polyroof interactive doc - arrow roofing ltd · specially developed flexi-resins fuse together to...
TRANSCRIPT
N A V I G A T I O NA guide to quickly access the informationyou need from this document
BOOKMARKSAllow you to jump to the area of interest.
Some areas have sub-topics which can be access by clicking on the symbol to
the left of the bookmark.
Next page
Previous page
Go to the next section
Go to beginning of a section
Clicking a contentheading will take youstraight to the topic.
Back to contents page
Clicking a sub-headingwill take you straightto the topic.
Page
CONTENTS
Polyroof Corporate Overview 3 - 6
Polyroof Product Selector Guide 7 - 11
Polyroof 185
Product Information & Design Guide 13 - 24
Guideline Specification - Standard Warm Roof Timber Joists 25 - 35
Balcony Warm Roof Timber Joists 36 - 47
Standard Cold Roof Timber Joists 48 - 58
Polyroof Elastex
Product Information & Design Guide 59 - 68
Guideline Specification - Asphalt 69 - 79
Felt 80 - 91
Galvanised Steel Gutters (Weathered) 92 - 102
Polyroof Protec
Product Information & Design Guide 103 - 112
Guideline Specification - Asphalt 113 - 124
Felt 125 - 136
Concrete Deck 137 - 148
Polyroof Case Files
Polyroof improves the home improvements market 149 - 150
Refurbishment Systems 151 - 152
Polyroof: Cold appied for lower fire risk and lower insurance cost 153 - 155
Lead and Copper Reproduction 155 - 156
Regeneration and New Build 157 - 160
A D V A N C E D L I Q U I D R O O F I N G S Y S T E M S
Contents Section Start Next Section Page Page
P O L Y R O O F A D V A N C E D L I Q U I D R O O F I N G S Y S T E M S
Cold applied liquid roofing
solutions
INTRODUCTIONContents Section Start Next SectionPage 3 Page �� Page
INTRODUCTIONPage 4 Contents Section Start Next Section Page �� Page
APPROVALS AND GUARANTEES
Polyroof 185 was the first membrane system to
receive (in 1988) the British Board of Agrément
(BBA) certificate. Polyroof 185 is also fire tested
to BS476 (Part 3) and designated external FAA,
the highest roof rating. Elastex is BBA approved
and Protec has attained the internationally
recognised Factory Mutual (FM) and Underwriters
Laboratories (UL) approvals.
Polyroof overlay systems come with flexible
guarantees from 10-25 years, dependent on the
substrate condition. The Polyroof 185 20 year
guarantee is supported by an insured and
independently administered trust-fund.
APPROVED CONTRACTORS
The quality systems of Polyroof Products are
approved to ISO 9001:2000. Our network of
approved contractors maintain these high
standards and receive training at our in-house
facilities as well as on-site. On-going technical
assistance and monitoring ensure that Polyroof's
criteria for the application of their membranes is
kept to the highest standards.
POLYROOF TECHNICAL SUPPORT
Polyroof offers its clients a high level of on-going
technical support. Our technical team will, when
required, carry out surveys and produce detailed
roof specifications, drawings and proposals.
COLD LIQUID APPLIED ROOFING SOLUTIONS
Polyroof Products Ltd. is one of the
country’s leading producers of cold,
liquid applied seamless membrane
systems for the waterproofing of flat and
inclined roofs. A range of quality
approved systems is available for new
roofs and for roof refurbishment. R&D
programmes are focused on continually
improving and extending our product
range. Over five million square metres of
Polyroof have been laid since the company
was first established in 1984. Most local
authorities now specify Polyroof systems
- together with major housing associations,
construction companies, banks, airports,
breweries and other industrial and
commercial organisations throughout the
country. Likewise in the domestic market,
Polyroof has brought peace of mind to
many thousands of homes by providing a
permanent solution to persistently
leaking roofs.
The Polyroof Group is also
active in North America
operating through a wholly
owned subsidiary, Applied
Liquid Technologies (ALT)
ALT has already won large
and prestigious contracts
such as the Empire State
Building and New York
State University
T H E P O L Y R O O F G R O U P
A D V A N C E D L I Q U I D R O O F I N G S Y S T E M S
INTRODUCTIONPage 5 Contents Section Start Next Section Page �� Page
L I Q U I D - A P P L I E D R O O F I N G S Y S T E M S
ElastexA fully reinforced, elastomeric polyurethane overlay available in
10 - 25 year guarantee versions. Suitable for overlaying a wide
range of existing roof surfaces such as felt, concrete, plastic
coated metals, stone, brick and most single ply membranes.
Elastex provides an extremely durable and long lasting
waterproofing solution.
■ For waterproofing existing roofs and gutters
■ Ideal for large refurbishment projects
■ Seamless, cold liquid applied membrane
■ Up to 25 year guarantees available
■ BBA approved
■ Minimal disruption
■ Minimal surface preparation
■ Highly flexible and resilient
■ Available in a range of colours and finishes including anti-slip
■ High levels of UV protection
Elastexprotection coat
Elastexembedmentcoat
Reinforcement
Elastexembedmentcoat
Existing prepared substrate
ELASTEX
Mineral finish(Optional)
Protec resin
Reinforcement
Protec resin
Primed existing substrate or new timber
PROTEC
Flexi-Resin 185C
Flexi-Resin 185B
Polymat
Flexi-Resin 185B
New plywood decking
POLYROOF 185Polyroof 185Complete glassfibre reinforced polyester (GRP) composite
roofing system applied to an exterior grade plywood deck.
Specially developed flexi-resins fuse together to form a seamless,
highly durable, impervious membrane that accommodates
normal structural variations and regular foot traffic. Polyroof
185 was the first GRP roofing system to receive BBA approval:
■ For all flat roofs and box / valley gutters
■ New build or refurbishment
■ Seamless, cold liquid applied membrane
■ BBA approved and 30 year durability rated
■ 20 year insurance backed guarantee
■ Withstands regular foot traffic
■ Highly suitable for balconies and walkways
■ Impact resistant and vandal resistant
■ Warm or cold roof specifications
■ Available in a range of colours and finishes
Polyroof 185 was used forwaterproofing the balcony
and barrel roof of this awardwinning project in Plymouth.
Protec was used to waterproofthis concrete roof in Greenwich
Village, New York.
A protective membraneof Elastex was applied to the
roofs of these refurbishedflats in Norwich.
ProtecFast curing overlay based on a highly flexible polyester resin with
glassfibre reinforcement. Adheres to a variety of substrates and
can be extremely cost effective. Suitable for large or small
projects. Since no stripping of the old roof is required, Protec is
ideal for contracts requiring minimal disruption.
■ For all flat roofs
■ New build or refurbishment
■ Seamless, cold liquid applied membrane
■ UL and FM approved
■ 10 year guarantees available
■ Withstands occasional foot traffic
■ Minimal disruption
■ Minimal surface preparation
■ Available in a range of colours and finishes
Nothing in this specification brochure or any other marketing literature produced by or on behalf of Polyroof Products Limitedis to be regarded as constituting a contract binding in law between Polyroof Products Limited and any customer.
The only contract which Polyroof will enter into with the customer is that contained in the Guarantees, the details of whichare available on request. This Guarantee is in the form of a written guarantee which takes effect only when issued in writingby Polyroof to the customer at the request of the Contractor.
PLUS OVER ONE HUNDRED LOCAL AUTHORITIES AND HOUSING ASSOCIATIONS
O U R C L I E N T S I N C L U D E :
POLYROOF PRODUCTS LTD
FURNESS HOUSE
CASTLE PARK INDUSTRIAL ESTATE
FL INT FL INTSHIRE
CH6 5XA
Tel : 01352 735 135
Fax: 01352 735 182
Emai l : technica l@polyroof .co.uk
www.polyroof .co.uk
FREEPHONEH E L P L I N E
0800 801 890
E S T. 1984
INTRODUCTIONPage 6 Contents Section Start Next Section Page �� Page
POLYROOF 185ELASTEX
PROTEC
PROTEC
THE NATIONAL FEDERATION OFROOFING CONTRACTORS LIMITED
Associate Member
■ Anglian Windows
■ Ansells Breweries
■ Asda Stores
■ ATS
■ BAE Systems
■ Barclays Bank
■ Barratt Homes
■ Batesman Brewery
■ Bath Breweries
■ Berkeley Homes
■ Bluesky Developments
■ BNFL
■ BP
■ Bradford & Bingley
■ British Alcan
■ British Gas
■ British Telecom
■ Buccleugh Estates
■ Burtonwood Brewery
■ Cable & Wireless
■ Cheltenham &
Gloucestershire
■ Clydesdale Bank
■ Cognies Chemicals
■ CO-OP ■ Corus ■ Dandara■ DSM Resins UK ■ Dublin Airport■ Eli Lilly■ English Partnerships ■ Gateway Building Society■ Gatwick Airport■ GlaxoSmithKline■ Greenhall Brewery ■ Heathrow Airport■ HSBC■ IBM ■ J W Lees Brewery■ Kimberly Clark■ King Sturge■ Laura Ashley ■ Lloyds Supersave
Drug Stores ■ Lloyds TSB■ Manchester Airport■ Marks & Spencer■ Marsden Brewery■ Marsdens Thomas
& Evershed
■ M O D
■ Nat West
■ National Trust ■ Nationwide
Building Society
■ NationwideEstate Agents
■ Nestlé
■ New York Port Authority
■ New York State University
■ Next
■ Northern Gas Board
■ Northern Ireland
Electricity Board
■ Northern IrelandHousing Executive
■ Oxford Brookes University
■ Raytheon
■ Remploy
■ Rentokil Property Care
■ Robinsons Brewery
■ Royal Bank Buildings
■ Royal Bank of Scotland
■ Royal MailProperty Holdings
■ Schering Plough
■ Scottish Hydro Electric
■ Scottish Landowners
■ Scottish & NewcastleBreweries
■ Severn Trent Water
■ Slough Estates
■ Southern Electric
■ South West Water
■ Spar Grocery Chains
■ Spillers Pet Food
■ Stead & Simpson
■ The Post Office
■ Thwaites Brewery
■ Tinsley Food
■ United Grain& Malt Distillery
■ United Utilities
■ Waitrose
■ Walkers Shortbread
■ Woolworths
■ Wrexham Lager Brewery
■ Zurich Financial Services
PRODUCT SELECTORPage 7
A D V A N C E D L I Q U I D R O O F I N G S Y S T E M S
P R O D U C T S E L E C T O R G U I D E
Contents Section Start Next Section Page �� Page
PRODUCT SELECTORPage 8
L I Q U I D - A P P L I E D R O O F I N G S Y S T E M S
Polyroof Products is a market leader in cold–applied,
liquid roofing solutions. Reinforced flexible resin
systems are available for new roofs, roof replacement,
over-decking and overlaying: everything from
complete roof strip and re-boarding to overlay
protection. They are completely seamless systems
that do not crack or blister and substantially outlast
and outperform traditional roofing materials. This
Product Selector Guide is designed to help you select
the right system for the job in question, but our
Technical Department are always on hand for advice
and assistance.
COMPLETE COMPOSITE ROOFING SYSTEM
For long life protection in new build or roof refurbishment
(strip and re-boarding or over-decking) we recommend a
consolidated GRP composite that is applied in-situ.
Polyroof 185
A reinforced, seamless, cold applied flexible polyester
resin system comprising base coat and topcoat. The
system is designed to be used with high-grade plywood
and glassfibre reinforcement to produce a totally
waterproof and weatherproof flat roof deck. Specially
developed flexi-resins fuse together to form an extremely
durable, impervious skin, which accommodates normal
structural variations and regular foot traffic, and is highly
resistant to vandalism. Polyroof 185 is 30-year durability
rated by the BBA (British Board of Agrément) and comes
with an insurance backed 20-year guarantee.
OVERLAY SYSTEMS
Our flexible overlay resin range is ideal for refurbishment
projects as they can overcoat virtually every existing
substrate with minimal preparation and disruption.
Overlay systems can be applied equally well to pitched or
flat roofs, and since no stripping of the old roof is
required, Polyroof overlay systems offer a quick and neat
solution with competitive price / performance. They
rapidly become weather resistant and provide high levels
of UV protection.
Protec
A seamless, cold applied, flexible reinforced polyester
resin for flat or inclined roofs. Single resin application
makes Protec very cost effective, especially for
commercial projects. The system is available with 10,
15 or 20 year guarantees
Elastex
A reinforced, seamless, cold applied, highly flexible
polyurethane overlay system available with 10, 15, 20
or 25 year guarantees. Ideal for larger commercial
contracts and for weatherproofing a wide range of flat
or inclined roof surfaces.
Roofcoat Plus
A reinforced, seamless, cold applied, flexible acrylic/PU
hybrid overlay system guaranteed 10 years. Ideal for
coating pitched asbestos sheeted roofs, Plastisol and
metal sheeting.
EBS (Elastex balcony system)
A reinforced, seamless, cold applied balcony
refurbishment system. EBS is a moisture-activated ultra-
high solids polyurethane overlay that is easy to clean and
has excellent UV resistance. Aluminium oxide grits are
incorporated into the system to provide an attractive
finish, slip resistance and surface wear protection.
Roofcoat (Repair system)
A reinforced, acrylic roof repair system, easily applied by
brush with minimum surface preparation. Roofcoat is the
ideal material for localised repair or for weather proofing
most roofs regardless of the substrate.
Contents Section Start Next Section Page �� Page
PRODUCT SELECTORPage 9
GRP COMPOSITETO PLYWOODDECKING
POLYURETHANEOVERLAY SYSTEM
PU/ACRYLICHYBRID OVERLAY SYSTEM
POLYESTEROVERLAY SYSTEM
Polymat
Flexi-Resin 185B
New plywood decking
Flexi-Resin 185B
Roofcoat PlusHB Smooth
Elastex treatment to laps and bolts
Roofcoat PlusFibretex
Existing primedsubstrate
Mineral finish(Optional)
Protec resin
Reinforcement
Protec resin
Existing substrate or timber
ElastexProtection Coat
ElastexEmbedment Coat
Reinforcement
ElastexEmbedment Coat
Existing substrate
POLYROOF 185
ROOFCOAT PLUSPROTEC
ELASTEX
Flexi-Resin 185C
Contents Section Start Next Section Page �� Page
PRODUCT SELECTORPage 10
Polyester(GRP)
New deck /overdeck
Flat / Inclined
✔ GRP Trims ✔ ✔ ✔
P R O D U C T S E L E C T O R
RESI
N B
ASE
TYPE
PITC
H
INSU
RAN
CEBA
CKIN
G
DET
AIL
ING
OCC
ASI
ON
AL
LIG
HT
TRA
FFIC
MED
IUM
TRA
FFIC
BALC
ON
Y/W
ALK
WAY
SH
EAVY
TRA
FFIC
✔
PON
DED
ARE
AS
There are many considerations to take into account in the specification of a new roof or roof
renovation system. They can include factors such as the type and condition of the substrate;
whether or not an upgrade to a warm roof is necessary; length of required guarantee; and the level
of anticipated foot traffic.
We’ve devised this selector guide to help you choose the most appropriate Polyroof system for the
job in question. If you are in any doubt which is the most suitable, or if you would like any further
information, then please call our freephone technical helpline on 0800 801 890.
SPECIFIER HELPLINE: 0800 801 890email: [email protected] or visit: www.polyroof.co.uk
There's no substitute for personal contact, so if you can't find what you're
looking for, or if you're not sure which is the best system for the job in
hand, then don't hesitate to call, fax or email our Technical Department.
C O N T A C T U S F O R F U R T H E R I N F O R M A T I O N
Polyurethane Overlay Flat / Inclined Opt
Refurbish existing detail
or use new GRP trims
✗ ✗
Polyester(Flexible GRP) Overlay Flat /
Inclined Opt
Refurbish existing detail
or use new GRP trims
✔ ✗ ✗
Polyurethane Overlay Flat Opt
Refurbish existing detail
or use new GRP trims
✔ ✔ ✗
PU/Acrylichybrid Overlay Pitched Opt N/A N/A N/A N/A
✔
✔
✔
✗
✔
S Y S T E M S G U I D E
185GUARANTEE 20 YEARS
NEW BUILD /OVERDECK
OVERLAYSYSTEMS
ELASTEXGUARANTEE 10, 15, 20, 25 YEARS
PROTECGUARANTEE 10-20 YEARS(Single resin application)
EBSGUARANTEE 10 YEARS(Balconies only)
ROOFCOAT PLUSGUARANTEE 10 YEARS
† Polyroof 185 must alwaysbe laid to a new plywooddeck. Defective substratesmust be replaced.
Detailed technical information and health and safety data on each of the products
mentioned in this Selector Guide are available on request from our Technical Department.
For green roof applications please contact Polyroof Technical Department.
Contents Section Start Next Section Page �� Page
PRODUCT SELECTORPage 11
ASP
HA
LT
FELT
CO
NC
RET
E
PLY
WO
OD
PITC
HED
ASB
ESTO
SC
EMEN
T SH
EETI
NG
LEA
D &
C
OPP
ER
PRO
FILE
MET
AL
SHEE
TIN
G /
PLA
STIS
OL
BR
ICK
& S
TON
E
SLA
TES
/ TI
LES
GR
P
ASB
ESTO
SG
UTT
ERS
MET
AL
GU
TTER
S
SIN
GLE
PLY
MEM
BR
AN
E *1
† Polyroof 185 must alwaysbe laid to a new plywooddeck. Defective substratesmust be replaced.
Detailed technical information and health and safety data on each of the products
mentioned in this Selector Guide are available on request from our Technical Department.
For green roof applications please contact Polyroof Technical Department.
✔ ✔ ✔ ✔ ✗ ✔ ✔ ✗ ✔ ✗ ✔ ✔† † †
✔† † † † † †
✔ ✔ ✔ ✔ ✗ ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔
✔ ✔ ✔ ✔ ✗ ✗ ✗ ✔ ✗ ✔ ✗ ✗ ✗
✔ ✗ ✔ ✗ ✗ ✗ ✗ ✔ ✗ ✔ ✗ ✗ ✗
✗ ✗ ✗ ✗ ✔ ✗ ✔ ✔ ✔ ✗ ✗ ✗ ✗
S U B S T R A T E C O M P A T I B I L I T Y
For advice on other substrates, including woodwool slabs, strammit, chipboard etc contact 0800 801 890
185GUARANTEE 20 YEARS
NEW BUILD /OVERDECK
OVERLAYSYSTEMS
ELASTEXGUARANTEE 10, 15, 20, 25 YEARS
PROTECGUARANTEE 10-20 YEARS(Single resin application)
EBSGUARANTEE 10 YEARS(Balconies only)
ROOFCOAT PLUSGUARANTEE 10 YEARS
Contents Section Start Next Section Page �� Page
PRODUCT SELECTORPage 12
A NATIONWIDE NETWORK OF COMPANY TRAINED TECHNICIANS
Polyroof guaranteed systems are only supplied to and installed by contractors fully application
trained and licensed by the company, to ensure consistent quality of installation. Contractors’
performance is regularly monitored. Failure to comply with the company’s stringent standards
leads to withdrawal of certification.
QUALITY CONTROL
Polyroof Products Ltd operates comprehensive and rigorous quality control procedures in
accordance with ISO 9001:2000. The scope of this approval includes the design and
installation of roofing systems, the provision of technical support, as well as the appointment
and monitoring of installers. Not only is the manufacture of Polyroof liquid applied roofing
systems and accessories quality approved, but so too is the procurement, storage and supply
of all related materials and consumables.
GUARANTEES
Flexible guarantees are available for most Polyroof systems, when applied by approved
contractors. Polyroof 185 carries a 20-year insurance backed guarantee supported by an
insured and independently administered Trust Fund. Different term guarantees are available
for overlay systems, the period of the guarantee being largely dependent on the soundness
of the substrate.
Nothing in this specification brochure or any other marketing literature produced by or on behalf of Polyroof Products Limitedis to be regarded as constituting a contract binding in law between Polyroof Products Limited and any customer.
The only contract which Polyroof will enter into with the customer is that contained in the Guarantees, the details of whichare available on request. This Guarantee is in the form of a written guarantee which takes effect only when issued in writingby Polyroof to the customer at the request of the Contractor.
POLYROOF 185
POLYROOF PRODUCTS LTD
FURNESS HOUSE
CASTLE PARK INDUSTRIAL ESTATE
FL INT FL INTSHIRE
CH6 5XA
Tel : 01352 735 135
Fax: 01352 735 182
Emai l : technica l@polyroof .co.uk
www.polyroof .co.uk
FREEPHONEH E L P L I N E
0800 801 890
E S T. 1984
THE NATIONAL FEDERATION OFROOFING CONTRACTORS LIMITED
Associate Member
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 13
A D V A N C E D L I Q U I D R O O F I N G S Y S T E M S
P R O D U C T I N F O R M A T I O N & D E S I G N G U I D E
185
POLYROOF 185
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 14
FLEXI-RESIN 185CAn unique combination of flexibility, toughness
and weather-resistance, exclusive to Polyroof.
FLEXI-RESIN 185BAnother exclusive resin,
which is also flexible and so highly impact-resistant
that it withstands a hammer blow without penetration.
POLYMATA reinforcing glass fibre mat,
which gives the system itsstrength to withstand expansion
and contraction forces.
FLEXI-RESIN 185BApplied either side of
the matting, it penetrates down into the decking
and up to chemically bond with Flexi-Resin
185C to form a single, homogeneous membrane.
DECKING18mm Polyroof approved
plywood such as Finnforest Spruce l l / l l l
A D V A N C E D S E A M L E S S R O O F I N G S Y S T E M S
■ COLD APPLIED ■ 20 YEAR GUARANTEE ■ SEAMLESS ■ MAINTENANCE-FREE ■ 30 YEAR DURABILITY ■ SUITABLE FOR FREQUENT FOOT TRAFFIC
F O R S P E C I F I C AT I O N A D V I C E
C A L L T H E T E C H N I C A L H E L P L I N E O N
0 8 0 0 8 0 1 8 9 0185
NOT THE SYSTEM YOU’RE LOOKING FOR?
Polyroof 185 is part ofour range of liquidapplied roofing systems.
If you’re not sure which isthe best system to use, referto our Product Selector or phone 0800 801 890.
RELATED BROCHURESPROTEC (Overlay)ELASTEX (Overlay)EBS (Balconies)ROOFCOAT PLUS (Overlay)ROOFCOAT (Repairs)PRODUCT SELECTOR
C O N T E N T S
POLYROOF 185
PRODUCT DATA
DESIGN CONSIDERATIONS
WARM ROOF DESIGNS
TYPICAL NBS WARM ROOF SPECIFICATION
COLD ROOF DESIGNS
TYPICAL NBS COLD ROOF SPECIFICATION
PRE-FORMED COMPONENTS
DESIGN DETAILING
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 15
■ COLD APPLIED ■ 20 YEAR GUARANTEE ■ SEAMLESS ■ MAINTENANCE-FREE ■ 30 YEAR DURABILITY ■ SUITABLE FOR FREQUENT FOOT TRAFFIC
Polyroof 185 is the UK’s market leading in-situ fibreglass
roofing system. Some ten million square metres have
been laid in domestic, commercial and industrial
applications since the product was first launched back in
1984. It is widely acknowledged by professional specifiers
as a quality benchmark and is specified for refurbishment
and new build by Housing Associations, Architectural
Practices and Local Authorities throughout the country.
■ Complete composite roofing solution
for flat roofs and box/valley gutters
■ New build or refurbishment
■ Seamless, cold liquid applied membrane
■ 30 year durability rated by the BBA
■ 20 year insurance backed guarantee
■ Withstands regular foot traffic
■ Impact resistant & vandal resistant
■ Warm or cold roof specifications
POLYROOF 185 IS NOT A COATING BUT A COMPLETE
COMPOSITE ROOF DECK SYSTEM
Developed exclusively with Europe’s largest polyester resin
producer and technology leader, Polyroof 185 is based on
specially developed flexi-resins that fuse together with the
reinforcement to form a tough, impervious skin, which is
applied to a substrate of high-grade plywood. The roof
deck accommodates normal structural variations and
regular foot traffic, while the durability of the product
makes it ideal for walkways and balconies. Individual
contracts of over 15,000m 2 have been laid as a single
membrane, and a range of BS4800 colours are available
to blend with natural stone, brick, slate and wood.
POLYROOF 185 IS COLD APPLIED FOR SPEED
AND SAFETY
Like all Polyroof systems, Polyroof 185 is cold applied so
there is minimum disruption, without the fire and safety
risks associated with conventional roofing systems that
rely on boilers and exposed flames. Polyroof 185 achieves
external FAA rating to BS 476 Part 3, the most stringent
test for roofing membranes in the UK.
POLYROOF 185 HAS CLASS LEADING 30 YEAR
DURABILITY RATING AND A 20 YEAR INSURANCE-
BACKED GUARANTEE
Polyroof 185 has been proven to be technically superior
to other fibreglass roofing systems. This is why Polyroof
185 is durability rated by the BBA for a full 30 years.
It was also the first such system to receive BBA approval
in 1988. All Polyroof 185 installations come with a
watertight, insurance backed, 20 year guarantee and
work is carried out by a national network of fully
accredited Polyroof contractors. Polyroof Products Ltd
is a ISO 9001:2000 approved company.
P O L Y R O O F 1 8 5
F O R S P E C I F I C AT I O N A D V I C E
C A L L T H E T E C H N I C A L H E L P L I N E O N
0 8 0 0 8 0 1 8 9 0
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 16
■ COLD APPLIED ■ 20 YEAR GUARANTEE ■ SEAMLESS ■ MAINTENANCE-FREE ■ 30 YEAR DURABILITY ■ SUITABLE FOR FREQUENT FOOT TRAFFIC
PROPERTIES IN RELATION TO FIRE
A system comprising Polyroof 185 applied to a 19mm thick
plywood substrate, when tested to BS.476 : Part 3 : 1958,
was designated EXT.F.A.A.
The designation of other specifications (e.g. on
combustible substrates) should be confirmed by:
England and Wales
Test or assessment in accordance with Document B,
Appendix A, Clause A1.
Scotland
Test to conform with Standards D2.5 and D3.6.
WEATHERTIGHTNESS
Test data confirms that the systems will adequately resist
the passage of moisture to the inside of the building and
so meet the requirements of the National Building
Regulations:
England and Wales
Approved Document C4, Section 5.1.
Scotland
Standard G3.1, Regulation 17.
Northern Ireland
Regulation C5.
The system is impervious to water when used as described,
and will give a weathertight roofing capable of accepting
minor structural movements without damage.
RESISTANCE TO WIND UPLIFT
Resistance to wind uplift is adequate to meet the effects of
wind suction likely to occur in practice.
DURABILITY
The British Board of Agrément has confirmed that a GRP
laminate constructed in accordance with the installation
guide and formed in satisfactory weather conditions,
can be expected to maintain its integrity and show no
measurable loss of physical properties for a period of 30
years. The system will have a life expectancy of at least 20
years provided there is no abnormal movement of the roof
structure and the roof is subject to the normal regular
inspections and maintenance.
STANDARDS COMPLIANCE
B.B.A Certificate No: 91/2604. Certificate held since 1988.
Fire tested to BS.476 (Part 3), designed Ext. F.A.A.
Resins manufactured to BS.3532 and BS.2872, matting to
BS.3496 and colours to BS.4800.
