port darlington wpcp expansion project

88
PORT DARLINGTON WPCP EXPANSION PROJECT Ryerson University Design Team: Nancy Afonso Ruston Bedasie Kirill Cheiko Andrew Iammatteo WEAO Student Design Competition

Upload: christine-thulani

Post on 30-Dec-2015

31 views

Category:

Documents


3 download

DESCRIPTION

PORT DARLINGTON WPCP EXPANSION PROJECT. WEAO Student Design Competition. Ryerson University Design Team : Nancy Afonso Ruston Bedasie Kirill Cheiko Andrew Iammatteo. Introduction. Regional Municipality of Durham has identified a need to expand the Port Darlington WPCP in two phases - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: PORT DARLINGTON WPCP EXPANSION PROJECT

PORT DARLINGTON WPCPEXPANSION PROJECT

Ryerson University Design Team: Nancy Afonso

Ruston Bedasie

Kirill Cheiko

Andrew Iammatteo

WEAO Student Design Competition

Page 2: PORT DARLINGTON WPCP EXPANSION PROJECT

2

• Objectives:

– Develop preliminary design and layout for Phase I expansion

– Conceptually design the Phase II expansion

– Adhere to design philosophy and limit usage of chemicals

Port Darlington WPCP

• Regional Municipality of Durham has identified a need to expand the Port Darlington WPCP in two phases

• Port Darlington WPCP – services the Bowmanville Urban Area

Introduction

Achieve innovation based on field proven projects, with environmental sustainability

and cost awareness always in mind. (Courtesy of Google Maps)

Page 3: PORT DARLINGTON WPCP EXPANSION PROJECT

3

Outline

• Design Basis and Challenges

• Process Selection and Facility Design:

– Headworks– Primary Treatment– Secondary Treatment– Disinfection– Solids Handling– Additional Considerations

• Process Control

• Phase I Economic Analysis

• Recommendations and Closing Remarks

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 4: PORT DARLINGTON WPCP EXPANSION PROJECT

4• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Design Basis and Challenges

Page 5: PORT DARLINGTON WPCP EXPANSION PROJECT

5

Plant Loading

• Hydraulic Loading:

ADF (m3/d) PDF (m3/d)Added

Capacity Total Plant Capacity

Added Capacity

Total Plant Capacity

Current Plant - 13,638 - 34,095

Phase I 13,638 27,276 45,005 90,010Phase II 13,201 40,477 43,563 133,574

Pollutant Annual Avg. Concentration (mg/L)BOD5 160TSS 180

Total Phosphorus 7Ammonia + Ammonium 36

TKN 54

• Pollutant Loading:

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 6: PORT DARLINGTON WPCP EXPANSION PROJECT

6

D.O = Design ObjectiveC.L = Compliance Limit

Existing Estimated Phase

I & Phase II Estimated

Existing + Phase I

D.O C.L D.O C.L D.O C.L

BOD5 (mg/L) 15 25 5 25 10 25TSS (mg/L) 15 25 5 25 10 25

Total Phosphorous (mg/L) 1 1 0.3 1 0.65 1Total Ammonia as N (mg/L)

- Summer14 N/A 10 14 12 14

Total Ammonia as N (mg/L) - Winter

14 N/A 14 24 14 24

E. Coli (org./100 mL) 100 200 100 200 100 200Total Residual Chlorine

(mg/L)0.5 N/A 0 0.2 0.25 0.2

Effluent Criteria• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 7: PORT DARLINGTON WPCP EXPANSION PROJECT

7

Design Challenges

• An alternative method of disinfection

• Nitrification

• Technologies selected must integrate into the existing plant

• Al2(SO4)3 for P removal must be reconsidered

• Phase I design and layout must take into account space limitations for Phase II

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 8: PORT DARLINGTON WPCP EXPANSION PROJECT

8• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Process Selection and Facility Design

Page 9: PORT DARLINGTON WPCP EXPANSION PROJECT

9

PFD – Phase I

Preliminary Treatment

Primary Treatment Secondary

TreatmentDisinfection

Phase I Sludge

Thickening

Existing Sludge

Stabilization

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 10: PORT DARLINGTON WPCP EXPANSION PROJECT

10

Plant Layout• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

10(Courtesy of Google Maps)

