Project Quality ManagementChapter 8
![Page 2: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/2.jpg)
2
Quality Theories
Evolution of Quality Management
8.1 Plan Quality Management
8.2 Perform Quality Assurance
8.3 Control Quality
KEY TERMS
![Page 3: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/3.jpg)
Project Quality Management
Knowledge
Area
Process
Initiating Planning ExecutingMonitoring &
ControlClosing
Cost8.1 Plan
Quality
Management
8.2 Perform
Quality Assurance
8.3 Control
Quality
Enter phase/
Start project
Exit phase/
End project
Initiating
Processes
Closing
Processes
Planning
Processes
Executing
Processes
Monitoring &
Controlling Processes
Quality is the degree to which the project fulfills
requirements.
3
![Page 4: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/4.jpg)
4
8.1 Plan Quality Management
The process of identifying quality requirements and/or
standards for the project and its deliverables and
documenting how the project will demonstrate compliance
with quality requirements.
8.2 Perform Quality Assurance
The process of auditing the quality requirements and the
results from quality control measurements to ensure that
appropriate quality standards and operational definitions are
used.
8.3 Control Quality
The process of monitoring and recording results of
executing the quality activities to assess performance and
recommend necessary changes.
![Page 5: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/5.jpg)
5
Joseph
Juran
• 80/20 principle, top management
involvement. Quality is fitness for use.
• Advocated top management involvement
Quality Theorists
Philip
Crosby
• Cost of poor quality, prevention over
inspection and zero defects.
• Quality = Conformance To Requirements
Edwards
Deming
• 14 steps of Total Quality Management,
Plan-Do-Check-Act cycle.
• Basis for quality improvement.
![Page 6: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/6.jpg)
Quality Concepts
Quality vs. Grade
Quality: the degree to which a set of inherent characteristics fulfill requirements
Quality level that fails to meet quality requirements is always a PROBLEM
Grade: a category assigned to product or service having the same functional use but different technical characteristics
Low grade may not be a problem
6
![Page 7: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/7.jpg)
• Customer satisfaction
• Conformance to requirement
• Fitness for use: product/service produced must satisfy real needs
• Prevention over inspection
• Cost of preventing mistakes < cost of correcting
• Continuous improvement (Kaizen) Japanese concept
• Based on PDCA cycle
• Using quality improvement initiatives e.g. TQM, 6 sigma
• Management responsibility
• To provide the resource needed to succeed
7
![Page 8: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/8.jpg)
8
Gold Plating: giving the customer extras not recommended
Marginal Analysis: looking for the point where..benefits/revenue to be received from improving quality EQUALS the incremental cost to achieve that quality
Just in Time (JIT): just when they are needed or just before they are needed. It forces attention on quality practices.
decreasing inventory to close to zero.
Total Quality Management (TQM) Company & their employees focus on finding ways to continuous
improve the quality of their business practices & products.
![Page 9: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/9.jpg)
9
• ISO to help ensure that organizations have quality
procedures and that they follow them.
• Six Sigma a methodology for organizational
process improvement and achieving high levels of
correctness with extremely reduced variances.)
• 1 sigma = 68.26 %
• 2 sigma = 95.44 %
• 3 sigma = 99.73 %
• 6 sigma = 99.99 %
![Page 10: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/10.jpg)
10
8.1- Plan Quality Management
![Page 11: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/11.jpg)
11
8.1- Plan Quality Management.
The process of identifying quality requirements and/or
standards for the project and its deliverables and
documenting how the project will demonstrate compliance
with quality requirements.
![Page 12: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/12.jpg)
12
![Page 13: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/13.jpg)
8.1- Plan Quality Management INPUTS
13
1. Project
Management Plan
• Scope baseline
• Work Breakdown Structure
• WBS Dictionary
• Schedule baseline
• Cost baseline
• Other management Plans
2. Stakeholder Register
3. Risk register
4. Requirements Documentation
5. OPA
![Page 14: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/14.jpg)
8.1- Plan Quality Management T & T
14
• Cost-benefit Analysis The primary benefit of meeting
quality requirements is less rework, i.e., higher
productivity, lower costs and increased stakeholder
satisfaction.
