to a total project or to segments of project, in conjunction with other estimating methods.
Continue…
186Project Management Framework Version 1.0 Project Management Framework
Estimation MethodsEstimation Methods3.Three-Point Estimates:
The accuracy of activity duration estimates can be improved by considering estimation uncertainty and risk.
Program Evaluation and Review Technique (PERT) uses three estimates to define an approximate range for an activity's duration:
Most likely (tM) - Realistic expectation
Optimistic (tO) - Best-case
Pessimistic (tP) - Worst-case
PERT analysis calculates an Expected (tE) activity duration using a weighed average of these estimates
tE = (tO + 4tM + tP )
______________
6
Standard Deviation (SD) = (tP – tO ) / 6
Variance = ( SD ) 2 = [(tP – tO ) / 6 ] 2
187Project Management Framework Version 1.0 Project Management Framework
Example using PERT• For example, take a network with the following dependent tasks,
with each successor task having a finish-to-start relationship with the predecessor task:
The standard deviation of the total path is given by taking the square root of the sum of the squares of each task standard deviation.
188Project Management Framework Version 1.0 Project Management Framework
Sigma calculations
189Project Management Framework Version 1.0 Project Management Framework
Develop ScheduleDevelop Schedule
190Project Management Framework Version 1.0 Project Management Framework
Develop Schedule
The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
Developing an acceptable project schedule is often an iterative process.
It determines the planned start and finish dates for project activities and milestones (dates).
Revising and maintaining a realistic schedule continues throughout the project as work progresses, the project management plan changes, and the nature of risk events evolves.
191Project Management Framework Version 1.0 Project Management Framework
Develop Schedule – Inputs, Tools, and OutputsDevelop Schedule – Inputs, Tools, and Outputs
Activity list Activity attributes Project schedule network
diagrams Activity resource
requirements Resource calendars Activity duration estimates Project scope statement Enterprise environmental
factors Organizational process
assets
Schedule network analysis
Critical path method Critical chain method Resource levelling What-If scenario analysis Applying leads and lags Schedule compression Schedule tool
Project schedule Schedule baseline Schedule data Project document
updates
192Project Management Framework Version 1.0 Project Management Framework
Develop Schedule Data Flow DiagramDevelop Schedule Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 6-13. Page 153.
193Project Management Framework Version 1.0 Project Management Framework
Schedule Network Analysis
It is a technique to generate the project schedule.
It employs various analytical techniques, to calculate the early and late start and finish dates for the uncompleted portions of project activities.
These techniques are: Critical Path Method Critical Chain Method What-if Analysis Resource leveling
Develop Schedule – Tools and TechniquesDevelop Schedule – Tools and Techniques
194Project Management Framework Version 1.0 Project Management Framework
Critical Path Method (CPM)
This method calculates the theoretical early start and finish dates, and the late start and finish dates, for all activities without regard for any resource limitations.
This is done by performing a forward and backward pass analysis through the schedule network.
Develop Schedule – Tools and TechniquesDevelop Schedule – Tools and Techniques
Continue…
195Project Management Framework Version 1.0 Project Management Framework
Critical Path MethodCritical Path Method
Continue…
196Project Management Framework Version 1.0 Project Management Framework
Float = Late Start – Early Start (or) Late Finish – Early Finish
Critical Path MethodCritical Path Method
Demo-Float
Continue…
197Project Management Framework Version 1.0 Project Management Framework
Critical Path MethodCritical Path Method
Early start and finish dates and late start and finish dates – Affected by activity total float
Critical paths – A zero or negative total float
Critical Activities – Schedule activities on a critical path
Networks can have multiple near critical paths
Positive difference between early and late dates –Total Float
198Project Management Framework Version 1.0 Project Management Framework
Critical Chain Method
The resource-constrained critical path is known as the critical chain.
After the critical path is identified, resource availability is entered and the resource-limited schedule result is determined.
Determining schedule status by comparing
Develop Schedule – Tools and TechniquesDevelop Schedule – Tools and Techniques
amount of buffer remaining
amount of buffer needed to protect the delivery date
Difference between the buffer needed and the buffer remaining, determine if corrective action is appropriate.
199Project Management Framework Version 1.0 Project Management Framework
Resource leveling
A schedule network analysis technique applied to a schedule that has already been analyzed by the critical path method.
Used when shared or critical required resources are only available at certain time, in limited quantities, or to keep resource usage at a constant level.
Often cause the original critical path to change.
Develop Schedule – Tools and TechniquesDevelop Schedule – Tools and Techniques
200Project Management Framework Version 1.0 Project Management Framework
What-If Scenario Analysis (Monte Carlo Analysis)
An analysis of the question “What if the situation represented by scenario ‘X’ happens?”
Develop Schedule – Tools and TechniquesDevelop Schedule – Tools and Techniques
Applying Leads and Lags
Refinements applied during network analysis to develop a viable schedule.
201Project Management Framework Version 1.0 Project Management Framework
Crashing
Fast Tracking
Schedule Compression
Shortens the project schedule without changing the project scope.
Develop Schedule – Tools and TechniquesDevelop Schedule – Tools and Techniques
Scheduling Tool
Expedite the scheduling process by generating start and finish dates based on:
the inputs of activities network diagrams resources and activity durations
202Project Management Framework Version 1.0 Project Management Framework
Develop Schedule – OutputsDevelop Schedule – Outputs
Project Schedule
Includes a planned start date and planned finish date for each activity. Can be presented in summary form, sometimes referred to as the master schedule or
milestone schedule or presented in details Project schedule can be presented in any of the following forms:
206Project Management Framework Version 1.0 Project Management Framework
Control ScheduleControl Schedule
207Project Management Framework Version 1.0 Project Management Framework
Control ScheduleControl Schedule The process of monitoring the status of the project to update project progress and
manage changes to the schedule baseline.
It is concerned with: Determining the current status of the project schedule Influencing the factors that create schedule changes Determining that the project schedule has changed Managing the actual changes as they occurs
It is a component of the Perform Integrated Change Control process.
208Project Management Framework Version 1.0 Project Management Framework
Control Schedule – Inputs, Tools, and OutputsControl Schedule – Inputs, Tools, and Outputs
Project management plan
Project schedule Work performance
information Organizational
process assets
Performance review Variance analysis Project management
software Resource leveling What-if scenario
analysis Adjusting leads and
lags Schedule compression Scheduling tool
Work performance measurement
Organizational process assets updates
Change requests Project management plan Project document updates
209Project Management Framework Version 1.0 Project Management Framework
Control Schedule Data Flow DiagramControl Schedule Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 6-16. Page 161.
210Project Management Framework Version 1.0 Project Management Framework
Control Schedule - OutputsControl Schedule - Outputs Work performance measurement
- The work packages and control accounts, are documented and communicated to stakeholders.
Organizational process assets updates - Causes of variances - Corrective action chosen and the reasons - Other types of lessons learned from project schedule control
Change requests Project management plan
- Schedule baseline - Schedule management plan - Cost baseline
Project document updates - Schedule Data - Project Schedule
211Project Management Framework Version 1.0 Project Management FrameworkThe PMI Registered Education Provider logo and PMP are registered marks of the Project Management Institute, Inc
212Project Management Framework Version 1.0 Project Management Framework
PROJECT COST MANAGEMENTPROJECT COST MANAGEMENT
The PMI Registered Education Provider logo and PMP are registered marks of the Project Management Institute, Inc
213Project Management Framework Version 1.0 Project Management Framework
Course Structure
Project Cost Management
Introduction
Project Cost Management – Introduction
Estimate Costs : Inputs, Tools, and Outputs
Estimate Costs
Control Costs
Control Costs : Inputs, Tools, and Outputs
Determine Budget
Determine Budget : Inputs, Tools, and Outputs
214Project Management Framework Version 1.0 Project Management Framework
IntroductionIntroduction
215Project Management Framework Version 1.0 Project Management Framework
Project Cost Management - IntroductionProject Cost Management - Introduction It includes the processes involved in estimating, budgeting and controlling costs so that
the project can be completed within the approved budget.
Project Cost Management includes:
Estimate Costs – process of developing an approximation of the monetary resources needed to complete project activities.
Determine Budget – process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.
Control Costs – process of monitoring the status of the project to update the project budget and managing changes to the cost baseline.
216Project Management Framework Version 1.0 Project Management Framework
On the smaller scope projects, cost estimating and cost budgeting are tightly linked and they are viewed as a single process.
The work involved in performing the Project Cost Management processes is preceded by a planning effort
This planning effort is part of the Develop Project Management Plan process, which produces a Cost Management Plan.
As example, the Cost Management Plan can establish:
Level of accuracy Unit of measure Organizational procedure links Control thresholds Rules of performance measurement Reporting formats Process descriptions
Project Cost Management - IntroductionProject Cost Management - Introduction
217Project Management Framework Version 1.0 Project Management Framework
It is primarily concerned with the cost of resources needed to complete schedule activities.
This broader view of Project Cost Management is called Life Cycle Costing, it should also consider the effect of project decisions on the cost of -
Using Maintaining and Supporting
the product, service, or result of the project.
Value Engineering
Project Cost Management - IntroductionProject Cost Management - Introduction
218Project Management Framework Version 1.0 Project Management Framework
Estimate CostsEstimate Costs
219Project Management Framework Version 1.0 Project Management Framework
Estimate CostsEstimate Costs
It is the process of developing an approximation of the monetary resources needed to complete the project activities.
It includes identification and consideration of costing alternatives such as make versus buy, buy versus lease, and the sharing of resources in order to achieve optimal costs.
The accuracy of an estimate will increase as the project progresses through the project life cycle and thus, cost estimating is an iterative process from phase to
phase.
±50% Rough Order of Magnitude (ROM)
Acc
ura
cy
±10% Definitive Estimate
220Project Management Framework Version 1.0 Project Management Framework
Estimate Costs – Inputs, Tools, and OutputsEstimate Costs – Inputs, Tools, and Outputs
Scope baselineScope statement- Work breakdown structure- WBS dictionary
Project schedule Human resource plan Risk register Enterprise environmental
factors Organizational process
assets
Expert judgement Analogous estimating Parametric estimating Bottom-up estimating Three-point estimates Reserve analysis Cost of quality Project management
estimating software Vendor bid analysis
Activity cost estimates Basis of estimates Project document
updates
221Project Management Framework Version 1.0 Project Management Framework
Estimate Costs Data Flow DiagramEstimate Costs Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 7-3. Page 169.