Page 11: PORT DARLINGTON WPCP EXPANSION PROJECT

11

Phase I Expansion• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

11

Page 12: PORT DARLINGTON WPCP EXPANSION PROJECT

12• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Headworks

Phase I Expansion

Page 13: PORT DARLINGTON WPCP EXPANSION PROJECT

13• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Primary Clarifiers

Phase I Expansion

Page 14: PORT DARLINGTON WPCP EXPANSION PROJECT

14• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

BNR Bioreactors

Phase I Expansion

Page 15: PORT DARLINGTON WPCP EXPANSION PROJECT

15

Secondary Clarifiers

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Phase I Expansion

Page 16: PORT DARLINGTON WPCP EXPANSION PROJECT

16• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

UV Facility

Phase I Expansion

Page 17: PORT DARLINGTON WPCP EXPANSION PROJECT

17• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Fermenter

Phase I Expansion

Page 18: PORT DARLINGTON WPCP EXPANSION PROJECT

18• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Gravity Belt Thickener

Phase I Expansion

Page 19: PORT DARLINGTON WPCP EXPANSION PROJECT

19

Hydraulic Profile• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Available head = 3.0 m

L.L.EL. 79.66 m

Outfall Pipe

L.L.EL. 76.64 m

Conduit from

Headworks

Page 20: PORT DARLINGTON WPCP EXPANSION PROJECT

20

Headworks• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Headworks

Page 21: PORT DARLINGTON WPCP EXPANSION PROJECT

21

Headworks

• Installation of two 94 kW raw sewage pumps

• Commissioning of third headworks channel

• Commissioning of aerated grit tank

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 22: PORT DARLINGTON WPCP EXPANSION PROJECT

22

Primary Treatment• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Primary Clarifiers

Page 23: PORT DARLINGTON WPCP EXPANSION PROJECT

23

• Four (4) rectangular clarifier installation

• Total Volume: 1960m3

– BOD Removal: 30%

– TSS Removal: 55%

– HRT: 3.5h @ ADF

• Chain & flight scum/sludge collection

Primary Treatment• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 24: PORT DARLINGTON WPCP EXPANSION PROJECT

24

Secondary Treatment• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

BNR Bioreactors

Page 25: PORT DARLINGTON WPCP EXPANSION PROJECT

25

Process Selection

• Activated Sludge with incorporated biological nutrient removal (BNR)

– Reduced chemical dependency

– Reliable effluent quality

– Low sludge production

• Sludge has higher levels of bioavailable nutrients

– Reduced aeration requirements

– Improved sludge settleability

– Environmentally sustainable

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 26: PORT DARLINGTON WPCP EXPANSION PROJECT

26Process Selection: WESTBANK

PR

EA

NO

XIC

AN

AE

RO

BIC

AN

OX

IC

AE

RO

BIC

Influent

Secondary Effluent

NMLR

RAS WAS

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

BNR Bioreactor Secondary Clarifier

VFAs

Page 27: PORT DARLINGTON WPCP EXPANSION PROJECT

27

Equipment Design

40%20% 40%

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

= Anaerobic = Anoxic = Aerobic

Page 28: PORT DARLINGTON WPCP EXPANSION PROJECT

28

Equipment Design

Mechanical Mixers

Fine Bubble Diffusers

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

= Anaerobic = Anoxic = Aerobic

Page 29: PORT DARLINGTON WPCP EXPANSION PROJECT

29

Equipment Design

4.8% 8% 7.8%

79.4%

Mechanical Mixers

Fine Bubble Diffusers

• Total Bioreactor Volume: 1,782m3

• SRT: 12 days• HRT: 12.5 hours @ ADF • Average MLSS: 3,000 mg/L• Required VFA concentration: 15 – 25 mg/L

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

= Anaerobic = Anoxic = Aerobic

Page 30: PORT DARLINGTON WPCP EXPANSION PROJECT

30

Secondary Treatment

Secondary Clarifiers

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 31: PORT DARLINGTON WPCP EXPANSION PROJECT

31

Secondary Clarifiers

• Based on the solids loading rate

• “Gould II” type clarifiers

• Common sludge collector between sets of two clarifiers

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 32: PORT DARLINGTON WPCP EXPANSION PROJECT

32

Disinfection• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

UV Facility

Page 33: PORT DARLINGTON WPCP EXPANSION PROJECT

33

Process Selection

• Provide additional hydraulic capacity and meet new compliance criteria

• Selection between chlorination/dechlorination and UV disinfection

• UV disinfection selected:

– Effluent toxicity and safety issues with chlorination

– Costs of two processes are becoming comparable

– UV capable of the same process reliability, performance track record, and full automatic control capability

– Minimal space requirements

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 34: PORT DARLINGTON WPCP EXPANSION PROJECT

35

• Open – channel, modular design with horizontal, LP-HI lamps

• Design Objective: 100 E.Coli/100 mL at PDF

• UV Transmittance of 65%

Design Basis• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

(Courtesy of Trojan Technologies Inc.)