• Benchmarking This technique involves looking at other
projects to get ideas for improvement on the current
project and to provide a basis (or benchmark) to use in
measuring quality performance.
• Meetings
![Page 15: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/15.jpg)
15
• Cost Of Quality
Refers to the total cost of the conformance work and the
nonconformance work
8.1- Plan Quality Management T & T
![Page 16: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/16.jpg)
16
• Design of Experiment DOE statistical method
• Helps identify which factors might influence specific variables.
• DOE can help shorten the time and effort required to discover the best
conditions to produce a quality deliverable
Which parts are
best integrated to
give best result
8.1- Plan Quality Management T & T
![Page 17: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/17.jpg)
17
• Seven Basic Quality Tools 7QC Tools
used within the context of the PDCA Cycle to solve quality-
related problems.
1. Cause-and-effect (fishbone diagrams / Ishikawa diagrams) Trace
the problem’s source back to its “actionable root cause”
![Page 18: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/18.jpg)
18
• Seven Basic Quality Tools 7QC Tools
2. Flowcharting (Process Map) a graphical representation of a
process showing the relationships among process steps and display the
sequence of steps
![Page 19: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/19.jpg)
19
• Seven Basic Quality Tools 7QC Tools
3. Check sheet (Tally Sheet) a type of checklist that can be used to
keep track of data such as quality problems uncovered during inspections.
![Page 20: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/20.jpg)
20
• Seven Basic Quality Tools 7QC Tools
4. Pareto Diagram (Pareto Chart)
Identify the vital few sources that are responsible for causing most of a
problem’s effects.
• Focus attention to most
critical issues
• Pareto Principle :
80/20 principle states that
80 percent of problems
are due to 20 percent of
the root causes
![Page 21: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/21.jpg)
21
• Seven Basic Quality Tools 7QC Tools
5. Histograms
A bar chart and are used to describe the central tendency, distraction.
Does not consider the influence of time on the variation exists within a
distribution.
Helps identify which Problems are worth dealing with.
![Page 22: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/22.jpg)
22
• Seven Basic Quality Tools 7QC Tools
6. Control Charts
Graphic displays of the results, over time, of a process; used to assess
whether the process is “in control”.
Control Limits : represent the performing organization's standards
Mean (Average) : It shows the middle of the range of acceptable variation.
Specification Limits : represent the customer's expectations or contractual
requirements
![Page 23: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/23.jpg)
23
• Seven Basic Quality Tools 7QC Tools
6. Control Charts
• Rule of Seven : seven points toward upper or lower control limit may indicate
that process is out of control
Assignable causes – Variations may be caused by differences in
machines, workers overtime, etc. Identify the root cause.
A process is considered out of control when :
1. a data point exceeds a control limit.
2. seven consecutive plot points are above the mean
3. seven consecutive plot points are below the mean.
![Page 24: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/24.jpg)
24
Upper
control limit
Mean Line
(center )
Out of control
Assignable/special
cause
Specification limit:
is point determines by
customer, not calculated
based on control chart
Normal and expected
variation Usually 3 or 6
sigma
Rule of seven (non random
data points) Out of control
Assignable/special cause
Normal
distribution
curve
Lower
control limit
![Page 25: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/25.jpg)
25
• Seven Basic Quality Tools 7QC Tools
7. Scatter diagrams ( correlation charts )
• Tracks two variables to determine their relationship.
• Determines the relationship of independent variables such as paint
quantity, dryer fan speed, and door weight to the dependent variable of
drying time.