222Project Management Framework Version 1.0 Project Management Framework
Estimate Costs – Tools and TechniquesEstimate Costs – Tools and Techniques
Expert Judgment
• Guided by historical information
• Determine use of combined methods of estimating
• Reconcile differences between these methods
Top-down Estimating
Analogous Estimating Parametric Estimating
• Relies on the actual cost of previous similar projects • Uses historical information and expert judgment• Used when limited amount of detailed information about the project is available• Less costly, time consuming, and less accurate• Applies to a total project or to segments of a project
• Uses a statistical relationship between historical data and other variables• Produces higher levels of accuracy• Applies to a total project or to segments of a project
223Project Management Framework Version 1.0 Project Management Framework
Estimate Costs – Tools and TechniquesEstimate Costs – Tools and Techniques
Bottom-Up Estimating
• A method of estimating a component of work
• Detailed estimation on cost of individual work packages or activities
• Summarizing detailed cost for subsequent reporting and tracking purposes
• Cost and accuracy depends on the size and complexity of individual activity or work package
224Project Management Framework Version 1.0 Project Management Framework
Estimate Costs – Tools and TechniquesEstimate Costs – Tools and Techniques
Three-Point Estimates
PERT analysis calculated an expected (CE) activity cost using a weighted average
of these three estimates.
• Accuracy of single-point activity cost estimates can be improved by considering estimation uncertainty and risk
• Three estimates to define an approximate range for an activity’ cost:
– Most likely (CM)
– Optimistic (CO)
– Pessimistic (CP)
• Add-on techniques– Reserve Analysis– Cost of Quality (COQ)– Project Management Estimating Software– Vendor Bid Analysis
CE = CO +4CM +CP
6
225Project Management Framework Version 1.0 Project Management Framework
Estimate Costs - Outputs Estimate Costs - Outputs
Activity Cost Estimates
Cost can be either Variable or Fixed
Variable Cost: Cost changes with the amount of work (e.g. Material Cost)
Fixed Cost: Cost does not change with the amount of work (e.g. Rentals)
Cost can be either Direct or Indirect
Direct Cost: Costs that are directly attributable to work on the project. (Team Wages)
Indirect Cost: Overheads or costs incurred for the benefit of more than one project. (h/w, s/w purchased)
226Project Management Framework Version 1.0 Project Management Framework
Estimate Costs – OutputsEstimate Costs – Outputs
Basis of estimates- The amount and type of additional details supporting the cost estimate vary by application area.
- Supporting details for activity cost estimates provide a clear and complete
understanding of how the cost estimate was derived.
Project document updates- For example, Risk register
227Project Management Framework Version 1.0 Project Management Framework
Determine BudgetDetermine Budget
228Project Management Framework Version 1.0 Project Management Framework
Determine BudgetDetermine Budget
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.
Project budgets constitute the funds authorized to execute the project.
This baseline includes all authorized budgets, but excludes management reserves.
Project cost performance will be measured against the authorized budget.
Cash Flow, Cost Baseline and Funding - Graphical Display
230Project Management Framework Version 1.0 Project Management Framework
Determine Budget – Inputs, Tools, and OutputsDetermine Budget – Inputs, Tools, and Outputs
Activity cost estimates Basis of estimates Scope baseline
- Scope Statement- Work breakdown structure- WBS dictionary
Project schedule Resource calendars Contracts Organizational process
assets
Cost aggregation Reserve analysis Expert judgment Historical
relationships Funding limit
reconciliation
Cost performance baseline
Project funding requirements
Project document updates
231Project Management Framework Version 1.0 Project Management Framework
Determine Budget Data Flow DiagramDetermine Budget Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 7-5. Page 175.
232Project Management Framework Version 1.0 Project Management Framework
Determine Budget – Tools and Techniques Determine Budget – Tools and Techniques
Reserve Analysis
It can establish both, the contingency reserves and the management reserves for the project.
Contingency reserves – Allowances for unplanned but potentially required changes that can result from realized risks identified in the risk register.
Management reserves – Budgets reserves for unplanned changes to project scope and cost.
Reserves are not a part of the project cost baseline, but may be included in the total budget for the project and they are not included as a part of the earned value measurement calculations.
233Project Management Framework Version 1.0 Project Management Framework
Cost Roll UpCost Roll Up
234Project Management Framework Version 1.0 Project Management Framework
Control CostsControl Costs
235Project Management Framework Version 1.0 Project Management Framework
Control CostsControl Costs The process of monitoring the status of the project to update the project budget and managing changes to the cost baseline.
Any increase to the authorized budget can only be approved through the Perform Integrated Change Control process.
The key to effective cost control is the management of the approved cost performance baseline and the changes to that baseline.
What type of different activities could be included? Influencing factors that create changes to cost baseline.
Ensuring that all change requests are acted on in a timely manner. Managing the actual changes when and as they occur. Ensuring that cost expenditure do not exceed the authorized funding, by period and in total
for the project. Monitoring cost performance to isolate and understand variance from the approved cost
baseline. Monitoring work performance against funds expended. Preventing unapproved changes from being included in the reported cost or resource usage. Incoming appropriate stakeholders of all approved changes and associated cost. Acting to bring expected cost overruns within acceptable limits.
236Project Management Framework Version 1.0 Project Management Framework
Control Costs – Inputs, Tools, and OutputsControl Costs – Inputs, Tools, and Outputs
Project management plan Project funding
requirements Work performance
information Organizational process
assets
Earned value management Forecasting To-complete performance
index Performance reviews Variance analysis Project management software
Work performance measurements
Budge forecasts Organizational process
assets updates Change requests
- Analysis of project performance can result to the cost performance baseline or other components of the project management plan.
Project management plan updates
Project document updates
237Project Management Framework Version 1.0 Project Management Framework
Control Costs Data Flow DiagramControl Costs Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 7-8. Page 180.
238Project Management Framework Version 1.0 Project Management Framework
Earned Value Management (EVM) integrates project scope, cost, and schedule measures to help the project management team assess and measure project performance and progress.
Planned Value (PV): Estimated value of the work planned to be done.Earned Value (EV): Estimated value of the work actually
accomplished.Actual Cost (AC): Actual money spent for the work accomplished.Budget at Completion (BAC): Budget for the total project work.
Important Terms:
Control Costs – Tools and TechniquesControl Costs – Tools and Techniques
239Project Management Framework Version 1.0 Project Management Framework
Earned Value, Planned Value, and Actual CostsEarned Value, Planned Value, and Actual Costs
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 7-9. Page 183.
240Project Management Framework Version 1.0 Project Management Framework
ForecastingForecasting
The project team can develop a forecast for the estimate at completion(EAC) that may differ from the budget at completion (BAC) based on the project performance.
Estimate at Completion (EAC): How much at present we expect total project to cost.
Estimate to Complete (ETC): How much more, at present, we expect it to cost to finish the project.
Variance at Completion (VAC): How much over or under budget, do we expect to be at the end of project.
Control Costs – Tools and TechniquesControl Costs – Tools and Techniques
241Project Management Framework Version 1.0 Project Management Framework
Cost Management Formulae Cost Management Formulae Item Formula Remark
Cost Variance (CV) EV – AC Negative value indicates over budget and positive value indicates under budget
Schedule Variance (SV) EV – PV Negative value indicates behind schedule and positive value indicates ahead of schedule
Cost Performance Index (CPI) EV / AC Lesser than one indicates over budget and greater than one indicates under budget
Schedule Performance Index (SPI)
EV / PV Lesser than one indicates behind schedule and greater than one indicates ahead of schedule
Estimate at Completion (EAC) BAC / CPI Considering that the rate of spending remains the same
AC + ETC Considering that the current estimate is fundamentally flawed
AC + (BAC – EV) Considering atypical variances
AC + [(BAC – EV) / CPI]
Considering typical variances
Estimate to Complete (ETC) EAC – AC Considering that the current estimate is fundamentally flawed
BAC – EV Considering atypical variances
(BAC – EV) / CPI Considering typical variances
Variance at Completion (VAC) BAC – EAC Considering the status of the budget expected at the end of the project
242Project Management Framework Version 1.0 Project Management Framework
To-Complete Performance Index (TCPI)To-Complete Performance Index (TCPI)
Control Costs – Tools and TechniquesControl Costs – Tools and Techniques
If it becomes obvious that the BAC is no longer viable, then the project manager develops a forecasted estimate at completion (EAC).
Work Remaining (BAC – EV) = TCPIFunds Remaining (BAC – AC) or (EAC – AC)
Once approved, the EAC effectively supersedes the BAC as the cost performance goal.
The calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal, such as the BAC or the EAC.
243Project Management Framework Version 1.0 Project Management Framework
Important Financial Terms Important Financial Terms Financial Term Definition
Benefit Cost Ratio (BCR)
Compares the benefits (revenues) to the costs of different options
Chart of Accounts
Any numbering system used to monitor project costs by category (for example, labor, supplies, and materials)
Depreciation Reduced price of an asset over time attributable to deterioration, obsolescence, and impending retirement Applies particularly to physical assets such as equipment and structures Straight Line depreciation: Standard amount depreciating every year Accelerated depreciation: Value depreciating at a faster rate, for example, Double Declining method and Sum of the Years Digits
Internal Rate of Return (IRR)
Rate at which the project inflows and project outflows are equal Project with greatest IRR is generally selected
Net Present Value (NPV)
Present value of the total benefits minus costs over many time periods Investment is profitable for positive NPV Project with greatest NPV is selected
Opportunity Cost
Opportunity given up by selecting one project over another
Payback Period Time period it takes to recover the investment made in the project before the profits start accumulating
Present Value The current value of future cash flows.