Tested for impact resistance and strength by Natlas
certified laboratories.
Produced to quality management ISO 9001:2000.
COLOUR RANGE
Polyroof is supplied in a range of five standard BS.4800
colours to blend with natural stone, brick, slate, wood etc.
Non-standard colours are available on request.
P R O D U C T D A T A
Dark Grey
Dark Battleship Grey
Light Battleship Grey
Lead Green
Havana Brown
For technical reasons connected with the colour printing process
these colours may not precisely match the topcoat colour.
F O R S P E C I F I C AT I O N A D V I C E
C A L L T H E T E C H N I C A L H E L P L I N E O N
0 8 0 0 8 0 1 8 9 0
Contents Section Start Next Section Page �� Page
SUITABLE SUBSTRATES
Polyroof 185 is always applied to a quality Polyroof approved
plywood such as Finnforest II/III, in accordance with BS 5268
Part 2. Roof design to which the Polyroof system is to be
applied, should be in accordance with the relevant regulations,
codes and good practice existing at the time of construction.
For a list of Polyroof approved plywood, please contact Polyroof
Technical Services.
PREPARATION
Refurbishment
Strip to a sound structure of good order to take a positive
mechanical fixing i.e. to the joist, concrete, or metal deck.
Covering existing felt and chipboard decking must be avoided.
New Build
The deck should be a solid structure to which a positive
mechanical fixing can be made.
■ Timber satisfying the relevant British Standards preservativetreatment requirements.
■ Metal decking complying with the Metal Deck AssociationDesign Code.
■ Concrete in-situ or pre-cast.
FIXINGS
Substrate should be mechanically fixed to a sound substrateusing appropriate timber, masonry or metal deck fixings. Fixingheads should be countersunk into the decking to avoidunsightly finish. Advice and pull-out tests can be arranged bythe Polyroof Technical Services Dept.
FALLS
Minimum fall recommended by the relevant British StandardCode of Practice is 1:80. However, a design fall of 1:40 is oftenadopted to provide a construction tolerance. In refurbishment,falls may be increased by the use of firrings or cut-to-fall insulation.
DRAINAGE
Advice on roof drainage is given in Code of Practice BS.6367.The majority of standard rainwater outlets can be incorporatedinto Polyroof installations and care should be taken to ensurethat they are always recessed into the plywood substrate.
PENETRATIONS
The system can be moulded tosuit penetrations such as soilpipes, stanchions or machineryfixing positions.
EXPANSION AND CONTRACTION
Polyroof 185 laid in accordance with specifications will
withstand normal building movement without the need for
special expansion joints on contracts up to 100m2. Expansion
joints may be required on warm roof designs over 100m2 and
the advice of the Polyroof Technical services should be sought.
PRE-CONTRACT APPROVAL
Specifications of roofs over 100m2 must be approved by
Technical Services prior to commencement of works.
WALKWAYS/TRAFFIC
Polyroof is available with non-slip finish with BBA approval,
Certificate No. 91/2604. Polyroof 185 Non-Slip should be
specified for traffic areas and will provide adequate protection
for normal use on verandas, terraces and walkways on flat
roofs, without further covering. The surface finish is anti-slip
but cannot possibly eliminate all risk of slipping, this is
particularly relevant in the event of ice forming on the roof
surface.
BOX AND VALLEY GUTTERS
Polyroof 185 is BBA approved for use in internal gutterapplications under Certificate No. BBA 91/2604. Box and valleygutters and special trims, in strong GRP can be either suppliedpre-formed or constructed on site.Generally pre-formedversions will offer economy on larger, new-build projects, whileon-site construction is used for refurbishment and canaccommodate “lead steps”. Compared to lead, Polyroof iseasily and economically laid, is highly damage resistant and,since it has no resale value, it is not prone to theft.
ABUTMENTS
A minimum girth of a 150mm should be achieved under anycover flashing in accordance with building regulations. Thecover flashing would typically be created using traditional lead.GRP alternatives do exist, but please note the Cover flashing isnot covered under the guarantee. The adhesion of the PolyroofSystem directly to a door or windowsill should not be relied onand a cover flashing or tray should be installed. If this is notpossible, consult Polyroof Technical Services for further advice.
REPRODUCTION LEAD AND COPPER
Polyroof 185 can be used to reproduce the appearance of leadand copper rolls or standing seams. The roll is formed using apreformed fibre glass trim. Various levels of reproductionquality exist and it is recommended that a sample is producedand agreed as the standard to which the reproduction will beproduced before the contract begins.
POLYROOF 185Page 17
■ COLD APPLIED ■ 20 YEAR GUARANTEE ■ SEAMLESS ■ MAINTENANCE-FREE ■ 30 YEAR DURABILITY ■ SUITABLE FOR FREQUENT FOOT TRAFFIC
F O R S P E C I F I C AT I O N A D V I C E C A L L T H E
T E C H N I C A L H E L P L I N E O N 0 8 0 0 8 0 1 8 9 0
D E S I G N C O N S I D E R A T I O N S
Contents Section Start Next Section Page �� Page
F O R S P E C I F I C AT I O N A D V I C E
C A L L T H E T E C H N I C A L H E L P L I N E O N
0 8 0 0 8 0 1 8 9 0
POLYROOF 185Page 18
■ COLD APPLIED ■ 20 YEAR GUARANTEE ■ SEAMLESS ■ MAINTENANCE-FREE ■ 30 YEAR DURABILITY ■ SUITABLE FOR FREQUENT FOOT TRAFFIC
Warm Roofs are the preferred method for
constructing a flat roof, giving the best
thermal performance and vapour control,
whilst maximising flexibility of design by
reducing the need for natural ventilation.
In general, any high risk condensation areas
should have a Warm Roof construction.
General advice for Warm Roof constructions
can be found in BS 5250 : 2002.
Care should be taken to ensure the chosen
insulation can withstand the loads likely to be
applied to the roof, particularly in balcony
and walkway applications. We recommend
when fixing to joist or metal deck, that a
layer of plywood is incorporated prior to
fixing the insulation, to act as a spreadsheet
and avoid point loading.
Standard Calculations based on British
Standard BS.6229, exist for checking the
thermal characteristics and condensation risk
for a roof construction. It is recommended
that whenever a warm roof is specified, and
particularly over a humid environment, that
these calculations are carried out.
The majority of insulation manufacturers such
as Kingspan provide a calculation service and
our own technical department can provide
standard calculations, if supplied with full
construction and environmental details.
W A R M R O O F D E S I G N S
TIMBER DECK
CONCRETE DECK
METAL DECK
1 Polyroof pre-formed edge detail
2 Polyroof 185 membrane
3 18mm Polyroof approved plywood such as Finnforest Spruce l l / l l l
4 Kingspan Thermaroof TR26 Insulation
5 1000 Gauge visqueen vapour barrier
6 12mm shuttering grade plywood
7 Structure (Joist/Concrete/Metal Deck)
1
The examples above show typical warm roof constructions
2 3 4 5 6 7
1 2 3 4 5 6 7
1 2 3 4 5 7
Contents Section Start Next Section Page �� Page
F O R S P E C I F I C AT I O N A D V I C E
C A L L T H E T E C H N I C A L H E L P L I N E O N
0 8 0 0 8 0 1 8 9 0
POLYROOF 185Page 19
■ COLD APPLIED ■ 20 YEAR GUARANTEE ■ SEAMLESS ■ MAINTENANCE-FREE ■ 30 YEAR DURABILITY ■ SUITABLE FOR FREQUENT FOOT TRAFFIC
T Y P I C A L W A R M R O O F (Based on Timber Construction)
T Y P I C A L N B S S P E C I F I C A T I O N F O R T I M B E R J O I S T S
GENERAL:
Application can only be carried out by Polyroof Products Ltd trained and
approved applicators. Consult Polyroof Products Ltd for details. Polyroof
Products can also provide a design and specification advisory service and
it is recommended that they are consulted early in the design process.
BASE (support layer for warm roof construction):
12mm Sheathing Plywood laid on timber joists and S.W. Firrings (min 1 :
80 fall), at 400mm C/S. Lay boards staggered with long edges 90º to
joists, with 3mm gaps between boards and 20mm at wall abutments.
End Joints to be centred over joists. Ensure fixings do not protrude above
surface of board. Fixings to be of a type recommended for the purpose
by the manufacturer. Minimum fixings per board 24Nr.
VAPOUR CONTROL LAYER:
1000 Gauge Visqueen, Monarflex Monofilament 250VB or similar. Lay sheets
loose, flat and without wrinkles. Seal Joints using materials and method
recommended by the sheet manufacturer. Dress sheets up all upstands,
kerbs and other penetrations around the edge of the insulation and lap over.
INSULATION:
Kingspan Thermaroof TR26FM zero ODP, approved by factory mutual
research USA, comprising a CFC/HCFC -free rigid urethane insulation core
with bonded low emissivity composite foil facings on both sides
manufactured to BS EN ISO 9002 : 1994 / IS EN 9001 : 2000 by Kingspan
Insulations Limited and shall be applied in accordance with the instructions
issued by them.
BASE (substrate for coating):
18mm Polyroof approved plywood such as Finnforest Spruce l l / l l l .
Lay boards staggered with long edges 90º to joists, with 3mm gaps
between boards and 20mm at wall abutments. End Joints to be centred
over joists. Ensure fixings do not protrude above surface of board. Fixings
to be SFS STADLER IR2-C range or similar. Minimum fixings per board 24Nr.
PREPARATION:
■ Plywood decking to be dry, sound and free from loose material
or contamination.
■ Tape joints to plywood decking with 75mm Polyroof glass fibre tape.
■ Fix in place all roof trims.
■ Consult with Polyroof Products to receive a site inspection report
and for recommendations and details.
WATERPROOF COATING:
Polyester based system with glass fibre reinforcement.
MANUFACTURER:
Polyroof Products Ltd. Furness House,
Castle Park Industrial Estate, Flint, Flintshire CH6 5XA
Tel: 01352 735 135
Fax: 01352 735 182
Email: [email protected]
Web: www.polyroof.co.uk
MEMBRANE SYSTEM REFERENCE:
Polyroof 185 System.
APPLICATION:
1 coat comprising Flexi-Resin 185B applied at a rate of 1.2 litres/m2 using a
synthetic lambswool roller, with Polymat glass fibre reinforcement. 1 coat
Flexi-Resin 185C applied at a rate of 0.6 litres/m2 using a synthetic
lambswool roller.
COLOUR:
Dark Grey / Dark Battleship Grey / Light Battleship Grey / Lead Green /
Havana Brown. Consult with Polyroof Products Ltd for the availability of
alternative colours and to obtain samples.
REINFORCEMENT:
Polymat glass fibre matting.
MINIMUM DRY FILM THICKNESS:
2mm.
SURFACE PROTECTION:
For Anti slip finish, add grit at rate of 250 g/litre to Flexi-Resin 185C topcoat
mix. Polyroof 185 is BBA Approved as a balcony / walkway surface.
ACCESSORIES :
Polyroof GRP Trims.
Note: This is a typical application. For more specific details visit our website or contact our Technical Helpline.
Contents Section Start Next Section Page �� Page
F O R S P E C I F I C AT I O N A D V I C E
C A L L T H E T E C H N I C A L H E L P L I N E O N
0 8 0 0 8 0 1 8 9 0
POLYROOF 185Page 20
■ COLD APPLIED ■ 20 YEAR GUARANTEE ■ SEAMLESS ■ MAINTENANCE-FREE ■ 30 YEAR DURABILITY ■ SUITABLE FOR FREQUENT FOOT TRAFFIC
Cold Roofs are the traditional method for
constructing a flat roof. They rely on ventilation
to the roof space to reduce condensation.
The thermal performance achievable is also
restricted, based on the size of the roof
members. This type of construction is generally
adequate for low risk condensation areas only.
General advice for Cold Roof constructions
can be found in BS 5250 : 2002.
There are a number of instances where cold
roof designs are commonly used. For example
in refurbishment projects if constraints such
as existing window heights do not permit
conversion to a warm roof: or in new build
situations where adequate insulation and
ventilation can be achieved, such as a
mansard roof, insulated at ceiling level.
A minimum of 50mm ventilation space is
required between the insulation and the
underside of the roof deck. As a minimum
this should be ventilated at both ends of the
roof structure. It is recommended that advice
is sought from a specialist manufacturer to
ensure adequate ventilation is achieved to
required standards to comply with building
regulations approved document F2 and
BS 5250 : 2002.
C O L D R O O F D E S I G N S
TIMBER DECK
1 Polyroof pre-formed edge detail
2 Polyroof 185 membrane
3 18mm Polyroof approved plywood such as Finnforest Spruce l l / l l l
4 Existing joist/firrings
5 Rockwool insulation or similar
6 Plaster board ceiling or similar
Installation at flat roof abutment
Installation at flat roof edge
2 3 4 5 61
Contents Section Start Next Section Page �� Page
F O R S P E C I F I C AT I O N A D V I C E
C A L L T H E T E C H N I C A L H E L P L I N E O N
0 8 0 0 8 0 1 8 9 0
POLYROOF 185Page 21
■ COLD APPLIED ■ 20 YEAR GUARANTEE ■ SEAMLESS ■ MAINTENANCE-FREE ■ 30 YEAR DURABILITY ■ SUITABLE FOR FREQUENT FOOT TRAFFIC
T Y P I C A L C O L D R O O F (Based on Timber Construction)
T Y P I C A L N B S S P E C I F I C A T I O N F O R T I M B E R J O I S T S
GENERAL:
Application can only be carried out by Polyroof Products Ltd trained and
approved applicators. Consult with Polyroof Products Ltd for details.
Consult Polyroof Products technical literature for details. Polyroof Products
can also provide a design and specification advisory service and it is
recommended that they are consulted early in the design process.
INSULATION:
Rockwool or similar insulation. Thickness dependant on material specified
and size of roof members. All insulation to comply with building
regulations Part L (England and Wales) and Part J (Scotland).
VENTILATION:
Glidevale FV250 ventilator at wall abutments and perimeter drip details to
provide continuous ventilation through joisted structure.
BASE (substrate for coating):
18mm Polyroof approved plywood such as Finnforest Spruce l l / l l l .
Lay boards staggered with long edges 90º to joists, with 3mm gaps
between boards and 20mm at wall abutments. End Joints to be centred
over joists. Ensure fixings do not protrude above surface of board. Fixings
to be Annular Ringshank Nails 75mm. Minimum fixings per board 24Nr.
PREPARATION:
■ Plywood decking to be dry, sound and free from loose material
or contamination.
■ Tape joints to plywood decking with 75mm Polyroof glass fibre tape.
■ Fix in place all roof trims.
■ Consult with Polyroof Products to receive a site
inspection report and for recommendations and details.
WATERPROOF COATING:
Polyester based system with glass fibre reinforcement.
MANUFACTURER:
Polyroof Products Ltd. Furness House,
Castle Park Industrial Estate, Flint,
Flintshire CH6 5XA
Tel: 01352 735135
Fax: 01352 735 182
Email: [email protected]
Web: www.polyroof.co.uk
MEMBRANE SYSTEM REFERENCE:
Polyroof 185 System.
APPLICATION:
1 coat comprising Flexi-Resin 185B applied at a rate of 1.2 litres/m2 using
a synthetic lambswool roller, with Polymat glass fibre reinforcement.
1 coat Flexi-Resin 185C applied at a rate of 0.6 litres/m2 using a synthetic
lambswool roller.
COLOUR:
Dark Grey / Dark Battleship Grey / Light Battleship Grey / Lead Green /
Havana Brown. Consult with Polyroof Products Ltd for the availability of
alternative colours and to obtain samples.
REINFORCEMENT:
Polymat glass fibre matting.
MINIMUM DRY FILM THICKNESS:
2mm.
SURFACE PROTECTION:
For anti slip finish, add grit at a rate of 250 g/litre to Flexi-Resin 185C
topcoat mix. Polyroof 185 is BBA approved as a balcony / walkway surface.
ACCESSORIES:
Polyroof GRP Trims.
Note: This is a typical application. For more specific details visit our website or contact our Technical Helpline.
Contents Section Start Next Section Page �� Page
F O R S P E C I F I C AT I O N A D V I C E C A L L T H E T E C H N I C A L H E L P L I N E O N 0 8 0 0 8 0 1 8 9 0
POLYROOF 185Page 22
■ COLD APPLIED ■ 20 YEAR GUARANTEE ■ SEAMLESS ■ MAINTENANCE-FREE ■ 30 YEAR DURABILITY ■ SUITABLE FOR FREQUENT FOOT TRAFFIC
P R E - F O R M E D C O M P O N E N T S
The polyroof range of rigid GRP trims offers a fast, reliable way of
installing finishing trims and ensuring perfect detailing.
A wide range of non standard profiles exists. Consult Polyroof with
your specific requirements.
Polyroof pre-formed GRP Trims have a nominal thickness of 2.15mm
and are supplied in 2.44m lengths. NB. Drawings are not to scale.
Thickness (mm) Dial gauge 2.15
Apparent density (kgm-3 ) ISO 1183 1360
Glass/resin ratio BS.2782: 1 : 4Part 10 : 1002
Barcol hardness BS.2782: 9 - 18Part 10 : 1001
Cross-breaking strength (MPa) BS.2782:unaged Part 10 : 1005 135heat aged (1) (test speed
0-5mm min-1) 173UV aged (2) 138
Tensile strength (Nmm-2) BS.2782unaged Part 10 : 1003 72.8heat aged (1) (test speed
2mm min-1) 53.5UV aged (2) 53.0water soak(3) 59.5
Water vapour permeability BS.3177 0.83(gm-2d-1)
Water vapour resistance BS.3177 247(MNsg-1)
Dimensional stability (%) MOAT 27: 5.1.6longitudinal direction -0.08transverse direction -0.88
(1) Heat aged 100 days at 80ºC
(2) UV aged 1500 light hours using UQUV 313 lamps and a cycle of 4 hour light at 50ºC and 4 hours condensation at 50ºC
(3) Water soak 60 days at 60ºC
TEST UNITS METHOD MEANRESULT
S E R V I C E P E R F O R M A N C E
TEST UNITS METHOD MEANRESULT
Resistance to water pressure MOAT 27: 5.1.4 pass(6 metre head)
Static indentation MOAT 27: 5.1.9 L 4
Dynamic impact MOAT 27: 5.1.10 I 4
Fatigue cycling MOAT 27: 5.1.8unaged passheat aged (1) pass
Tensile strength (MPa) BS.5241unaged 0.254(3)
heat aged (2) 0.202
(1) Heat aged 28 days in an oven at 80± 2ºC
(2) Heat aged 56 days in an oven at 80± 2ºC
(3) All failures within the plywood
TEST ON POLYROOF 185 Non-s l ip
TEST UNITS METHOD MEANRESULT
Apparent density (kgm-2) ISO 1183 1541
Barcol hardness BS.2782:Part 10 : 1001 25-35
Tensile strength (Nmm-2) BS.2782unaged 66.3UV aged (1) 71.1
(1) UV aged 1000 light hours using QUV 313 lamps and a cycle of 4 hours light at 45ºC and 4 hours condensation at 40ºC
110mm
Butt strap required
Available in lengths:100mm125mm175mm
Butt strap required
Available in lengths:75mm100mm150mm
UPSTAND FASCIA TRIMS
Butt strap not required
Available in lengths:150mm250mm350mm400mm
Butt strap not required
Available in 300mm lengths:
Butt strap required
Available with internal angles:126º145º155ºNB. 155º has external length of 300mm.
Alternative detail available for exposed areas.
FILLET TRIM
100mm
DRIP TRIMS
FLAT TRIMS
75mm
MANSARD TRIMS
100mm
126º
300mm
250mm
P H Y S I C A L P R O P E R T I E S
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 23
■ COLD APPLIED ■ 20 YEAR GUARANTEE ■ SEAMLESS ■ MAINTENANCE-FREE ■ 30 YEAR DURABILITY ■ SUITABLE FOR FREQUENT FOOT TRAFFIC
ABUTMENT DETAIL DRIP DETAIL
FIXING STANCHIONS
1. Pre-formed trim2. Plywood deck3. Polyroof basecoat4. Polyroof topcoat5. Cover flashing
Note: It should benoted that flashingdetails are notcovered by thePolyroof guarantee.
1. Drip detail2. Plywood deck3. Polyroof basecoat4. Polyroof topcoat5. Polyroof butt strap6. Guttering
PIPE DETAILROOF-LIGHT UPSTAND
MANSARD DETAIL
D E S I G N D E T A I L I N G
BOX GUTTER DETAIL7. Tile and felt8. Polyroof laid to
plywood kickboard or flat trim (300mm) mechanically fixed
9. Fillet trim
Note: It may be possible to create the detail using special ornon-standard trim profiles. This may prove to be moreeconomic, but will depend on the size and shape of the gutter.
1. Pre-formed trim2. Plywood deck
(mechanically fixed)3. Polyroof basecoat4. Polyroof topcoat5. Right angle trim
(lip removed from trim)6. Re-inforced with extra
layer of base and mat
1
2
3
4
56
1
23
4
5
1
23
41
23
4
5
6
5
12
3
3
4
5
1. Pre-formed drip trim
2. Plywood deck3. Polyroof basecoat4. Polyroof topcoat5. Lead ‘mansard
flashing’ detail6. Timber support
battens
1. Stanchion mechanically fixed to hardwood block
2. Hardwood block3. Polyroof basecoat4. Polyroof basecoat
to completely encapsulate hardwood block creating a double seal
5. Polyroof topcoat
Note: A popular alternativeinvolves the use of a socketinto which the stanchionupstand fits. The socket canbe completely enclosedwithin the Polyroof system.
1
2
3
45
1. Pre-formed trim2. Plywood deck3. Polyroof basecoat4. Polyroof topcoat5. Roof-light upstand
Note: It is preferable touse proprietary roof lightsincorporating a GRPupstand whereverpossible. GRP upstand tobe abraded prior tolaminating direct.
1. Polymat (Re-inforced usingtwo layers)
2. Plywood deck3. Polyroof basecoat4. Polyroof topcoat5. Weathering
flange/seal
Note: A flashing detailshould be created with aweathering flange/seal.
15
2
3
6
8
99
7
4
Contents Section Start Next Section Page �� Page
Nothing in this specification brochure or any other marketing literature produced by or on behalf of Polyroof Products Limitedis to be regarded as constituting a contract binding in law between Polyroof Products Limited and any customer.
The only contract which Polyroof will enter into with the customer is that contained in the Guarantees, the details of whichare available on request. This Guarantee is in the form of a written guarantee which takes effect only when issued in writingby Polyroof to the customer at the request of the Contractor.
A NATIONWIDE NETWORK OF COMPANY TRAINED TECHNICIANSPolyroof is only supplied to and installed by contractors fully application trained and licensed by the company, to ensure consistent quality of installation. Contractors’ performance is regularly monitored and random inspection of installations carried out. Failure to comply with the Company’s stringent standards leads to withdrawal of certification.
QUALITY CONTROLPolyroof Products Ltd operates comprehensive and rigorous quality control procedures in accordance with ISO 9001:2000. The scope of this approval includes the design and installation of roofing systems, the provision of technical support, as well as the appointment and monitoring of installers.Not only is the manufacture of Polyroof liquid applied roofing systems and accessories quality approved, but so too is the procurement, storage and supply of all related materials and consumables.
20 YEAR INDEPENDENTLY BACKED GUARANTEEThe Polyroof 20-year Guarantee is supported by an insured and independently administered Trust Fund. For your total security and peace of mind Polyroof Products Limited will indemnify any customer against their liability in respect of the cost of labour and materials incurred in rectifying degeneration of glass fibre roof materials supplied by the Company and installed in accordance with their instructions by an approved contractor.An Independent Trust administers the Guarantee and therefore protection will continue irrespective of the existence of Polyroof Products Limited. The Trustees have arranged an annually renewable insurance to augment this valuable protection with leading UK insurers.
POLYROOF 185Page 24
POLYROOF 185
POLYROOF PRODUCTS LTD
FURNESS HOUSE
CASTLE PARK INDUSTRIAL ESTATE
FL INT FL INTSHIRE
CH6 5XA
Tel : 01352 735 135
Fax: 01352 735 182
Emai l : technica l@polyroof .co.uk
www.polyroof .co.uk
FREEPHONEH E L P L I N E
0800 801 890
E S T. 1984
THE NATIONAL FEDERATION OFROOFING CONTRACTORS LIMITED
Associate Member
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 25
Please note that this is an outline proposal only and will be subject tofurther site investigation by Polyroof Products Ltd Technical Department
Standard Warm RoofTimber Joists
GUIDELINE SPECIFICATION
1.1 Overview
1.2 Structural Preparation
Falls and Drainage
New Construction
Plywood and Fixing Schedule
1.3 Polyroof 185 Trims
1.4 Polyroof 185 Membrane
Taping
Base Coat
Top Coat
1.5 General
Thermal Performance
Guarantee Details
Other Notes
1.6 Appendices
Appendix A Polyroof 185 Features & Benefits
Appendix B Polyroof 185 General Material Requirements
Appendix C Polyroof 185 Material Requirements
Appendix D Expansion Trim Guidelines
Appendix E Approved Plywood List
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 26
1.1 Overview
Proposed Construction
1. Polyroof 185 membrane
2. 18mm Finnforest Spruce II/III plywood
3. 110mm Kingspan Thermaroof TR26 insulation
4. 1000 gauge visqueen vapour barrier
5. 12mm shuttering ply
6. Timber firrings to create a minimum 1 in 80 design fall
7. Timber joists at 400mm centres
8. Pre-formed Polyroof edge details
9. Tanilised timber support batten
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 27
1.2 Structural Preparation
Falls & Drainage
This proposal provides for a minimum recommended 1 in 80 design fall. You
may wish to note that standing water is not detrimental to the Polyroof 185
system. Please note however that additional consideration should be given to
the falls on walkways as standing water could be hazardous to foot traffic in
icy conditions. It has been assumed that the current/proposed drainage
capacity is adequate.
New Construction
Timber firrings are to be mechanically fixed to the timber joists to create a
minimum recommended 1 in 80 design fall.
A 12mm plywood spreadsheet is to be mechanically fixed to the timber joists
and a 1000 gauge visqueen vapour barrier laid.
110mm Kingspan Thermaroof TR26 insulation and 18mm Finnforest Spruce
II/III plywood decking, are then to be mechanically fixed to the timber joists,
creating a warm deck.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 28
Plywood / Fixing Schedule
A 12mm Shuttering Plywood to Timber Joists
Fixing Type Annular Ringshank Nails
Min Penetration into Timber Joists 45mm
Minimum Fixings per Board 24 Nr
B 18mm Finnforest II/III Plywood to Timber Joists
Fixing Type SFS Intec IR2-C Range
Min Penetration into Timber Joists 35mm
Minimum Fixings per Board 24 Nr
Lay Boards staggered (brick pattern) with long edges 90° to joists, with 3mm
gaps between boards and 20mm at wall abutments. End joints to be centred
over joists. Boards should be fixed at each corner and at a maximum of
400mm (16”) centres with a minimum of 24 fixings per 2400mm x 1200mm
(8’ x 4’) sheet. Fixing heads must always be countersunk into the decking.
For roof areas in excess of 100m2 or for any continuous run exceeding 15lm
further advice should be sought from Polyroof Products with regards
Expansion Trim Positions. At Expansion Trim positions a 20mm allowance in
plywood board joint must be made.