Door Paint Spray
Quantity (mL/sqm)Dryer Fan Speed
(rpm)Door weight
Do
or
Dry
ing
Tim
e(m
inu
tes)
![Page 26: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/26.jpg)
26
• Statistical Sampling
8.1- Plan Quality Management T & T
Involves choosing part of a population of interest for inspection
(e.g., selecting 10 samples of 75 electronic components).
Appropriate sampling can often reduce the cost of quality
control.
Brainstorming. This technique is used to generate ideas.
Nominal group technique. This technique is used to allow
ideas to be brainstormed in small groups and then reviewed by
a larger group.
• Additional Quality Planning Tools
![Page 27: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/27.jpg)
8.1- Plan Quality Management Outputs
27
Quality
Management
Plan
• What processes will be followed to help ensure
quality
• Review of earlier decisions to make sure those
decisions are correct
• The meetings to be held addressing quality
• The reports that will address quality
• What metrics will be used to measure quality
• What parts of the project or deliverables will be
measured and when
Process
Improvement
Plan
• Process boundaries. purpose of the process, the start
and end of the process, its inputs
and outputs, the process owner, and the stakeholders of
the process.
• Process configuration. Provides a graphic depiction of
processes, How to improve quality processes.
• Process metrics.
• Targets for improved performance.
![Page 28: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/28.jpg)
8.1- Plan Quality Management Outputs
28
Quality Metrics
• How the control quality process will measure the
deliverables / product.
• What is the measures for each part including
time / cost tolerance / quality accepted level.
Quality
Checklists
a structured tool, used to verify that a set of required
steps has been performed.
Project
Documents
Updates
• Stakeholder register assign new people for tasks.
• Responsibility assignment matrix (change
responsibilities.
• WBS and WBS Dictionary.
![Page 29: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/29.jpg)
29
8.2- Perform Quality Assurance
![Page 30: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/30.jpg)
30
8.2- Perform Quality Assurance.
The process of auditing the quality requirements and the
results from quality control measurements to ensure that
appropriate quality standards and operational definitions
are used.
Are we using the standard?
Can we improve the standard?
![Page 31: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/31.jpg)
31
![Page 32: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/32.jpg)
8.2- Perform Quality Assurance Inputs
32
1. Quality Management Plan
2. Process Improvement Plan
3. Quality Metrics
4. Project Documents
5.
Quality Control
Measurements
• Are the results of control quality activities.
• Analyze and evaluate the quality of the
processes of the project against the standards
of the performing organization or the requirements
specified
.
• Compare the processes used to create the
measurements, and validate actual
measurements to determine their level of
correctness.
![Page 33: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/33.jpg)
8.2- Perform Quality Assurance T & T
33
• Quality Audits
• To see if you are complying to company policies,
standards & procedures.
• Determine whether they are used efficiently & effectively
• Identify all the good practices being implemented
• Identify all the gaps/shortcomings
• Look for new lesson learned & good practices
• Process Analysis
• Includes root cause analysis
• How is the processes going to
find out the defect.
![Page 34: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/34.jpg)
• Quality Management and Control Tools
34
1. Affinity Diagram: A technique that allows large numbers of ideas to be
classified into groups for review and analysis.
8.2- Perform Quality Assurance T & T
![Page 35: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/35.jpg)
35
2. Process Decision Program Charts Used to understand a
goal in relation to the steps for getting to the goal. The PDPC is useful as
a method for contingency planning.
8.2- Perform Quality Assurance T & T
• Quality Management and Control Tools
![Page 36: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/36.jpg)
36
3. Interrelationship Digraphs analyze the relationships among
numerous different issues to find the root cause of the problem.
8.2- Perform Quality Assurance T & T
• Quality Management and Control Tools
![Page 37: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/37.jpg)
37
4. Tree Diagrams (systematic diagrams )
• Used to represent decomposition hierarchies such as the WBS, RBS
(risk breakdown structure), and OBS (organizational breakdown
structure), RBS (resource breakdown structure)
• Decompose processes to find a solution to a problem, and arrive at
corrective or preventive action.