Page 35: PORT DARLINGTON WPCP EXPANSION PROJECT

36

• UV Dose of 30 mW.s/cm2 using LP-HI lamps

• 3 channels constructed: 1 Duty and 1 Redundant (equipped); 1 for Phase II (channel only)

UV Facility Design• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

∆ Water Level = 0.881m

UV Banks

Automatic Level Controller

PDC and Hydraulic Manifold

48 lamps/bank

Variable output electronic ballasts

Automated quartz sleeve cleaning system

(Courtesy of Trojan Technologies Inc.)

Page 36: PORT DARLINGTON WPCP EXPANSION PROJECT

37

Solids Handling• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Fermenter

Page 37: PORT DARLINGTON WPCP EXPANSION PROJECT

38

Fermenter

• Bio-P removal requires VFAs as a source of energy

• Insufficient VFA supply during winter

• Addition of a static fermenter will accomplish two goals:– Provide a source of additional VFA’s– Increase sludge solids concentration

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 38: PORT DARLINGTON WPCP EXPANSION PROJECT

39

Fermenter Schematic• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Influent Sludge from Primary Clarifiers

Effluent Sludge to DigestersVFA Rich Supernatant to Anaerobic Zones

VFAVFAVFA

(Courtesy of www.gc3.com)

Page 39: PORT DARLINGTON WPCP EXPANSION PROJECT

40

Fermenter Design

• Design Basis:– SRT required: 3-5 days– Sludge loading: 1517 kg/d or 36.8 m3/d (PMF)

• Fermenter Design Summary:– Volume: 157 m3 (10 m diameter, 2 m tall)– Sludge solids concentration increased from 4% to

6%– Additional VFAs supplied to the BNR process:

11.2 mg/L

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 40: PORT DARLINGTON WPCP EXPANSION PROJECT

41

Solids Handling• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Gravity Belt Thickener

Page 41: PORT DARLINGTON WPCP EXPANSION PROJECT

42

Thickening

• Construction of a new digester incurs large capital investments

• Thickening can reduce the volume of sludge and allow the use of the existing digesters

• Gravity Belt Thickener– Good control capabilities– High cake solids concentration – Relatively low capital and operating costs

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 42: PORT DARLINGTON WPCP EXPANSION PROJECT

43

Gravity Belt Thickener• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

- Sludge - Separated water

Page 43: PORT DARLINGTON WPCP EXPANSION PROJECT

44

Gravity Belt Thickener

• Design Basis:– Peak solids loading: 13,784 kg/d– Peak hydraulic loading: 675 m3/d– Desired cake solids concentration: 7%

• GBT Design Summary:– Length-Width-Height: 5.1 m : 1.7m : 1.5 m– Belt width: 1.2 m– Solids capture: ~95%– Polymer Usage: 2-4 kg/tonne of sludge

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 44: PORT DARLINGTON WPCP EXPANSION PROJECT

46Additional Considerations

• Noise & odour control• Septage receiving station• Backup generator• Phase II Conceptual Design

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Courtesy of Envirocan

Phase II Conceptual Design

Phase IILiquidFacility

Page 45: PORT DARLINGTON WPCP EXPANSION PROJECT

47Phase II Conceptual Design

Phase IISolidsFacility

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 46: PORT DARLINGTON WPCP EXPANSION PROJECT

48• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Process Control

Page 47: PORT DARLINGTON WPCP EXPANSION PROJECT

49Highlights of Process Control

• Plant to be operated with minimum supervision required

• Process Control will rely on automation and plant operators

49

• Existing SCADA system is to be upgraded to include control in addition to monitoring

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

(Courtesy of Port Darlington WPCP)

Page 48: PORT DARLINGTON WPCP EXPANSION PROJECT

50

MOE Requirements

Compliance Sampling required by the MOE

(To be done by the operators)

