PMP ® Sample Questions PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied

Upload: osp-international-llc

Post on 18-Dec-2014

556 views

Category:

Education


2 download

DESCRIPTION

Second Set of PMP Exam Sample Questions

TRANSCRIPT

Page 1: PMP Sample Questions Set 2

PMP® Sample

Questions

PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.

Page 2: PMP Sample Questions Set 2

This presentation will showcase free sample PMP® questions that

will help and guide you in studying for your PMP® exam

Find more free sample questions when you visit www.free-pm-exam-questions.com and free.pm-exam-

simulator.com

Page 3: PMP Sample Questions Set 2

Sensitivity Analysis has strong similarities to which of the following?

a. Probability Distributionsb. Risk Identificationc. Design of Experimentsd. Statistical Sampling

Sample PMP® Exam Question

HINT: Sensitivity Analysis is a risk analysis technique not a risk identification technique.

Page 4: PMP Sample Questions Set 2

The correct answer is C

Don't get carried away by choice B. Sensitivity Analysis is a risk analysis technique not a risk identification technique. It is not a sampling technique or a distribution. In Design of Experiments one studies the effect of some process or intervention (the treatment) on some objects (the experimental units). In Sensitivity Analysis one looks at the effect of varying the inputs of a mathematical model on the output of the model itself. In both disciplines one strives to obtain information from the system with a minimum of physical or numerical experiments.

Answer and Explanation

Page 5: PMP Sample Questions Set 2

You are performing the Plan Risk Responses process for your manufacturing project when encounter a critical risk that may have a high impact on the project completion. All of the following are valid responses to this new risk except?

a. Allocating Contingency Reservesb. Developing Fallback Optionsc. Conducting Bidder Conferencesd. Reviewing risks driven by strategies

Sample PMP® Exam Question

HINT: A Fallback Plan is used when a primary response plan proves to be inadequate.

Page 6: PMP Sample Questions Set 2

The correct answer is C

Conducting Bidder Conferences is not a strategy used in Risk Management. All other answer choices are valid risk responses.

Answer and Explanation

Page 7: PMP Sample Questions Set 2

Cultural resistance is the root cause of quality issues according to whom?

a. Demingb. Malcolm Baldridgec. Jurand. Shelby

Sample PMP® Exam Question

HINT: Juran is credited for adding human dimensions to quality management.

Page 8: PMP Sample Questions Set 2

The correct answer is C

Juran says the cultural resistance or resistance to change is the primary reason for quality problems.

Answer and Explanation

Page 9: PMP Sample Questions Set 2

You are working on a web development project. You looked on the internet for some off-the-shelf software to support the project. Your internet search may lead to better products but which of the following problems are associated with those products?

a. Off-the-shelf-products always charge variable rates.b. Often the software does not work.c. It is difficult to get support after installation.d. Internet search cannot be used for highly complex

procurements.

Sample PMP® Exam Question

HINT: Internet search may be good for procuring small products.

Page 10: PMP Sample Questions Set 2

The correct answer is D

Highly complex, and high-risk procurement efforts that must be closely monitored cannot be obtained by internet search.

Answer and Explanation

Page 11: PMP Sample Questions Set 2

Which of the following documents is in a text-oriented format compared to other documents?

a. Organizational Breakdown Structureb. Responsibility Assignment Matrixc. Resource Breakdown Structured. Role-Responsibility-Authority Forms

Sample PMP® Exam Question

HINT: Look for the keyword 'forms'.

Page 12: PMP Sample Questions Set 2

The correct answer is D

Role-Responsibility-Authority Forms are text-oriented forms used as a tool to in the Develop Human Resource Plan.

Answer and Explanation

Page 13: PMP Sample Questions Set 2

On your project you handle known risks by performing the Plan Risk Responses process. Which of the following would you use when you encounter unknown risks?

a. Risk Reservesb. Risk Mitigationc. Risk Transferd. Risk Acceptance

Sample PMP® Exam Question

HINT: Unknown risks cannot be managed proactively.

Page 14: PMP Sample Questions Set 2

The correct answer is A

Unknown risks are handled by applying Risk Reserves in the project.

Answer and Explanation