Sunk Cost Expended costs, to be avoided when deciding whether to continue with a troubled project
244Project Management Framework Version 1.0 Project Management FrameworkThe PMI Registered Education Provider logo and PMP are registered marks of the Project Management Institute, Inc
245Project Management Framework Version 1.0 Project Management Framework
PROJECT HUMAN RESOURCE MANAGEMENTPROJECT HUMAN RESOURCE MANAGEMENT
The PMI Registered Education Provider logo and PMP are registered marks of the Project Management Institute, Inc
246Project Management Framework Version 1.0 Project Management Framework
Course Structure
Project Human Resource Management
Introduction
Project Human Resource Management Skills
Develop Human Resource Plan : Inputs, Tools, and Outputs
Project Human Resource Management Processes
Human Resource Theories
Develop Human Resource Plan
Develop Project Team : Inputs, Tools, and Outputs
Develop Project Team
Acquire Project Team
Acquire Project Team : Inputs, Tools, and Outputs
Manage Project Team
Manage Project Team : Inputs, Tools, and Outputs
247Project Management Framework Version 1.0 Project Management Framework
Project Human Resource Management SkillsProject Human Resource Management Skills
Project Human Resource Management relies on the substantial body of literature
about dealing with people.
248Project Management Framework Version 1.0 Project Management Framework
Project Human Resource Management - IntroductionProject Human Resource Management - Introduction
Project Human Resource Management includes the processes that organize, manage, and lead the project team.
The project team is comprised of the people who have been assigned roles and responsibilities for completing the project.
Involvement and participation of team members in project planning and decision making can be beneficial and early involvement adds their expertise and strengthens their commitment to the project.
The project management team (referred as the core, executive, or leadership team) is a subset of the project team and is responsible for the project management and leadership activities.
249Project Management Framework Version 1.0 Project Management Framework
Project Human Resource Management - IntroductionProject Human Resource Management - Introduction
Managing and leading the project team includes:
Influencing the project team
Professional and ethical behavior
Human Resource factors that may impact the project:
Team environmentGeographical locations of team membersCommunications among stakeholdersInternal and external politicsCultural issuesOrganizational uniqueness
250Project Management Framework Version 1.0 Project Management Framework
251Project Management Framework Version 1.0 Project Management Framework
Develop Human Resource PlanDevelop Human Resource Plan
It is the process of identifying and documenting:
Project roles, responsibilities, and required skills
Reporting relationships and
Creating a staffing management plan
252Project Management Framework Version 1.0 Project Management Framework
Develop Human Resource PlanDevelop Human Resource Plan
It also documents:
Timetable for staff acquisition and release Identification of training needs Team-building strategies Plans for recognition and rewards programs Compliance considerations Safety issues Impact of the staffing management
plan on the organization
The availability of, or competition for, scarce or limited human resources should be considered.
253Project Management Framework Version 1.0 Project Management Framework
Develop Human Resource Plan – Inputs, Tools, Develop Human Resource Plan – Inputs, Tools, and Outputsand Outputs
Activity resource requirements Enterprise environmental factors Organizational process assets
Organization charts and position descriptions
Networking Organizational theory
Human resource plan
254Project Management Framework Version 1.0 Project Management Framework
Develop Human Resource Plan – Tools and TechniquesDevelop Human Resource Plan – Tools and Techniques
Organization Charts Position Descriptions
Hierarchical Matrix-based
- A responsibility assignment matrix (RAM) is used to illustrate the connections between work packages or activities and project team members. - One example of RAM is RACI (responsible, accountable, consult, and inform)
Text-orientedformats
Other sectionsof the Project Management Plan
- Responsibilities related to managing the project are listed and explained in other sections of the project management plan. - For example, risk register lists risk owners, communication plan lists team members responsible for communication activities.
255Project Management Framework Version 1.0 Project Management Framework
Develop Human Resource Plan – Tools and Develop Human Resource Plan – Tools and TechniquesTechniques
Networking – Formal and informal interaction with others in an organisation, industry, or professional environment.
Organizational Theory – Provides information regarding the way in which people, teams, and organizational units behave.
256Project Management Framework Version 1.0 Project Management Framework
1. Maslow’s Hierarchy of Needs:
Human Resource TheoriesHuman Resource Theories
257Project Management Framework Version 1.0 Project Management Framework
Human Resource TheoriesHuman Resource Theories
2. Hezberg’s Theory of Motivation:
Presence of hygiene factors will not motivate people to perform as these are expected, however, their absence will demotivate performance.
258Project Management Framework Version 1.0 Project Management Framework
Human Resource TheoriesHuman Resource Theories
3. McGregor’s Theory of X and Y:
‘X’ (Micro Management)
‘Y’ (Self Motivated)
4. Expectancy Theory:
People will behave based on what they expect as a result of their
behavior.
259Project Management Framework Version 1.0 Project Management Framework
Develop Human Resource Plan – OutputsDevelop Human Resource Plan – Outputs
Human Resource Plan include: Roles and responsibilities
Role Authority Responsibility Competency
Project organization chart
Staffing Management Plan includes: Staff Acquisition Resource calendars (Resource Histogram) Staff release plan Training Needs Recognition and Rewards Compliance Safety
261Project Management Framework Version 1.0 Project Management Framework
Acquire Project TeamAcquire Project Team
The project management team have limited control over selecting the team members due to:
Collective bargaining agreements, Use of subcontractor personnel, Matrix project environment, Internal or external reporting relationships
and other various reasons
It is the process of confirming human resource availability and obtaining the team necessary to complete project assignments.
Continue…
262Project Management Framework Version 1.0 Project Management Framework
Acquire Project TeamAcquire Project Team Impact of unavailability of the required human resources get reflected in:
Project schedules Project budgets Customer satisfaction Project quality Project risks Training plans and the other project
management plan as required
263Project Management Framework Version 1.0 Project Management Framework
Acquire Project Team – Inputs, Tools, and OutputsAcquire Project Team – Inputs, Tools, and Outputs
Project management plan Enterprise environmental
factors Organizational process
assets
Pre-assignment Negotiation Acquisition Virtual teams
Project staff assignments
Resource availability
Staffing management plan updates
264Project Management Framework Version 1.0 Project Management Framework
Virtual Teams
Groups of people with a shared goal who fulfill their roles with little or no time meeting face to face.
The availability of electronic communication such as e-mail, audio conferencing, web-based meetings and video conferencing has made such teams feasible.
Communications planning becomes increasingly important in a Virtual Team Environment.
Acquire Project Team – Tools and TechniquesAcquire Project Team – Tools and Techniques
265Project Management Framework Version 1.0 Project Management Framework
Develop Project TeamDevelop Project Team
It is the process of improving
To achieve high performance and to meet the project’s objectives, project managers should have skills to:
Identify Build Maintain Motivate, Lead, and Inspire project teams
Competencies
Interactions
Overall environment
Continue…
266Project Management Framework Version 1.0 Project Management Framework
Develop Project TeamDevelop Project Team
Teamwork is critical for project success, and developing effective project teams is one of the primary responsibilities of the project manager.
Project managers should motivate their team by: Providing challenges and opportunities Providing timely feedback and support as needed Recognizing and rewarding good performance
High team performance can be achieved by: Using open and effective communication Developing trust among team members Managing conflicts in a constructive manner Encouraging collaborative problem-solving
and decision-making
Continue…
267Project Management Framework Version 1.0 Project Management Framework
Develop Project Team – Inputs, Tools, and OutputsDevelop Project Team – Inputs, Tools, and Outputs
Project staff assignments
Project management plan
Resource calendars
Interpersonal skills Training Team-building
Activities Ground rules Co-location Recognition and
rewards
Team performance assessments Enterprise environmental factors
updates
268Project Management Framework Version 1.0 Project Management Framework
Team-Building Activities Forming Storming Norming Performing Adjourning
Develop Project Team – Tools and TechniquesDevelop Project Team – Tools and Techniques
Co-location - Involves placing of the most active project team members in the same
physical location to enhance their ability to perform as a team.
- This may require, a team meeting room places to post schedules other conveniences that enhance communication and a sense of community.
Continue…
269Project Management Framework Version 1.0 Project Management Framework
Recognition and Rewards
– Recognition and Rewards should be given - willingness to work overtime to meet an aggressive schedule objective
– Recognition and rewards should not be given - need to work overtime due to poor planning by the team member
– Avoid win-lose (zero sum) rewards
– People are motivated When they feel they are valued in the organization
Develop Project Team – Tools and TechniquesDevelop Project Team – Tools and Techniques
Recognition and rewards should be given to make them feel that they are valued
270Project Management Framework Version 1.0 Project Management Framework
Team Performance Assessments
Develop Project Team – OutputsDevelop Project Team – Outputs
– The project management team makes formal or informal assessments of the project team’s effectiveness and as a result, the project management team can identify the specific: - training
- coaching - mentoring - assistance of changes required to improve the team’s performance.
– The evaluation of a team’s effectiveness include: Improvements in skills and competencies Reduced staff turnover rate Increased team cohesiveness
271Project Management Framework Version 1.0 Project Management Framework
Manage Project TeamManage Project Team
It is the process of:
Tracking team member performance Providing feedback Resolving issues Managing conflict Managing changes to optimize project performance Appraising team member performance
Continue…
272Project Management Framework Version 1.0 Project Management Framework
Manage Project TeamManage Project Team
As a result of managing project team:
Change requests are submitted. Human resource plan is updated. Issues are resolved. Input is provided for performance appraisal. Lesson learned are added to the organization database.
273Project Management Framework Version 1.0 Project Management Framework
Manage Project Team – Inputs, Tools, and OutputsManage Project Team – Inputs, Tools, and Outputs
Project staff assignments Project management plan Staffing management plan Team performance
assessment Performance reports Organizational process
assets
Observation and conversation
Project performance appraisals
Conflict management Issue log Interpersonal skills
Enterprise environmental factors updates
Organizational process assets updates
Change requests- Staffing changes, whether by choice or by uncontrollable events, can affect the rest of the project management plan.
Project management plan updates
274Project Management Framework Version 1.0 Project Management Framework
Leadership StylesLeadership Styles
Directing : Telling others what to do.
Facilitating : Coordinating the inputs of others.
Coaching : Instructing others.
Supporting : Providing assistance along the way.
Autocratic : Making decisions without gathering information from other team members.
Consultative : Inviting ideas and suggestions from team members.
Consensus : Problem solving in a group with decision making based on group agreement.