8.2- Perform Quality Assurance T & T
• Quality Management and Control Tools
Arrive at school
on time
Arrive at school
late
Miss school
Catch 1st train
Catch 2nd train
Miss trains
Catch 1st bus
Catch 2nd bus
Miss buses
Leave
home
![Page 38: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/38.jpg)
38
4. Prioritization MatricesIdentify the key issues and the suitable alternatives to be prioritized as
a set of decisions for implementation
8.2- Perform Quality Assurance T & T
• Quality Management and Control Tools
5. Activity Network Diagram if you're looking to improve time
management processes.
6. Matrix Diagrams• Used to perform data analysis within the organizational structure.
• Seeks to show the strength of relationships between factors,
causes, and objectives
![Page 39: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/39.jpg)
39
![Page 40: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/40.jpg)
8.2- Perform Quality Assurance Outputs
40
1. Change Requests
2. Project Management Plan Updates
3. Project Documents Updates
4. OPA
![Page 41: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/41.jpg)
41
8.3- Control Quality
![Page 42: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/42.jpg)
42
8.3- Control Quality.
• The process of monitoring and recording results of
executing the quality activities to assess performance
• The key benefits of this process include
Identifying the causes of poor quality
Validating that project deliverables and work meet
the requirements
![Page 43: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/43.jpg)
43
8.3- Control Quality.
Prevention (Keeping errors out of the process).
Inspection (Keeping errors out of the hands of the
customer).
Attribute sampling ( either conform or not )
Variables sampling (degree of conformity)
Tolerance (range of acceptable results) and
Control limits (thresholds which may indicate out of
control)
![Page 44: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/44.jpg)
44
![Page 45: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/45.jpg)
8.3- Control Quality Inputs
45
Project Management Plan
Quality Metrics
Quality checklists
Work Performance Data
Approved Change Requests
Deliverables
Project
Documents
• Agreements,
• Quality audit reports
• Training plans and assessments of effectiveness.
• Process documentation
OPA
![Page 46: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/46.jpg)
8.3- Control Quality T & T
46
Seven Basic Quality Tools
Statistical Sampling
Inspection
Approved Change Request Reviews
![Page 47: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/47.jpg)
8.3- Control Quality Outputs
47
Quality Control Measurements
Validated Changes
Verified Deliverables
Work Performance Information
Change Requests
Project Management Plan Updates
Project Document Updates
OPA
![Page 48: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/48.jpg)
Questions
48
1. When a product or service completely meets a customer's
requirements:
A. Quality is achieved.
B. The cost of quality is high.
C. The cost of quality is low.
D. The customer pays the minimum price.
![Page 49: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/49.jpg)
Questions
49
1. When a product or service completely meets a customer's
requirements:
A. Quality is achieved.
B. The cost of quality is high.
C. The cost of quality is low.
D. The customer pays the minimum price.
Answer : A
![Page 50: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/50.jpg)
Questions
50
2. To what does the following definition refer? "The point
where the benefits or revenue to be received from improving
quality equals the incremental cost to achieve that quality ?
A. Quality control analysis
B. Marginal analysis
C. Standard quality analysis
D. Conformance analysis
![Page 51: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/51.jpg)
Questions
51
2. To what does the following definition refer? "The point
where the benefits or revenue to be received from improving
quality equals the incremental cost to achieve that quality ?
A. Quality control analysis
B. Marginal analysis
C. Standard quality analysis
D. Conformance analysis
Answer : B
![Page 52: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/52.jpg)
Questions
52
3. Who is ultimately responsible for quality management on
the project?
A. The project engineer
B. The project manager
C. The quality manager
D. The team member
![Page 53: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/53.jpg)
Questions
53
3. Who is ultimately responsible for quality management on
the project?