Where required, provide temporary covers as required to keep plywood
deck dry.
1.3 Polyroof 185 Trims (Pre-Formed)
Pre-formed Trims
Polyroof pre-formed GRP trims are to be mechanically fixed to the plywood
deck to form edge detailing. Trims to be fitted with butt straps (where relevant).
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 29
1.4 Polyroof 185 Membrane (In-Situ)
Taping
Plywood Boards and GRP Trim Butt Joints are to be taped with 75mm wide
Polymat and Polyroof 185B Flexi-Resin.
Base Coat
Polyroof 185B Flexi-Resin and Polymat is then to be cold applied to the roof
area.
Top Coat
Polyroof 185C Flexi-resin is then to be cold applied in desired colour to the
whole roof including faces of all trims.
1.5 General
Thermal Performance
Approximate U value achieved by construction 0.20 W/m2K.
NB: This specification is for a new ‘Warm Roof construction’.
The above U-Value is for consideration by the architect. It is the architect’s
responsibility to confirm the required U-value based on performance
requirements and current building regulations standards.
Guarantee Details
20 Year Insurance Backed Guarantee.
30 Year BBA Durability Statement.
Other Notes
Please refer to Appendices for further information and general material
requirements.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 30
1.6 Appendices
Appendix A - Polyroof 185 Features & Benefits
Further to discussions regarding the Polyroof specification requirements, our
recommendation to utilise the Polyroof 185 System is supported by the following:
• A twenty year guarantee supported by Lloyd's of London insurance through
an independent trust fund is provided on completion of the project.
• The Polyroof 185 and Anti-Slip systems have been fully tested and approved
by the British Board of Agrement (Cert. No BBA 91/2604). The BBA can
confirm that Polyroof 185 constructed in accordance with the installation
guide and formed in satisfactory conditions can be expected to maintain its
integrity and show no measurable loss of physical properties for a period of
30 years.
• The ability to provide a waterproof structure capable of withstanding
regular foot traffic is unique to this system and avoids the hazards
associated with foot traffic which occurs up and down valley gutters.
BBA 91/2604 C1.9.2
• To achieve a totally waterproof solution it is possible to lay Polyroof along a
flat roof into a gutter, up underneath slates or encapsulate parapet walls in
one durable, completely seamless membrane.
• Polyroof flexi-resin system will provide a high degree of flexibility to accommodate
structural expansion/contraction without the requirement of special expansion
joints. BBA 91/2604 T.3
• The Polyroof 185 System is a maintenance free solution.
• The Polyroof 185 System is available in a variety of 5 standard colours, enabling
it to blend into local environments.
• The Polyroof 185 System is cold-applied and achieves F.A.A. external fire
certification.
• All Polyroof contractors are trained and approved to a CITB registered scheme
and their performance is monitored thereafter.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 31
Appendix B - Polyroof 185 General Material Requirements
Insulation
Boards should be laid staggered and should comply with the specification of
the manufacturer.
Vapour Barrier
Shall be continuous and encapsulate the insulation boards at abutments,
penetrations and at exposed edges.
Support
Timber supports should be fixed at all roof edges using proprietary fixings
applicable to the construction and environmental conditions.
Fixings
Should be capable of withstanding necessary wind uplift and environmental
conditions. Fixings should finish flush with the surface of the plywood and
should not be over fixed.
Hydro - Thermal Calculations
The roofing contractor is responsible to provide Hydrothermal calculations in
respect of insulation values and condensation/dew points of the roof coverings
and deposit a copy of the calculations with the architect on completion of the
contract. Calculations are available through Polyroof Products Ltd.
Note
Care should be taken to ensure accessories such as skylights and vents are
compatible with the Polyroof 185 System and adhesion will be sufficient.
Although good adhesion can be obtained on the majority of surfaces by simply
abrading the surface a mechanical joint under a collar or lip should be created.
If detailing to accessories is not covered in the Polyroof Manual advice should
be sought in writing from the Polyroof Technical department.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 32
Appendix C - Polyroof 185 Material Requirements
Approved Contractors
Polyroof 185 should only be applied by contractors in possession of a current
approval certificate. Confirmation of approval can be sought by calling
Polyroof Products Ltd Technical Services on 01352 735135. A final inspection
shall be carried out by a Polyroof technician prior to a guarantee being issued.
Approved Applicators
The contractor must provide an approved applicator to supervise the Polyroof
185 work and the approved applicator must remain on the site until the works
are complete. The contractor must obtain the consent of the client before
changing the approved applicator.
Immediate Plywood Decking
Plywood decking to be Finnforest Spruce II/III grade. Permission should be
sought from Polyroof Products Ltd before any variation is made to this
specification. Boards should be laid staggered and have a 3mm expansion gap
between all joints and a 15mm gap at abutments.
Preparation
All joints in the plywood should be reinforced with a 75mm wide strip of
Polyroof glassfibre tape. Any angles or details formed without pre-formed
trims should be double taped.
Pre-formed Trims
Shall be fixed to the plywood at 150mm maximum centres using treated clout
nails. All angles shall be mitred and all jobs reinforced with butt straps where
applicable and reinforced with a 75mm Polyroof tape.
Application
The Polyroof 185 Waterproof system consists of glassfibre reinforced polyester
resin, cold applied on site by hand lay and processed to a minimum thickness
of 1.5mm giving a seamless, joint-free construction. The System should be
applied in accordance with the Polyroof Application Manual issued August
1996 and the British Board of Agrement Certificate 91/2604.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 33
Appendix C - Polyroof 185 Material Requirements Continued
Note, The system should not be applied if the air or surface temperature is
outside the range of 5degC - 30degC; in damp or cold conditions which could
cause surface condensation; during frost or if there is a risk of rain.
Anti-Slip Grit
If anti-slip is specified it should be mixed into the top-coat and applied in
accordance with the Polyroof Application Manual issued August 1996. It
should be noted that this surface finish is anti-slip and cannot possibly
eliminate all risk of slipping.
Collars
Collars are to be formed at all protrusions.
Hoppers/Outlets
The Polyroof system should be dressed sufficiently into all outlets of this nature.
Box/Valley gutters
Box and valley gutters should be formed whenever possible with a Finnforest
II/III plywood base. Any right angles joints should be removed using timber
fillets or preferably pre-formed Polyroof trims.
Note
It is important that the full application of base and top coat is completed
within each working day. However in certain circumstances this is not possible
due to a sudden change in weather conditions. In such cases the correct Polyroof
application procedure of vacuum drying and solvent wiping must be followed
to re-juvenate the base coat prior to application of the top coat.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 34
Appendix D - Expansion Trim Guidelines
GUIDELINES FOR THE FITTING OF EXPANSION TRIMS
• A 20mm gap is to be left between the plywood board joints at the position
of the expansion trim.
• Expansion trims to be overlapped, NOT butted, by a minimum of 50mm.
• All overlaps to be double taped using normal Polyroof chopped strand matting
with Poly Patch.
• The curved section of the Expansion trim (the whole flat area in the case of
flat expansion trims) should be coated using Poly Patch resin only. Under no
circumstances must normal Polyroof Topcoat be used as cosmetic hairline
cracks will appear.
• Masking tape should be used to ensure that a clean line is created between
the Polyroof 185 finish and the Poly Patch resin.
Extra Note:
All decking must be staggered in at least one direction on all contracts over
50m2.
Apply Polypatch following same procedure as that used for applying Polyroof
Base coat. Catalyst addition is per Polyroof Base resin, scale coverage 10 litres
per 6m2.
GUIDELINES FOR WHERE EXPANSION TRIM MEETS EDGE DETAILS
• The expansion trim must be taken to the very edge of the roof. At this point
the standard Polyroof trim i.e. upstand, drip, fillet, mansard trim etc should
be jointed with a 10mm gap left.
• The trim is then to be double taped using Poly Patch resin and normal
chopped strand matting. Care should be taken to avoid any untidy overlaps
between the two systems.
• Expansion trims to be chamfered appropriately against mansard and fillet
details. Should you require clarification on any of the above points please
contact the Technical Department on 0800 801 890.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 35
Appendix E - Approved Plywood List
Name Grade 3rd Party CPD Compliance CommentsControl
Finnforest II/III Fin ply / BBA CE Marked Strong, lightweight, rarely warps.
Spruce Structural 2+ Will have very small knot holes on
good face but acceptable for Polyroof.
Wisa II/III BBA CE Marked Strong, lightweight, rarely warps.
Spruce Structural 2+ Will have very small knot holes on
good face but acceptable for Polyroof.
Southern BCX American CE Marked Good quality veneer with few
Yellow Plywood Structural 2+ knotholes. Susceptible to slight
Pine Association deflection / warping during storage.
(SYP) Currently expensive.
Canadian Select Canply CE Marked Strong, lightweight, rarely warps.
Softwood Tight Structural 2+ Will have small knotholes on good
(CSP) Faced face but acceptable for Polyroof.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 36
Please note that this is an outline proposal only and will be subject tofurther site investigation by Polyroof Products Ltd Technical Department
1.1 Overview
1.2 Structural Preparation
Falls and Drainage
New Construction
Plywood and Fixing Schedule
1.3 Polyroof 185 Trims
1.4 Polyroof 185 Membrane (In-Situ)
Taping
Base Coat
Top Coat
1.5 General
Thermal Performance
Guarantee Details
Other Notes
1.6 Appendices
Appendix A Polyroof 185 Features & Benefits
Appendix B Polyroof 185 General Material Requirements
Appendix C Polyroof 185 Material Requirements
Appendix D Expansion Trim Guidelines
Appendix E Approved Plywood List
Contents Section Start Next Section Page �� Page
Balcony Warm RoofTimber Joists
GUIDELINE SPECIFICATION
POLYROOF 185Page 37
1.1 Overview
Proposed Construction
1. Polyroof 185 (Anti-Slip) membrane
2. 18mm Finnforest Spruce II/III plywood
3. 50mm Kingspan TR26 between battens at 400mm centres
4. 75mm Kingspan TR26 between battens at 400mm centres
5. 1000 gauge visqueen vapour barrier
6. 12mm shuttering ply
7. Timber firrings to create a minimum 1 in 80 design fall
8. Timber joists at 400mm centres
9. Pre-formed Polyroof edge details
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 38
1.2 Structural Preparation
Falls & Drainage
This proposal provides for a minimum recommended 1 in 80 design fall. You
may wish to note that standing water is not detrimental to the Polyroof 185
system. Please note however that additional consideration should be given to
the falls on walkways as standing water could be hazardous to foot traffic in
icy conditions. It has been assumed that the current/proposed drainage
capacity is adequate.
New Construction
Timber firrings are to be mechanically fixed to the timber joists to create a
minimum recommended 1 in 80 design fall.
A 12mm plywood spreadsheet is to be mechanically fixed to the joists and a
1000 gauge visqueen vapour barrier laid.
75mm x 50mm timber battens are then to be mechanically fixed perpendicular
to the timber joists and at 400mm centres, with 75mm Kingspan Thermaroof
TR26 insulation laid in between.
A layer of 50mm x 50mm timber battens are then to be mechanically fixed to
the first layer of timber battens and at 400mm centres, with 50mm Kingspan
Thermaroof TR26 insulation laid in between.
18mm Finnforest Spruce II/III plywood decking is then to be mechanically fixed
to the timber battens, creating a warm deck.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 39
Plywood / Fixing Schedule
A Timber Battens to Timber Joists & Timber Battens to Timber Battens
Fixing Type SFS Intec IR2-C Range
Min Penetration into Joists/Battens 35mm
Minimum Fixings per Board 24 Nr
B 18mm Finnforest Spruce II/III Plywood to Timber Battens
Fixing Type Annular Ringshank Nails
Min Penetration into Battens 45mm
Minimum Fixings per Board 24 Nr
Lay Boards staggered (brick pattern) with long edges 900 to joists, with 3mm
gaps between boards and 20mm at wall abutments. End joints to be centred
over joists. Boards should be fixed at each corner and at a maximum of
400mm (16”) centres with a minimum of 24 fixings per 2400mm x 1200mm
(8’ x 4’) sheet. Fixing heads must always be countersunk into the decking.
For roof areas in excess of 100m2 or for any continuous run exceeding 15lm
further advice should be sought from Polyroof Products with regards
Expansion Trim Positions. At Expansion Trim positions a 20mm allowance in
plywood board joint must be made.
Where required, provide temporary covers as required to keep plywood deck dry.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 40
1.3 Polyroof 185 Trims (Pre-Formed)
Pre-formed Trims
Polyroof pre-formed GRP trims are to be mechanically fixed to the plywood
deck to form edge detailing. Trims to be fitted with butt straps (where
relevant).
1.4 Polyroof 185 Membrane (In-Situ)
Taping
Plywood Boards and GRP Trim Butt Joints are to be taped with 75mm wide
Polymat and Polyroof 185B Flexi-Resin.
Base Coat
Polyroof 185B Flexi-Resin and Polymat is then to be cold applied to the roof
area.
Top Coat
Polyroof 185C Flexi-resin (Anti-Slip Version) is then to be cold applied in
desired colour to the whole roof including faces of all trims.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 41
1.5 General
Thermal Performance
Approximate U value achieved by construction 0.25 W/m2K.
NB: This specification is for a new ‘Warm Roof construction’.
The above U-Value is for consideration by the architect. It is the architect’s
responsibility to confirm the required U-value based on performance requirements
and current building regulations standards.
Guarantee Details
20 Year Insurance Backed Guarantee.
30 Year BBA Durability Statement.
Other Notes
Please refer to Appendices for further information and general material
requirements.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 42
1.6 Appendices
Appendix A - Polyroof 185 Features & Benefits
Further to discussions regarding the Polyroof specification requirements, our
recommendation to utilise the Polyroof 185 System is supported by the
following:
• A twenty year guarantee supported by Lloyd's of London insurance
through an independent trust fund is provided on completion of the
project.
• The Polyroof 185 and Anti-Slip systems have been fully tested and
approved by the British Board of Agrement (Cert. No BBA 91/2604). The
BBA can confirm that Polyroof 185 constructed in accordance with the
installation guide and formed in satisfactory conditions can be expected
to maintain its integrity and show no measurable loss of physical
properties for a period of 30 years.
• The ability to provide a waterproof structure capable of withstanding
regular foot traffic is unique to this system and avoids the hazards
associated with foot traffic which occurs up and down valley gutters.
BBA 91/2604 C1.9.2
• To achieve a totally waterproof solution it is possible to lay Polyroof along
a flat roof into a gutter, up underneath slates or encapsulate parapet
walls in one durable, completely seamless membrane.
• Polyroof flexi-resin system will provide a high degree of flexibility to
accommodate structural expansion/contraction without the requirement
of special expansion joints. BBA 91/2604 T.3
• The Polyroof 185 System is a maintenance free solution.
• The Polyroof 185 System is available in a variety of 5 standard colours,
enabling it to blend into local environments.
• The Polyroof 185 System is cold-applied and achieves F.A.A. external fire
certification.
• All Polyroof contractors are trained and approved to a CITB registered
scheme and their performance is monitored thereafter.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 43
Appendix B - Polyroof 185 General Material Requirements
Insulation
Boards should be laid staggered and should comply with the specification of
the manufacturer.
Vapour Barrier
Shall be continuous and encapsulate the insulation boards at abutments,
penetrations and at exposed edges.
Support
Timber supports should be fixed at all roof edges using proprietary fixings
applicable to the construction and environmental conditions.
Fixings
Should be capable of withstanding necessary wind uplift and environmental
conditions. Fixings should finish flush with the surface of the plywood and
should not be over fixed.
Hydro - Thermal Calculations
The roofing contractor is responsible to provide Hydrothermal calculations in
respect of insulation values and condensation/dew points of the roof coverings
and deposit a copy of the calculations with the architect on completion of the
contract. Calculations are available through Polyroof Products Ltd.
Note
Care should be taken to ensure accessories such as skylights and vents are
compatible with the Polyroof 185 System and adhesion will be sufficient.
Although good adhesion can be obtained on the majority of surfaces by simply
abrading the surface a mechanical joint under a collar or lip should be created.
If detailing to accessories is not covered in the Polyroof Manual advice should
be sought in writing from the Polyroof Technical department.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 44
Appendix C - Polyroof 185 Material Requirements
Approved Contractors
Polyroof 185 should only be applied by contractors in possession of a current
approval certificate. Confirmation of approval can be sought by calling
Polyroof Products Ltd Technical Services on 01352 735135. A final inspection
shall be carried out by a Polyroof technician prior to a guarantee being issued.
Approved Applicators
The contractor must provide an approved applicator to supervise the Polyroof
185 work and the approved applicator must remain on the site until the works
are complete. The contractor must obtain the consent of the client before
changing the approved applicator.
Immediate Plywood Decking
Plywood decking to be Finnforest Spruce II/III grade. Permission should be
sought from Polyroof Products Ltd before any variation is made to this
specification. Boards should be laid staggered and have a 3mm expansion gap
between all joints and a 15mm gap at abutments.
Preparation
All joints in the plywood should be reinforced with a 75mm wide strip of Polyroof
glassfibre tape. Any angles or details formed without pre-formed trims should
be double taped.
Pre-formed Trims
Shall be fixed to the plywood at 150mm maximum centres using treated clout
nails. All angles shall be mitred and all jobs reinforced with butt straps where
applicable and reinforced with a 75mm Polyroof tape.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 45
Appendix C - Polyroof 185 Material Requirements Continued
Application
The Polyroof 185 Waterproof system consists of glassfibre reinforced polyester
resin, cold applied on site by hand lay and processed to a minimum thickness
of 1.5mm giving a seamless, joint-free construction. The System should be
applied in accordance with the Polyroof Application Manual issued August
1996 and the British Board of Agrement Certificate 91/2604.
Note, The system should not be applied if the air or surface temperature is
outside the range of 5degC - 30degC; in damp or cold conditions which could
cause surface condensation; during frost or if there is a risk of rain.
Anti-Slip Grit
If anti-slip is specified it should be mixed into the top-coat and applied in
accordance with the Polyroof Application Manual issued August 1996. It
should be noted that this surface finish is anti-slip and cannot possibly
eliminate all risk of slipping.
Collars
Collars are to be formed at all protrusions.
Hoppers/Outlets
The Polyroof system should be dressed sufficiently into all outlets of this nature.
Box/Valley gutters
Box and valley gutters should be formed whenever possible with a Finnforest
II/III plywood base. Any right angles joints should be removed using timber
fillets or preferably pre-formed Polyroof trims.
Note
It is important that the full application of base and top coat is completed
within each working day. However in certain circumstances this is not possible
due to a sudden change in weather conditions. In such cases the correct
Polyroof application procedure of vacuum drying and solvent wiping must be
followed to re-juvenate the base coat prior to application of the top coat.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 46
Appendix D - Expansion Trim Guidelines
GUIDELINES FOR THE FITTING OF EXPANSION TRIMS
• A 20mm gap is to be left between the plywood board joints at the
position of the expansion trim.
• Expansion trims to be overlapped, NOT butted, by a minimum of 50mm.
• All overlaps to be double taped using normal Polyroof chopped strand
matting with Poly Patch.
• The curved section of the Expansion trim (the whole flat area in the case
of flat expansion trims) should be coated using Poly Patch resin only.
Under no circumstances must normal Polyroof Topcoat be used as
cosmetic hairline cracks will appear.
• Masking tape should be used to ensure that a clean line is created
between the Polyroof 185 finish and the Poly Patch resin.
Extra Note:
All decking must be staggered in at least one direction on all contracts over 50m2.
Apply Polypatch following same procedure as that used for applying Polyroof
Base coat. Catalyst addition is per Polyroof Base resin, scale coverage 10 litres
per 6m2.
GUIDELINES FOR WHERE EXPANSION TRIM MEETS EDGE DETAILS
• The expansion trim must be taken to the very edge of the roof. At this
point the standard Polyroof trim i.e. upstand, drip, fillet, mansard trim etc
should be jointed with a 10mm gap left.
• The trim is then to be double taped using Poly Patch resin and normal
chopped strand matting. Care should be taken to avoid any untidy
overlaps between the two systems.
• Expansion trims to be chamfered appropriately against mansard and fillet
details.
Should you require clarification on any of the above points please
contact the Technical Department on 0800 801 890.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 47
Appendix E - Approved Plywood List
Name Grade 3rd Party CPD Compliance CommentsControl
Finnforest II/III Fin ply / BBA CE Marked Strong, lightweight, rarely warps.
Spruce Structural 2+ Will have very small knot holes on
good face but acceptable for Polyroof.
Wisa II/III BBA CE Marked Strong, lightweight, rarely warps.
Spruce Structural 2+ Will have very small knot holes on
good face but acceptable for Polyroof.
Southern BCX American CE Marked Good quality veneer with few
Yellow Plywood Structural 2+ knotholes. Susceptible to slight
Pine Association deflection / warping during storage.
(SYP) Currently expensive.
Canadian Select Canply CE Marked Strong, lightweight, rarely warps.
Softwood Tight Structural 2+ Will have small knotholes on good
(CSP) Faced face but acceptable for Polyroof.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 48
Please note that this is an outline proposal only and will be subject tofurther site investigation by Polyroof Products Ltd Technical Department
1.1 Overview
1.2 Structural Preparation
Falls and Drainage
New Construction
Plywood and Fixing Schedule
1.3 Polyroof 185 Trims (Pre-formed)
1.4 Polyroof 185 Membrane (In-Situ)
Taping
Base Coat
Top Coat
1.5 General
Thermal Performance
Guarantee Details
Other Notes
1.6 Appendices
Appendix A Polyroof 185 Features & Benefits
Appendix B Polyroof 185 General Material Requirements
Appendix C Polyroof 185 Material Requirements
Appendix D Expansion Trim Guidelines
Appendix E Approved Plywood List
Contents Section Start Next Section Page �� Page
Standard Cold RoofTimber Joists
GUIDELINE SPECIFICATION
POLYROOF 185Page 49
1.1 Overview
Proposed Construction
1. Polyroof 185 membrane
2. 18mm Finnforest Spruce II/III Plywood
3. Timber joists/firrings
4. Loosely laid insulation (Rockwool or similar)
5. Plaster board ceiling (or similar)
6. Polyroof pre-formed edge detail
NB: This construction relies on a minimum 50mm
unobstructed void and an adequate cross-flow of ventilation.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 50
1.2 Structural Preparation
Falls & Drainage
This proposal provides for a minimum recommended 1 in 80 design fall. You
may wish to note that standing water is not detrimental to the Polyroof 185
system. Please note however that additional consideration should be given to
the falls on walkways as standing water could be hazardous to foot traffic in
icy conditions.
It has been assumed that the current/proposed drainage capacity is adequate.
New Construction
18mm Finnforest Spruce II/III plywood decking is to be mechanically fixed to
the timber joists.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 51
Plywood / Fixing Schedule
A 18mm Finnforest II/III Plywood to Timber Joists
Fixing Type Annular Ringshank Nails
Min Penetration into Timber Joists 45mm
Minimum Fixings per Board 24 Nr
Lay Boards staggered (brick pattern) with long edges 900 to joists, with 3mm
gaps between boards and 20mm at wall abutments. End joints to be centred
over joists. Boards should be fixed at each corner and at a maximum of
400mm (16”) centres with a minimum of 24 fixings per 2400mm x 1200mm
(8’ x 4’) sheet. Fixing heads must always be countersunk into the decking.
For roof areas in excess of 100m2 or for any continuous run exceeding 15lm
further advice should be sought from Polyroof Products with regards
Expansion Trim Positions. At Expansion Trim positions a 20mm allowance in
plywood board joint must be made.
Where required, provide temporary covers as required to keep plywood
deck dry.
1.3 Polyroof 185 Trims (Pre-Formed)
Pre-formed Trims
Polyroof pre-formed GRP trims are to be mechanically fixed to the plywood
deck to form edge detailing. Trims to be fitted with butt straps (where
relevant).
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 52
1.4 Polyroof 185 Membrane (In-Situ)
Taping
Plywood Boards and GRP Trim Butt Joints are to be taped with 75mm wide
Polymat and Polyroof 185B Flexi-Resin.
Base Coat
Polyroof 185B Flexi-Resin and Polymat is then to be cold applied to the roof area.
Top Coat
Polyroof 185C Flexi-resin is then to be cold applied in desired colour to the
whole roof including faces of all trims.
1.5 General
Thermal Performance
This construction will not alter the existing thermal performance of the roof
and any existing condensation problems will remain. Options for improving the
thermal performance of the roof are available upon request from the Technical
Department.
Guarantee Details
20 Year Insurance Backed Guarantee.
30 Year BBA Durability Statement.
Other Notes
Please refer to Appendices for further information and general material
requirements.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 53
1.6 Appendices
Appendix A - Polyroof 185 Features & Benefits
Further to discussions regarding the Polyroof specification requirements, our
recommendation to utilise the Polyroof 185 System is supported by the
following:
• A twenty year guarantee supported by Lloyd's of London insurance
through an independent trus tfund is provided on completion of the project.
• The Polyroof 185 and Anti-Slip systems have been fully tested and
approved by the British Board of Agrement (Cert. No BBA 91/2604).
The BBA can confirm that Polyroof 185 constructed in accordance with
the installation guide and formed in satisfactory conditions can be
expected to maintain its integrity and show no measurable loss of
physical properties for a period of 30 years.
• The ability to provide a waterproof structure capable of withstanding
regular foot traffic is unique to this system and avoids the hazards
associated with foot traffic which occurs up and down valley gutters.
BBA 91/2604 C1.9.2
• To achieve a totally waterproof solution it is possible to lay Polyroof along
a flat roof into a gutter, up underneath slates or encapsulate parapet
walls in one durable, completely seamless membrane.
• Polyroof flexi-resin system will provide a high degree of flexibility to
accommodate structural expansion/contraction without the requirement
of special expansion joints. BBA 91/2604 T.3
• The Polyroof 185 System is a maintenance free solution.
• The Polyroof 185 System is available in a variety of 5 standard colours,
enabling it to blend into local environments.
• The Polyroof 185 System is cold-applied and achieves F.A.A. external fire
certification.
• All Polyroof contractors are trained and approved to a CITB registered
scheme and their performance is monitored thereafter.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 54
Appendix B - Polyroof 185 General Material Requirements
Insulation
Boards should be laid staggered and should comply with the specification of
the manufacturer.
Vapour Barrier
Shall be continuous and encapsulate the insulation boards at abutments,
penetrations and at exposed edges.
Support
Timber supports should be fixed at all roof edges using proprietary fixings
applicable to the construction and environmental conditions.
Fixings
Should be capable of withstanding necessary wind uplift and environmental
conditions. Fixings should finish flush with the surface of the plywood and
should not be over fixed.
Hydro - Thermal Calculations
The roofing contractor is responsible to provide Hydrothermal calculations in
respect of insulation values and condensation/dew points of the roof coverings
and deposit a copy of the calculations with the architect on completion of the
contract. Calculations are available through Polyroof Products Ltd.
Note
Care should be taken to ensure accessories such as skylights and vents are
compatible with the Polyroof 185 System and adhesion will be sufficient.
Although good adhesion can be obtained on the majority of surfaces by simply
abrading the surface a mechanical joint under a collar or lip should be created.
If detailing to accessories is not covered in the Polyroof Manual advice should
be sought in writing from the Polyroof Technical department.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 55
Appendix C - Polyroof 185 Material Requirements
Approved Contractors
Polyroof 185 should only be applied by contractors in possession of a current
approval certificate.