275Project Management Framework Version 1.0 Project Management Framework
Various Powers of a Project ManagerVarious Powers of a Project Manager
Formal (Legitimate)
Reward
Penalty (Coercive)
Expert
Referent
(Best forms of power are EXPERT and REWARD)
276Project Management Framework Version 1.0 Project Management Framework
Conflict ManagementConflict Management
Characteristics of conflict and the conflict management process: Conflict is natural and forces a search for alternatives Conflict is a team issue Openness resolves conflict Conflict resolution should focus on issues, not personalities Conflict resolution should focus on the present, not the past
Six general techniques for resolving conflict: Withdrawal / Avoidance Smoothing / Accommodating Compromise Forcing Collaborating Confronting / Problem Solving
277Project Management Framework Version 1.0 Project Management Framework
Interpersonal SkillsInterpersonal Skills Project managers use a combination of,
Technical Human Conceptual skills
To analyze situations and interact appropriately with team members
Using appropriate interpersonal skills aids project managers in capitalizing on the strengths of all team members.
278Project Management Framework Version 1.0 Project Management FrameworkThe PMI Registered Education Provider logo and PMP are registered marks of the Project Management Institute, Inc
279Project Management Framework Version 1.0 Project Management Framework
PROJECT COMMUNICATIONS MANAGEMENTPROJECT COMMUNICATIONS MANAGEMENT
280Project Management Framework Version 1.0 Project Management Framework
Course StructureProject Communications Management
Introduction
Basic Communication Model
Plan Communications : Inputs, Tools, and Outputs
Project Communications Management Processes
Plan Communications
Manage Stakeholder Expectation : Inputs, Tools, and Outputs
Distribute Information
Distribute Information : Inputs, Tools, and Outputs
Report Performance
Report Performance : Inputs, Tools, and Outputs
General Communication Dimensions
Manage Stakeholder Expectation
Identify Stakeholders
Identify Stakeholders : Inputs, Tools, and Outputs
281Project Management Framework Version 1.0 Project Management Framework
Project Communications ManagementProject Communications Management
It includes the processes required to ensure timely and appropriate: Generation Collection Distribution Storage Retrieval and Ultimate disposition of
project information
Continue…
Project Manager’s majority of time (90%) is spent in communicating with the project team and other stakeholders (internal or external to the organization).
282Project Management Framework Version 1.0 Project Management Framework
Project Communications Management Project Communications Management
Effective communication creates a bridge between diverse stakeholders involved
in a project by:Connecting various cultural and organizational backgroundsDifferent levels of expertise
Various perspectives and interests in the project execution or outcome
Continue…
283Project Management Framework Version 1.0 Project Management Framework
Project Communications ManagementProject Communications Management Communication activity has many potential dimensions, including:
Internal (within the project) and external (customer, other projects, the media, the public)
Formal (reports, memos, briefings) and informal (emails, ad-hoc discussions) Vertical (up and down the organization) and horizontal (with peers) Official (newsletters, annual report) and unofficial (off the record communications) Verbal and non-verbal (voice inflections, body language) Written and oral
Continue…
284Project Management Framework Version 1.0 Project Management Framework
Project Communications ManagementProject Communications Management Communication skills common for general and project management:
Listening actively and effectively Questioning, probing ideas and situations Educating to increase team’s knowledge Fact-finding to identify or confirm information Setting and managing expectations Persuading a person or organization Negotiating to achieve mutually
acceptable agreements between parties Resolving conflict to prevent disruptive
impacts Summarizing, recapping, and
identifying the next steps
285Project Management Framework Version 1.0 Project Management Framework
Project Communications Management - ProcessesProject Communications Management - Processes
286Project Management Framework Version 1.0 Project Management Framework
Identify StakeholdersIdentify Stakeholders
It is critical to identify stakeholders early in the project, and to analyze their levels of interests, expectations, importance, and influence.
A strategy can be developed for approaching each stakeholder and determining the level and timing of their involvement to maximize positive influences and mitigate potential negative impacts.
Stakeholders should be classified according to their interest, influence and involvement as this enables the project manager to focus on the relationships necessary to ensure the success of the project due to limited time.
287Project Management Framework Version 1.0 Project Management Framework
Identify Stakeholders – Inputs, Tools, and OutputsIdentify Stakeholders – Inputs, Tools, and Outputs
Project charter Procurement documents Enterprise environmental
factors Organizational process
assets
Stakeholder analysis Expert Judgement
Stakeholder register Stakeholder management
strategy
288Project Management Framework Version 1.0 Project Management Framework
Identify Stakeholders – Tools and TechniquesIdentify Stakeholders – Tools and Techniques
Stakeholder analysis – Generally follows three steps
Step 1: Identify all potential project stakeholders and relevant information
Step 2: Identify the potential impact each stakeholder could generate, and classify them so as to define an approach strategy.
Stakeholder’s classification models: Power/interest grid Power/influence grid Influence/impact grid Salience model
Continue…
Example
289Project Management Framework Version 1.0 Project Management Framework
Identify Stakeholders – Tools and TechniquesIdentify Stakeholders – Tools and Techniques
Step 3: Assess how key stakeholders are likely to react or respond in various
situations, in order to plan: How to influence them to enhance their support and Mitigate potential negative impacts
290Project Management Framework Version 1.0 Project Management Framework
Plan CommunicationsPlan Communications It determines information and communication needs of the project stakeholders. For
example: Who needs what information When they will need it How it will be given to them, and By whom
This process is tightly linked with enterprise environmental factors, because the organization’s structure will have a major effect on the project's communications requirements.
291Project Management Framework Version 1.0 Project Management Framework
Plan Communications – Inputs, Tools, and OutputsPlan Communications – Inputs, Tools, and Outputs
Stakeholder register Stakeholder management
strategy Enterprise environmental
factors Organizational process
assets
Communication requirements analysis
Communications technology
Communication models Communication methods
Communicationmanagement plan
Project documents updates
292Project Management Framework Version 1.0 Project Management Framework
Communications Requirements AnalysisCommunications Requirements Analysis
Number of communication channels : [ n ( n -1) ] 2
where n = Number of stakeholders
Continue…
293Project Management Framework Version 1.0 Project Management Framework
Communications Requirements AnalysisCommunications Requirements Analysis
Number of communication channels = [ n ( n -1) ]
2 = [ 5 ( 5 -1) ] 2 =10
294Project Management Framework Version 1.0 Project Management Framework
Communication TechnologyCommunication Technology
Factors that can affect the selection of communication technology in a project include:
Urgency of the need for information Availability of technology Expected project staffing Duration of the project Project environment
295Project Management Framework Version 1.0 Project Management Framework
Basic Communication ModelBasic Communication Model
The Sender is responsible for making the information Clear Unambiguous and Complete
so that the Receiver receives it correctly.
The Receiver is responsible for ensuring that the information is received in its entirety, understood correctly and acknowledged.
296Project Management Framework Version 1.0 Project Management Framework
Communication MethodsCommunication Methods Methods used to share information among project stakeholders are classified into:
Interactive communication – Between two or more parties performing multidirectional exchange of information.
e.g. meetings, phone calls, video conferencing, etc.
Push communication – Sent to specific recipients who need to know the information. e.g. letters, memos, reports, emails, etc.
Pull communication – Used for very large audiences that requires the recipients to access the communication content at their own discretion. e.g. intranet sites, e-learning, etc.
297Project Management Framework Version 1.0 Project Management Framework
Communications Management PlanCommunications Management Plan
The Communications Management Plan provides:
Stakeholder communication requirements. Information to be communicated. (Format, Content,
Level of detail) Person responsible for communicating the information. Methods or technology used to convey the information. Escalation process. Glossary of common terminology.
Continue…
298Project Management Framework Version 1.0 Project Management Framework
Communications Management PlanCommunications Management Plan
Type of Information
Purpose of Distribution
Document Format
Method of Distribution
FrequencyPerson
Responsible
Audience
Requirements gathering
To understand customer
requirements
MS Word document
Meeting and written
communication
During project
initiation
Project manager
Project team
Weekly status Project status update
MS Word document
E-mail communication followed by a
meeting
Weekly Project manager
All project stakeholders
Executive status
To check progress and
discuss corrective
actions
MS Power Point
presentation
Meeting and written
communication
Bi-weekly Operations manager
Senior executives
and functional
heads
Knowledge sharing
To share lessons learned
MS Power Point
presentation
Classroom Presentation
Monthly Team members
Project team
299Project Management Framework Version 1.0 Project Management Framework
Distribute InformationDistribute Information
It is the process of making relevant information available to project stakeholders as planned, this involves:
Implementing communications management plan Responding to unexpected requests for information
Information distribution methods include:
Sender-receiver models Choice of media Writing style Meeting management techniques Presentation techniques Facilitation techniques
300Project Management Framework Version 1.0 Project Management Framework
Distribute Information– Inputs, Tools, and OutputsDistribute Information– Inputs, Tools, and Outputs
Project management plan
Performance reports- Used to distribute project performance and status information, - Should be made available prior to project meetings, - Should be as precise and current as possible.
Organizational process assets
Communication methods Information distribution tools
- Hard-copy document distribution- Electronic communication and conferencing tools- Electronic tools for project management
Organizational process assets updates- Stakeholder notifications- Project reports- Project presentation- Project records- Feedback from
stakeholders- Lessons learned documentation
301Project Management Framework Version 1.0 Project Management Framework
Manage Stakeholder ExpectationsManage Stakeholder Expectations It is the process of communicating and working with stakeholders to meet their needs and addressing issues, such as:
Actively managing the expectations of stakeholders Addressing concerns that have not become issues yet Clarifying and resolving issues that have been identified
Managing expectations helps to increase the probability of project success by ensuring that the stakeholders understand the project benefits and risks.
302Project Management Framework Version 1.0 Project Management Framework
Manage Stakeholder Expectations – Inputs, Tools, and Manage Stakeholder Expectations – Inputs, Tools, and OutputsOutputs
Stakeholder register Stakeholder management
strategy Project management plan Issue log Change log Organizational process
assets
Communication methods
Interpersonal skills Management skills
Organizational process assets updates
Change requests Project management
plan updates Project document
updates
303Project Management Framework Version 1.0 Project Management Framework
Issue LogIssue Log
Used to document and monitor the resolution of issues. Used to facilitate communication and ensure a common understanding of issues.
Issue # IssueDate
AddedRaised
ByPerson
AssignedResolution Due Date
StatusDate
ResolvedResolution
304Project Management Framework Version 1.0 Project Management Framework
Report PerformanceReport Performance It is the process of collecting and distributing performance information, including status reports, progress measurements, and forecasts.