Raw Sewage Influent

• BOD5

• TSS

• NH3 and NH4

• TP

Final Effluent

• BOD5

• TSS

• NH3 and NH4

• TP

• E. Coli

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 49: PORT DARLINGTON WPCP EXPANSION PROJECT

51

Process Control

Performance monitoring Sampling

(To be done by the operators)

1

Raw Sewage Influent

Headworks Effluent

Primary Clarifier

Secondary Clarifier

UV Influent

Final Effluent

1 2 3 4 5 6

• pH

• Temperature

• BOD5

• TSS

• TP

• NH3 and NH4

• BOD5

• TSS

• TP

• NH3 and NH4

• SVI

• MLSS

• NO2

- and

NO3

-

• TP

• E. Coli

• pH

•Temperature

• DO

• NO2

- and

NO3

-

2 3 4 5 6

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 50: PORT DARLINGTON WPCP EXPANSION PROJECT

52

Raw Sewage Influent

Headworks Primary Clarifier

BNR Reactors

Secondary Clarifier UV Influent Final

Effluent

1 2 3 4 5 6 7

• Flow-Rate

• Air flow-rate to the

Grit Chamber

• Flow-rate

• Primary Sludge

pumping

• Flow-rate

• Temp.

• MLSS

• DO

• Sludge Age

• Recycle Rate

• Ortho-Phosphorus

• WAS rate

• RAS rate

• Alum addition

(Polishing)

• UV Transmittance

• UV Intensity

• Level

• Flow-rate

•UV Dose

• Flow-rate

Automatic Monitoring and Control (SCADA)

Process Control

1 2 3 4 5 6 7

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

1 2 3 4 5 6 7

Page 51: PORT DARLINGTON WPCP EXPANSION PROJECT

53• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Phase I Economic Analysis

Page 52: PORT DARLINGTON WPCP EXPANSION PROJECT

54

Capital Investment

• Trade form with 16 Market Price Divisions

• Detailed analysis for major equipment and concrete costs

• Mark-ups, allowances and contingencies based on industry recommendations (Hussein, 2010)

• Phase I estimation: $36 M

• Accuracy within +50/-30 % for this conceptual level of design

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 53: PORT DARLINGTON WPCP EXPANSION PROJECT

55

Capital Investment

Total Project Cost = $36 M

$25.9 M

$3.2 M

$3.9 M

$3.0 MBasic Facility Cost

Engineering Services

Allowances and Contingencies

General Contractor’s Overhead & Profit

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 54: PORT DARLINGTON WPCP EXPANSION PROJECT

56

Capital Investment

$25.9 M

$3.2 M $3

.9 M

$3.0 M

Basic Facility Cost

Engineering Services

Allowances and Contingencies

General Contractor’s Overhead & Profit

$2.6 M

$7.3 M

$5.7 M

$1.6 M $2.

8 M $1.0 M

$4.9 M

Mechanical

Electrical

Conceptual Design Contingency Allowance

Retrofit/Upgrade Allowance

Concrete

Major Equipment

Other

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Total Project Cost = $36 M

Page 55: PORT DARLINGTON WPCP EXPANSION PROJECT

57

O&M Costs

Total Annual O&M Costs = $927K

Maintenance

Labour Electrical

Chemical

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

34%

17%

31%

18%

Page 56: PORT DARLINGTON WPCP EXPANSION PROJECT

58• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Recommendations and Closing Remarks

Page 57: PORT DARLINGTON WPCP EXPANSION PROJECT

59

D.O = Design ObjectiveC.L = Compliance Limit

Existing Estimated Phase

I & Phase II Estimated

Existing + Phase I

D.O C.L D.O C.L D.O C.L

BOD5 (mg/L) 15 25 5 25 10 25

TSS (mg/L) 15 25 5 25 10 25Total Phosphorous (mg/L) 1 1 0.3 1 0.65 1

Total Ammonia as N (mg/L) - Summer

14 N/A 10 14 12 14

Total Ammonia as N (mg/L) - Winter

14 N/A 14 24 14 24

E. Coli (org./100 mL) 100 200 100 200 100 200Total Residual Chlorine

(mg/L)0.5 N/A 0 0.2

Recommendations

• Implement dechlorination in existing facility

• Retrofit of existing plant to incorporate BNR

• Increase hydraulic capacity of Headworks

• Biogas capture and reuse

– OPA Feed-in Tariff program (14.7¢/kWh generated)