Confirmation of approval can be sought by calling Polyroof Products Ltd
Technical Services on 01352 735135. A final inspection shall be carried out by
a Polyroof technician prior to a guarantee being issued.
Approved Applicators
The contractor must provide an approved applicator to supervise the Polyroof
185 work and the approved applicator must remain on the site until the works
are complete. The contractor must obtain the consent of the client before
changing the approved applicator.
Immediate Plywood Decking
Plywood decking to be Finnforest Spruce II/III grade. Permission should be
sought from Polyroof Products Ltd before any variation is made to this
specification. Boards should be laid staggered and have a 3mm expansion gap
between all joints and a 15mm gap at abutments.
Preparation
All joints in the plywood should be reinforced with a 75mm wide strip of
Polyroof glassfibre tape. Any angles or details formed without pre-formed
trims should be double taped.
Pre-formed Trims
Shall be fixed to the plywood at 150mm maximum centres using treated clout
nails. All angles shall be mitred and all jobs reinforced with butt straps where
applicable and reinforced with a 75mm Polyroof tape.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 56
Appendix C - Polyroof 185 Material Requirements Continued
Application
The Polyroof 185 Waterproof system consists of glassfibre reinforced polyester
resin, cold applied on site by hand lay and processed to a minimum thickness
of 1.5mm giving a seamless, joint-free construction. The System should be
applied in accordance with the Polyroof Application Manual issued August
1996 and the British Board of Agrement Certificate 91/2604.
Note, The system should not be applied if the air or surface temperature is
outside the range of 5degC - 30degC; in damp or cold conditions which could
cause surface condensation; during frost or if there is a risk of rain.
Anti-Slip Grit
If anti-slip is specified it should be mixed into the top-coat and applied in
accordance with the Polyroof Application Manual issued August 1996. It
should be noted that this surface finish is anti-slip and cannot possibly
eliminate all risk of slipping.
Collars
Collars are to be formed at all protrusions.
Hoppers/Outlets
The Polyroof system should be dressed sufficiently into all outlets of this
nature.
Box/Valley gutters
Box and valley gutters should be formed whenever possible with a Finnforest
II/III plywood base. Any right angles joints should be removed using timber
fillets or preferably pre-formed Polyroof trims.
Note
It is important that the full application of base and top coat is completed
within each working day. However in certain circumstances this is not possible
due to a sudden change in weather conditions. In such cases the correct
Polyroof application procedure of vacuum drying and solvent wiping must be
followed to re-juvenate the base coat prior to application of the top coat.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 57
Appendix D - Expansion Trim Guidelines
GUIDELINES FOR THE FITTING OF EXPANSION TRIMS
• A 20mm gap is to be left between the plywood board joints at the
position of the expansion trim.
• Expansion trims to be overlapped, NOT butted, by a minimum of 50mm.
• All overlaps to be double taped using normal Polyroof chopped strand
matting with Poly Patch.
• The curved section of the Expansion trim (the whole flat area in the case
of flat expansion trims) should be coated using Poly Patch resin only.
Under no circumstances must normal Polyroof Topcoat be used as
cosmetic hairline cracks will appear.
• Masking tape should be used to ensure that a clean line is created
between the Polyroof 185 finish and the Poly Patch resin.
Extra Note:
All decking must be staggered in at least one direction on all contracts over 50m2.
Apply Polypatch following same procedure as that used for applying Polyroof Base
coat. Catalyst addition is per Polyroof Base resin, scale coverage 10 litres per 6m2.
GUIDELINES FOR WHERE EXPANSION TRIM MEETS EDGE DETAILS
• The expansion trim must be taken to the very edge of the roof. At this
point the standard Polyroof trim i.e. upstand, drip, fillet, mansard trim etc
should be jointed with a 10mm gap left.
• The trim is then to be double taped using Poly Patch resin and normal
chopped strand matting. Care should be taken to avoid any untidy
overlaps between the two systems.
• Expansion trims to be chamfered appropriately against mansard and
fillet details.
Should you require clarification on any of the above points please
contact the Technical Department on 0800 801 890.
Contents Section Start Next Section Page �� Page
POLYROOF 185Page 58
Appendix E - Approved Plywood List
Name Grade 3rd Party CPD Compliance CommentsControl
Finnforest II/III Fin ply / BBA CE Marked Strong, lightweight, rarely warps.
Spruce Structural 2+ Will have very small knot holes on
good face but acceptable for Polyroof.
Wisa II/III BBA CE Marked Strong, lightweight, rarely warps.
Spruce Structural 2+ Will have very small knot holes on
good face but acceptable for Polyroof.
Southern BCX American CE Marked Good quality veneer with few
Yellow Plywood Structural 2+ knotholes. Susceptible to slight
Pine Association deflection / warping during storage.
(SYP) Currently expensive.
Canadian Select Canply CE Marked Strong, lightweight, rarely warps.
Softwood Tight Structural 2+ Will have small knotholes on good
(CSP) Faced face but acceptable for Polyroof.
Contents Section Start Next Section Page �� Page
ELASTEXPage 59
ELASTEXA D V A N C E D L I Q U I D R O O F I N G S Y S T E M S
P R O D U C T I N F O R M A T I O N & D E S I G N G U I D E
Contents Section Start Next Section Page �� Page
ELASTEXPage 60
A D V A N C E D S E A M L E S S R O O F I N G S Y S T E M S
■ COLD APPL IED ■ 10 - 25 YEAR GUARANTEES ■ SEAMLESS ■ MINIMAL D ISRUPT ION ■ COST EFFECT IVE ■ S INGLE PACK
F O R S P E C I F I C AT I O N A D V I C E
C A L L T H E T E C H N I C A L H E L P L I N E O N
0 8 0 0 8 0 1 8 9 0
ELASTEXPROTECTION COAT
Highly durable & flexible finishing coat.
ELASTEX EMBEDMENT COAT
Reinforcement saturated with embedment coat.
ELASTEX EMBEDMENT COAT
REINFORCEMENTReinforcing mat offers
strength plus flexibility properties.
EXISTING PREPAREDSUBSTRATE
ELASTEX
NOT THE SYSTEM YOU’RE LOOKING FOR?
Elastex is part of ourrange of liquid appliedroofing systems.
If you’re not sure which isthe best system to use, referto our Product Selector or phone 0800 801 890.
RELATED BROCHURESPOLYROOF 185 (GRP System)PROTEC (Overlay)EBS (Balconies)ROOFCOAT PLUS (Overlay)ROOFCOAT (Repairs)PRODUCT SELECTOR
C O N T E N T S
ELASTEX
APPLICATIONS
DESIGN CONSIDERATIONS & PRODUCT DATA
OVERLAY SYSTEMS
OPTIONAL PREFORMEDCOMPONENTS
PHYSICAL PROPERTIES
TYPICAL NBS COLD ROOF SPECIFICATION
DESIGN DETAILING
Contents Section Start Next Section Page �� Page
ELASTEXPage 61
■ COLD APPL IED ■ 10 - 25 YEAR GUARANTEES ■ SEAMLESS ■ MINIMAL D ISRUPT ION ■ COST EFFECT IVE ■ S INGLE PACK
E L A S T E X
TECHNICALLY ADVANCED OVERLAY SYSTEM
Elastex is a cost-effective single pack reinforced
polyurethane overlay system that is ideal for extending
the life of existing roofs and gutters. This tough membrane
provides a resilient long lasting barrier to water penetration
and is resistant to UV degradation. The toughness and
flexibility of the system easily accommodates normal
surface movement and it is also resistant to occasional
foot traffic.
Elastex is the ideal refurbishment system as it can be applied
virtually all year round, to practically all roof surfaces,
including built-up felt, concrete, asphalt, asbestos cement,
plastic coated metals, stone, brick and some single plys.
It is effective on complex areas such as valley gutters,
extraction units, coping stones and parapet walls. Because
there is generally no stripping of the old roof, Elastex is
ideal for projects that require a fast solution with minimum
disruption. It is cold applied and rapidly becomes weather
resistant, providing high levels of UV protection.
Suitable for both warm and cold roofs, flexible Elastex can
also withstand maintenance foot traffic, and through the
addition of bauxite grits, provide an anti-slip surface.
� For waterproofing existing roofs and gutters
� Seamless cold liquid applied membrane
� 10 - 25 year guarantees available
� Suited to larger projects
� Minimal disruption
� Quickly becomes weather resistant
� Highly flexible and resilient
ELASTEX IS COLD APPLIED FOR SPEED AND SAFETY
Like all Polyroof systems, Elastex is cold applied so there
is minimum disruption, without the fire and safety risks
associated with conventional systems that rely on boilers
and exposed flames. Full tests also show that the system
achieves FAA rating (to BS476 : Part 3).
GUARANTEES
Elastex is fully backed by a manufacturer’s guarantee.
10 - 25 year systems are available. All Work is carried out
by a network of fully accredited Polyroof Contractors.
Polyroof Products Limited is an ISO 9001:2000
approved company.
Elastex protection coat
Elastex embedment coat
Contents Section Start Next Section Page �� Page
ELASTEXPage 62
■ COLD APPL IED ■ 10 - 25 YEAR GUARANTEES ■ SEAMLESS ■ MINIMAL D ISRUPT ION ■ COST EFFECT IVE ■ S INGLE PACK
A P P L I C A T I O N S
FLAT & LOW PITCHED ROOF APPLICATIONS
During refurbishment, care should be taken that existing
roofs have sufficient insulation and condensation control,
in accordance with correct Buildings Regulations Standards.
Advice on warm and cold roof designs can be found in
BS5250. The main types of substrates encountered in flat
& low-pitched roof refurbishment are:
Asphalt
For typical NBS specification please refer to page 8.
Built-up Felt (Existing)
Chippings should be stripped and removed from site.
All areas to be treated should be thoroughly cleaned
and a fungicide used if fungal growth or moss is present.
Areas of badly damaged or decayed felt should be
replaced to provide a sound substrate for the system.
Loose or de-bonded felt must be made good. Any blisters
should be made good by star cutting and re-bonding to
the substrate. Allow to dry out before re-fixing.
Primer may be required*, consult Polyroof Products
Technical Department for advice 0800 801890.
Single Ply PVC Membranes
Adhesion tests may be required due to the variation of single
ply systems on the market – please contact Polyroof Products
for advice. Standard preparation will include thorough
cleaning followed by wiping with Elastex solvent.
Lead Sheeting
Thoroughly clean down all areas to be treated and remove
all patination. Apply approved Elastex primer*.
COATED ROOFS
Solar reflective
Adhesion tests may be required for these areas,
especially in the case of aluminium pigmented coatings.
Consult Polyroof Products Technical Department for
Advice 0800 801890.
Liquid applied polyurethanes and GRP
Thoroughly clean down all areas to be treated.
Wipe surfaces using Elastex solvent.
GUTTER REFURBISHMENT APPLICATIONS
Elastex is the ideal seamless membrane to line existing
box and valley gutters due to its flexibility and resilience
to standing water. The main types of gutters encountered
are as follows:
Galvanised Metal Gutters (weathered)
Clean out and remove debris and dirt from the gutters
and water outlets to be treated, ensuring free drainage.
Wipe surfaces with Elastex solvent. Mechanically abrade
surfaces and remove debris. Apply approved Elastex
primer*.
Concrete Gutters (Finlock)
Clean out and remove debris and dirt from the gutters and
water outlets to be treated, and ensure free drainage.
Remove any existing, loose or poorly adhering materials
and repair where appropriate and then treat with a
fungicidal wash to kill off any moss or fungal spores left in
the gutters. Remove all residues and apply Elastex primer*.
Asbestos Gutters 1
Thoroughly clean down all areas to be treated to remove
all mould, moss, dirt, etc. Treat cleaned Asbestos with
fungicidal wash to ensure all moss and fungal spores are
destroyed. Remove all residues and inspect asbestos for
damage or cracks. Make good or replace broken or
defective profiles as required. Inspect all fixing bolts and
make good or replace as required. Apply Elastex primer*
to bolts and main gutter areas.
1Ensure compliance with the HSE guidelines regarding any material containing asbestos.
*Consult Overlays Manual. Tel: 0800 801 890 or visit www.polyroof.co.uk
Call or email for Inverted, Warm orGreen Roof specifications
Contents Section Start Next Section Page �� Page
ELASTEXPage 63
■ COLD APPLIED ■ 20 YEAR GUARANTEE ■ SEAMLESS ■ MAINTENANCE-FREE ■ 30 YEAR DURABILITY ■ SUITABLE FOR FREQUENT FOOT TRAFFIC
The design of the roof or gutter to which the Elastex system
is to be applied should be in accordance with the relevant
building regulations codes and good practice existing at the
time of construction. Since the Elastex system is also designed
as an overlay membrane for existing constructions, care should
be taken to ensure that the existing construction is structurally
sound and is unaffected by problems such as condensation.
PREPARATION
This varies depending on the substrate type and the condition.
In general all areas need to be thoroughly cleaned to remove all
dirt and debris, mould growth, moss, etc. A fungicidal wash
may also be required. Any loose or flaking material must be
removed and any defective areas made good or replaced.
Certain metals will require abrasion or pre-treatment,
before application of the required primer, and some aluminium
leaf based coatings may require special treatment.
Adhesion tests are usually recommended for such areas.
It is strongly recommended that Polyroof Products Technical
Services are consulted at an early stage in the design process
to determine exact preparation and priming required for any
particular contract.
FALLS
Elastex is normally applied to existing substrates and therefore
no changes to falls are usually necessary. Standing water is not
detrimental to the Elastex system, but where it is seen as a
problem - particularly if the area is to be accessed - then cut to
falls insulation or timber firrings and plywood can be used to
reduce the problem. The minimum fall recommended by the
relevant British Standard code of practice is 1 in 80, although
a design fall of 1 in 40 is commonly adopted to provide
a construction tolerance.
PROTRUSIONS
The system can be moulded to suit penetrations such as soil
pipes, stanchions or machinery fixing positions.
EXPANSION AND CONTRACTION
Elastex laid in accordance with specifications, will withstand
normal building movement without the need for special
expansion joints. Existing expansion joints in structures can
be accommodated by use of a de-bonding tape.
PRE-CONTRACT APPROVAL
Roof specifications require approval from Polyroof Technical
Services before the contract begins.
WALKWAYS / TRAFFIC
Elastex is available with a slip resistant finish that is suitable for
light maintenance foot traffic.
Please note that, although the surface finish is slip resistant,
it cannot possibly eliminate all risk of slipping. This is particularly
relevant in the event of ice forming on the roof surface.
If regular foot traffic is a requirement, please consult Polyroof
Products for advice on additional surface protection or details
of our specialist balcony / walkway systems (See Polyroof 185
and EBS brochures).
DRAINAGE
Advice on roof drainage is given in code of practice BS.6367.
The Elastex system is compatible with the majority of standard
rainwater outlets.
PROPERTIES IN RELATION TO FIRE
Full tests show that the system achieves EXT FAA in
accordance with (BS476 Part 3)
WEATHERTIGHTNESS
Test data confirms that the system will adequately resist the
passage of moisture to the inside of the building and so meet
the requirements of the National Building Regulations.
RESISTANCE TO WIND UPLIFT
Elastex is a fully bonded system. Resistance to wind uplift is
adequate to meet the effects of wind suction likely to occur
in practice.
DURABILITY
The Elastex Systems have minimum durability ratings of up to
25 years depending on the system specified.
STANDARDS COMPLIANCE
Systems and components are produced to ISO 9001:2000
quality standards.
COLOUR
Elastex is supplied in standard Dove Grey and Slate Grey.
Other colours available subject to minimum quantities.
D E S I G N C O N S I D E R A T I O N S
P R O D U C T D A T A
Contents Section Start Next Section Page �� Page
O V E R L A Y S Y S T E M S
Overlay systems offer an alternative to the complete
replacement of existing flat roofs. The principal advantage
of this is to minimise disruption and, in the majority of
cases, keep the building fully operational during the
refurbishment.
An overlay system is usually considered when the existing
roof covering is showing early signs of breakdown.
This, for example, could be a felt roof where bubbles or
blisters are starting to appear, or a single ply or gutter
installation where seams or joints are beginning to fail.
The condition of the existing roof largely determines the
level of preparation required.
In general, most common roof coverings can be overlaid
but care should be taken to ensure that the existing
underlying substrate is sound and of reasonable quality.
We recommend that a site survey is carried out by Polyroof
Technical Services if there is any doubt about the condition
of the substrate. Existing detailing is also usually retained,
but new detailing can also be integrated into the system
if required.
It is advisable that, where possible, the whole area is
overlaid rather than carrying out localised repairs. This
ensures that the system is completely seamless throughout
and offers a fully guaranteed solution. Localised repairs
are, of course, possible if a short-term solution is required.
Overlay systems should not be considered a ‘cure-all’ for
a badly designed roof. Care should always be taken to
ensure that any underlying problems are first addressed -
such as condensation or inadequate insulation (poor U-
Values) – before work begins. Advice on upgrading to a
warm roof design can be obtained from Polyroof Technical
Services.
1 2 3 4
TYPICAL BUILD-UP
61 542 3
INSULATED DECK
1 Existing substrate made goodto form VCL or new metal lined felt VCL
2 Rigid urethane insulation core
3 Felt prepared and primed
4 Elastex embedment coat
5 Elastex mat reinforcement
6 Elastex protection coat
1 Existing prepared substrate
2 Elastex embedment coat
3 Elastex mat reinforcement
4 Elastex protection coat
■ COLD APPLIED ■ 20 YEAR GUARANTEE ■ SEAMLESS ■ MAINTENANCE-FREE ■ 30 YEAR DURABILITY ■ SUITABLE FOR FREQUENT FOOT TRAFFIC
ELASTEXPage 64 Contents Section Start Next Section Page �� Page
■ COLD APPLIED ■ 20 YEAR GUARANTEE ■ SEAMLESS ■ MAINTENANCE-FREE ■ 30 YEAR DURABILITY ■ SUITABLE FOR FREQUENT FOOT TRAFFIC
ELASTEXPage 65
The Polyroof range of rigid GRP components offer a fast reliable way of
upgrading and finishing most flat roof detailing requirements. All trims
are optional as, in many cases, the existing detailing can be retained.
A wide range of non standard profiles exists. Consult Polyroof with
your specific requirements.
Polyroof pre-formed GRP Trims have a nominal thickness of 2.15mm
and are supplied in 2.44Im lengths. NB. Drawings are not to scale.
Tensile Strength (BS2782 : 320A)
Unreinforced System 7N/mm2
Reinforced System 10 9N/mm2
Elongation (BS2782 : 320A)
Unreinforced System 300%
Reinforced System 10 30%
Tear Strength (BS2782 : 320A)
Unreinforced System 7N/mm
Reinforced System 10 25N/mm
Coating Adhesion (ASTM D4541)
Unprimed concrete 2N/mm2
Primed concrete 3-5N/mm2
Thermal Cycling/Low Temperature Flexibility(BS3900 : EI : 1992)
Thermally cycled film (16 hours @ -25ºC/8hrs + 80ºC. 7cycles)Tested a 0ºC. Pass 5mm dia. mandrel
Freeze/Thaw
Constant immersion, 16 hours @ +20ºC 8 hrs @ -25ºC. 5 cyclesNo significant changes in mechanical properties
Impact Resistance
ASTM G14-88 2.5 JoulesBS3900 : E3 No cracking
or detachment from substrate
Heat Ageing (56 days) @ 70ºC
No significant change in mechanical properties
Water Vapour Transmission (ASTM E96/1653)
Specific permeability 25g/m2/day
Resistance to Fire (BS476 : Part 3)
Ext. FAA FAA
Accelerated Weathering (ASTM G53 - 2000 hours)
Minor surface chalking, no blisters, no loss of adhesion
Salt Spray (ASTM B117 - 1000 hours)
Minor surface chalking, no blisters, no loss of adhesion
Water Absorption (ASTM D570)
7 days - 5% weight gain21 days - 6.5% weight gain
T E C H N I C A L D A T A
110mm
Butt strap required
Available in lengths:100mm125mm175mm
Butt strap required
Available in lengths:75mm100mm150mm
UPSTAND FASCIA TRIMS
Butt strap not required
Available in lengths:150mm250mm350mm400mm
Butt strap not required
Available in 300mm lengths:
FILLET TRIM
100mm
DRIP TRIMS
FLAT TRIMS
75mm
300mm
P H Y S I C A L P R O P E R T I E SO P T I O N A L P R E - F O R M E DC O M P O N E N T S
Contents Section Start Next Section Page �� Page
■ COLD APPLIED ■ 20 YEAR GUARANTEE ■ SEAMLESS ■ MAINTENANCE-FREE ■ 30 YEAR DURABILITY ■ SUITABLE FOR FREQUENT FOOT TRAFFIC
ELASTEXPage 66
T Y P I C A L L I Q U I D A P P L I E D C O L D R O O F C O A T I N G S P E C I F I C A T I O N
T Y P I C A L N B S S P E C I F I C A T I O N F O R O V E R L A Y O F A S P H A L T R O O F
DRAWING REFERENCE(S):
N/A
BASE (SUBSTRATE FOR COATING):
Asphalt Flat Roof.
PREPARATION:
It is advised that the Polyroof contractor consults Polyroof Technical
Department (0800) 801890 for advice on detailing and preparation prior
to commencement of contract.
IMPORTANT - if any areas of aluminium solar reflective paint or
unidentified coatings are present, adhesion tests may be required.
Make good existing Asphalt
Any blistered or slumped areas of asphalt should be inspected and made
good as required. Should removal be required, replace with a suitable
repair compound. Allow repairs to cure prior to the system application.
Where required, use biocidal wash.
Remove debris and make good existing coverings, apply a biocidal solution
recommended by coating manufacturer to all areas previously subject to
organic growth. Allow to dry.
Powerwash roof areas.
To provide a contamination free surface for system application, clean all
areas using a water jet and allow to dry.
WATERPROOF COATING:
Seamless Liquid Applied Polyurethane.
MANUFACTURER:
Polyroof Products Ltd. Furness House,
Castle Park Industrial Estate, Flint,
Flintshire CH6 5XA
Tel: 01352 735135
Fax: 01352 735 182
Email: [email protected]
Web: www.polyroof.co.uk
PRIMER REFERENCE:
Polyroof Binder / Sealer.
COATING SYSTEM REFERENCE:
Polyroof Elastex System.
APPLICATION:
Laid by Polyroof Approved Contractor in accordance with Polyroof Products
Ltd Instructions.
Coverage Rates below are indicative and will depend on porosity / surface
roughness. Contractors should visit site to ascertain coverage rates –
consult Polyroof Products Technical Services for advice (0800) 801890.
10 Year System: Embedment Coat 1m2/litre
Protection Coat 2m2/litre
Embedment Coat to be fully reinforced using Elastex Mat.
15 Year System: Embedment Coat 1m2/litre
Protection Coat 1.33m2/litre
Embedment Coat to be fully reinforced using Elastex Mat.
20 Year System: Embedment Coat 1m2/litre
Protection Coat (1st Coat) 2m2/litre
Protection Coat (2nd Coat) 2m2/litre
Embedment Coat to be fully reinforced using Elastex Mat.
25 Year System: Embedment Coat 1m2/litre
Protection Coat (1st Coat) 1.6m2/litre
Protection Coat (2nd Coat) 1.6m2/litre
REINFORCEMENT:
Elastex 100 gm-2 Glassfibre Mat.
MINIMUM DRY FILM THICKNESS:
10 Year System 1.1 mm 15 Year System 1.3 mm
20 Year System 1.5 mm 25 Year System 1.7 mm
SURFACE PROTECTION:
Maintenance Foot Traffic
No additional surface protection required, however a slip resistant finish
can be applied (consult Polyroof Technical Department for advice).
Regular Foot Traffic
Consult Polyroof Technical Department for details on protection or
alternative Polyroof systems.
ACCESSORIES:
Polyroof Pre-formed GRP Trims (if required).
Call or email for Inverted, Warm orGreen Roof specifications
Contents Section Start Next Section Page �� Page
ELASTEXPage 67
■ COLD APPLIED ■ 20 YEAR GUARANTEE ■ SEAMLESS ■ MAINTENANCE-FREE ■ 30 YEAR DURABILITY ■ SUITABLE FOR FREQUENT FOOT TRAFFIC
D E S I G N D E T A I L I N G
PIPE DETAILALUMINIUM TRIM DETAILING
RAINWATER OUTLET1. Existing substrate2. Elastex embedment
coat and glass reinforcement
3. Elastex protection coat
4. Rainwater outlet
Note: The Elastex systemshould be dressed into theoutlet as far practicable.
1. Existing substrate2. Elastex embedment
coat and glass reinforcement
3. Elastex protection coat
4. Aluminium trim5. Glass reinforced
Note: Aluminium trims tobe wiped with Elastexsolvent abraded andmetallic primed.
NB: System to be doubletaped at trim joints.
ROOF-LIGHT UPSTAND
1
1
2
2
3
3
4
4
1. Existing substrate2. Elastex embedment
coat and glass reinforcement
3. Elastex protection coat
4. Roof-light upstand
Note: It is preferable touse proprietary roof lightsincorporating a GRPupstand wherever possible.GRP upstand to beabraded prior tolaminating direct.
1. Existing substrate2. Elastex embedment
coat and glass reinforcement
3. Elastex protection coat
4. Weathering flange/seal
4
4
5
3
3
2
2
1
1
METAL GUTTER1. De-bonding tape2. Elastex Fibretex3. Elastex embedment
coat and glass reinforcement
4. Elastex protection coat
5. Metal Gutter
Note: Metal gutter to bewiped with Elastex solventand metallic primed. NB: Some metals willrequire abrading*
*Do not abrade galvanised metals.
5
1
23
4
WELTED DRIP1. Existing substrate2. Elastex embedment
coat and glass reinforcement
3. Elastex protection coat
4. Welted drip
Note: Existing felt andwelted drip to be cleanedand made good as required.
1
2
4
3
Contents Section Start Next Section Page �� Page
Nothing in this specification brochure or any other marketing literature produced by or on behalf of Polyroof Products Limitedis to be regarded as constituting a contract binding in law between Polyroof Products Limited and any customer.
The only contract which Polyroof will enter into with the customer is that contained in the Guarantees, the details of whichare available on request. This Guarantee is in the form of a written guarantee which takes effect only when issued in writingby Polyroof to the customer at the request of the Contractor.
A NATIONWIDE NETWORK OF COMPANY TRAINED TECHNICIANSPolyroof is only supplied to and installed by contractors fully application trained and licensed by the company, to ensure consistent quality of installation. Contractors’ performance is regularly monitored and random inspection of installations carried out. Failure to comply with the Company’s stringent standards leads to withdrawal of certification.
QUALITY CONTROLPolyroof Products Ltd operates comprehensive and rigorous quality control procedures in accordance with ISO 9001:2000
The scope of this approval includes the design and installation of roofing systems, the provision of technical support, as well as the appointment and monitoring of installers.
Not only is the manufacture of Polyroof liquid applied roofing systems and accessories quality approved, but so too is the procurement, storage and supply of all related materials and consumables.
GUARANTEESManufacturers guarantees are available for 10 - 25 years subject to specification. Insurance backing available, please call 0800 801 890 for details.