Types of Performance Reports
The performance reporting process involves: Periodic collection and analysis of baseline versus actual data
Forecasting the project results
Simple Reports Elaborate Reports
- Performance information, such as percent complete, or status dashboards for each area(i.e., scope, schedule, cost, and quality)
- Analysis of past performance- Current status of risks and issues- Work completed during the period and to be completed next- Other relevant information which must be reviewed and discussed
305Project Management Framework Version 1.0 Project Management Framework
Report Performance – Inputs, Tools, and OutputsReport Performance – Inputs, Tools, and Outputs
Project management plan Work performance information Work performance measurements Budget forecasts Organizational process assets
• Variance analysis• Forecasting
methods• Communication methods• Reporting systems
• Performance reports• Organizational process
assets updates• Change requests
306Project Management Framework Version 1.0 Project Management Framework
Communications MethodsCommunications Methods
307Project Management Framework Version 1.0 Project Management Framework
Report Performance – Tools and TechniquesReport Performance – Tools and Techniques
Forecasting Methods –The process of predicting future project performance based on the actual performance to date.
Classification of Forecasting Methods:
Time series methods – Use historical data as the basis for estimating future outcomes. Example, earned value, moving average, etc.
Casual/econometric methods – Use the assumption that it is possible to identify the underlying factors that might influence the variable that is being forecasted. Example, sale of umbrellas associated with weather conditions.
Judgmental methods – Incorporate intuitive judgements, opinions, and probability estimates. Example, composite forecasts, surveys, etc.
Other methods – Include simulation, probabilistic forecasting, and ensemble forecasting.
308Project Management Framework Version 1.0 Project Management Framework
Tabular Performance Report SampleTabular Performance Report Sample
309Project Management Framework Version 1.0 Project Management Framework
310Project Management Framework Version 1.0 Project Management Framework
PROJECT PROCUREMENT MANAGEMENTPROJECT PROCUREMENT MANAGEMENT
The PMI Registered Education Provider logo and PMP are registered marks of the Project Management Institute, Inc
311Project Management Framework Version 1.0 Project Management Framework
Course Structure
Project Procurement Management
Introduction
Project Procurement Management – Introduction
Plan Procurements : Inputs, Tools, and Outputs
Plan Procurements
Administer Procurements
Administer Procurements : Inputs, Tools, and Outputs
Conduct Procurements
Conduct Procurements : Inputs, Tools, and Outputs
Close Procurements
Close Procurements : Inputs, Tools, and Outputs
312Project Management Framework Version 1.0 Project Management Framework
Project Procurement Management – Project Procurement Management – IntroductionIntroduction
313Project Management Framework Version 1.0 Project Management Framework
Project Procurement Management – IntroductionProject Procurement Management – Introduction The processes necessary to purchase or acquire products, services, or results needed
from outside the project team.
It includes the contract management and change control processes required to develop and administer contracts or purchase orders.
The organization can be either the buyer or seller of the products, services, or results of a project.
314Project Management Framework Version 1.0 Project Management Framework
ContractContract A contract is a mutually binding agreement that obligates:
Seller to provide the specified products, services, or results.
Buyer to provide monetary or other valuable consideration.
It is a legal relationship subject to remedy in courts.
Legally binding nature of a contract usually means that it will be subjected to a more extensive approval process.
The project management team may seek support early from specialists in contracting, purchasing, law, and technical disciplines.
Continue…
315Project Management Framework Version 1.0 Project Management Framework
ContractContract Depending upon the application area, the seller can also be called contractor,
subcontractor, or vendor, service provider, or supplier.
Depending on the buyer’s position in the project acquisition cycle, the buyer can be called a client, customer, prime contractor, contractor, acquiring organization, service requester, or purchaser.
316Project Management Framework Version 1.0 Project Management Framework
Project Procurement Management ProcessesProject Procurement Management ProcessesProject Procurement Management processes includes:
Plan Procurements — process of documenting project purchasing decisions, specifying the approach, and identifying potential sellers.
Conduct Procurements — process of obtaining seller responses, selecting a seller, and awarding a contract.
Administer Procurements — process of managing procurement relationships, monitoring contract performance, and making changes and corrections as needed.
Close Procurements — process of completing each project procurement.
317Project Management Framework Version 1.0 Project Management Framework
Centralized vs. Decentralized ContractingCentralized vs. Decentralized ContractingCENTRALISED CONTRACTING DECENTRALISED CONTRACTING
Advantages Increased expertise in
contracting. Standardized company
practices. Contracting professional have a
clearly defined career path. Dept will provide its employees
training/shared knowledge for continuous improvement.
Disadvantages Contracting help may be difficult
to obtain as & when needed. Contract person may be shared
by different projects
Advantages Easier access to contracting
expertise. Loyalty to the project. More focused contracting
experience.
Disadvantages No Home Department for contract
person, after project is completed. Difficult to maintain high level of
contracting expertise. Lack of standardization & replication
of efforts.
318Project Management Framework Version 1.0 Project Management Framework
Project Manager’s Role in ProcurementProject Manager’s Role in Procurement
In procurement, the Project Manager should:
Know the procurement process. Understand contract terms and conditions. Make sure the contract contains all Project Management Requirements
(Attendance at meeting, reporting, communication etc.) Identify risks and incorporate mitigation and allocation of risks into the
contract. Help tailor the contract to the unique needs of the project. Incorporate schedule for procurement process into the schedule for the project. Be involved during contract negotiations to protect relationship with the seller
and protect the integrity of the project. Uphold the entire contract (Not just the contract statement of work). Work with the Contract Manager to manage changes to the contract.
319Project Management Framework Version 1.0 Project Management Framework
Plan ProcurementsPlan Procurements
320Project Management Framework Version 1.0 Project Management Framework
Plan ProcurementsPlan Procurements
The process of documenting project purchasing decisions, specifying the approach, and identifying potential sellers.
This process involves determining:
321Project Management Framework Version 1.0 Project Management Framework
Plan Procurement – Inputs, Tools, and OutputsPlan Procurement – Inputs, Tools, and Outputs
Scope baseline- Scope statement, WBS, and WBS dictionary
Requirements documentation Teaming agreements Risk register Risk-related contract decisions Activity resource requirements Project schedule Activity cost estimates Cost performance baseline Enterprise environmental factors Organizational process assets
Make-or-buy analysis
Expert judgment Contract types
Procurement management plan
Procurement statements of work
Make-or-buy decisions
Procurement documents
Source selection criteria
Change requests
322Project Management Framework Version 1.0 Project Management Framework
Plan Procurements Data Flow DiagramPlan Procurements Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 12-3. Page 318.
323Project Management Framework Version 1.0 Project Management Framework
Plan Procurement – InputsPlan Procurement – Inputs
Requirements documentation include:
Important information about project requirements that is considered during planning for procurements. Requirements with contractual and legal implications that may include health, safety, security
Teaming agreements:
Teaming agreements are legal contractual agreements between two or more entities to form a partnership or joint venture, or some other arrangements as defined by the parties.
Teaming agreement ends with the ending of new business opportunity.
324Project Management Framework Version 1.0 Project Management Framework
Make-or-Buy Analysis Make-or-Buy Analysis A general management technique used to determine whether particular work can
best be accomplished by the project team or must be purchased from outside sources.
Budget constraints may influence make-or-buy decisions.
The analysis includes both indirect as well as direct costs.
325Project Management Framework Version 1.0 Project Management Framework
Contract Types Contract Types The risk shared between the buyer and seller is determined by the contract type.
Types of Contract
Fixed-price Contracts Cost-reimbursable Contracts
Time and MaterialContracts (T&M)
Continue…
326Project Management Framework Version 1.0 Project Management Framework
Fixed-price Contracts
Fixed Price Incentive FeeContract (FPIF)
Fixed Price with EconomicsPrice Adjustment Contract
(FP- EPA)
Firm Fixed Price Contract(FFP)
Examples
Contract = $1,100,000
Contract = $1,100,000. For every monthearly the project is finished, an
additional $10,000 is paid to the seller.
Contract = $1,100,000, but a price increase will be allowed in year two
based on the U.S. Consumer Price Index report for the year one.
Contract = the contract price is $1,100,000 but a price increase will be
allowed in year two to account for increases in specific material costs.
327Project Management Framework Version 1.0 Project Management Framework
Examples
Contract = Cost plus a fee of $1,100,000
Contract = Cost plus $5,000 for every month production exceeds 100,000 units.
Maximum award available is $50,000.
Contract = Cost plus an award fee (to be determined) for each deliverable completed at least 7 days early.
Cost-reimbursable Contracts
Cost Plus Fixed FeeContracts (CPFF)
Cost Plus Award FeeContracts (CPAF)
Cost Plus Incentive FeeContracts (CPIF)
Continue…
Cost Plus Percentage of Cost Contracts (CPPC)
X -- 10 X - Y -- 20X + Y -- 5
328Project Management Framework Version 1.0 Project Management Framework
Example
Contract = $100 per hour plus expenses or materials at cost.
Contract = $100 per hour plus materials at $5 per linear meter of wood.
Time and MaterialContracts (T&M)
329Project Management Framework Version 1.0 Project Management Framework
Risk and Contract Types Risk and Contract Types
330Project Management Framework Version 1.0 Project Management Framework
Describes how the procurement process will be managed from developing procurement documents through contract closure. This includes:
Procurement Management Plan
Plan Procurement – OutputsPlan Procurement – Outputs
Types of contracts to be used Risk management issues Whether independent estimates will be used and if they are needed as evaluation criteria; Managing multiple suppliers; Coordinating procurement with other project aspects, such as scheduling and performance reporting Constraints and assumptions that could affect planned procurements Establishing the form and format to be used for the procurement/contract statements of work Identifying prequalified sellers Procurement metrics to manage contracts and evaluate sellers. Handling the make-or-buy decisions and linking them into the Estimate Activity Resource and Develop Schedule processes Identifying requirements for performance bonds or insurance contracts to mitigate some forms of project risk Establishing the direction to be provided to the sellers on developing and maintaining a work breakdown structure (WBS)
331Project Management Framework Version 1.0 Project Management Framework
A Procurement Management Plan can be: Formal or informal Highly detailed or broadly framed Based upon the needs of each project
Plan Procurement – OutputsPlan Procurement – Outputs
Procurement Statements of workProcurement Statements of work
The statement of work (SOW) for each procurement is developed from the project scope baseline and defines only that portion of the project scope that is to be included within the related contract.