A. The project engineer
B. The project manager
C. The quality manager
D. The team member
Answer : B
![Page 54: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/54.jpg)
Questions
54
4. All the following are tools of Control Quality EXCEPT:
A. Inspection.
B. Cost of quality.
C. Pareto diagram.
D. Fishbone diagram.
![Page 55: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/55.jpg)
Questions
55
4. All the following are tools of Control Quality EXCEPT:
A. Inspection.
B. Cost of quality.
C. Pareto diagram.
D. Fishbone diagram.
Answer : B
![Page 56: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/56.jpg)
Questions
56
5. Pareto diagrams help the project manager:
A. Focus on the most critical issues to improve quality.
B. Focus on stimulating thinking.
C. Explore a desired future outcome.
D. Determine if a process is out of control.
![Page 57: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/57.jpg)
Questions
57
5. Pareto diagrams help the project manager:
A. Focus on the most critical issues to improve quality.
B. Focus on stimulating thinking.
C. Explore a desired future outcome.
D. Determine if a process is out of control.
Answer : A
![Page 58: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/58.jpg)
Questions
58
6. A control chart helps the project manager:
A. Focus on the most critical issues to improve quality.
B. Focus on stimulating thinking.
C. Explore a desired future outcome.
D. Determine if a process is functioning within set limits.
![Page 59: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/59.jpg)
Questions
59
6. A control chart helps the project manager:
A. Focus on the most critical issues to improve quality.
B. Focus on stimulating thinking.
C. Explore a desired future outcome.
D. Determine if a process is functioning within set limits.
Answer : D
![Page 60: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/60.jpg)
Questions
60
7. Testing the entire population would:
A. Take too long.
B. Provide more information than wanted.
C. Be mutually exclusive.
D. Show many defects.
![Page 61: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/61.jpg)
Questions
61
7. Testing the entire population would:
A. Take too long.
B. Provide more information than wanted.
C. Be mutually exclusive.
D. Show many defects.
Answer : A
![Page 62: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/62.jpg)
Questions
62
8. All of the following are examples of the cost of
nonconformance EXCEPT:
A. Rework.
B. Quality training.
C. Scrap.
D. Warranty costs.
![Page 63: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/63.jpg)
Questions
63
8. All of the following are examples of the cost of
nonconformance EXCEPT:
A. Rework.
B. Quality training.
C. Scrap.
D. Warranty costs.
Answer : B
![Page 64: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/64.jpg)
Questions
64
9. You are asked to select tools and techniques to implement
a quality assurance program to supplement existing quality
control activities. Which of the following would NOT be
appropriate for this purpose?
A. Quality audits
B. Statistical sampling
C. Pareto diagrams
D. Focus groups
![Page 65: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/65.jpg)
Questions
65
9. You are asked to select tools and techniques to implement
a quality assurance program to supplement existing quality
control activities. Which of the following would NOT be
appropriate for this purpose?
A. Quality audits
B. Statistical sampling
C. Pareto diagrams
D. Focus groups
Answer : DFocus groups are a tool of the Collect Requirements process, and
would not be useful in the Perform Quality Assurance process.
![Page 66: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/66.jpg)
Questions
66
10. As the project manager, you are preparing your quality
management plan. You are looking for a tool that can
demonstrate the relationship between events and their
resulting effects. You want to use this tool to depict the events
that cause a negative effect on quality. Which of the following is
the BEST choice for accomplishing your objective?
A. Histogram
B. Pareto diagram
C. Ishikawa diagram
D. Control chart
![Page 67: Pmp quality chapter 8](https://reader034.vdocument.in/reader034/viewer/2022052305/5873492c1a28ab56378b4953/html5/thumbnails/67.jpg)
Questions
67
10. As the project manager, you are preparing your quality
management plan. You are looking for a tool that can
demonstrate the relationship between events and their
resulting effects. You want to use this tool to depict the events
that cause a negative effect on quality. Which of the following is
the BEST choice for accomplishing your objective?
A. Histogram
B. Pareto diagram
C. Ishikawa diagram
D. Control chart
Answer : C