ELASTEXPage 68
POLYROOF PRODUCTS LTD
FURNESS HOUSE
CASTLE PARK INDUSTRIAL ESTATE
FL INT FL INTSHIRE
CH6 5XA
Tel : 01352 735 135
Fax: 01352 735 182
Emai l : technica l@polyroof .co.uk
www.polyroof .co.uk
FREEPHONEH E L P L I N E
0800 801 890
E S T. 1984
THE NATIONAL FEDERATION OFROOFING CONTRACTORS LIMITED
Associate Member
Contents Section Start Next Section Page �� Page
ELASTEXPage 69
Please note that this is an outline proposal only and will be subject tofurther site investigation by Polyroof Products Ltd Technical Department
1.1 Overview
1.2 Preparation
Surface Preparation
Priming
1.3 Main Elastex System
Local Reinforcement
Embedment Coat
Protection Coat
Anti-Slip Finish
1.4 General
Other Notes
Coverage Rate Guidelines
Thermal Performance
Falls
Guarantee Details
1.5 Appendices
Appendix A General Guidance Notes
Appendix B General Inspection & Preparation Notes
Contents Section Start Next Section Page Page
Asphalt
GUIDELINE SPECIFICATION
ELASTEXPage 70
1.1 Overview
Existing Construction (Assumed)
1. Asphalt
2. Existing Substrate
Note: Any unidentified coatings are subject to adhesion tests.
Proposed Construction
1 2 3 4
TYPICAL BUILD-UP
1 Existing prepared substrate
2 Elastex embedment coat
3 Elastex mat reinforcement
4 Elastex protection coat
Contents Section Start Next Section Page �� Page
ELASTEXPage 71
1.2 Preparation
Surface Preparation
Special attention should be given to any solar reflective
coatings (especially aluminium pigmented). Adhesion tests
will be required to determine if full or partial removal of the
paint will be required. Please consult Polyroof Products
Technical Department on 0800 801890.
Remove chippings from roof surface, any embedded chippings should
be removed by a mechanical scabbling device or other means as
necessary. Ensure the roof is able to carry the weight of any equipment.
Thoroughly clean down all areas to be treated, removing dirt, debris,
surface lying water, mould growth and moss, etc.
Treat any areas of fungal growth or moss with Polykill “W” Anti-
Fungal Wash to ensure all spores are destroyed. Powerwash to
remove any residues.
Inspect all surfaces to assess soundness of existing substrates
including any existing coatings, repairs and any test areas. This is to
verify compatibility for the proposed coating system and to assess
the need for priming.
Any blow holes in asphalt are to be smoothed out or removed and
levelled off using a suitable repair compound, i.e. sand cement mix
with a suitable hardener. Allow repairs to cure prior to priming.
For wet or saturated insulation or decking, careful consideration
should be given to the installation of permanent roof ventilation.
Areas where the insulation or underlying substrate has collapsed or
is defective or decayed, should be cut out, repaired and reinstated to
provide a good solid base for the coating system.
NB: For general guidance and preparation information (please
refer to appendix).
Contents Section Start Next Section Page �� Page
ELASTEXPage 72
Priming
Apply by brush or roller one coat of MC Binder/Sealer to all prepared
surfaces at an approximate coverage rate of 6 - 10m2/litre. Rough or
highly porous surfaces will significantly reduce the coverage rate.
Visually check that all porous surfaces are adequately sealed. Touch-
in suspect areas where necessary. Allow to dry for at least 2 to 4
hours before overcoating.
Overcoat within 24 hours. After this period it may be necessary to
rub down and/or re-prime.
1.3 Main Elastex System
Local Reinforcement (Cracks/Voids, etc)
Apply de-bonding (masking) tape across all large splits/cracks. Then
locally reinforce with Elastex Mat and Elastex Embedment Coat.
Embedment Coat
Apply by brush or roller one overall coat of Elastex Embedment Coat
to the prepared surfaces at an approximate coverage rate of (see
below)** and whilst wet insert Elastex Mat Regular glass fibre
matting and thoroughly ‘wet-in’ using a short to medium pile roller.
Allow to dry before applying next coat.
Overlap adjacent reinforcement areas already laid by at least 50mm
ensuring sufficient extra embedment material is applied to these
areas. When embedding Elastex Mat into Elastex it may be necessary
to tamp the mat. Use a soft nylon brush or specialist roller ensuring
that there are no tented areas. Check for any upstanding glass fibre
strands and cut flush with surface with a sharp knife. Overcoat cut
areas. Allow to dry before applying next coat.
De-Chipped Asphalt 0.8 - 1.0m2/Litre (1.0 - 1.25Litre/m2)
Asphalt 1.0m2/Litre (1.0Litre/m2)
**Please note - rough or uneven or heavily mineralised surfaces may significantlyreduce the coverage rate - make further material allowances where necessary. All coverage rates are indicative only and it is the contractors’ responsibility toascertain their own coverage rates on site.
Contents Section Start Next Section Page �� Page
ELASTEXPage 73
Protection Coat (10 or 20 Year System)
10 Year System:
Apply by brush or roller one overall coat of Elastex Protection Coat at
an approximate coverage rate of 2.0m2/litre (0.5 Litres/m2). Allow to dry.
20 Year System:
Apply by brush or roller a first coat of Elastex Protection Coat at an
approximate coverage rate of 2.0m2/litre (0.5 Litres/m2). Allow to
dry.
Apply by brush or roller a second coat of Elastex Protection Coat at
an approximate coverage rate of 2.0m2/litre (0.5 Litres/m2). Allow to
dry.
Anti-Slip Finish
An extra application of protection coat will be required for an anti-
slip finish; this should be applied at a minimum rate of 4.0m2/litre
(0.25 Litres/m2).
General application of anti-slip material is broad cast onto wet
protection coat. Coverage rates may vary depending on requirements.
Consult Polyroof Products Technical Department for Advice on
0800 801890.
Contents Section Start Next Section Page �� Page
ELASTEXPage 74
1.4 General
Other Notes
The system should not be laid when the temperature is below 5 oC
or above 30 oC.
On completion of each coat check for pinholes and misses and rectify
appropriately.
Allow at least 7 days before replacing cables etc.
Coverage Rate Guidelines
IMPORTANT: Coverage rates of all materials are indicative will vary
according to dimensions and nature of substrates. If in any doubt, it
is advised that the Contractor carries out a test patch to ascertain
coverage rates prior to commencement of the contract. Any
significant variations should be notified to the Polyroof Technical
Department immediately.
Thermal Performance
The Elastex system will not alter the thermal performance of the roof
and any existing condensation problems will remain. Options for
improving the thermal performance of the roof are available on
request.
Falls
This system will not alter the existing falls of the roof. However, you
may wish to note that standing water is not detrimental to the
Elastex System.
NB: Options for improving falls are however available on request.
Guarantee Details
10 or 20 Year Manufacturers Guarantee.
Contents Section Start Next Section Page �� Page
ELASTEX Page 75
1.5 Appendices
Appendix A - General Guidance Notes
Inspect roofing substrate to ensure suitability for coating.
Previously coated areas must be carefully checked to ensure integrity
and adhesion to the substrate.
Ensure by adhesion tests that the proposed coating system is fully
compatible with existing surfaces. Testing should include determining
the necessity/selection of a primer.
Check building for visible structural defects which may adversely
affect the stability of the roof.
All roof surfaces to be treated must be sound, dry and completely
free from all contaminants.
Inspect all roof fittings, i.e. trims, flashings, cappings, etc. Make
good all defective areas (renew if necessary) prior to coating.
Inspect all old remedial repairs, patches, cracks etc. Make good
where necessary. (remove unsound repairs) prior to coating.
Where air intake units of air conditioning/ventilation systems are
present, the client and coatings manufacturer should be consulted to
take any steps necessary to prevent entry of solvent vapours (where
applicable).
Inspect all upstands, vents and any other protrusions. Make good or
replace prior to coating.
Do not remove, or suspend cables, lightning conductors, wires, etc.,
without due authorisation. Lightning conductors should not be
coated under any circumstances. Other items should not be coated
unless agreed.
Before work commences ensure all health & safety data sheets are
read and understood.
Contents Section Start Next Section Page �� Page
ELASTEXPage 76
Appendix A - General Guidance Notes Continued
No provision has been made to alter roof falls (standing water is not
detrimental).
Coverage rates of all materials will vary according to dimensions and
nature of substrates.
On completion of all coating activity, dispose of all empty material
cans, material contaminated tools, overalls and site waste in
accordance with the relevant environmental regulations.
Completely clear site including scaffolding, etc.
All work should be carried out in a safe and tidy manner. Relevant
Health & safety/COSHH regulations should be observed at all times.
Note, The system should not be applied if the air or surface
temperature is outside the range of 5ºC - 30ºC; in damp or cold
conditions which could cause surface condensation; during frost or if
there is a risk of rain.
Contents Section Start Next Section Page �� Page
ELASTEXPage 77
Appendix B - General Inspection & Preparation Notes
Inspect all surfaces to assess soundness of existing substrates and
coatings, and any test areas, to verify compatibility and proposed
coating system to assess the need for priming.
Thoroughly clean down all areas to be treated, removing all loose
chippings, dirt and debris, surface lying water, mould growth, moss, etc.
Embedded chippings should be removed by a mechanical scabbling
device or other means as necessary. Ensure the roof is able to carry
the weight of any equipment.
After cleaning down, treat all areas of fungal growth or moss with
Polykill “W” Anti-Fungal Wash to ensure all spores are destroyed.
Remove all residues.
Any spalled, loose, unsound brickwork or concrete should be broken
out and repaired using a suitable repair mortar.
All screeds, concrete surfaces and repair areas to be treated should
be lightly abraded with suitable equipment (e.g. vacu-blast, diamond
disc grind etc) to remove all laitance and other contamination to
provide a clean, dry and open surface.
Special attention should be given to solar reflective (especially
aluminium pigmented) coatings. Adhesion tests may be required for
these areas.
Remove all loose, suspect and friable materials, cutting back to a
sound firm edge. Prepare all surfaces to a clean, dry and sound
condition to promote satisfactory adhesion, if necessary removing
existing coatings and test patches.
Any blow holes in asphalt are to be smoothed out or removed and
levelled off using a suitable repair compound, i.e. sand cement mix
with a suitable hardener. Allow repairs to cure prior to priming.
Areas of badly damaged or decayed felt should be replaced to
provide a sound substrate for the system.
Contents Section Start Next Section Page �� Page
ELASTEXPage 78
Appendix B - General Inspection & Preparation Notes
Continued
Loose or disbonded felt must be re-bonded to the substrate. Any
blisters should be made good by star cutting and re-bonding to the
substrate. Allow to dry out before re-fixing.
Scrape away volatile asphalt surfaces and stabilise with primer.
When preparing lead surfaces for treatment, ensure all precautions
are taken to avoid skin contact, ingestion, inhalation, environmental
contamination and unsafe disposal of debris etc.
Clean out and remove debris and dirt from the gutters and water
outlets to be treated. Ensure free drainage.
Make good or repair any defective areas of lead. Any unsound
remedial repairs should be removed prior to coating.
Scrub down all surfaces to be treated, completely remove all slats,
oxidations, dirt and debris.
Lead sheets must be wet-abraded, the residues collected and the
area subsequently washed again. The residues should be, once,
collected and disposed of appropriately.
All unsound remedial repairs should be removed and made good.
All large cracks and voids should be cleaned and made good using a
suitable repair compound.
For wet or saturated substrates careful consideration should be given
to the installation of permanent roof ventilation.
Areas where the insulation or underlying substrate has collapsed
should be cut out, repaired and reinstated to provide a good solid
base for the coating system.
Contents Section Start Next Section Page �� Page
ELASTEXPage 79
Appendix B - General Inspection & Preparation Notes
Continued
At all upstands, cut a chase at least 150mm above the roof surface
into which the reinforced coating should be taken. Re-point on
completion (allow a min 2 days to cure). Inspect all fixing bolts and
tighten or replace as required. Crop all protruding bolt heads.
Mechanically abrade to remove excess corrosion and remove debris.
Mechanically abrade any ferrous or other metal surfaces included in
the coating schedule and remove debris.
Advice on surface pre-treatment and priming of galvanised and other
non-ferrous substrates should be sought from the Company's
Technical Department.
Contents Section Start Next Section Page �� Page
ELASTEXPage 80
Please note that this is an outline proposal only and will be subject tofurther site investigation by Polyroof Products Ltd Technical Department
1.1 Overview
1.2 Preparation
Surface Preparation
Priming
1.3 Main Elastex System
Embedment Coat
Protection Coat
Anti-Slip Finish
1.4 General
Other Notes
Coverage Rate Guidelines
Thermal Performance
Falls
Guarantee Details
1.5 Appendices
Appendix A General Guidance Notes
Appendix B General Inspection & Preparation Notes
Contents Section Start Next Section Page �� Page
Felt
GUIDELINE SPECIFICATION
ELASTEXPage 81
1.1 Overview
Existing Construction (Assumed)
1. Felt
2. Existing Substrate
Note: Any unidentified coatings are subject to adhesion tests.
Proposed Construction
1 2 3 4
TYPICAL BUILD-UP
1 Existing prepared substrate
2 Elastex embedment coat
3 Elastex mat reinforcement
4 Elastex protection coat
Contents Section Start Next Section Page �� Page
ELASTEXPage 82
1.2 Preparation
Surface Preparation
Special attention should be given to any solar reflective
coatings (especially aluminium pigmented). Adhesion tests
will be required to determine if full or partial removal of the
paint will be required. Please consult Polyroof Products
Technical Department on 0800 801890.
Remove chippings from roof surface, any embedded chippings
should be removed by a mechanical scabbling device or other means
as necessary.
Ensure the roof is able to carry the weight of any equipment.
Thoroughly clean down all areas to be treated, removing dirt, debris,
surface lying water, mould growth and moss, etc.
Treat any areas of fungal growth or moss with Polykill “W” Anti-
Fungal Wash to ensure all spores are destroyed. Powerwash to
remove any residues.
Inspect all surfaces to assess soundness of existing substrates
including any existing coatings, repairs and any test areas. This is to
verify compatibility for the proposed coating system and to assess
the need for priming.
Areas of badly damaged or decayed felt should be replaced to
provide a sound substrate for the system.
Loose or de-bonded felt must be re-bonded to the substrate. Any
blisters should be made good by star cutting and re-bonding to the
substrate. Allow to dry out before re-fixing.
Contents Section Start Next Section Page �� Page
ELASTEXPage 83
For wet or saturated insulation or decking, careful consideration
should be given to the installation of permanent roof ventilation.
Areas where the insulation or underlying substrate has collapsed or
is defective or decayed, should be cut out, repaired and reinstated to
provide a good solid base for the coating system.
NB: For general guidance and preparation information (please refer
to appendix).
Priming
Apply by brush or roller one coat of MC Binder/Sealer to all prepared
surfaces at an approximate coverage rate of 6 - 10m2/litre. Rough or
highly porous surfaces will significantly reduce the coverage rate.
Visually check that all porous surfaces are adequately sealed. Touch-
in suspect areas where necessary. Allow to dry for at least 2 to 4
hours before overcoating.
Overcoat within 24 hours. After this period it may be necessary to
rub down and/or re-prime.
Contents Section Start Next Section Page �� Page
ELASTEXPage 84
1.3 Main Elastex System
Embedment Coat
Apply by brush or roller one overall coat of Elastex Embedment Coat
to the prepared surfaces at an approximate coverage rate of (see
below)** and whilst wet insert Elastex Mat Regular glass fibre
matting and thoroughly ‘wet-in’ using a short to medium pile roller.
Allow to dry before applying next coat.
Overlap adjacent reinforcement areas already laid by at least 50mm
ensuring sufficient extra embedment material is applied to these
areas.
When embedding Elastex Mat into Elastex it may be necessary to
tamp the mat. Use a soft nylon brush or specialist roller ensuring that
there are no tented areas. Check for any upstanding glass fibre
strands and cut flush with surface with a sharp knife. Overcoat cut
areas. Allow to dry before applying next coat.
De-Chipped Felt 0.8 - 1.0m2/Litre (1.0 - 1.25Litre/m2)
Mineral Felt 0.8m2/Litre (1.25Litre/m2)
Sanded Felt 1.0m2/Litre (1.0Litre/m2)
**Please note - rough or uneven or heavily mineralised surfaces may
significantly reduce the coverage rate - make further material
allowances where necessary. All coverage rates are indicative only
and it is the contractors’ responsibility to ascertain their own
coverage rates on site.
Contents Section Start Next Section Page �� Page
ELASTEXPage 85
Protection Coat (10 or 20 Year System)
10 Year System:
Apply by brush or roller one overall coat of Elastex Protection Coat at
an approximate coverage rate of 2.0m2/litre (0.5 Litres/m2). Allow to dry.
20 Year System:
Apply by brush or roller a first coat of Elastex Protection Coat at an
approximate coverage rate of 2.0m2/litre (0.5 Litres/m2). Allow to dry.
Apply by brush or roller a second coat of Elastex Protection Coat at
an approximate coverage rate of 2.0m2/litre (0.5 Litres/m2). Allow to dry.
Anti-Slip Finish
An extra application of protection coat will be required for an anti-
slip finish; this should be applied at a minimum rate of 4.0m2/litre
(0.25 Litres/m2).
General application of anti-slip material is broad cast onto wet
protection coat. Coverage rates may vary depending on requirements.
Consult Polyroof Products Technical Department for Advice on
0800 801890.
Contents Section Start Next Section Page �� Page
ELASTEXPage 86
1.4 General
Other Notes
The system should not be laid when the temperature is below 5ºC or
above 30ºC.
On completion of each coat check for pinholes and misses and rectify
appropriately.
Allow at least 7 days before replacing cables etc.
Coverage Rate Guidelines
IMPORTANT: Coverage rates of all materials are indicative will vary
according to dimensions and nature of substrates. If in any doubt, it
is advised that the Contractor carries out a test patch to ascertain
coverage rates prior to commencement of the contract. Any significant
variations should be notified to the Polyroof Technical Department
immediately.
Thermal Performance
The Elastex system will not alter the thermal performance of the roof
and any existing condensation problems will remain. Options for
improving the thermal performance of the roof are available on
request.
Falls
This system will not alter the existing falls of the roof. However, you
may wish to note that standing water is not detrimental to the
Elastex System.
NB: Options for improving falls are however available on request.
Guarantee Details
10 or 20 Year Manufacturers Guarantee.
Contents Section Start Next Section Page �� Page
ELASTEXPage 87
1.5 Appendices
Appendix A - General Guidance Notes
Inspect roofing substrate to ensure suitability for coating.
Previously coated areas must be carefully checked to ensure integrity
and adhesion to the substrate.
Ensure by adhesion tests that the proposed coating system is fully
compatible with existing surfaces.
Testing should include determining the necessity/selection of a
primer.
Check building for visible structural defects which may adversely
affect the stability of the roof.
All roof surfaces to be treated must be sound, dry and completely
free from all contaminants.
Inspect all roof fittings, i.e. trims, flashings, cappings, etc. Make
good all defective areas (renew if necessary) prior to coating.
Inspect all old remedial repairs, patches, cracks etc. Make good
where necessary. (remove unsound repairs) prior to coating.
Where air intake units of air conditioning/ventilation systems are
present, the client and coatings manufacturer should be consulted to
take any steps necessary to prevent entry of solvent vapours (where
applicable).
Inspect all upstands, vents and any other protrusions. Make good or
replace prior to coating.
Do not remove, or suspend cables, lightning conductors, wires, etc.,
without due authorisation. Lightning conductors should not be
coated under any circumstances. Other items should not be coated
unless agreed.
Contents Section Start Next Section Page �� Page
ELASTEXPage 88
Appendix A - General Guidance Notes Continued
Before work commences ensure all health & safety data sheets are
read and understood.
No provision has been made to alter roof falls (standing water is not
detrimental).
Coverage rates of all materials will vary according to dimensions and
nature of substrates.
On completion of all coating activity, dispose of all empty material
cans, material contaminated tools, overalls and site waste in
accordance with the relevant environmental regulations.
Completely clear site including scaffolding, etc.
All work should be carried out in a safe and tidy manner. Relevant
Health & safety/COSHH regulations should be observed at all times.
Note, The system should not be applied if the air or surface
temperature is outside the range of 5ºC - 30ºC; in damp or cold
conditions which could cause surface condensation; during frost or if
there is a risk of rain.
Contents Section Start Next Section Page �� Page
ELASTEXPage 89
Appendix B - General Inspection & Preparation Notes
Inspect all surfaces to assess soundness of existing substrates and
coatings, and any test areas, to verify compatibility and proposed
coating system to assess the need for priming.
Thoroughly clean down all areas to be treated, removing all loose
chippings, dirt and debris, surface lying water, mould growth, moss, etc.
Embedded chippings should be removed by a mechanical scabbling
device or other means as necessary. Ensure the roof is able to carry
the weight of any equipment.
After cleaning down, treat all areas of fungal growth or moss with
Polykill “W” Anti-Fungal Wash to ensure all spores are destroyed.
Remove all residues.
Any spalled, loose, unsound brickwork or concrete should be broken
out and repaired using a suitable repair mortar.
All screeds, concrete surfaces and repair areas to be treated should
be lightly abraded with suitable equipment (e.g. vacu-blast, diamond
disc grind etc) to remove all laitance and other contamination to
provide a clean, dry and open surface.
Special attention should be given to solar reflective (especially
aluminium pigmented) coatings.
Adhesion tests may be required for these areas.
Remove all loose, suspect and friable materials, cutting back to a
sound firm edge. Prepare all surfaces to a clean, dry and sound
condition to promote satisfactory adhesion, if necessary removing
existing coatings and test patches.
Any blow holes in asphalt are to be smoothed out or removed and
levelled off using a suitable repair compound, i.e. sand cement mix
with a suitable hardener. Allow repairs to cure prior to priming.
Contents Section Start Next Section Page �� Page
ELASTEXPage 90
Appendix B - General Inspection & Preparation Notes
Continued
Areas of badly damaged or decayed felt should be replaced to
provide a sound substrate for the system.
Loose or disbonded felt must be re-bonded to the substrate. Any
blisters should be made good by star cutting and re-bonding to the
substrate. Allow to dry out before re-fixing.
Scrape away volatile asphalt surfaces and stabilise with primer.
When preparing lead surfaces for treatment, ensure all precautions
are taken to avoid skin contact, ingestion, inhalation, environmental
contamination and unsafe disposal of debris etc.
Clean out and remove debris and dirt from the gutters and water
outlets to be treated. Ensure free drainage.
Make good or repair any defective areas of lead. Any unsound
remedial repairs should be removed prior to coating.
Scrub down all surfaces to be treated, completely remove all slats,
oxidations, dirt and debris.
Lead sheets must be wet-abraded, the residues collected and the
area subsequently washed again.
The residues should be, once, collected and disposed of appropriately.
All unsound remedial repairs should be removed and made good.
All large cracks and voids should be cleaned and made good using a
suitable repair compound.
For wet or saturated substrates careful consideration should be given
to the installation of permanent roof ventilation.
Contents Section Start Next Section Page �� Page
ELASTEXPage 91
Appendix B - General Inspection & Preparation Notes
Continued
Areas where the insulation or underlying substrate has collapsed
should be cut out, repaired and reinstated to provide a good solid
base for the coating system.
At all upstands, cut a chase at least 150mm above the roof surface
into which the reinforced coating should be taken. Re-point on
completion (allow a min 2 days to cure).
Inspect all fixing bolts and tighten or replace as required. Crop all
protruding bolt heads. Mechanically abrade to remove excess
corrosion and remove debris.
Mechanically abrade any ferrous or other metal surfaces included in
the coating schedule and remove debris.
Advice on surface pre-treatment and priming of galvanised and
other non-ferrous substrates should be sought from the Company's
Technical Department.
Contents Section Start Next Section Page �� Page
ELASTEXPage 92
Please note that this is an outline proposal only and will be subject tofurther site investigation by Polyroof Products Ltd Technical Department
1.1 Overview
1.2 Preparation
Surface Preparation
Priming
1.3 Main Elastex System
Lap Bridging
Embedment Coat
Protection Coat (10 or 20 Year System)
1.4 General
Other Notes
Coverage Rate Guidelines
Thermal Performance
Falls
Guarantee Details
1.5 Appendices
Appendix A General Guidance Notes
Appendix B General Inspection & Preparation Notes
Contents Section Start Next Section Page �� Page
Galvanized Steel Gutters (Weathered)
GUIDELINE SPECIFICATION
ELASTEXPage 93
1.1 Overview
Existing Construction (Assumed)
1. Weathered Galvanized Steel Gutters
Note: Any unidentified or solar reflective coatings are subject to
adhesion tests. Please consult Polyroof Products Ltd Technical
Department for further advice.
Proposed Construction
Contents Section Start Next Section Page �� Page
METAL GUTTER1. De-bonding tape2. Elastex Fibretex3. Elastex embedment
coat and glass reinforcement
4. Elastex protection coat
5. Metal Gutter
Note: Metal gutter to bewiped with Elastex solventand metallic primed. NB: Some metals willrequire abrading*
*Do not abrade galvanised metals.
5
1
23
4
ELASTEXPage 94
1.2 Preparation
Surface Preparation
Important - Please note that the following is based on existing
weathered galvanised surfaces.
Thoroughly clean down all gutters and water outlets areas to be
treated. Remove any dirt and debris, oil and grease, surface lying
water, mould growth, moss, etc. Ensure free drainage.
Treat any areas of fungal growth or moss with Polykill “W” Anti-
Fungal Wash to ensure all spores are destroyed. Powerwash to
remove any residues.
Inspect all surfaces to assess soundness of existing substrates
including any existing coatings, repairs and any test areas.
Ensure the substrate to be treated is sound and free from defects.
Remove any existing loose or poorly adhering materials and repair
where appropriate. Repair, replace and reinstate any defective
fixtures and fittings (bolts, seals etc.).
All rust, loose and flaking materials are to be removed by wire brush
or other means and all debris removed.
Any areas of significant rusting which can not be removed should be
treated with a suitable proprietary rust converter. This should be
applied in accordance with the manufacturer’s recommendations.
Thoroughly degrease by wiping with clean Elastex TH99 solvent.
Allow to dry.
NB: For general guidance and preparation information (please refer
to appendix).
Contents Section Start Next Section Page �� Page
ELASTEXPage 95
Priming
Apply by brush or roller one coat of MC Metallic Primer to all
prepared surfaces at an approximate coverage rate of 8 - 12m2/litre.
Rough or porous surfaces will significantly reduce the coverage rate.
Allow to dry for at least 2 hours before overcoating. Overcoat within
24 hours. After this period it may be necessary to rub down and/or
re prime.
1.3 Main Elastex System
Lap Bridging
Once gutter has been fully prepared and primed insert a 25mm de-
bonding tape on the joint (1/3 on top sheet 2/3 on bottom sheet)
prior to the application of local reinforcement.
Apply by brush or roller a coat of Elastex Fibretex to all gutter joints
and bolts at an approximate coverage rate of 6 lm/litre.
The gutter joints are then to be fully reinforced with Elastex
Embedment Coat and 75mm wide Elastex Mat prior to the
application of the main system.
Contents Section Start Next Section Page �� Page
ELASTEXPage 96
Embedment Coat
Apply by brush or roller one overall coat of Elastex Embedment Coat
to the prepared surfaces at an approximate coverage rate of 1.0 -
1.33m2/Litre (0.75 - 1.0Litre/m2)** and whilst wet insert Elastex Mat
Regular glass fibre matting and thoroughly ‘wet-in’ using a short to
medium pile roller. Allow to dry before applying next coat.