332Project Management Framework Version 1.0 Project Management Framework
Common terms for different types of procurements include: Request for information (RFI), Invitation for bid (IFB), Request for proposal (RFP), Request for quotation (RFQ), Tender notice, Invitation for negotiation, and Invitation for seller’s initial response
Procurement DocumentsProcurement Documents
Plan Procurement – OutputsPlan Procurement – Outputs
Source Selection CriteriaSource Selection Criteria
Selection criteria are often included as a part of the procurement documents.
Such criteria are developed and used to rate or score seller proposals, and can be objective or subjective.
333Project Management Framework Version 1.0 Project Management Framework
Plan Procurement – OutputsPlan Procurement – Outputs
Source Selection Criteria, examples:Source Selection Criteria, examples: Understanding of need Overall or life-cycle cost Technical capability Risk Management approach Technical approach Warranty Financial capacity Production capacity and interest Business size and type Past performance of sellers References Intellectual property rights Proprietary
334Project Management Framework Version 1.0 Project Management Framework
Conduct ProcurementConduct Procurement
335Project Management Framework Version 1.0 Project Management Framework
Conduct ProcurementsConduct Procurements
The process of obtaining seller responses, selecting a seller, and awarding a Contract.
The team will receive bids or proposals and will apply previously defined selection criteria to select one or more sellers who are qualified to perform the work and acceptable as a seller.
336Project Management Framework Version 1.0 Project Management Framework
Conduct Procurements – Inputs, Tools, and OutputsConduct Procurements – Inputs, Tools, and Outputs
Project management plan Procurement documents Source selection criteria Qualified seller list Seller proposals Project documents Make-or-buy decisions Teaming agreement Organizational process
assets
Bidder conferences Proposal evaluation techniques Independent
estimates Expert judgment Advertising Internet search Procurement
negotiations
Selected sellers Procurement contract
award Resource calendars Change requests Project management
plan updates Project document
updates
337Project Management Framework Version 1.0 Project Management Framework
Conduct Procurements Data Flow DiagramConduct Procurements Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 12-5. Page 329.
338Project Management Framework Version 1.0 Project Management Framework
Conduct Procurements – Tools and TechniquesConduct Procurements – Tools and Techniques Bidder Conferences (also called as contractor, vendor, and pre-bid conferences)
- meetings with sellers and buyers prior to submission of a bid or proposal- these conferences used to ensure that:
- prospective sellers have a clear and common understanding of the procurement (technical and contractual requirements)- no bidders receive preferential treatment- incorporation of responses on questions into the procurement documents as amendments- sellers hear every question from each seller and answers from the buyer
339Project Management Framework Version 1.0 Project Management Framework
Administer ProcurementsAdminister Procurements
340Project Management Framework Version 1.0 Project Management Framework
Administer ProcurementsAdminister Procurements The process of managing procurement relationship, monitoring contract
performance, and making changes and corrections as needed.
Due to varying organizational structures, many organizations treat contract administration as an administrative function separate from the project organization.
While a procurement administrator may be on the project team, this individual typically reports to a supervisor from a different department.
341Project Management Framework Version 1.0 Project Management Framework
Administer ProcurementsAdminister Procurements
Project Management Processes that apply to Contractual relationship include:
Direct & Manage Project Execution – to authorize the seller’s work at the appropriate time
Report Performance – to monitor contract scope, cost, schedule, and technical performance
Perform Quality Control – to inspect and verify the adequacy of the seller’s product
Perform Integrated Change Control – to assure that changes are approved and conveyed to all the concern people
Monitoring and Control Risk – to ensure that risks are mitigated
342Project Management Framework Version 1.0 Project Management Framework
Administer Procurements – Inputs, Tools, and OutputsAdminister Procurements – Inputs, Tools, and Outputs
Procurement documentsProject management planContractPerformance reportsApproved change
requestsWork performanceinformation
Contract change controlsystem Procurement
performance reviews Inspections and audits Performance reporting Payment systems Claims administration Records management
system
Procurement documentationOrganizational process assets updatesChange requestsProject management
plan updates
343Project Management Framework Version 1.0 Project Management Framework
Administer Procurements Data Flow DiagramAdminister Procurements Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 12-7. Page 336.
344Project Management Framework Version 1.0 Project Management Framework
Close ProcurementsClose Procurements
345Project Management Framework Version 1.0 Project Management Framework
Close ProcurementsClose Procurements
The process of completing each project procurement.
It also involves administrative activities such as:- Finalizing open claims,- Updating records to reflect final results
and - Archiving such information for future use
Unresolved claims may be subjected to litigation after Contract Closure.
The contract terms and conditions can prescribe specific procedure for Contract Closure.
346Project Management Framework Version 1.0 Project Management Framework
Close Procurements – Inputs, Tools, and OutputsClose Procurements – Inputs, Tools, and Outputs
Project management plan Procurement documentation
Procurement audits Negotiated settlements Records management system
Closed procurements Organizational process
assets updates
347Project Management Framework Version 1.0 Project Management Framework
Close Procurements Data Flow DiagramClose Procurements Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 12-9. Page 342.
348Project Management Framework Version 1.0 Project Management Framework
Close Procurements – Tools and TechniquesClose Procurements – Tools and Techniques
Procurement audits
Is a structured review of the procurement process originating from the Plan Procurement process through Administer Procurements.
Objective – to identify successes and failures that warrant recognition in the preparation or administration of other procurement contracts on the project or other projects within the performing organization.
349Project Management Framework Version 1.0 Project Management FrameworkThe PMI Registered Education Provider logo and PMP are registered marks of the Project Management Institute, Inc
350Project Management Framework Version 1.0 Project Management Framework
PROJECT RISK MANAGEMENTPROJECT RISK MANAGEMENT
351Project Management Framework Version 1.0 Project Management Framework
Course StructureProject Risk Management
Introduction
Project Risk Management – Introduction
Plan Risk Management : Inputs, Tools, and Outputs
Plan Risk Management
Perform Qualitative Risk Analysis
Perform Qualitative Risk Analysis : Inputs, Tools, and Outputs
Identify Risks
Identify Risk : Inputs, Tools, and Outputs
Perform Quantitative Risk Analysis
Perform Quantitative Risk Analysis : Inputs, Tools, and Outputs
Plan Risk Responses
Plan Risk Response : Inputs, Tools, and Outputs
Monitor and Control Risks
Monitor and Control Risks : Inputs, Tools, and Outputs
353Project Management Framework Version 1.0 Project Management Framework
Project Risk Management – IntroductionProject Risk Management – Introduction
Project Risk is an uncertain event or condition. If it occurs, it has a positive or negative effect on at least one project objective ( i.e. Time, Cost, Scope or Quality). Project Risk is always in future
A risk may have one or more causes and if it occurs, one or more impacts.
Continue…
354Project Management Framework Version 1.0 Project Management Framework
Some examples of areas of uncertainty are since we fail to:
Understand who the project is for Appoint an executive user responsible for sponsoring the project Appoint a fully qualified and supported project manager Define the objectives of the project Secure commitments from people who are needed to assist with the project Estimate costs accurately Specify very precisely the end users' requirements
Project Risk Management – IntroductionProject Risk Management – Introduction
Continue…
355Project Management Framework Version 1.0 Project Management Framework
Project Risk ManagementProject Risk Management
Risk conditions could include aspects of the project’s or organization’s environment, such as:
Poor project management practices.
Lack of integrated management system.
Concurrent multiple projects.
Dependency on participants not under control,
etc.
Continue…
356Project Management Framework Version 1.0 Project Management Framework
Risk Process Overview Risk Process Overview
358Project Management Framework Version 1.0 Project Management Framework
Project Risk Management - ProcessesProject Risk Management - Processes
360Project Management Framework Version 1.0 Project Management Framework
ProcessProcess - Plan Risk Management - Plan Risk Management
The process of deciding to approach and conduct risk management activities for a project.
It ensures that level, type and visibility of risk management are commensurate with
Risks and Importance of the project to the organization.
It also ensures that: Sufficient resources and time are provided to manage
risks. There is agreed upon basis for evaluating risks.
361Project Management Framework Version 1.0 Project Management Framework
Plan Risk Management – Inputs, Tools, and Plan Risk Management – Inputs, Tools, and OutputsOutputs
Project scope statement
Cost management plan Schedule management
plan Communications
management plan Enterprise
environmental factors Organizational process
assets
Planning meetings and analysis Risk management plan
362Project Management Framework Version 1.0 Project Management Framework
Plan Risk ManagementPlan Risk Management
Plan Risk Management includes the following:
Methodology (Approach, tools & data sources)
Roles and Responsibilities
Budgeting (Cost for the risk management processes)
Timing (How & when the Risk Management activities will be performed throughout
the project lifecycle).
Continue…
363Project Management Framework Version 1.0 Project Management Framework
Plan Risk ManagementPlan Risk Management
Risk Categories (Risk Breakdown Structure (RBS))
Definition of Risk Probability Levels and Impact Levels
Probability and Impact Matrix
Stakeholder Risk Tolerances
Reporting Formats (Content & Format of Risk Register)
Risk Tracking Mechanism
364Project Management Framework Version 1.0 Project Management Framework
Risk Breakdown Structure Risk Breakdown Structure (As per PMBOK(As per PMBOK ® Guide) Guide)
365Project Management Framework Version 1.0 Project Management Framework
Impact Levels Impact Levels (As per PMBOK(As per PMBOK® Guide) Guide)
366Project Management Framework Version 1.0 Project Management Framework
Probability and Impact Matrix Probability and Impact Matrix (As per PMBOK(As per PMBOK® Guide) Guide)
367Project Management Framework Version 1.0 Project Management Framework
Questions to be Addressed in a Plan Risk Management
Why is it important to take/not take this risk in relation to the project objectives?
What is the specific risk, and what are the risk mitigation deliverables?
How is the risk going to be mitigated? (What risk mitigation approach is to be used?)
Who are the individuals responsible for implementing the risk management plan?
When will the milestones associated with the mitigation approach occur?
How much is required in terms of resources to mitigate risk?
368Project Management Framework Version 1.0 Project Management Framework
Plan Risk Management Data Flow DiagramPlan Risk Management Data Flow Diagram
370Project Management Framework Version 1.0 Project Management Framework
Process Process - Identify Risks- Identify Risks
It determines which risks might effect the project and documents their characteristics.
All project personnel should be encouraged to identify risks.