– Potential O&M Savings: $382 K /yr

0.25 0.2

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 58: PORT DARLINGTON WPCP EXPANSION PROJECT

60

Closing Remarks

• Phase I uses AS process with incorporated BNR and UV

• Effluent will meet more stringent compliance levels

• Economically feasible

– Total Phase I Expansion Cost: $36 M

– Annual Phase I Operating Cost: $927 K

• Environmentally Sustainable

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 59: PORT DARLINGTON WPCP EXPANSION PROJECT

61

Acknowledgements

Dr. Manual Alvarez – Cuenca, Faculty Supervisor Professor of Chemical Engineering – Ryerson University

Gisselly Anania, Consultant Advisor Associate Project Manager – CH2M Hill, Water Business Group

Jeremy KraemerAssociate Engineer – CH2M Hill, Water Business Group

Abu HusseinRegional Estimator – CH2M Hill, Canada Region

WEAO Student Design Competition Sub - Committee

Vendors: • Rob Anderson H2Flow Equipment Inc.• Edward M. Pikovnik ENV Treatment Systems Inc.• Allen Vivian, Geoff Coate Pro Aqua Inc.• Frank Ferrie ITT Water & Wastewater• Dale Jackson ACG Technology Ltd.• Darrin Hopper H2Flow Tanks & Systems Inc.• Michel Bruneau John Meunier Inc.

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 60: PORT DARLINGTON WPCP EXPANSION PROJECT

62

Questions

Page 61: PORT DARLINGTON WPCP EXPANSION PROJECT

63

Supporting Documentation

Page 62: PORT DARLINGTON WPCP EXPANSION PROJECT

64

BNR Bioreactors

Page 63: PORT DARLINGTON WPCP EXPANSION PROJECT

65Biological Nutrient Removal

65

• Anaerobic Zone

PAO

VFAs

PHB P

P Release

Energy

Page 64: PORT DARLINGTON WPCP EXPANSION PROJECT

66Biological Nutrient Removal

66

• Anoxic and Aerobic Zones

PAO

PHB

P

Energy

O2 or NO3

CO2 + H2O

Cell growth

Page 65: PORT DARLINGTON WPCP EXPANSION PROJECT

67Aerobic Zone Assumptions

• 20% of the influent TSS are considered inert

• 40% of the remaining TSS are non-biodegradable

• 10% of the influent TKN is incorporated into the heterotrophic biomass

• Heterotrophic organisms do not differentiate between forms of nitrogen in the wastewater

• Autotrophic organisms do not assimilate an appreciable amount of nitrogen

• Average sewage temperature of 15°C (minimum: 10°C; maximum 20°C)

Page 66: PORT DARLINGTON WPCP EXPANSION PROJECT

68

Parameter Symbol 15ºC 10ºC 20ºCHeterotrophic organisms

True Yield(kg VSS/kg BOD5)

Yhtrue 0.6 does not vary with temperature

Observed Yield(kg VSS/kg BOD5)

Yh-obs -- 0.38 0.33

Decay Coefficient(d-1)

bh 0.06 0.05 0.07

Autotrophic organisms

True Yield(kg VSS/kg BOD5)

Yatrue 0.15 does not vary with temperature

Observed Yield(kg VSS/kg BOD5)

Yh-obs -- 0.10 0.09

Decay Coefficient(d-1)

ba 0.05 0.04 0.06

Half-velocity constant for N(mg/NH3-N/L)

Ksn 1 does not vary with temperature

Half-velocity constant for O(mg DO/L)

Ko 0.5 does not vary with temperature

Max. growth rate(d-1)