Overlap adjacent reinforcement areas already laid by at least 50mm
ensuring sufficient extra embedment material is applied to these
areas. When embedding Elastex Mat into Elastex it may be necessary
to tamp the mat. Use a soft nylon brush or specialist roller ensuring
that there are no tented areas. Check for any upstanding glass fibre
strands and cut flush with surface with a sharp knife. Overcoat cut
areas. Allow to dry before applying next coat.
**Please note - rough or uneven or heavily mineralised surfaces may
significantly reduce the coverage rate - make further material
allowances where necessary. All coverage rates are indicative only
and it is the contractors’ responsibility to ascertain their own
coverage rates on site.
Protection Coat (10 or 20 Year System)
10 Year System:
Apply by brush or roller one overall coat of Elastex Protection Coat at
an approximate coverage rate of 2.0m2/litre (0.5 Litres/m2). Allow to
dry.
20 Year System:
Apply by brush or roller a first coat of Elastex Protection Coat at an
approximate coverage rate of 2.0m2/litre (0.5 Litres/m2). Allow to dry.
Apply by brush or roller a second coat of Elastex Protection Coat at an
approximate coverage rate of 2.0m2/litre (0.5 Litres/m2). Allow to dry.
Contents Section Start Next Section Page �� Page
ELASTEXPage 97
1.4 General
Other Notes
The system should not be laid when the temperature is below 5ºC or
above 30ºC.
On completion of each coat check for pinholes and misses and rectify
appropriately.
Allow at least 7 days before replacing cables etc.
Coverage Rate Guidelines
IMPORTANT: Coverage rates of all materials are indicative will vary
according to dimensions and nature of substrates. If in any doubt, it
is advised that the Contractor carries out a test patch to ascertain
coverage rates prior to commencement of the contract. Any
significant variations should be notified to the Polyroof Technical
Department immediately.
Thermal Performance
The Elastex system will not alter the thermal performance of the
gutter and any existing condensation problems will remain. Options for
improving the thermal performance of the gutter are available on
request.
Falls
This system will not alter the existing falls of the gutter. However, you
may wish to note that standing water is not detrimental to the
Elastex System.
NB: Options for improving falls are however available on request.
Guarantee Details
10 or 20 Year Manufacturers Guarantee.
Contents Section Start Next Section Page �� Page
ELASTEXPage 98
1.5 Appendices
Appendix A - General Guidance Notes
Inspect roofing substrate to ensure suitability for coating.
Previously coated areas must be carefully checked to ensure integrity
and adhesion to the substrate.
Ensure by adhesion tests that the proposed coating system is fully
compatible with existing surfaces.
Testing should include determining the necessity/selection of a primer.
Check building for visible structural defects which may adversely
affect the stability of the roof.
All roof surfaces to be treated must be sound, dry and completely
free from all contaminants.
Inspect all roof fittings, i.e. trims, flashings, cappings, etc. Make
good all defective areas (renew if necessary) prior to coating.
Inspect all old remedial repairs, patches, cracks etc. Make good
where necessary. (remove unsound repairs) prior to coating.
Where air intake units of air conditioning/ventilation systems are
present, the client and coatings manufacturer should be consulted to
take any steps necessary to prevent entry of solvent vapours (where
applicable).
Inspect all upstands, vents and any other protrusions. Make good or
replace prior to coating.
Do not remove, or suspend cables, lightning conductors, wires, etc.,
without due authorisation. Lightning conductors should not be
coated under any circumstances. Other items should not be coated
unless agreed.
Before work commences ensure all health & safety data sheets are
read and understood.
Contents Section Start Next Section Page �� Page
ELASTEXPage 99
Appendix A - General Guidance Notes Continued
No provision has been made to alter roof falls (standing water is not
detrimental).
Coverage rates of all materials will vary according to dimensions and
nature of substrates.
On completion of all coating activity, dispose of all empty material
cans, material contaminated tools, overalls and site waste in
accordance with the relevant environmental regulations.
Completely clear site including scaffolding, etc.
All work should be carried out in a safe and tidy manner. Relevant
Health & safety/COSHH regulations should be observed at all times.
Note, The system should not be applied if the air or surface
temperature is outside the range of 5ºC - 30ºC; in damp or cold
conditions which could cause surface condensation; during frost or if
there is a risk of rain.
Contents Section Start Next Section Page �� Page
ELASTEXPage 100
Appendix B - General Inspection & Preparation Notes
Inspect all surfaces to assess soundness of existing substrates and
coatings, and any test areas, to verify compatibility and proposed
coating system to assess the need for priming.
Thoroughly clean down all areas to be treated, removing all loose
chippings, dirt and debris, surface lying water, mould growth, moss, etc.
Embedded chippings should be removed by a mechanical scabbling
device or other means as necessary. Ensure the roof is able to carry
the weight of any equipment.
After cleaning down, treat all areas of fungal growth or moss with
Polykill “W” Anti-Fungal Wash to ensure all spores are destroyed.
Remove all residues.
Any spalled, loose, unsound brickwork or concrete should be broken
out and repaired using a suitable repair mortar.
All screeds, concrete surfaces and repair areas to be treated should
be lightly abraded with suitable equipment (e.g. vacu-blast, diamond
disc grind etc) to remove all laitance and other contamination to
provide a clean, dry and open surface.
Special attention should be given to solar reflective (especially
aluminium pigmented) coatings.
Adhesion tests may be required for these areas.
Remove all loose, suspect and friable materials, cutting back to a
sound firm edge. Prepare all surfaces to a clean, dry and sound
condition to promote satisfactory adhesion, if necessary removing
existing coatings and test patches.
Any blow holes in asphalt are to be smoothed out or removed and
levelled off using a suitable repair compound, i.e. sand cement mix
with a suitable hardener. Allow repairs to cure prior to priming.
Contents Section Start Next Section Page �� Page
ELASTEXPage 101
Appendix B - General Inspection & Preparation Notes
Continued
Areas of badly damaged or decayed felt should be replaced to
provide a sound substrate for the system.
Loose or disbonded felt must be re-bonded to the substrate. Any
blisters should be made good by star cutting and re-bonding to the
substrate. Allow to dry out before re-fixing.
Scrape away volatile asphalt surfaces and stabilise with primer.
When preparing lead surfaces for treatment, ensure all precautions
are taken to avoid skin contact, ingestion, inhalation, environmental
contamination and unsafe disposal of debris etc.
Clean out and remove debris and dirt from the gutters and water
outlets to be treated. Ensure free drainage.
Make good or repair any defective areas of lead. Any unsound
remedial repairs should be removed prior to coating.
Scrub down all surfaces to be treated, completely remove all slats,
oxidations, dirt and debris.
Lead sheets must be wet-abraded, the residues collected and the
area subsequently washed again.
The residues should be, once, collected and disposed of appropriately.
All unsound remedial repairs should be removed and made good.
All large cracks and voids should be cleaned and made good using a
suitable repair compound.
For wet or saturated substrates careful consideration should be given
to the installation of permanent roof ventilation.
Areas where the insulation or underlying substrate has collapsed
should be cut out, repaired and reinstated to provide a good solid
base for the coating system.
Contents Section Start Next Section Page �� Page
ELASTEXPage 102
Appendix B - General Inspection & Preparation Notes
Continued
At all upstands, cut a chase at least 150mm above the roof surface
into which the reinforced coating should be taken. Re-point on
completion (allow a min 2 days to cure).
Inspect all fixing bolts and tighten or replace as required. Crop all
protruding bolt heads. Mechanically abrade to remove excess
corrosion and remove debris.
Mechanically abrade any ferrous or other metal surfaces included in
the coating schedule and remove debris.
Advice on surface pre-treatment and priming of galvanised and other
non-ferrous substrates should be sought from the Company's
Technical Department.
Contents Section Start Next Section Page �� Page
PROTECPage 103
PROTECA D V A N C E D L I Q U I D R O O F I N G S Y S T E M S
P R O D U C T I N F O R M A T I O N & D E S I G N G U I D E
Contents Section Start Next Section Page �� Page
MINERAL FINISH(OPTIONAL)
To provide anti-slip surface if required.
PROTEC RESINHighly durable and
flexible resin.
PROTEC RESINHighly durable and
flexible resin.
REINFORCEMENTReinforcing mat offers
strength plus flexibility properties.
PRIMER
EXISTING SUBSTRATE OR NEW TIMBER
A D V A N C E D L I Q U I D R O O F I N G S Y S T E M S
PROTEC
NOT THE SYSTEM YOU’RE LOOKING FOR?
Protec is part of ourrange of liquid appliedroofing systems.
If you’re not sure which isthe best system to use, referto our Product Selector or phone 0800 801 890.
RELATED BROCHURESPOLYROOF 185 (GRP System)ELASTEX (Overlay)EBS (Balconies)ROOFCOAT PLUS (Overlay)ROOFCOAT (Repairs)PRODUCT SELECTOR
C O N T E N T S
PROTEC
APPLICATIONS
DESIGN CONSIDERATIONS & PRODUCT DATA
GENERAL GUIDELINES
OPTIONAL PREFORMEDCOMPONENTS
PHYSICAL PROPERTIES
TYPICAL NBS COLD ROOF SPECIFICATION
DESIGN DETAILING
PROTECPage 104
■ COLD APPL IED ■ 10 - 20 YEAR GUARANTEE ■ SEAMLESS ■ SINGLE SYSTEM ■ MINIMAL DISRUPTION ■ COST EFFECTIVE
F O R S P E C I F I C AT I O N A D V I C E
C A L L T H E T E C H N I C A L H E L P L I N E O N
0 8 0 0 8 0 1 8 9 0
Contents Section Start Next Section Page �� Page
PROTECPage 105
■ COLD APPL IED ■ 10 - 20 YEAR GUARANTEE ■ SEAMLESS ■ SINGLE SYSTEM ■ MINIMAL DISRUPTION ■ COST EFFECTIVE
F O R S P E C I F I C AT I O N A D V I C E
C A L L T H E T E C H N I C A L H E L P L I N E O N
0 8 0 0 8 0 1 8 9 0
P R O T E C
TECHNICALLY ADVANCED OVERLAY SYSTEM
Protec is a cost-effective, single coat, fast curing polyester
overlay system that is ideal for new roofs and for
extending the life of existing roofs and gutters.
This tough membrane provides a resilient long lasting
barrier to water penetration and is resistant to UV
degradation. The toughness and flexibility of the system
easily accommodates surface movement and it is also
resistant to occasional foot traffic.
Protec is the ideal refurbishment system for any size of
roof and can be applied to a variety of roof surfaces,
including built-up felt, concrete, and asphalt. The system
can also be used in conjunction with a new timber deck,
which allows the product to be used for applications such
as new build, deck replacement, or warm roof upgrades.
It is effective on complex areas such as valley gutters,
extraction units, coping stones and parapet walls. In most
cases there is generally no stripping of the old roof, therefore
Protec is ideal for projects that require a fast solution with
minimum disruption. It is cold applied and rapidly becomes
weather resistant, providing high levels of UV protection.
Suitable for both warm and cold roofs, flexible Protec can
also withstand maintenance foot traffic, and through the
addition of various aggregates, provide an anti-slip surface.
■ For waterproofing flat roofs and gutters
■ Refurbishment or new build applications
■ Suited to large or small projects
■ Minimal disruption
■ Quickly weather resistant
■ Seamless cold liquid applied membrane
■ Durable finish
■ Choice of colours including a slate finish
■ 10, 15 or 20 Year Guarantee
PROTEC IS COLD APPLIED FOR SPEED AND SAFETY
Like all Polyroof systems, Protec is cold applied so there is
minimum disruption, without the fire and safety risks
associated with conventional systems that rely on boilers
and exposed flames. Indicative tests also show that the
system achieves FAA rating (to BS476 : Part 3).
GUARANTEES
Protec is fully backed with a manufacturer’s guarantee of
either 10, 15 or 20 years. All work is carried out by a
network of fully accredited Polyroof contractors. Polyroof
Products Limited is an ISO 9001:2000 approved company.
Contents Section Start Next Section Page �� Page
PROTECPage 106
■ COLD APPL IED ■ 10 - 20 YEAR GUARANTEE ■ SEAMLESS ■ SINGLE SYSTEM ■ MINIMAL DISRUPTION ■ COST EFFECTIVE
A P P L I C A T I O N S
PROTEC
OVERLAY APPLICATIONS
During refurbishment, care should be taken that existing
roofs have sufficient insulation and condensation control,
in accordance with correct Buildings Regulations Standards.
Advice on warm and cold roof designs can be found in
BS5250. The main types of substrates encountered in flat
& low-pitched roof refurbishment are:
Asphalt
All areas to be treated should be thoroughly cleaned and
a fungicide used if fungal growth or moss is present.
Any blistered or slumped areas of asphalt should be made
good. Should removal be required, replace with a suitable
repair compound. Allow repairs to cure prior to priming*.
Built-up Felt
Chippings should be stripped and removed from site.
All areas to be treated should be thoroughly cleaned
and a fungicide used if fungal growth or moss is present.
Areas of badly damaged or decayed felt should be
replaced to provide a sound substrate for the system.
Loose or de-bonded felt must be made good. Any
blisters should be made good by star cutting and
re-bonding to the substrate. Allow to dry out before
re-fixing. Apply primer*.
Liquid applied Polyesters and GRP
Thoroughly clean down all areas to be treated. Wipe
surfaces using Acetone.
Other Surfaces
Consult Polyroof Products Technical Department for advice.
GUTTER REFURBISHMENT APPLICATIONS
Protec is the ideal seamless membrane to line existing
concrete or timber box and valley gutters due to its
flexibility and resistance to standing water.
Concrete Gutters (Finlock)
Clean out and remove debris and dirt from the gutters and
water outlets to be treated, and ensure free drainage.
Remove any existing, loose or poorly adhering materials
and repair where appropriate and then treat with a
fungicidal wash* to kill off any moss or fungal spores left
in the gutters. Remove all residues and apply Primer*.
NEW BUILD APPLICATIONS
New build applications must be carried out in accordance
with current Building Regulations Standards and may be a
Warm Roof, Cold Roof or Inverted Roof design.
Timber Deck
A new timber deck is to be provided to BS 5268-2:2002
(EN13986 Structural 2+). Typical example is 18mm
finnforest Plywood Spruce Grade II/III. Boards to be
staggered (brick pattern) with long edges 90° to joists,
with 3mm gaps between boards and 20mm at wall
abutments. End joints to be centred over joists. Roofs in
excess of 100m2 require a specification from the Polyroof
technical department. New structural deck to be
mechanically fixed to a sound structure using appropriate
corrosion resistant timber, masonry or metal fixings.
Fixing heads must always be countersunk into the decking.
Apply primer*.
Inverted Roofs. New Concrete/Screed
All smooth concrete surfaces should be lightly abraded
with suitable equipment where necessary to remove
laitence and/or remove any other impervious matter,
concrete curing membranes etc., until a dry and open
surface is attained.
For newly laid concrete/screed, following general
guidelines allowing a curing time of 28 days or 1 week per
25mm. In the case of polymer modified screed, refer to
manufacturers instructions. Apply primer*.
*Consult Overlays Manual. Tel: 0800 801 890 or visit www.polyroof.co.uk
Call or email forInverted, Warm or Green Roof specifications
Contents Section Start Next Section Page �� Page
PROTECPage 107
■ COLD APPL IED ■ 10 - 20 YEAR GUARANTEE ■ SEAMLESS ■ SINGLE SYSTEM ■ MINIMAL DISRUPTION ■ COST EFFECTIVE
ROOF DESIGN
The design of the roof or gutter to which the Protec system is
to be applied should be in accordance with the relevant
regulations codes and good practice existing at the time of
construction. Since the Protec system is designed primarily as
an overlay membrane for existing constructions, care should be
taken to ensure that the existing construction is structurally
sound and is unaffected by problems such as condensation.
PREPARATION
This varies depending on the substrate type and the condition.
In general all areas need to be thoroughly cleaned to remove all
dirt and debris, mould growth, moss, etc. A fungicidal wash
may also be required. Any loose or flaking material must be
removed and any defective areas made good or replaced before
primer is applied. Certain metals will require abrasion or pre-
treatment, before application of the required primer. Adhesion
tests are recommended for solar reflective coatings or other
unidentified coatings or surfaces. New decks must be timber
panel to a structural grade BS 5268-2:2002 (EN13986
Structural 2+). It is strongly recommended that Polyroof
Products Technical Services are consulted at an early stage in
the design process to determine exact preparation and priming
required for any particular project.
FALLS
When applied to existing substrates no changes to falls are
usually necessary. Standing water is not detrimental to the
Protec system, but where it is seen as a problem - particularly if
the area is to be accessed - then cut to falls insulation or timber
firrings and plywood can be used. The minimum fall
recommended by the relevant British Standard code of practice
is 1 in 80, although a design fall of 1 in 40 is commonly
adopted to provide a construction tolerance. These guidelines
also apply to new builds.
PROTRUSIONS
The system can be moulded to suit penetrations such as soil
pipes, stanchions or machinery fixing positions.
EXPANSION AND CONTRACTION
Protec laid in accordance with specifications, will withstand
normal building movement.
PRE-CONTRACT APPROVAL
Roof specifications over 100m2 require approval from Polyroof
Technical Services before the contract begins.
WALKWAYS / TRAFFIC
Protec is available with a slip resistant finish that is suitable for
light maintenance foot traffic. Please note that, although the
surface finish is slip resistant, it cannot possibly eliminate all risk
of slipping. This is particularly relevant in the event of ice forming
on the roof surface. If regular foot traffic is a requirement,
please consult Polyroof Products for advice on additional surface
protection or details of our specialist balcony / walkway systems.
DRAINAGE
Advice on roof drainage is given in code of practice BS.6367.
Protec is compatible with most standard rainwater outlets.
PROPERTIES IN RELATION TO FIRE
Indicative tests show that the system achieves EXT FAA in
accordance with BS476 Part 3.
WEATHERTIGHTNESS
Test data confirms that the system will adequately resist the
passage of moisture to the inside of the building and so meet
the requirements of the National Building Regulations.
RESISTANCE TO WIND UPLIFT
Protec is a fully bonded system. Resistance to wind uplift is
adequate to meet the effects of likely wind suction.
DURABILITY
The Protec System has a minimum durability rating of 20 years.
STANDARDS COMPLIANCE
Systems and components are produced to ISO 9001:2000
quality standards.
COLOUR
Protec is available in three standard colours.
Non-standard colours are available on request.
D E S I G N C O N S I D E R A T I O N S
P R O D U C T D A T A
Due to limitations in the colour
printing process these colours
should be taken as a guide only.
Sample plaques of the actual
colours are available on request.
Dark Grey
Mid Grey
Light Grey
F O R S P E C I F I C AT I O N A D V I C E
C A L L T H E T E C H N I C A L H E L P L I N E O N
0 8 0 0 8 0 1 8 9 0
Contents Section Start Next Section Page �� Page
PROTECPage 108
■ COLD APPL IED ■ 10 - 20 YEAR GUARANTEE ■ SEAMLESS ■ SINGLE SYSTEM ■ MINIMAL DISRUPTION ■ COST EFFECTIVE
PROTEC
G E N E R A L G U I D E L I N E S
PROTEC
OVERLAY SYSTEMS
Overlay systems offer an alternative to the complete
replacement of existing flat roofs, as they minimise
disruption and in most cases keep the building fully
operational during the refurbishment.
An overlay system is usually considered when the existing
roof covering is showing early signs of breakdown: e.g. a
felt roof where bubbles or blisters are starting to appear, or
a single ply or gutter installation where seams or joints are
beginning to fail. The condition of the existing roof largely
determines the required level of preparation.
Most common roof coverings can be overlaid but care
should be taken to ensure that the existing underlying
substrate is sound and of reasonable quality.
We recommend that a site survey is carried out by Polyroof
Technical Services if there is any doubt about the condition
of the substrate. Existing detailing is usually retained, but new
detailing can be integrated into the system if required.
It is advisable that, where possible, the whole area is
overlaid rather than carrying out localised repairs. This
ensures that the system is completely seamless throughout
and offers a fully guaranteed solution. Localised repairs
are, of course, possible if a short-term solution is required.
Overlay systems should not be considered a ‘cure-all’ for a
badly designed roof, care should always be taken to ensure
that any underlying problems are first addressed - such as
condensation or insufficient insulation (Poor U-Values) –
before work begins. Advice on upgrading to a warm roof
design can be obtained from Polyroof Technical Services.
DECK REPLACEMENT WORK / WARM ROOF UPGRADES
Where the existing roof decking is found to be in poor
condition, it will not be possible to use an overlay system.
The roof deck should be stripped and replaced with a
structural grade timber panel to BS 5268-2:2002 (EN13986
Structural 2+). Where the roof is over a dwelling or other
building that is heated, a warm roof upgrade may be required.
The new roof should be reconstructed to part L building
regulations standards and insulation provided accordingly
to meet required U-Values. Further advice regarding this
subject can be obtained from Polyroof Technical Services.
NEW BUILD
Protec may be used in new build situations for new timber
decks or concrete inverted roofs. Timber decks must be
provided to BS 5268-2:2002 (EN13986 Structural 2+).
The new roof should also meet the thermal performance
requirements of current building regulations.
Further advice and specification information regarding new
build work may be obtained from Polyroof Products
Technical Services.
1 2 3
TYPICAL BUILD-UP
1 2 3 4 5
INSULATED DECK
1 Existing substrate made goodto form VCL or new metal lined felt VCL
2 Rigid urethane insulation core
3 Felt prepared/primed
4 Mat reinforcement
5 Protec system
1 2 3 4
TIMBER PANEL SUBSTRATE
1 Timber joist 3 Mat reinforcement
2 Prepared/primed 4 Protec system
Plywood
1 Existing prepared /primed substrate 3 Protec system
2 Mat reinforcement
Contents Section Start Next Section Page �� Page
PROTECPage 109
■ COLD APPL IED ■ 10 - 20 YEAR GUARANTEE ■ SEAMLESS ■ SINGLE SYSTEM ■ MINIMAL DISRUPTION ■ COST EFFECTIVE
F O R S P E C I F I C AT I O N A D V I C E
C A L L T H E T E C H N I C A L H E L P L I N E O N
0 8 0 0 8 0 1 8 9 0
The Polyroof range of rigid GRP trims offers a fast, reliable way of
installing finishing trims and ensuring perfect detailing. These trims are
optional as, in many cases, the existing detailing can be retained. A
wide range of non standard profiles exists. Consult Polyroof with your
specific requirements.
Polyroof pre-formed GRP Trims have a nominal thickness of 2.15mm
and are supplied in 2.44Im lengths. NB. Drawings are not to scale.
110mm
Butt strap required
Available in lengths:100mm125mm175mm
Butt strap required
Available in lengths:75mm100mm150mm
UPSTAND FASCIA TRIMS
Butt strap not required
Available in lengths:150mm250mm350mm400mm
Butt strap not required
Available in 300mm lengths:
FILLET TRIM
100mm
DRIP TRIMS
FLAT TRIMS
75mm
300mm
P H Y S I C A L P R O P E R T I E SO P T I O N A L P R E - F O R M E DC O M P O N E N T S
C O M P O S I T E
TEST UNITS METHODMEANRESULT
Thickness 1.5mm
Tensile strength 58 (MPa) (Nmm-2) (ISO 3268)
Elongation 1.7% (ISO 3268)
LOI 24.1% 02 (ISO 4589)
Hardness 67 (Shore A)
L I Q U I D R E S I N
TEST UNITS METHODMEANRESULT
Specific Gravity 1.32 (ISO 2811)
Viscosity 200 mPa.s (ISO 3219)
Thixotropic Index 4.2 (ISO 9219)
Gel Time (25ºc) 13.5 mins (BS 2782.835c)
P R O T E C T E S T D A T A
STANDARDMETHODTEST
C A S T R E S I N
TEST UNITS METHODMEANRESULT
Tensile strength 7.0 N/mm2 (ISO R527)
Tensile Modulus 2.1 N/mm2 (ISO R527)
Elongation 70% (ISO R527)
ANSI/UL 790PU Foam Class A
Fire Tests DensDeck Prime Class A
ASTM E108-06PU Foam Class ADensDeck Prime Class A
FM Calorimeter Test Class 1
Wind Uplift FM Test Up to Class 1-990
Foot Traffic FM TestPU Foam (91kg) Pass
Hail Damage FM TestPU Foam Pass(0.4kg from 5.4m)
Concrete Pass(0.4kg from 5.4m)
Water FM Test
Leakage 150mm head of water Pass7 days (After 1000 hrs accelerated weathering)
Contents Section Start Next Section Page �� Page
PROTECPage 110
■ COLD APPL IED ■ 10 - 20 YEAR GUARANTEE ■ SEAMLESS ■ SINGLE SYSTEM ■ MINIMAL DISRUPTION ■ COST EFFECTIVE
T Y P I C A L L I Q U I D S U P P L I E D C O L D R O O F C O A T I N G S P E C I F I C A T I O N
T Y P I C A L N B S S P E C I F I C A T I O N F O R O V E R L AY O F B U I LT- U P F E LT R O O F
DRAWING REFERENCE(S):
N/A
BASE (SUBSTRATE FOR COATING):
Built up Felt.
PREPARATION:
It is advised that the Polyroof contractor consults Polyroof Technical
Department (0800) 801890 for advice on detailing and preparation prior
to commencement of contract.
IMPORTANT - if any areas of aluminium solar reflective paint or
unidentified coatings are present, adhesion tests may be required.
Make good existing felt.
Star cut blisters, dry out and re-bond. Cut back to base badly cracked and
defective areas of felt where instructed. Dry out base and patch level with
existing surface with layers of matching felt lapped not less than 100 mm
onto existing felt.
Where required, use biocidal wash.
After cleaning down and making good existing coverings, apply a biocidal
solution recommended by coating manufacturer to all areas previously
subject to organic growth. Allow to dry.
Powerwash roof areas.
To provide a contamination free surface for coating application, clean all
areas using a water jet and allow to dry.
WATERPROOF COATING:
Liquid Applied Polyester Overlay System.
MANUFACTURER:
Polyroof Products Ltd. Furness House,
Castle Park Industrial Estate, Flint,
Flintshire CH6 5XA
Tel: 01352 735135
Fax: 01352 735 182
Email: [email protected]
Web: www.polyroof.co.uk
PRIMER REFERENCE:
Polyroof Uni-Primer.
COATING SYSTEM REFERENCE:
Polyroof Protec System.
APPLICATION:
Laid by Polyroof Approved Contractor in accordance with Polyroof Products
Ltd Instructions.
Coverage Rates below are indicative and will depend on porosity / surface
roughness. Contractors should visit site to ascertain coverage rates –
consult Polyroof Products Technical Services for advice (0800) 801890.
Protec Resin: 1.8 - 2.0 litres/m2 (0.55 - 0.63m2/litre)
Protec System must be fully reinforced using Protec Mat reinforcement.
REINFORCEMENT:
Protec Mat Reinforcement.
MINIMUM DRY FILM THICKNESS:
> 1.5mm
SURFACE PROTECTION:
Maintenance Foot Traffic
No additional surface protection required, however a slip resistant finish
can be applied (consult Polyroof Technical Department for advice).