Iterative process - new risks may become known as the project progresses through its life cycle.
Risk Identification Qualitative Risk Analysis
Quantitative Risk Analysis
Methods for prioritizing identified risks
371Project Management Framework Version 1.0 Project Management Framework
Identify Risks – Inputs, Tools, and OutputsIdentify Risks – Inputs, Tools, and Outputs
Risk management plan Activity cost estimates Activity duration estimates Scope baseline Stakeholder register Cost management plan Schedule management
plan Quality management plan Project documents Enterprise environmental
factors Organizational process
assets
Documentation reviews Information gathering
techniques Checklist analysis Assumptions analysis Diagramming techniques SWOT analysis Expert judgment
Risk register
372Project Management Framework Version 1.0 Project Management Framework
Identify Risks – Tools and TechniquesIdentify Risks – Tools and Techniques
Documentation reviews
Risk information gathering techniques. (Brainstorming, Delphi, Interviewing, Root Cause Identification)
Checklist Analysis
Assumptions Analysis
Diagramming techniques (Cause–and- Effect Diagram, Process Flow Charts, System Flow Charts, Influence Diagrams)
373Project Management Framework Version 1.0 Project Management Framework
Risk RegisterRisk Register
The primary output of risk identification and is a component of the Project Management Plan.
Contents of Risk Register
List of
identified risks
List of
potential responsesRoot causes of risk
Updated risk categories
374Project Management Framework Version 1.0 Project Management Framework
Identify Risks Data Flow DiagramIdentify Risks Data Flow Diagram
376Project Management Framework Version 1.0 Project Management Framework
Process Process - Perform Qualitative Risk Analysis- Perform Qualitative Risk Analysis
The specific objectives of perform qualitative risk analysis are:
Subjectively evaluate the probability and impact of each risk.
Create a starter list of risks by determining the critical or top risks that you will quantify further.
Go / No- Go decision (having evaluated the risks, do we still want to do this project).
377Project Management Framework Version 1.0 Project Management Framework
Perform Qualitative Risk AnalysisPerform Qualitative Risk Analysis
Beginning in qualitative risk analysis, the project team relies on the data about risk acquired in risk identification
(Data Precision ranking : “how well understood is the risk”). It should include analysis of the following:
Extent of understanding of the risk.
Data available about the risk.
Reliability and Integrity of the data.
378Project Management Framework Version 1.0 Project Management Framework
Perform Qualitative Risk Analysis – Inputs, Perform Qualitative Risk Analysis – Inputs, Tools, and OutputsTools, and Outputs
Risk register Risk management plan Project scope statement Organizational process
assets
Risk probability and impact
assessment Probability and impact matrix Risk data quality assessment Risk data categorization Risk urgency assessment Expert Judgement
Risk register updates
379Project Management Framework Version 1.0 Project Management Framework
Tigers - High Probability, High Impact. These are dangerous animals and must be neutralized as soon as possible.
Alligators - Low Probability, High Impact. These are dangerous animals which can be avoided with care.
Puppies - High Probability, Low Impact. We all know that delightful pup will grow into an animal which can do damage, but a little training will ensure that not too much trouble ensures.
Kittens - Low Probability, Low Impact. The largest cat is rarely the source of trouble, but on the other hand a lot of effort can be wasted on training it!
380Project Management Framework Version 1.0 Project Management Framework
Perform Qualitative Risk Analysis Data Flow DiagramPerform Qualitative Risk Analysis Data Flow Diagram
382Project Management Framework Version 1.0 Project Management Framework
ProcessProcess - Perform Quantitative Risk Analysis - Perform Quantitative Risk Analysis
The specific objectives of perform quantitative risk analysis include:
Numerically evaluating probability and impact of each risk.
Determining the level of risk the project currently has and whether that level of risk is acceptable for the expected gain from the product of the project.
Determining the probability of cost or schedule objectives for the project.
383Project Management Framework Version 1.0 Project Management Framework
Perform Quantitative Risk Analysis – Inputs, Perform Quantitative Risk Analysis – Inputs, Tools, and OutputsTools, and Outputs
Risk register Risk management plan Cost management plan Schedule management plan Organizational process assets
Data gathering and representation techniques
Quantitative risk analysis and modelling techniques
Expert judgement
Risk register updates
384Project Management Framework Version 1.0 Project Management Framework
Perform Quantitative Risk Analysis – Tools and Perform Quantitative Risk Analysis – Tools and TechniquesTechniques
Data Gathering and Representation Techniques Interviewing
Range of Project Cost Estimates Collected During the Risk Interview
385Project Management Framework Version 1.0 Project Management Framework
Perform Quantitative Risk AnalysisPerform Quantitative Risk Analysis
Commonly used techniques in perform quantitative risks analysis include:
Sensitivity Analysis
Decision Tree Analysis
Expected Monetary Value Analysis (EMV)
Modeling and Simulation
386Project Management Framework Version 1.0 Project Management Framework
Sensitivity AnalysisSensitivity analysis helps to determine which risks have the most potential impact on the project. It examines the extent to which the uncertainty of each project element affects the objective being examined when all other uncertain elements are held at their baseline values. One typical display of sensitivity analysis is the tornado diagram, which is useful for comparing relative importance and impact of variables that have a high degree of uncertainty to those that are more stable.
R1
R2
R3
R4
R5
387Project Management Framework Version 1.0 Project Management Framework
Diagrams that show the sequence of interrelated decisions and the expected results of choosing one alternative over the other.
Let’s take an example of a company which is trying to decide whether an e-learning prototyping is worthwhile on the project. The impact of whether the equipment works or fails is shown in the diagram below. As per the information provided in the diagram, what is the expected monetary value of your decision?
Failure: 35% probability and $120,000impact
Failure: 70% probability and $450,000 impact
Pass: No impactDo not e-learning prototype:Setup cost $0
Pass: No impact
E-learning Prototype:Setup cost $200,000
Decision Tree Analysis
388Project Management Framework Version 1.0 Project Management Framework
Continue…
Calculated by multiplying the probability of the risk times its impact and thenadding them together. Positive results indicate opportunities and negative generally indicate threat to the project.
EMV = P x I (where, P = Probability and I = Times Impact)
Expected Monetary Value Analysis (EMV)
389Project Management Framework Version 1.0 Project Management Framework
Expected Monetary Value Analysis (EMV)
Continue…
390Project Management Framework Version 1.0 Project Management Framework
Expected Monetary Value Analysis (EMV)
391Project Management Framework Version 1.0 Project Management Framework
Expected Monetary Value Analysis (EMV)
Continue…
392Project Management Framework Version 1.0 Project Management Framework
Airline A(20% * Rs. 50,000 = Rs. 10,000) + (80% * Rs. 0 = Rs. 0) + Rs. 9,000 = Rs. 19,000
Airline B(40% * Rs. 50,000 = Rs. 20,000) + (60% * Rs. 0 = Rs. 0) + Rs. 3,000 = Rs. 23,000
Expected Monetary Value Analysis (EMV)
393Project Management Framework Version 1.0 Project Management Framework
Modeling and SimulationA project simulation uses a model that translates the specified detailed uncertainties of the projectinto their potential impact on project objectives. Iterative simulations are typically performed usingthe Monte Carlo technique. In a simulation, the project model is computed many times (iterated), with the input values (e.g., cost estimates or activity durations) chosen at random for each iteration from the probability distributions of these variables.
394Project Management Framework Version 1.0 Project Management Framework
Perform Quantitative Risk Analysis Data Flow Perform Quantitative Risk Analysis Data Flow DiagramDiagram
396Project Management Framework Version 1.0 Project Management Framework
Process Process - Plan Risk Responses- Plan Risk Responses
It involves arriving at strategy or mix of strategies most likely to be effective for each risk.
Primary and Back-up strategy may be selected.
A Fall back plan can be developed if the selected strategy does not turn to be fully effective or if an accepted risk occurs.
Contingency plan can be developed, along with identification of conditions that trigger their execution.
397Project Management Framework Version 1.0 Project Management Framework
Plan Response Responses – Inputs, Tools, Plan Response Responses – Inputs, Tools, and Outputsand Outputs
Risk register Risk
management plan
Strategies for negative risks or threats
Strategies for positive risks or opportunities
Contingent response strategy Expert judgement
Risk register updates Risk-related
contractual agreements
Project management plan updates
Project document updates
398Project Management Framework Version 1.0 Project Management Framework
Plan Risk Responses - StrategiesPlan Risk Responses - Strategies
399Project Management Framework Version 1.0 Project Management Framework
Plan Response Responses Data Flow DiagramPlan Response Responses Data Flow Diagram
401Project Management Framework Version 1.0 Project Management Framework
ProcessProcess - Monitoring and Control Risks - Monitoring and Control Risks
Project work should be continuously monitored for new and changing risks.
Monitoring and Control Risks involves:
Identifying, analyzing and planning for newly arising risks. Keeping track of identified risks and those on the watch list. Monitoring trigger conditions for contingency plans. Monitoring residual risks. Reviewing the execution of risk responses.
402Project Management Framework Version 1.0 Project Management Framework
Residual Risk, Secondary Risk & WorkaroundResidual Risk, Secondary Risk & Workaround
Residual Risk A risk that remains after risk responses have been implemented.
Secondary Risk A risk that arises as a direct result of implementing a risk response.
Workaround A response to a negative risk that has occurred. Distinguished from contingency plan in that a workaround is not planned in advance of the occurrence of the risk event.