µmax 0.47 0.29 0.77

Sizing Aerobic Zone

Page 67: PORT DARLINGTON WPCP EXPANSION PROJECT

69

Sizing Aerobic Zone

)(5 * TobsT YBODM

bSRT

YY true

Tobs *1)(

produce biomass cAutotrophi+

produced biomass hicHeterotrop+

VSS dableNonbidegra+SolidsInert =PT

MLSS

P*SRT=V C10

AER

biomass2

ionnitrificat2BOD2total2

demand) (O+

demand) (O+demand) (O=demand) (O

Page 68: PORT DARLINGTON WPCP EXPANSION PROJECT

70

• Anoxic Zone

• Anaerobic Zone

Sizing Zones

Parameter Symbol Unit Coming from Aeration tank

Nitrate in influent TKNomg/L 53.6

Nitrate in effluent Nemg/L 10

Nitrogen in cell tissue PX,biomg/L 4.35

bioX,er P-N-TKN=) Ooxidized(NNitrogen

VSS))(SDNR)(ML (V=NO ANOr

0.029+M):0.03(F=SDNR

Q*HRT=VANA

SS)0.029)(MLV+M):(0.03(F

NOV r

ANO

Page 69: PORT DARLINGTON WPCP EXPANSION PROJECT

71

Other Design

Page 70: PORT DARLINGTON WPCP EXPANSION PROJECT

72Primary Clarifier Specifications

Parameter PDF ADF

Total Volume 1960 m3

Number of clarifiers 4

Volume per clarifier 490 m3

Dimensions (Length : Width : Depth) 25.5 m : 6.3 m : 3.05 m

L:W 4

L:D 8.36

Weir Length 30 m/clarifier

Hydraulic Retention Time 1.05 h 3.45 h

Overflow Rate 70 m3/m2*d 21.2 m3/m2*d

TSS Removal (55%* Removal)1 4208 kg/d 1275.2 kg/d

BOD5 Removal (30%* Removal)2 2070.23 kg/d 627.35 kg/d

Page 71: PORT DARLINGTON WPCP EXPANSION PROJECT

73Primary Clarifier Profile

73

Page 72: PORT DARLINGTON WPCP EXPANSION PROJECT

74

Factor ValueUV Dose 30,000 mWs / m2

Channel Dimensions(Length : Width : Depth)

10 m : 0.61 m : 1.575 m

Number of Channels (equipped) 2 (1 Duty, 1 Redundant)Number of Banks/Channel 2

# of Modules/Bank 6# of Lamps/Module 8

Total # of Lamps/channel 96

Power Requirement/ChannelConnected Load = 24 kW

Average power draw (avg. flow) = 7.2 kWHydraulic Design 0.881 m of head lossLevel controller Automatic Level Controller

Guaranteed lamp life 12,000 hoursControl of UV dose delivery Yes, automatic dose pacing

Cleaning Mechanism Automatic mechanical/chemical cleaning

UV Facility Design

Page 73: PORT DARLINGTON WPCP EXPANSION PROJECT

75Sludge Stream Evaluation

75

Stream 5 Properties

Mass Flow-rate: 4970.7 kg/d

Solids Concentration: 2%

Volume Flow-rate: 243 m3

Stream 8 Properties

Mass Flow-rate: 1476 kg/d

Solids Concentration: 6%

Volume Flow-rate: 24.6 m3

Stream 9 Properties

Mass Flow-rate: 6322 kg/d

Solids Concentration: 6.7%

Volume Flow-rate: 95 m3

Desired Stream 6 PropertiesMass Flow-rate: 4970.7 kg/d

Solids Concentration: 7%

Volume Flow-rate: 70.4 m3

Thickening

Page 74: PORT DARLINGTON WPCP EXPANSION PROJECT

76Septage receiving station

76

Page 75: PORT DARLINGTON WPCP EXPANSION PROJECT

77Hydraulic Profile Equations

• Manning equation of head loss through open channels

77

• Minor head losses through pipes

Page 76: PORT DARLINGTON WPCP EXPANSION PROJECT

78

Economics

Page 77: PORT DARLINGTON WPCP EXPANSION PROJECT

79Inclusions, Assumptions and Allowances

• Equipment estimates are based on vender quotations or catalogue costs

• Major Equipment Installation Costs: 30% of delivered major equipment cost

• Major Equipment Costs: 15% allowance for equipment not included (eg: RAS, WAS, and primary sludge pipe, UV grates, etc.)

• Allowances for the 16 Market Price Divisions: see Table D1.1 (Hussein, 2010)

• Retrofit Allowance for building renovations and facilities that require significant tie-ins to existing facilities: 5% (Hussein, 2010)

• Contractors’ Markup (Overhead and Profit): 15% (Hussein, 2010)

Page 78: PORT DARLINGTON WPCP EXPANSION PROJECT

80Inclusions, Assumptions and Allowances

• Contingencies (Hussein, 2010):

– Conceptual Design Contingency Allowance: 20% (Hussein, 2010)

– Construction Contingency: 5%

– Construction Escalation and Market Contingency: 3% each of total estimated

• Engineering Services for Design and Construction Administration: 12% of total facility construction costs (Hussein, 2010)

• Concrete:

– $ 1100 / m3 (frame, concrete, rebar) (Hussein, 2010)

– Allowances (Anania, 2010):

• 7% for common channels

• 20% for galleries and tunnels

Page 79: PORT DARLINGTON WPCP EXPANSION PROJECT

81

Exclusions

• GST

• Timeline escalation contingency

• Non-competitive market conditions (i.e. shortage of materials, shortage of skilled labour)

• Additional costs if construction is accelerated

Page 80: PORT DARLINGTON WPCP EXPANSION PROJECT

82

Total Project Cost

Port Darlington WPCP Phase I Expansion - CAPITAL COST

Sub-Total Basic Facility Costs $20.09 M

Retrofit & phasing, demolition & upgrades $1.01 M

General Contractor's Overhead & Profit $3.17 M

Conceptual Design Contingency Allowance $4.85 M

Construction Contingency (Change Orders) $1.21 M

Construction Escalation $0.91 M

Market Contingency $0.91 M

Engineering Services for Design and Construction Administration

$3.86 M

Total Estimated Project Cost - Excluding GST $36 M

Page 81: PORT DARLINGTON WPCP EXPANSION PROJECT

83

Annual O&M

Port Darlington WPCP Phase I Expansion - ANNUAL O&M COST Item Units

Unit Cost

Daily Quantities

Yearly Quantities

Yearly Cost

1. Electrical Total - Electrical Costs (see Electricity Cost Table) $153,6002. Chemical - aluminum sulphate kg $1.2 669.6 244,404 $293,300 - polymer kg $6 12.2 4,453 $26,700Total - Chemical Costs $320,0003. Maintenance Total Major Equipment Cost (see Major Equipment Table) $5,746,387   % of Major Equipment Cost 5%  Total - Maintenance Costs $287,3004. Labour Full Time Operators 2 $40/hr   Total yearly hours (8 hrs/day, 5 days/week) 4160  Total - Labour Costs $166,400

Total Annual Operating Cost: $927,300

Page 82: PORT DARLINGTON WPCP EXPANSION PROJECT

84• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Process Control

Page 83: PORT DARLINGTON WPCP EXPANSION PROJECT

85Operator’s Sampling Duties

Parameter to measure

Raw Influent

Head works

Primary Clarifier

BNR Reactors

Secondary Clarifier

UV Facility

Final Effluent

Frequency

BOD Daily Monthly Monthly - - - Daily

TSS Daily Monthly Monthly - - - Daily

SVI - - - - Daily - -

pH Daily - - - - - Daily

Total Phosphorus

Daily - - - - - Daily

RAS blanket depth

- - - - Daily - -

Primary Sludge

blanket depth- - Daily - - - -

Ammonia Daily - - - - - Daily

Nitrate - - - - - - Daily

Dissolved Oxygen

- - - - - - Weekly

E. Coli - - - - Weekly - Weekly

Page 84: PORT DARLINGTON WPCP EXPANSION PROJECT

86Process Control - Solids

Performance monitoring Sampling – Solids Handling

(To be done by the operators)

1

Fermenter GBT Primary Digester

Secondary Digester

1 2 3 4 & 5

% Solids % Solids pH % Solids

VFA VSS TP

pH pH

VSS

23

4 5

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 85: PORT DARLINGTON WPCP EXPANSION PROJECT

87Process Control - Solids

Automatic Monitoring and Control – Solids Handling

(SCADA)

1

Fermenter GBT Primary Digester

Secondary Digester

1 2 3 4 & 5

Sludge Wasting Flow-Rate Level Level

Polymer Dosing Flow-rate

Temperature

Alum Dosing

23

4 5

• DESIGN BASIS AND CHALLENGES• PROCESS SELECTION AND FACILITY DESIGN• PROCESS CONTROL• ECONOMIC ANALYSIS• RECOMMENDATIONS AND CLOSING REMARKS

Page 86: PORT DARLINGTON WPCP EXPANSION PROJECT

88

Phase II Considerations

Page 87: PORT DARLINGTON WPCP EXPANSION PROJECT

89

Phase II Considerations

• New headworks facility • Four additional liquid trains (identical to Phase I)• Installation of UV equipment in 3rd chamber• Fermenter• Gravity Belt Thickener• Primary High Rate Anaerobic Digester

Page 88: PORT DARLINGTON WPCP EXPANSION PROJECT

90Implementation and Construction Schedule