Regular Foot Traffic
Consult Polyroof Technical Department for details on protection or
alternative Polyroof systems.
ACCESSORIES:
Polyroof Pre-formed GRP Trims (if required).
F O R S P E C I F I C AT I O N A D V I C E C A L L T H E T E C H N I C A L H E L P L I N E O N 0 8 0 0 8 0 1 8 9 0
Call or email for Inverted, Warm or Green Roof specifications
Contents Section Start Next Section Page �� Page
PROTECPage 111
■ COLD APPL IED ■ 10 - 20 YEAR GUARANTEE ■ SEAMLESS ■ SINGLE SYSTEM ■ MINIMAL DISRUPTION ■ COST EFFECTIVE
F O R S P E C I F I C AT I O N A D V I C E
C A L L T H E T E C H N I C A L H E L P L I N E O N
0 8 0 0 8 0 1 8 9 0
D E S I G N D E T A I L I N G
PIPE DETAILALUMINIUM TRIM DETAILING
RAINWATER OUTLET1. Existing substrate2. Reinforcement3. Protec membrane4. Rainwater outlet
Note: The Protec systemshould be dressed intothe outlet as far practicable.
1. Existing substrate2. Reinforcement3. Protec membrane4. Aluminium trim5. Protec reinforced
at joints
Note: Aluminium trimsto be wiped with Protecsurface rejuvenaterabraded and metallicprimed. NB. System to be doubletaped at trim joints.
ROOF-LIGHT UPSTAND
1
1
2
2
3
34
5
4
1. Existing substrate2. Reinforcement3. Protec membrane4. Roof-light
Note: On new build it is preferable to useproprietary roof lightsincorporating a GRPupstand whereverpossible. GRP upstand tobe abraded prior tolaminating direct.
1. Existing substrate2. Reinforcement3. Protec membrane4. Additional
reinforcement5. Weathering
flange/seal
Note: A flashing detailshould be created with aweathering flange/seal.
4
4
5
3
3
2
2
1
1
WELTED DRIP1. Existing substrate2. Reinforcement3. Protec membrane4. Welted drip
Note: Alternatively, if drip is in poorcondition this may bereplaced with a Polyroof GRP trim.
1
2
4
3
CONCRETE FINLOCK GUTTER1. Additional
reinforcement to joints
2. Reinforcement3. Protec membrane4. Concrete Gutter
Note: Refer topreparation notes on page 4.
1
2
3
4
Contents Section Start Next Section Page �� Page
PROTECPage 112
A NATIONWIDE NETWORK OF COMPANY TRAINED TECHNICIANSPolyroof is only supplied to and installed by contractors fully application trained and licensedby the company, to ensure consistent quality of installation. Contractors’ performance is regularly monitored and random inspection of installations carried out. Failure to complywith the Company’s stringent standards leads to withdrawal of certification.
QUALITY CONTROLPolyroof Products Ltd operates comprehensive and rigorous quality control procedures in accordance with ISO 9001:2000
The scope of this approval includes the design and installation of roofing systems, the provision of technical support, as well as the appointment and monitoring of installers.
Not only is the manufacture of Polyroof liquid applied roofing systems and accessories quality approved, but so too is the procurement, storage and supply of all related materials and consumables.
GUARANTEESManufacturer’s guarantees are available for 10 - 20 years, subject to specification. Insurance backing available, please call 0800 801 890 for details.
Nothing in this specification brochure or any other marketing literature produced by or on behalf of Polyroof Products Limitedis to be regarded as constituting a contract binding in law between Polyroof Products Limited and any customer.
The only contract which Polyroof will enter into with the customer is that contained in the Guarantees, the details of whichare available on request. This Guarantee is in the form of a written guarantee which takes effect only when issued in writingby Polyroof to the customer at the request of the Contractor.
POLYROOF PRODUCTS LTD
FURNESS HOUSE
CASTLE PARK INDUSTRIAL ESTATE
FL INT FL INTSHIRE
CH6 5XA
Tel : 01352 735 135
Fax: 01352 735 182
Emai l : technica l@polyroof .co.uk
www.polyroof .co.uk
FREEPHONEH E L P L I N E
0800 801 890
E S T. 1984
THE NATIONAL FEDERATION OFROOFING CONTRACTORS LIMITED
Associate Member
Contents Section Start Next Section Page �� Page
PROTECPage 113
Please note that this is an outline proposal only and will be subject tofurther site investigation by Polyroof Products Ltd Technical Department
1.1 Overview
1.2 Preparation
Surface Preparation
Priming
1.3 Main Protec System
Preparation
Application
Notes
1.4 General
Other Notes
Coverage Rate Guidelines
Thermal Performance
Falls
Guarantee Details
1.5 Appendices
Appendix A General Guidance Notes
Appendix B General Inspection & Preparation Notes
Contents Section Start Next Section Page �� Page
Asphalt
GUIDELINE SPECIFICATION
PROTECPage 114
1.1 Overview
Existing Construction (Assumed)
1. Asphalt
2. Existing Substrate
Note: Any unidentified coatings are subject to adhesion tests.
Proposed Construction
Contents Section Start Next Section Page �� Page
1 2 3
TYPICAL BUILD-UP
1 Existing prepared /primed substrate 3 Protec system
2 Mat reinforcement
PROTECPage 115
1.2 Preparation
Surface Preparation
Special attention should be given to any solar reflective
coatings (especially aluminium pigmented). Adhesion tests
will be required to determine if full or partial removal of the
paint will be required. Please consult Polyroof Products
Technical Department on 0800 801890.
Remove chippings from roof surface, any embedded chippings
should be removed by a mechanical scabbling device or other means
as necessary.
Ensure the roof is able to carry the weight of any equipment.
Thoroughly clean down all areas to be treated, removing dirt, debris,
surface lying water, mould growth and moss, etc.
Treat any areas of fungal growth or moss with Polykill “W” Anti-
Fungal Wash to ensure all spores are destroyed. Powerwash to
remove any residues.
Inspect all surfaces to assess soundness of existing substrates
including any existing coatings, repairs and any test areas. This is to
verify compatibility for the proposed coating system and to assess
the need for priming.
Any blow holes in asphalt are to be smoothed out or removed and
levelled off using a suitable repair compound, i.e. sand cement mix
with a suitable hardener. Allow repairs to cure prior to priming.
Contents Section Start Next Section Page �� Page
PROTECPage 116
For wet or saturated insulation or decking, careful consideration
should be given to the installation of permanent roof ventilation.
Areas where the insulation or underlying substrate has collapsed or
is defective or decayed, should be cut out, repaired and reinstated to
provide a good solid base for the coating system.
NB: For general guidance and preparation information (please refer
to appendix).
Priming
Apply by brush or roller one coat of catalysed Uni-Primer to all
prepared surfaces at an approximate coverage rate of 4-5m2/litre.
Rough or highly porous surfaces will significantly reduce the
coverage rate. Visually check that all porous surfaces are adequately
sealed. Touch-in suspect areas where necessary. Allow to dry for at
least 1 hour before overcoating.
Overcoat within 7 days. After this period it will be necessary to
solvent wipe with acetone prior to application of the system.
Temperature (ºC) Catalyst Addition %
3 -10 6
10 - 20 4
20 - 35 2
Contents Section Start Next Section Page �� Page
PROTECPage 117
1.3 Main Protec System
Product Preparation
Pigment should be added to the resin first. The pigment should be
mixed thoroughly. One standard pigment container is required for
each 10 litre container of Protec resin.
The required quantity of resin should be poured into a calibrated
bucket. The Catalyst can then be added to the pigmented resin. NB,
The minimum level of catalyst is 2% (2 measuring spoons per litre
of resin).
Temperature (ºC) Catalyst Addition %
5 -10 4
10 - 15 3
15 - 20 2.5 – 3
20 - 30 2 - 2.5
.
Contents Section Start Next Section Page �� Page
PROTECPage 118
Product Application
Local Reinforcement (Cracks/Voids, etc):
Apply de-bonding (masking) tape across all large splits/cracks. Then
locally reinforce with Protec resin and Protec Mat.
First Coat Application:
Roller apply 1st coat of Protec resin directly on to the prepared
surface to a width of approximately 1 metre. Roll out the 450 gm
chop strand matting and then apply extra resin immediately to
achieve a closed pinhole free surface. (Please note that the quantity
of resin required for embedment will vary depending on the surface
roughness and will typically vary between 1.25 and 1.5 litres/m2 -
very rough or heavily mineralised surfaces may require up to 2.0
litres/m2). Allow to cure.
Second Coat Application:
Roller apply 2nd coat of Protec resin at a coverage rate of 0.5
litres/m2. Repeat process on the next width, ensuring a 50mm lap is
achieved with the previously laid area.
Notes:
• On Horizontal surfaces, the majority of the Protec resin should
be applied to the substrate prior to embedding the mat.
• On Vertical work, care should be taken to avoid slump. The
initial application of Protec resin prior to embedding the mat
should therefore be reduced. An increased quantity will
therefore be required thereafter to achieve the required
coverage (and pinhole free surface).
• All flashing details should be completed prior to the main area.
• All matting should be laid with 50mm side laps and 50mm
end laps.
Contents Section Start Next Section Page �� Page
PROTECPage 119
1.4 General
Other Notes
The system should not be laid when the temperature is below 5 oC
or above 30ºC.
On completion of each coat check for pinholes and misses and rectify
appropriately.
Coverage Rate Guidelines
IMPORTANT: Coverage rates of all materials are indicative will vary
according to dimensions and nature of substrates. If in any doubt,
it is advised that the Contractor carries out a test patch to ascertain
coverage rates prior to commencement of the contract. Any significant
variations should be notified to the Polyroof Technical Department
immediately.
Thermal Performance
The Protec system will not alter the thermal performance of the
roof and any existing condensation problems will remain. Options
for improving the thermal performance of the roof are available
on request.
Falls
This system will not alter the existing falls of the roof. However, you
may wish to note that standing water is not detrimental to the Protec
System.
NB: Options for improving falls are however available on request.
Guarantee Details
10 Year Manufacturers Guarantee.
Contents Section Start Next Section Page �� Page
PROTECPage 120
1.5 Appendices
Appendix A - General Guidance Notes
Inspect roofing substrate to ensure suitability for coating.
Previously coated areas must be carefully checked to ensure integrity
and adhesion to the substrate.
Ensure by adhesion tests that the proposed coating system is fully
compatible with existing surfaces.
Testing should include determining the necessity/selection of a
primer.
Check building for visible structural defects which may adversely
affect the stability of the roof.
All roof surfaces to be treated must be sound, dry and completely
free from all contaminants.
Inspect all roof fittings, i.e. trims, flashings, cappings, etc. Make
good all defective areas (renew if necessary) prior to coating.
Inspect all old remedial repairs, patches, cracks etc. Make good
where necessary. (remove unsound repairs) prior to coating.
Where air intake units of air conditioning/ventilation systems are
present, the client and coatings manufacturer should be consulted to
take any steps necessary to prevent entry of solvent vapours (where
applicable).
Inspect all upstands, vents and any other protrusions. Make good or
replace prior to coating.
Do not remove, or suspend cables, lightning conductors, wires, etc.,
without due authorisation. Lightning conductors should not be
coated under any circumstances. Other items should not be coated
unless agreed.
Contents Section Start Next Section Page �� Page
PROTECPage 121
Appendix A - General Guidance Notes Continued
Before work commences ensure all health & safety data sheets are
read and understood.
No provision has been made to alter roof falls (standing water is not
detrimental).
Coverage rates of all materials will vary according to dimensions and
nature of substrates.
On completion of all coating activity, dispose of all empty material
cans, material contaminated tools, overalls and site waste in
accordance with the relevant environmental regulations.
Completely clear site including scaffolding, etc.
All work should be carried out in a safe and tidy manner. Relevant
Health & safety/COSHH regulations should be observed at all times.
Note, The system should not be applied if the air or surface
temperature is outside the range of 5ºC - 30ºC; in damp or cold
conditions which could cause surface condensation; during frost or if
there is a risk of rain.
Contents Section Start Next Section Page �� Page
PROTECPage 122
Appendix B - General Inspection & Preparation Notes
Inspect all surfaces to assess soundness of existing substrates and
coatings, and any test areas, to verify compatibility and proposed
coating system to assess the need for priming.
Thoroughly clean down all areas to be treated, removing all loose
chippings, dirt and debris, surface lying water, mould growth, moss, etc.
Embedded chippings should be removed by a mechanical scabbling
device or other means as necessary. Ensure the roof is able to carry
the weight of any equipment.
After cleaning down, treat all areas of fungal growth or moss with
Polykill “W” Anti-Fungal Wash to ensure all spores are destroyed.
Remove all residues.
Any spalled, loose, unsound brickwork or concrete should be broken
out and repaired using a suitable repair mortar.
All screeds, concrete surfaces and repair areas to be treated should
be lightly abraded with suitable equipment (e.g. vacu-blast, diamond
disc grind etc) to remove all laitance and other contamination to
provide a clean, dry and open surface.
Special attention should be given to solar reflective (especially
aluminium pigmented) coatings. Adhesion tests may be required for
these areas.
Remove all loose, suspect and friable materials, cutting back to a
sound firm edge. Prepare all surfaces to a clean, dry and sound
condition to promote satisfactory adhesion, if necessary removing
existing coatings and test patches.
Any blow holes in asphalt are to be smoothed out or removed and
levelled off using a suitable repair compound, i.e. sand cement mix
with a suitable hardener. Allow repairs to cure prior to priming.
Contents Section Start Next Section Page �� Page
PROTECPage 123
Appendix B - General Inspection & Preparation Notes
Continued
Areas of badly damaged or decayed felt should be replaced to
provide a sound substrate for the system.
Loose or disbonded felt must be re-bonded to the substrate. Any
blisters should be made good by star cutting and re-bonding to the
substrate. Allow to dry out before re-fixing.
Scrape away volatile asphalt surfaces and stabilise with primer.
When preparing lead surfaces for treatment, ensure all precautions
are taken to avoid skin contact, ingestion, inhalation, environmental
contamination and unsafe disposal of debris etc.
Clean out and remove debris and dirt from the gutters and water
outlets to be treated. Ensure free drainage.
Make good or repair any defective areas of lead. Any unsound
remedial repairs should be removed prior to coating.
Scrub down all surfaces to be treated, completely remove all slats,
oxidations, dirt and debris.
Lead sheets must be wet-abraded, the residues collected and the
area subsequently washed again.
The residues should be, once, collected and disposed of appropriately.
All unsound remedial repairs should be removed and made good.
All large cracks and voids should be cleaned and made good using a
suitable repair compound.
For wet or saturated substrates careful consideration should be given
to the installation of permanent roof ventilation.
Areas where the insulation or underlying substrate has collapsed
should be cut out, repaired and reinstated to provide a good solid
base for the coating system.
Contents Section Start Next Section Page �� Page
PROTECPage 124
Appendix B - General Inspection & Preparation Notes
Continued
At all upstands, cut a chase at least 150mm above the roof surface
into which the reinforced coating should be taken. Re-point on
completion (allow a min 2 days to cure).
Inspect all fixing bolts and tighten or replace as required. Crop all
protruding bolt heads. Mechanically abrade to remove excess
corrosion and remove debris.
Mechanically abrade any ferrous or other metal surfaces included in
the coating schedule and remove debris.
Advice on surface pre-treatment and priming of galvanised and
other non-ferrous substrates should be sought from the Company's
Technical Department.
Contents Section Start Next Section Page �� Page
PROTECPage 125
Please note that this is an outline proposal only and will be subject tofurther site investigation by Polyroof Products Ltd Technical Department
1.1 Overview
1.2 Preparation
Surface Preparation
Priming
1.3 Main Protec System
Preparation
Application
Notes
1.4 General
Other Notes
Coverage Rate Guidelines
Thermal Performance
Falls
Guarantee Details
1.5 Appendices
Appendix A General Guidance Notes
Appendix B General Inspection & Preparation Notes
Contents Section Start Next Section Page �� Page
Felt
GUIDELINE SPECIFICATION
PROTECPage 126
1.1 Overview
Existing Construction (Assumed)
1. Felt
2. Existing Substrate
Note: Any unidentified coatings are subject to adhesion tests.
Proposed Construction.
Contents Section Start Next Section Page �� Page
1 2 3
TYPICAL BUILD-UP
1 Existing prepared /primed substrate 3 Protec system
2 Mat reinforcement
PROTECPage 127
1.2 Preparation
Surface Preparation
Special attention should be given to any solar reflective
coatings (especially aluminium pigmented). Adhesion tests
will be required to determine if full or partial removal of the
paint will be required. Please consult Polyroof Products
Technical Department on 0800 801890.
Remove chippings from roof surface, any embedded chippings
should be removed by a mechanical scabbling device or other means as
necessary. Ensure the roof is able to carry the weight of any equipment.
Thoroughly clean down all areas to be treated, removing dirt, debris,
surface lying water, mould growth and moss, etc.
Treat any areas of fungal growth or moss with Polykill “W” Anti-
Fungal Wash to ensure all spores are destroyed. Powerwash to
remove any residues.
Inspect all surfaces to assess soundness of existing substrates
including any existing coatings, repairs and any test areas. This is to
verify compatibility for the proposed coating system and to assess
the need for priming.
Areas of badly damaged or decayed felt should be replaced to
provide a sound substrate for the system.
Loose or de-bonded felt must be re-bonded to the substrate. Any
blisters should be made good by star cutting and re-bonding to the
substrate. Allow to dry out before re-fixing.
For wet or saturated insulation or decking, careful consideration
should be given to the installation of permanent roof ventilation.
Areas where the insulation or underlying substrate has collapsed or
is defective or decayed, should be cut out, repaired and reinstated to
provide a good solid base for the coating system.
NB: For general guidance and preparation information (please refer
to appendix).
Contents Section Start Next Section Page �� Page
PROTECPage 128
Priming
Apply by brush or roller one coat of catalysed Uni-Primer to all
prepared surfaces at an approximate coverage rate of 4-5m2/litre.
Rough or highly porous surfaces will significantly reduce the
coverage rate. Visually check that all porous surfaces are adequately
sealed. Touch-in suspect areas where necessary. Allow to dry for at
least 1 hour before overcoating. Overcoat within 7 days. After this
period it will be necessary to solvent wipe with acetone prior to
application of the system.
Temperature (ºC) Catalyst Addition %
3 -10 6
10 - 20 4
20 - 35 2
Contents Section Start Next Section Page �� Page
PROTECPage 129
1.3 Main Protec System
Product Preparation
Pigment should be added to the resin first. The pigment should be
mixed thoroughly. One standard pigment container is required for
each 10 litre container of Protec resin.
The required quantity of resin should be poured into a calibrated
bucket. The Catalyst can then be added to the pigmented resin.
NB, The minimum level of catalyst is 2% (2 measuring spoons per
litre of resin).
Temperature (ºC) Catalyst Addition %
5 -10 4
10 - 15 3
15 - 20 2.5 – 3
20 - 30 2 - 2.5
Contents Section Start Next Section Page �� Page
PROTECPage 130
Product Application
First Coat Application:
Roller apply 1st coat of Protec resin directly on to the prepared
surface to a width of approximately 1 metre. Roll out the 450 gm
chop strand matting and then apply extra resin immediately to
achieve a closed pinhole free surface. (Please note that the quantity
of resin required for embedment will vary depending on the surface
roughness and will typically vary between 1.25 and 1.5 litres/m2 -
very rough or heavily mineralised surfaces may require up to 2.0
litres/m2). Allow to cure.
Second Coat Application:
Roller apply 2nd coat of Protec resin at a coverage rate of 0.5 litres/m2.
Repeat process on the next width, ensuring a 50mm lap is achieved
with the previously laid area.
Notes:
• On Horizontal surfaces, the majority of the Protec resin should
be applied to the substrate prior to embedding the mat.
• On Vertical work, care should be taken to avoid slump. The
initial application of Protec resin prior to embedding the mat
should therefore be reduced. An increased quantity will
therefore be required thereafter to achieve the required
coverage (and pinhole free surface).
• All flashing details should be completed prior to the main area.
• All matting should be laid with 50mm side laps and 50mm
end laps.
Contents Section Start Next Section Page �� Page
PROTECPage 131
1.4 General
Other Notes
The system should not be laid when the temperature is below 5ºC or
above 30ºC.
On completion of each coat check for pinholes and misses and rectify
appropriately.
Coverage Rate Guidelines
IMPORTANT: Coverage rates of all materials are indicative will vary
according to dimensions and nature of substrates. If in any doubt,
it is advised that the Contractor carries out a test patch to
ascertain coverage rates prior to commencement of the contract.
Any significant variations should be notified to the Polyroof Technical
Department immediately.
Thermal Performance
The Protec system will not alter the thermal performance of the
roof and any existing condensation problems will remain. Options
for improving the thermal performance of the roof are available
on request.
Falls
This system will not alter the existing falls of the roof. However, you
may wish to note that standing water is not detrimental to the Protec
System. NB: Options for improving falls are however available on
request.
Guarantee Details
10 Year Manufacturers Guarantee.
Contents Section Start Next Section Page �� Page
PROTECPage 132
1.5 Appendices
Appendix A - General Guidance Notes
Inspect roofing substrate to ensure suitability for coating.
Previously coated areas must be carefully checked to ensure integrity
and adhesion to the substrate.
Ensure by adhesion tests that the proposed coating system is fully
compatible with existing surfaces.
Testing should include determining the necessity/selection of a primer.
Check building for visible structural defects which may adversely
affect the stability of the roof.
All roof surfaces to be treated must be sound, dry and completely
free from all contaminants.
Inspect all roof fittings, i.e. trims, flashings, cappings, etc. Make
good all defective areas (renew if necessary) prior to coating.
Inspect all old remedial repairs, patches, cracks etc. Make good
where necessary. (remove unsound repairs) prior to coating.
Where air intake units of air conditioning/ventilation systems are
present, the client and coatings manufacturer should be consulted to
take any steps necessary to prevent entry of solvent vapours (where
applicable).
Inspect all upstands, vents and any other protrusions. Make good or
replace prior to coating.
Do not remove, or suspend cables, lightning conductors, wires, etc.,
without due authorisation. Lightning conductors should not be
coated under any circumstances. Other items should not be coated
unless agreed.
Before work commences ensure all health & safety data sheets are
read and understood.
Contents Section Start Next Section Page �� Page
PROTECPage 133
Appendix A - General Guidance Notes Continued
No provision has been made to alter roof falls (standing water is not
detrimental).
Coverage rates of all materials will vary according to dimensions and
nature of substrates.
On completion of all coating activity, dispose of all empty material
cans, material contaminated tools, overalls and site waste in
accordance with the relevant environmental regulations.
Completely clear site including scaffolding, etc.
All work should be carried out in a safe and tidy manner. Relevant
Health & safety/COSHH regulations should be observed at all times.
Note, The system should not be applied if the air or surface
temperature is outside the range of 5ºC - 30ºC; in damp or cold
conditions which could cause surface condensation; during frost or if
there is a risk of rain.
Contents Section Start Next Section Page �� Page
PROTECPage 134
Appendix B - General Inspection & Preparation Notes
Inspect all surfaces to assess soundness of existing substrates and
coatings, and any test areas, to verify compatibility and proposed
coating system to assess the need for priming.
Thoroughly clean down all areas to be treated, removing all loose
chippings, dirt and debris, surface lying water, mould growth, moss, etc.
Embedded chippings should be removed by a mechanical scabbling
device or other means as necessary. Ensure the roof is able to carry
the weight of any equipment.
After cleaning down, treat all areas of fungal growth or moss with
Polykill “W” Anti-Fungal Wash to ensure all spores are destroyed.
Remove all residues.
Any spalled, loose, unsound brickwork or concrete should be broken
out and repaired using a suitable repair mortar.
All screeds, concrete surfaces and repair areas to be treated should
be lightly abraded with suitable equipment (e.g. vacu-blast, diamond
disc grind etc) to remove all laitance and other contamination to
provide a clean, dry and open surface.
Special attention should be given to solar reflective (especially
aluminium pigmented) coatings.
Adhesion tests may be required for these areas.
Remove all loose, suspect and friable materials, cutting back to a
sound firm edge. Prepare all surfaces to a clean, dry and sound
condition to promote satisfactory adhesion, if necessary removing
existing coatings and test patches.
Any blow holes in asphalt are to be smoothed out or removed and
levelled off using a suitable repair compound, i.e. sand cement mix
with a suitable hardener. Allow repairs to cure prior to priming.
Contents Section Start Next Section Page �� Page
PROTECPage 135
Appendix B - General Inspection & Preparation Notes
Continued
Areas of badly damaged or decayed felt should be replaced to
provide a sound substrate for the system.
Loose or disbonded felt must be re-bonded to the substrate. Any
blisters should be made good by star cutting and re-bonding to the
substrate. Allow to dry out before re-fixing.
Scrape away volatile asphalt surfaces and stabilise with primer.
When preparing lead surfaces for treatment, ensure all precautions
are taken to avoid skin contact, ingestion, inhalation, environmental
contamination and unsafe disposal of debris etc.
Clean out and remove debris and dirt from the gutters and water
outlets to be treated. Ensure free drainage.
Make good or repair any defective areas of lead. Any unsound
remedial repairs should be removed prior to coating.
Scrub down all surfaces to be treated, completely remove all slats,
oxidations, dirt and debris.
Lead sheets must be wet-abraded, the residues collected and the
area subsequently washed again.
The residues should be, once, collected and disposed of appropriately.
All unsound remedial repairs should be removed and made good.
All large cracks and voids should be cleaned and made good using a
suitable repair compound.
For wet or saturated substrates careful consideration should be given
to the installation of permanent roof ventilation.
Areas where the insulation or underlying substrate has collapsed
should be cut out, repaired and reinstated to provide a good solid
base for the coating system.
Contents Section Start Next Section Page �� Page
PROTECPage 136
Appendix B - General Inspection & Preparation Notes
Continued
At all upstands, cut a chase at least 150mm above the roof surface
into which the reinforced coating should be taken. Re-point on
completion (allow a min 2 days to cure).
Inspect all fixing bolts and tighten or replace as required. Crop all
protruding bolt heads. Mechanically abrade to remove excess
corrosion and remove debris.
Mechanically abrade any ferrous or other metal surfaces included in
the coating schedule and remove debris.
Advice on surface pre-treatment and priming of galvanised and
other non-ferrous substrates should be sought from the Company's
Technical Department.
Contents Section Start Next Section Page �� Page
PROTECPage 137
Please note that this is an outline proposal only and will be subject tofurther site investigation by Polyroof Products Ltd Technical Department
1.1 Overview
1.2 Preparation
Surface Preparation
Priming
1.3 Main Protec System
Preparation
Application
Notes
1.4 General
Other Notes
Coverage Rate Guidelines
Thermal Performance
Falls
Guarantee Details
1.5 Appendices
Appendix A General Guidance Notes
Appendix B General Inspection & Preparation Notes
Contents Section Start Next Section Page �� Page
Concrete Deck
GUIDELINE SPECIFICATION
PROTECPage 138
1.1 Overview
Existing Construction (Assumed)
1. Concrete / Screed
Note: Any unidentified coatings are subject to adhesion tests.