403Project Management Framework Version 1.0 Project Management Framework
Monitoring & Control Risks– Inputs, Tools, Monitoring & Control Risks– Inputs, Tools, and Outputsand Outputs
Risk register Project management
plan Work performance
information Performance reports
Risk reassessment Risk audits Variance and trend
analysis Technical performance
measurement Reserve analysis Status meetings
Risk register updates Organizational
process assets updates
Change requests Project management
plan updates Project document
updates
404Project Management Framework Version 1.0 Project Management Framework
Risk AuditsRisk Audits
Risk Audits examine and document effectiveness of risk responses in dealing with:
Identified risks and their root causes and
Effectiveness of the risk management Process
405Project Management Framework Version 1.0 Project Management Framework
Monitor and Control Risks Data Flow DiagramMonitor and Control Risks Data Flow Diagram
406Project Management Framework Version 1.0 Project Management Framework
407Project Management Framework Version 1.0 Project Management Framework
PROJECT QUALITY MANAGEMENTPROJECT QUALITY MANAGEMENT
The PMI Registered Education Provider logo and PMP are registered marks of the Project Management Institute, Inc
408Project Management Framework Version 1.0 Project Management Framework
Course Structure
Project Quality Management
Introduction
Project Quality Management – Introduction
Plan Quality : Inputs, Tools, and Outputs
Plan Quality
Perform Quality Control
Perform Quality Control : Inputs, Tools, and Outputs
Perform Quality Assurance
Perform Quality Assurance : Inputs, Tools, and Outputs
409Project Management Framework Version 1.0 Project Management Framework
Project Quality Management – IntroductionProject Quality Management – Introduction
410Project Management Framework Version 1.0 Project Management Framework
Project Quality Management - IntroductionProject Quality Management - Introduction
The Project Quality Management processes include:
Plan Quality – process of identifying quality requirements and/or standards for the project and product and documenting how the project will demonstrate compliance.
Perform Quality Assurance – process of auditing the quality requirements and the results from quality control measurements to ensure appropriate quality standards and operational definitions are used.
The processes and activities of the performing organization that determine quality policies, objectives, and responsibilities to satisfy the project needs.
Perform Quality Control – process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes.
412Project Management Framework Version 1.0 Project Management Framework
Product Quality vs. Project QualityProduct Quality vs. Project Quality
Project quality management addresses the management of project and product of the project and applies to all projects, regardless of the nature of their product.
Product quality measures and techniques are specific to the type of product produced by the project.
Failure to meet product or project quality requirements can have serious negative consequences for any or all of project stakeholders, which may lead to:
Employees attrition Errors Rework
413Project Management Framework Version 1.0 Project Management Framework
Quality vs. GradeQuality vs. Grade Quality is the degree to which a set of inherent
characteristics fulfill requirements (Customer, Project).
Grade is a category assigned to products or services having the same functional use but different technical characteristics.
Low quality is always a problem; low grade may not be.
Project Manager and Project Management Team are responsible for determining and delivering the required level of both quality and grade. Quality and Grade are not the same
414Project Management Framework Version 1.0 Project Management Framework
Precision vs. AccuracyPrecision vs. Accuracy Precision and Accuracy are not equivalent.
Precision – The values of repeated measurements are clustered and have little scatter. (not necessarily accurate)
Accuracy – The measured value is very close to the true value. (not necessarily precise)
The Project Management Team must determine, how much accuracy or precision or both are required.
415Project Management Framework Version 1.0 Project Management Framework
Modern Quality ManagementModern Quality Management
Complements project management as both recognize the importance of:
Customer Satisfaction
Prevention over Inspection
Continuous Improvement
Management Responsibility
Process improvement models include Malcolm Baldrige, OPM3® CMMI®.
416Project Management Framework Version 1.0 Project Management Framework
Control Limits vs. ToleranceControl Limits vs. Tolerance
Control Limits: are the limits within which the variation of the process is permitted and are determined by the organization’s quality standard.
Tolerance: The result is acceptable if it falls within the range specified by the tolerance.
418Project Management Framework Version 1.0 Project Management Framework
Process Process - Plan Quality - Plan Quality
The process of identifying quality requirements and/or standards for the project and product, and documenting how the project will demonstrate compliance.
This process should be performed in parallel with the other project planning processes.
E.g. Proposed changes in the product to meet identified quality standards may require cost or schedule adjustments and a detailed risk analysis.
419Project Management Framework Version 1.0 Project Management Framework
Plan Quality – Inputs, Tools, and OutputsPlan Quality – Inputs, Tools, and Outputs
Scope baseline Stakeholder register Cost performance
baseline Schedule baseline Risk register Enterprise environmental
factors Organizational process
assets
Cost benefit analysis Cost of quality Control charts Benchmarking Design of experiments Statistical sampling Flowcharting Proprietary quality
management methodologies
Additional quality planning tools
Quality management plan
Quality Metrics Quality checklists Process improvement
plan- Process boundaries- Process configuration- Process metrics- Targets for improved
performance
Project document updates
420Project Management Framework Version 1.0 Project Management Framework
Plan Quality – InputsPlan Quality – Inputs
Quality Policy
Quality Policy
Either Or
By PerformingOrganization
By Project ManagementTeam
Project should have a Quality Policy.
421Project Management Framework Version 1.0 Project Management Framework
Plan Quality – Tools and TechniquesPlan Quality – Tools and Techniques
Cost-Benefit analysis Cost of quality Control charts Benchmarking Statistical sampling Design of experiments Flowcharting Proprietary quality management methodologies Additional quality planning tools
432Project Management Framework Version 1.0 Project Management Framework
Plan Quality – OutputsPlan Quality – Outputs
Quality Management Plan: Describes how the project management team will
implement the performing organization's quality policy.
Quality Metrics: An operational definition that describes, in very specific
terms, a project or product attribute and how the quality control process will measure it.
Quality Checklists: A structured toll, usually component-specific,
used to verify that a set of required steps has been performed.
Quality checklists are used in the quality control process
Continue…
433Project Management Framework Version 1.0 Project Management Framework
Plan Quality – OutputsPlan Quality – Outputs
Process improvement Plan: A subsidiary of the project management plan. Details the steps for analyzing processes to
identify activities which enhance their value. Areas to consider include:
Process boundaries Process configuration Process metrics Targets for improved performance
Project Document Updates: Stakeholder register Responsibility Assignment Matrix
434Project Management Framework Version 1.0 Project Management Framework
Plan Quality Data Flow DiagramPlan Quality Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 8-3. Page 193.
436Project Management Framework Version 1.0 Project Management Framework
Process Process - Perform Quality Assurance- Perform Quality Assurance
Perform Quality Assurance is the process of
Perform Quality Assurance also provides an umbrella for continuous process improvement, which Is an iterative means for improving the quality of all processes.
auditingQuality requirements
Results from quality control measurements
To ensure appropriate quality standards and operational definitions are used.
Perform Quality Assurance is an execution process that uses data created during Perform Quality Control.
437Project Management Framework Version 1.0 Project Management Framework
Performance Quality Assurance – Inputs, Tools, Performance Quality Assurance – Inputs, Tools, and Outputsand Outputs
Project management plan- Quality management plan- Process improvement plan
Quality metrics Work performance information Quality control measurements
Plan Quality and Perform Quality Control tools and techniques
Quality audits Process analysis
Organizational process assets updates
Change requests Project management
plan updates Project document
updates
438Project Management Framework Version 1.0 Project Management Framework
Perform Quality Assurance – Tools and TechniquesPerform Quality Assurance – Tools and Techniques
Quality Audits It is a structured, independent review to determine whether project
activities comply with organizational and project policies, processes, and procedures.
The objectives of a quality audit are: Identify all the good/best practices being implemented and all the gaps/shortcomings Share the good practices introduced or implemented in similar projects Proactively offer assistance in a positive manner to improve implementation of
processes to help the team raise productivity Highlight contributions of each audit in the lessons leaned repository of the
organization
They can confirm the implementation of approved change requests including: Corrective actions Defect repairs Preventive actions
Continue…
439Project Management Framework Version 1.0 Project Management Framework
Perform Quality Assurance – Tools and Perform Quality Assurance – Tools and TechniquesTechniques
Process Analysis Follows the steps outlined in the process improvement plan to
identify needed improvements
Process analysis includes root cause analysis -
A specific technique to identify a problem
Discover the underlying causes that lead to it
Develop preventive actions
440Project Management Framework Version 1.0 Project Management Framework
Performance Quality Assurance Data Flow DiagramPerformance Quality Assurance Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 8-9. Page 202.
442Project Management Framework Version 1.0 Project Management Framework
Process Process - Perform Quality Control- Perform Quality Control
The process of monitoring and recording results of executing the quality activities to: Assess performance Recommend necessary changes
Quality control activities identify: Causes of poor process or product quality Recommend and/or take action to eliminate them
Continue…
443Project Management Framework Version 1.0 Project Management Framework
Perform Quality ControlPerform Quality ControlKey Terminologies
Statistical Quality Control – Especially sampling and probability, to help evaluate quality control outputs
Prevention – Keeping errors out of the process Inspection – Keeping errors out of hands of the customer
Attribute Sampling – The results either conforms or does not conform Variables Sampling – The result is rated on a continuous scale that measures the degree of conformity
444Project Management Framework Version 1.0 Project Management Framework
Perform Quality Control – Inputs, Tools, and OutputsPerform Quality Control – Inputs, Tools, and Outputs
Project management plan
Quality metrics Quality checklists Work performance
information Approved change
requests Deliverables Organizational process
assets
Cause and effect diagram
Control charts Flowcharting Histogram Pareto chart Run chart Scatter diagram Statistical
sampling Inspection Approved change
requests review
Quality control measurements Validated changes Validated deliverables Organizational process assets
updates Change requests
- if the recommended corrective or preventive actions or a defect repair requires a change to the project management plan, a change request should be initiated in accordance with the defined Perform Integrated Change Control
Project management plan updates Project document updates
445Project Management Framework Version 1.0 Project Management Framework
Ishikawa’s seven basic tools of quality:
Cause and Effect Diagram
Histogram
Pareto Chart
Run Chart
Scatter Diagram
Control Charts
Flowcharting
Statistical Sampling
Inspection
Approved Change Requests
Review
Perform Quality Control – Tools and TechniquesPerform Quality Control – Tools and Techniques
452Project Management Framework Version 1.0 Project Management Framework
Quality TheoriesQuality Theories
Joseph Juran: • Developed the 80/20 principle.• Advocated Top Management involvement.• Defined Quality as “fitness for use”.
W. Edwards Deming:• Developed 14 steps to quality management• Advocated Plan - Do – Check - Act cycle for quality
improvement.
Philip Crosby:• Popularized the concept of cost of poor quality.• Advocated prevention over inspection & “zero defects”.• He believed quality is “Conformance to requirements”.
453Project Management Framework Version 1.0 Project Management Framework
Perform Quality Control Data Flow DiagramPerform Quality Control Data Flow Diagram
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®Guide) –Fourth Edition, Project Management Institute, Inc., 2008, Figure 8-11. Page 207.
454Project Management Framework Version 1.0 Project Management FrameworkThe PMI Registered Education Provider logo and PMP are registered marks of the Project Management Institute, Inc