Proposed Construction
Contents Section Start Next Section Page �� Page
1 2 3
TYPICAL BUILD-UP
1 Existing prepared /primed substrate 3 Protec system
2 Mat reinforcement
PROTECPage 139
1.2 Preparation
Surface Preparation
Special attention should be given to any solar reflective
coatings (especially aluminium pigmented). Adhesion tests
will be required to determine if full or partial removal of the
paint will be required. Please consult Polyroof Products
Technical Department on 0800 801890.
Thoroughly clean down all areas to be treated, removing any dirt and
debris, surface lying water, mould growth, moss, etc.
Treat any areas of fungal growth or moss with Polykill “W” Anti-
Fungal Wash to ensure all spores are destroyed. Powerwash to
remove any residues.
Inspect all surfaces to assess soundness of existing substrates
including any existing coatings, repairs and any test areas. This is to
verify compatibility for the proposed coating system and to assess
the need for priming.
All smooth concrete surfaces to be treated should be lightly abraded
with suitable equipment (e.g. vacu-blast, diamond disc grind etc)
where necessary to remove laitance and/or remove other impervious
matter, concrete curing membranes etc, until a clean, dry and open
surface is attained.
Any spalled, loose, unsound concrete or brickwork should be broken
out and repaired using a suitable repair mortar.
All large non-structural cracks and voids should be cleaned out and
made good using a suitable repair compound. The client should be
consulted and advice sought as how to best deal with structural
cracks or voids.
Wet or saturated substrates should be allowed to thoroughly dry out
before any products are applied.
Contents Section Start Next Section Page �� Page
PROTECPage 140
Note:
For newly laid concrete/screed, follow general guidelines allowing a
curing time of at least 28 days or one week per 25mm, or preferably
follow manufacturer’s instructions.
In the case of polymer modified material, refer to manufacturers
instructions.
NB: For general guidance and preparation information (please refer
to appendix).
Priming
Apply by brush or roller one coat of catalysed Uni-Primer (Wood
Concrete) to all prepared surfaces at an approximate coverage rate
of 4-5m2/litre.
Rough or highly porous surfaces will significantly reduce the
coverage rate.
Visually check that all porous surfaces are adequately sealed. Touch-
in suspect areas where necessary. Allow to dry for at least 1 hour
before overcoating. Overcoat within 7 days. After this period it will
be necessary to solvent wipe with acetone prior to application of
the system.
Temperature (ºC) Catalyst Addition %
3 -10 6
10 - 20 4
20 - 35 2
Contents Section Start Next Section Page �� Page
PROTECPage 141
1.3 Main Protec System
Product Preparation
Pigment should be added to the resin first. The pigment should be
mixed thoroughly. One standard pigment container is required for
each 10 litre container of Protec resin.
The required quantity of resin should be poured into a calibrated
bucket.
The Catalyst can then be added to the pigmented resin. NB, The
minimum level of catalyst is 2% (2 measuring spoons per litre of resin).
Temperature (ºC) Catalyst Addition %
5 -10 4
10 - 15 3
15 - 20 2.5 – 3
20 - 30 2 - 2.5
Contents Section Start Next Section Page �� Page
PROTECPage 142
Product Application
Local Reinforcement (Cracks/Voids, etc):
Apply de-bonding (masking) tape across all large splits/cracks. Then
locally reinforce with Protec resin and Protec Mat.
First Coat Application:
Roller apply 1st coat of Protec resin directly on to the prepared
surface to a width of approximately 1 metre. Roll out the 450 gm
chop strand matting and then apply extra resin immediately to
achieve a closed pinhole free surface. (Please note that the quantity
of resin required for embedment will vary depending on the surface
roughness and will typically vary between 1.25 and 1.5 litres/m2 -
very rough or heavily mineralised surfaces may require up to 2.0
litres/m2). Allow to cure.
Second Coat Application:
Roller apply 2nd coat of Protec resin at a coverage rate of 0.5 litres/m2.
Repeat process on the next width, ensuring a 50mm lap is achieved
with the previously laid area.
Notes:
• On Horizontal surfaces, the majority of the Protec resin should
be applied to the substrate prior to embedding the mat.
• On Vertical work, care should be taken to avoid slump. The
initial application of Protec resin prior to embedding the mat
should therefore be reduced. An increased quantity will
therefore be required thereafter to achieve the required
coverage (and pinhole free surface).
• All flashing details should be completed prior to the main area.
• All matting should be laid with 50mm side laps and 50mm
end laps.
Contents Section Start Next Section Page �� Page
PROTECPage 143
1.4 General
Other Notes
The system should not be laid when the temperature is below 5 oC
or above 30ºC.
On completion of each coat check for pinholes and misses and rectify
appropriately.
Coverage Rate Guidelines
IMPORTANT: Coverage rates of all materials are indicative will vary
according to dimensions and nature of substrates. If in any doubt,
it is advised that the Contractor carries out a test patch to
ascertain coverage rates prior to commencement of the contract.
Any significant variations should be notified to the Polyroof Technical
Department immediately.
Thermal Performance
The Protec system will not alter the thermal performance of the
roof and any existing condensation problems will remain. Options
for improving the thermal performance of the roof are available
on request.
Falls
This system will not alter the existing falls of the roof. However, you
may wish to note that standing water is not detrimental to the Protec
System.
NB: Options for improving falls are however available on request.
Guarantee Details
10 Year Manufacturers Guarantee.
Contents Section Start Next Section Page �� Page
PROTECPage 144
1.5 Appendices
Appendix A - General Guidance Notes
Inspect roofing substrate to ensure suitability for coating.
Previously coated areas must be carefully checked to ensure integrity
and adhesion to the substrate.
Ensure by adhesion tests that the proposed coating system is fully
compatible with existing surfaces.
Testing should include determining the necessity/selection of a primer.
Check building for visible structural defects which may adversely
affect the stability of the roof.
All roof surfaces to be treated must be sound, dry and completely
free from all contaminants.
Inspect all roof fittings, i.e. trims, flashings, cappings, etc. Make
good all defective areas (renew if necessary) prior to coating.
Inspect all old remedial repairs, patches, cracks etc. Make good
where necessary. (remove unsound repairs) prior to coating.
Where air intake units of air conditioning/ventilation systems are
present, the client and coatings manufacturer should be consulted to
take any steps necessary to prevent entry of solvent vapours (where
applicable).
Inspect all upstands, vents and any other protrusions. Make good or
replace prior to coating.
Do not remove, or suspend cables, lightning conductors, wires, etc.,
without due authorisation. Lightning conductors should not be
coated under any circumstances. Other items should not be coated
unless agreed.
Contents Section Start Next Section Page �� Page
PROTECPage 145
Appendix A - General Guidance Notes Continued
Before work commences ensure all health & safety data sheets are
read and understood.
No provision has been made to alter roof falls (standing water is not
detrimental).
Coverage rates of all materials will vary according to dimensions and
nature of substrates.
On completion of all coating activity, dispose of all empty material
cans, material contaminated tools, overalls and site waste in
accordance with the relevant environmental regulations.
Completely clear site including scaffolding, etc.
All work should be carried out in a safe and tidy manner. Relevant
Health & safety/COSHH regulations should be observed at all times.
Note, The system should not be applied if the air or surface
temperature is outside the range of 5ºC - 30ºC; in damp or cold
conditions which could cause surface condensation; during frost or if
there is a risk of rain.
Contents Section Start Next Section Page �� Page
PROTECPage 146
Appendix B - General Inspection & Preparation Notes
Inspect all surfaces to assess soundness of existing substrates and
coatings, and any test areas, to verify compatibility and proposed
coating system to assess the need for priming.
Thoroughly clean down all areas to be treated, removing all loose
chippings, dirt and debris, surface lying water, mould growth, moss, etc.
Embedded chippings should be removed by a mechanical scabbling
device or other means as necessary. Ensure the roof is able to carry
the weight of any equipment.
After cleaning down, treat all areas of fungal growth or moss with
Polykill “W” Anti-Fungal Wash to ensure all spores are destroyed.
Remove all residues.
Any spalled, loose, unsound brickwork or concrete should be broken
out and repaired using a suitable repair mortar.
All screeds, concrete surfaces and repair areas to be treated should
be lightly abraded with suitable equipment (e.g. vacu-blast, diamond
disc grind etc) to remove all laitance and other contamination to
provide a clean, dry and open surface.
Special attention should be given to solar reflective (especially
aluminium pigmented) coatings.
Adhesion tests may be required for these areas.
Remove all loose, suspect and friable materials, cutting back to a
sound firm edge. Prepare all surfaces to a clean, dry and sound
condition to promote satisfactory adhesion, if necessary removing
existing coatings and test patches.
Any blow holes in asphalt are to be smoothed out or removed and
levelled off using a suitable repair compound, i.e. sand cement mix
with a suitable hardener. Allow repairs to cure prior to priming.
Contents Section Start Next Section Page �� Page
PROTECPage 147
Appendix B - General Inspection & Preparation Notes
Continued
Areas of badly damaged or decayed felt should be replaced to
provide a sound substrate for the system.
Loose or disbonded felt must be re-bonded to the substrate. Any
blisters should be made good by star cutting and re-bonding to the
substrate. Allow to dry out before re-fixing.
Scrape away volatile asphalt surfaces and stabilise with primer.
When preparing lead surfaces for treatment, ensure all precautions
are taken to avoid skin contact, ingestion, inhalation, environmental
contamination and unsafe disposal of debris etc.
Clean out and remove debris and dirt from the gutters and water
outlets to be treated. Ensure free drainage.
Make good or repair any defective areas of lead. Any unsound
remedial repairs should be removed prior to coating.
Scrub down all surfaces to be treated, completely remove all slats,
oxidations, dirt and debris.
Lead sheets must be wet-abraded, the residues collected and the
area subsequently washed again.
The residues should be, once, collected and disposed of appropriately.
All unsound remedial repairs should be removed and made good.
All large cracks and voids should be cleaned and made good using a
suitable repair compound.
For wet or saturated substrates careful consideration should be given
to the installation of permanent roof ventilation.
Areas where the insulation or underlying substrate has collapsed
should be cut out, repaired and reinstated to provide a good solid
base for the coating system.
Contents Section Start Next Section Page �� Page
PROTECPage 148
Appendix B - General Inspection & Preparation Notes
Continued
At all upstands, cut a chase at least 150mm above the roof surface
into which the reinforced coating should be taken. Re-point on
completion (allow a min 2 days to cure).
Inspect all fixing bolts and tighten or replace as required. Crop all
protruding bolt heads. Mechanically abrade to remove excess
corrosion and remove debris.
Mechanically abrade any ferrous or other metal surfaces included in
the coating schedule and remove debris.
Advice on surface pre-treatment and priming of galvanised and
other non-ferrous substrates should be sought from the Company's
Technical Department.
Contents Section Start Next Section Page �� Page
CASE FILESPage 149
Polyroof improves the home improvement marketPolyroof Products are the country’s leading producers of liquid applied fibreglass roofing systems.
We offer tough durable, seamless roofing solutions for the domestic home improvement market:
typical applications include extensions, balconies, dormers, garage roofs and conservatories.
Polyroof 185 is applied on-site ensuring a watertight custom fit and making it the ideal solution
for bespoke conservatories. Polyroof 185 is the ideal material for lean-to and flat roofed
conservatories. The latest product developed for this market is a simulated lead roll system for
traditional flat or pitched roof profiles.
Polyroof lead roll is proving especially popular with owners of period buildings and anyone else
looking for an elegant finish which complements the character of their home, and which blends
in with roof finishes.
Polyroof also shades the conservatory, preventing overheating in the summer. It also reduces
condensation, and can incorporate insulation to reduce heat loss during the winter months.
• Attractive appearance thatcomplements roof colour
• Tough, seamless integrated finish,no joints or loose panels to worry about
• Totally waterproof and weatherproof
• Custom-installed on site by accredited contractors
• 20 year independent guarantee
• Can be designed to incorporate insulation
Benefits for conservatories:
Contents Section Start Next Section Page �� Page
CASE FILESPage 150
Polyroof 185 isn’t just for roof
refurbishments. Leading developers
specify it for new build and
regeneration projects in applications
such as balconies and porches,
dormers and flat roofs.
• Totally waterproof, maintenance- free fibreglass membrane
• Tough and impact resistant:ideal and approved for balconies
• Exclusive finish in a varietyof colours
• Insurance backed guaranteed to last at least 20 years without any maintenance
• Independent 30 year durability rating
• Installation by approved local contractors
• It can incorporate insulation
• No messy stones, leaves,moss or lichen
• Specified by local authorities and housing associations throughout the country
• Proven history: over 5 million square metres laid
The Benefits:
Above: Garage roof before and after reproofing
with Polyroof 185 - in just one day.
Above: Polyroof is the ideal product for balconies
and walkways.
Before After
Contents Section Start Next Section Page �� Page
CASE FILESPage 151
ElastexElastex is a cost effective, flexible, reinforced polyurethane refurbishment system. It provides a durable,
seamless finish to pitched and flat roofs, bonding well to most existing roof substrates including
felt, asphalt, concrete, plywood, asbestos cement, galvanised metal, lead, aluminium and GRP.
Because stripping of the old flat roof covering is not always necessary, Elastex is ideally suited to
refurbishment work in domestic, commercial and industrial applications. It is cold applied and
rapidly becomes weather resistant, providing high levels of UV protection. Suitable for both
warm and cold roof designs.
Elastex accommodates structural movements and withstands regular foot traffic without any
additional protection. Elastex is guaranteed for up to 20 years subject to the condition of the
substrate and system specifications.
Refurbishment SystemsPolyroof offer a range of overlay systems to suit the budget, the substrate or the performance
requirements of each job. Elastex, Protec, Roofcoat and Roofcoat Plus are ideal solutions for roof
refurbishments requiring rapid protection and minimum disruption.
All Polyroof refurbishment systems are cold applied for maximum safety and are designed to
adhere to almost all roof substrates with minimum preparation.
The overlay forms a strong, permanent bond with the substrate and the end result is a tough,
seamless membrane, which - subject to the condition of the substrate - can be independently
guaranteed for up to 20 years.
Elastex used to overlay mineral felt on this
complex internally pitched roof at Castle Head
field studies centre.
The rapidly deteriorating roofs of these council flats were
renovated and made fit for another 20 years thanks to a
seamless membrane of Elastex overlayed onto the existing felt.
Contents Section Start Next Section Page �� Page
CASE FILESPage 152
ProtecProtec is a cost-effective single coat, fast curing polyester
overlay system that is ideal for extending the life of existing
roofs and for rehabilitating gutters. This tough membrane
provides a resilient long lasting barrier to water penetration.
The elasticity of the system easily accommodates surface
movement and it is resistant to occasional foot traffic and
UV degradation. Protec is the ideal refurbishment system
for any size of roof and can be applied to a variety of roof
surfaces, including built-up felt, concrete, and asphalt.
RoofcoatRoofcoat is an acrylic resin based coating
with a built-in fibre reinforcement. It’s ideal
for localised, short term repair and for the
weather proofing of most roofs – regardless
of the substrate.
Roofcoat PlusRoofcoat Plus has been specially modified for
the over coating of coated and composite
sheeted pitched roofs. Roofcoat Plus bonds
well to all substrates including asbestos
sheet, Plastisol coated sheet, aluminium
coated sheet and galvanised steel sheet.
Protec being applied to a roof protrusion
ensuring a totally water-tight seal.
All joints and laps were first sealed
with Elastex before the protective
coating of Roofcoat Plus was applied.
Case study: Roofcoat Plus and ElastexRoofcoat Plus was used to overcoat the composite sheeted roof at
the factory of Brixworth Engineering. Cracks were appearing on the
surface and water was leaking through the joints, laps and skylights
of the shallow pitched roof. What was needed was a cost-effective
flexible coating that would seal and protect the entire roof surface
against further deterioration and water ingress.
Roofcoat Plus was chosen for this particular project because of its
exceptional adhesion to composite substrates. The skylights were
sealed with Transglaze and the box gutters were relined with
Elastex. Almost 400m2 of overlay coatings were applied by Polyroof
approved contractors, Dryseal of Northampton. The client can now
rest assured in the knowledge that the roof’s new watertight
membrane is guaranteed for 10 years.
Elastex is here used for the internal
box gutters at Brixworth Engineering.
Contents Section Start Next Section Page �� Page
CASE FILESPage 153
Polyroof: cold applied for lower fire risk andlower insurance costsThe UK’s roofing contractors are being hit by tremendous hikes in insurance premiums.
Contractors, including those with a faultless claims history, are facing large rises and cases have
even been reported of a tenfold increase in premiums.
One of the best ways of reducing the claims risk for potential insurers is to move away from hot
works to Polyroof cold applied liquid roofing systems. Cold applied systems substantially reduce
the risk of fire since there are no heat or flames involved in the application and, once applied,
the systems achieve an external FAA Fire Rating of BS 476 Part 3. This is the highest rating
available for roofing membranes.
The risks associated with naked flames were dramatically highlighted recently with the fire at
Center Parcs in Suffolk, attributed to hot works being carried out on a flat roof. This case in
particular made insurers, specifiers and contractors seriously re-assess the use of a high fire risk
processes that involve bitumen boilers and hot air/gas guns (typically operating at between 500º
and 800ºC): especially in public areas and other highly fire sensitive applications.
For many years Polyroof cold applied systems have been the roofing material of choice for
optimal fire safety. Examples are shown opposite and overleaf. It is also worth remembering that
not only are Polyroof cold applied systems a much safer alternative to traditional felt bitumen,
but they also give a far more durable seamless and attractive finish that is independently
guaranteed for 20 years.
The shop roof on the BP filling station forecourt (opposite) was fitted with a new roof of Polyroof
185 fibreglass roofing system. Being cold applied meant here was no need to close the busy
station during installation so no losses in petrol or retail income. It was pigmented green to
match corporate colours.
Polyroof systems are based on thermoset resins that
have been fire tested to all relevant British Standards.
Thermoset resins are inherently fire retardant and
will char rather than melt, in a fire situation.
In applications such as this chemical plant roof (above) and
filling station (left), open flames and any other potential ignition
source are forbidden. Polyroof cold applied membrane is the
ideal alternative.
Contents Section Start Next Section Page �� Page
CASE FILESPage 154
Because of the potential fire risk of hot works, many airport authorities now specify cold applied
systems. Most naked flame processes also require a special, work permit, which can be a lengthy
process for contractors. Polyroof 185 also gives a very tough, durable and seamless finish
resistant to foot traffic, which is another reason why it was specified for the viewing platform at
Dublin airport, (shown below).
• Cold applied so no heat and nonaked flames, torches or boilers
• Systems are available for complete reroofing projects (Polyroof 185) or as an overlay to existing substrates (Elastex,Protec or Roofcoat)
• Tough, waterproof, impact resistant and seamless finish:ideal for balconies and walkways
• Available in a variety of colours and finishes (e.g. lead roll effect)
• Insurance backed andguaranteed to last 20 years without any maintenance
• 30 year durability rated by the BBA (Polyroof 185)
• Can be designed to incorporate insulation
• Specified by local authorities,housing associations and private companies throughout the country
• Polyroof is the UK market leader in fibreglass roofing systems,with a proven history:over 10 million square metres have been laid since the company was established in the 1980s.
Benefits of Polyroof cold liquid applied roofing systems:
Left: Viewing platform at Dublin Airport.
Above: refurbishment to existing flat roof using a Polyroof
overlay system cold applied onto existing substrate.
Polyroof was chosen for the major refurbishment
of this swimming baths / leisure complex because
of its durable, low maintenance, quality finish and
improved fire safety.
Contents Section Start Next Section Page �� Page
CASE FILESPage 155
Lead and copper reproductionFor the look of lead and copper at a fraction of the price, Polyroof Products offer highly authentic
looking liquid-applied alternatives. A distinctive and authentic lead roll finish for new build as
well as renovation work can be achieved using Polyroof 185. Attractive, tough and maintenance-
free, the Polyroof 185 system is guaranteed for 20 years and durability rated by the BBA for 30
years. In traditional lead colour, Polyroof 185 can be used on flat or pitched roofs and all forms
of internal guttering.
• Polyroof can be up to 40% cheaper than lead
• Polyroof is a single membrane which is totally seamless
• Polyroof is very strong and withstands heavy foot traffic
• Polyroof is highly vandal resistant
• Polyroof has no scrap value so attempted theft is futile
• Polyroof is much lighter than lead so the mechanical loading on the roof structure is greatly reduced
• Polyroof is installed via a network of fully trained and approved contractors, which means there is always someone available locally with the necessary skills - which is not always the case with lead
• Polyroof is independently guaranteed for 20 years
Although it looks remarkably like lead,Polyroof offers many distinct advantages:
Left: A Victorian style conservatory is given a Polyroof lead
roll effect roof which is in character with the property.
Above: Lead roll for commercial building.
Lead roll applied to a steeply pitched roof
Contents Section Start Next Section Page �� Page
CASE FILESPage 156
Lead roll applicationPolyroof provide a range of prefabricated
fibreglass trims and edging strips in a variety of
profiles. Special shapes and cladding sections
etc can also be prefabricated ready for on-site
installation.
The main picture (left) shows the lead-effect
flexi-resin topcoat during application onto a 30°
pitched roof. The roof has been re-boarded
using special exterior grade BCX plywood onto
which the glassfibre reinforced Polyroof 185 has
been applied, with prefabricated lead roll effect
strips bonded in.
Over-coating LeadPolyroof Products also offer systems for the over-
coating of existing lead roofs. This is an ideal solution
where you are looking to cure the leaks and restore the
looks of an authentic lead roof.
The example on the left shows a period mansion house
on the Scottish borders where, as part of a major
refurbishment project, the roof was repaired and
renovated using some 150 sq metres of Elastex
polyurethane overlay.
Elastex forms an excellent bond with most substrates and
can be applied with the minimum of surface preparation.
The aesthetic improvement over the old surface finish is
clear to see. The structure of the house, as well as the
interior, is thus being returned to its former glory.
Simulated CopperPPolyroof 185 was used on this
award winning renovation of a
derelict Victorian bandstand in
Wrexham, North Wales. The patina
of weathered copper is achieved by
using pale green pigment in the
resin. Since the roof has no scrap
value, it is no longer targeted by
vandals and will last for many
decades to come.
Contents Section Start Next Section Page �� Page
CASE FILEPage 157
A D V A N C E D L I Q U I D R O O F I N G S Y S T E M S
F L A T R O O F S O L U T I O N S F O R D E V E L O P E R S
CASE FILE
Contents Section Start Next Section Page �� Page
Regeneration & New Build
CASE FILESPage 158
The balconies of these executive townhouses have a warm
roof construction of Polyroof for maximum efficiency and
durability. The Polyroof finish is attractive as a surface finish
but it also provides a reliable waterproof substrate where
concrete pavers or ceramic tiled finishes are preferred.
Polyroof has been used to waterproof and protect the
balconies and roofs of this apartment complex in Weston-
Super- Mare. A floating timber deck was laid on top to
form a roof terrace. The system provides a long lasting
water resistant substrate that is ideal for green roofs.
Polyroof laid onto a timber deck forms an ideal,
hardwearing, nonslip surface for these apartment balconies.
These balconies for a development of executive homes
were constructed using the Polyroof system for a tough,
waterproof, anti-slip surface. Since Polyroof flexi-resins
chemically fuse to the substrate there are no laps to come
loose or coverings to tear.
Totally seamless, highly durable liquidroofing systems for flat roofs,
balconies and gutters
Full range of products and solutions
Cold applied for maximum site safety
20 year insurance-backed guarantees
30 year durability rated by the BBA
Ideal for balconies and heavy foot traffic
Attractive choice of colours and finishes
Tough: withstands neglect by onsite trades
Warm or Cold roof designs
Ideal for green roofs and inverted roof designs
B A L C O N I E S A N D W A L K W A Y S
F O R S P E C I F I C AT I O N A D V I C E C A L L T H E
T E C H N I C A L H E L P L I N E O N 0 8 0 0 8 0 1 8 9 0
Contents Section Start Next Section Page �� Page
CASE FILESPage 159
Left: Being an in-situ, liquid
applied system, Polyroof is ideal
for complex or difficult
configurations such as the bay in
this brownfield urban
regeneration and, right, this
turret roof on a new school
media block in Wales.
Above: The dormer windows of this urban regeneration
and the flat roofs of these newbuild apartment blocks
(above right) are constructed in Polyroof.
D O R M E R S A N D F L A T R O O F S
F O R S P E C I F I C AT I O N A D V I C E C A L L T H E
T E C H N I C A L H E L P L I N E O N 0 8 0 0 8 0 1 8 9 0
Right: Polyroof gives
maintenance-free
protection and an
attractive finish to the
visible internal flat roofs
of this executive
apartment complex in
Chester.
Left: Dormer windows
and mansard roof in
Polyroof used in the
regeneration of old
brewery buildings in
Oxford city centre into
upmarket apartments and
townhouses. A Polyroof
flat roof is an ideal
solution wherever ridge
height restrictions apply.
Left: Extensive use of
Polyroof for the dormers,
bays and flat roofs for
this new build
development.
Contents Section Start Next Section Page �� Page
CASE FILESPage 160
ABOUT POLYROOF
Polyroof Products Ltd is one of the country’s leading producers of liquid applied roofing system
solutions. Some five million square metres of Polyroof have been laid since the company was
first established in 1984. The systems are widely used on new build and regeneration projects
throughout the country. Polyroof systems are applied via a national network of fully trained and
approved contractors.
POLYROOF ADVANCED ROOFING SYSTEMS
Polyroof 185 is a complete seamless GRP systemthat does not crack or blister. All Polyroof
systems are cold applied so there is less on-site disruption and fewer safety considerations.
Specially developed flexiresins fuse together with glassfibre reinforcement, on a high-grade
plywood deck, to form an attractive, tough and impervious skin that accommodates normal
structural variations and regular foot traffic, while resisting site abuse or neglect by other trades.
Polyroof 185 is supplied with independent and fully transferable 20-year guarantees. Colour
options, lead roll finishes and special balcony systems and finishes are available.
The Polyroof range of overlay systems, including Elastex and Protec are ideal for overlaying all
structural substrates and offer a cost-effective alternative for developments requiring refurb and
renovation as well as new build. Manufacturers guarantees from 10 to 20 years are available
with optional insurance backing.
CLIENTS NATIONWIDE
Many leading house builders and developers specify Polyroof. Over 100 local authorities as well
as housing associations, banks, airports, breweries and many other industrial and commercial
organisations throughout the country, also testify to the quality and versatility of Polyroof
systems.
Nothing in this specification brochure or any other marketing literature produced by or on behalf of Polyroof Products Limitedis to be regarded as constituting a contract binding in law between Polyroof Products Limited and any customer.
The only contract which Polyroof will enter into with the customer is that contained in the Guarantees, the details of whichare available on request. This Guarantee is in the form of a written guarantee which takes effect only when issued in writingby Polyroof to the customer at the request of the Contractor.
POLYROOF 185
POLYROOF PRODUCTS LTD
FURNESS HOUSE
CASTLE PARK INDUSTRIAL ESTATE
FL INT FL INTSHIRE
CH6 5XA
Tel : 01352 735 135
Fax: 01352 735 182
Emai l : technica l@polyroof .co.uk
www.polyroof .co.uk
FREEPHONEH E L P L I N E
0800 801 890
E S T. 1984
THE NATIONAL FEDERATION OFROOFING CONTRACTORS LIMITED
Associate Member
Contents Section Start Next Section Page �� Page