Port Everglades Master Plan Update 2006Phase II WorkshopThe Board of County Commissioners ofBroward County
August 28, 2007
Port Everglades Master Plan Update 2006
August 28, 20072
Economic Impact of Port Everglades’Cargo and Cruise Activities (2006)
– Total Jobs: 188,203§ Direct (local): 10,982§ Induced (local/regional): 10,021§ Indirect (local/regional): 6,525§ Related User (statewide): 160,676
– Personal Income: $6.4 billion§ Direct (local): $394,355,000§ Induced (local/regional): $1,077,899,000§ Indirect (local/regional): $249,507,000§ Related User (statewide): $4,680,533,000
– Total Value of Economic Activities: $16.9 billion
– State and Local Taxes: $589.1 million
Port Everglades Master Plan Update 2006
August 28, 20073
Port Everglades Today
Port Everglades Master Plan Update 2006
August 28, 20074
20Year Vision Plan Presented at Workshop I
Port Everglades Master Plan Update 2006
August 28, 20075
Tenant / Stakeholder Input20Year Vision Plan
Port Everglades Master Plan Update 2006
August 28, 20076
Northport Slip Study
294’ 298’ 286’
475’475’600’
Port Everglades Master Plan Update 2006
August 28, 20077
Conservation Easement Impact Map
Port Everglades Master Plan Update 2006
August 28, 20078
Aviation Flight Surfaces Impact
– ‘
Port Everglades Master Plan Update 2006
August 28, 20079
20Year Vision Plan
NN
Port Everglades Master Plan Update 2006
August 28, 200710
5Year Vision Plan Goals
6.1 (6)1000RTG Operations501.7 (2)700RORO (wheeled)
Container Terminals
NonContainer Cargo Terminals
10001200900750
700900
650
BerthLength
(FT)
TerminalArea
(gross acres)
BerthsRequired(rounded)
6.71.4 (2)Cement7.11.1 (1)General Cargo
4.40.8 (1)Bananas (wheeled)
89
1.80.6 (1)Aggregate
3573 vessel/1 bargePetroleum Terminals648Cruise Terminals
Port Everglades Master Plan Update 2006
August 28, 200711
5Year CIP
N
Port Everglades Master Plan Update 2006
August 28, 200712
Conceptual ByPass Road
Port Everglades Master Plan Update 2006
August 28, 200713
– Northport Improvements Project Cost ($ million)• CT 2 Renovations 1.7• CT 4 Redevelopment/ Expansion 13.0• Molasses Tank Reuse RFP 0.0• Bypass Road 19.0• FTZ / Warehouse RFP 10.3• Relocate Public Works/Port Maintenance 2.0
– Midport Improvements• Midport Roadway Expansion 2.3• Berth 1617 Crane Replacement 24.0• Demo Transit Shed 16 / Reconfigure Terminal 0.8• CT 18 Redevelopment / Expansion 37.4• Midport Parking Garage 30.8• Day Cruise Pier / Terminal Relocation / Addition 17.2• CT 19 Expansion 6.7• FPL Discharge Canal Bridge 7.2• CT 21/22 Expansion 22.0
– Southport Improvements• Phase 1 Turning Notch Expansion 48.7• Southport Phase Vlll 16.5• McIntosh Loop Road 7.8• Dry Stack Marina RLI 0.0• Aggregate Terminal & Rail Yard Facility 55.0• ICTF Rail (Phase 1 for import crushed rock facility) 8.4TOTAL $330.80
5Year CIP Master Plan Project List
Port Everglades Master Plan Update 2006
August 28, 200714
– Northport Improvements
• CT 2 Renovations• CT 4 Redevelopment/ Expansion• Molasses Tank Reuse RFP• Bypass Road• FTZ / Warehouse RFP• Relocate Public Works/Port Maintenance
– Midport Improvements
• Midport Roadway Expansion• Berth 1617 Crane Replacement• Demo Transit Shed 16 / Reconfigure Terminal• CT 18 Redevelopment / Expansion• Midport Parking Garage• Day Cruise Pier / Terminal Relocation / Addition• CT 19 Expansion• FPL Discharge Canal Bridge• CT 21/22 Expansion
– Southport Improvements
• Phase 1 Turning Notch Expansion• Southport Phase Vlll• McIntosh Loop Road• Dry Stack Marina RLI
• Aggregate Terminal & Rail Yard Facility• ICTF Rail (Phase 1 for import crushed rock facility)
TOTAL
5Year CIP Master Plan Project List
Cost ($ million)
Total20122011201020092008
1.9
2.1
4.92.0
6.74.0
16.54.6
.5
.213.0
17.110.32.0
16.5
0.2
0.832.528.8
3.2
1.2
1.5
1.2
2.0
2.7
24.0
16.0
5.0
11.0
2.0
5.3
15.0
37.7
55.0
1.713.0
19.010.32.0
2.324.00.8
37.430.817.2
6.77.2
22.0
48.7
7.8
55.08.4
0.0
330.843.2 109.1 7.4 63.3 107.8
0.0 0.0
0.0
Port Everglades Master Plan Update 2006
August 28, 200715
134.3
4.2
20.8
107.8
1.5
2012
408.277.414.3123.858.4TOTAL
29.54.25.48.57.2Other Port Capital Improvements(Maintenance, Renewal and Replacement)
32.68.43.4ACOE Dredging Program
330.863.37.4109.143.2Master Plan Projects
15.31.51.52.88.0General InfrastructureImprovements
TOTAL2011201020092008
Cost ($ million)
5Year Capital Improvement Plan (CIP)Year 2008 to 2012
Funding the FiveYear Capital Improvement Plan (CIP)
$408.2 Years 2008 2012
$305.0
$234.1
$185.4
Debt Funding: $103.2
Private Investment: $70.9
Grants: $48.7
Internal Revenue:$185.4
U
G
I
P
(In $ Millions)
Port Everglades Master Plan Update 2006
August 28, 200717
2008 2009 2010 2011 2012 Total
By Existing Infrastructure 16.500 16.995 17.505 18.030 18.571 87.601
By Previous Funding 21.616 4.047 0.000 16.000 0.000 41.663
By New Project Net Revenue 0.000 0.569 6.080 12.161 12.161 30.971
By Cost Recovery 3.060 11.220 11.220 12.620 15.620 53.740
By Future Grants 2.500 2.500 2.500 2.500 10.000
Less Debt Payment (7.840) (7.840) (8.940) (8.940) (33.560)
Less Dynegy Payment (5.000)
185.415
Internal Revenue BreakdownYear 2008 to 2012
(in $ Million)
Port Everglades Master Plan Update 2006
August 28, 200718
10Year Vision Plan Goals
995.7 (6)1000RTG Operations602.1 (2)700RORO (wheeled)
Container Terminals
NonContainer Cargo Terminals
10001200900750
700900
650
BerthLength
(FT)
Terminal Area(gross acres)
BerthsRequired(rounded)
7.31.5 (2)Cement7.71.3 (1+)General Cargo
4.50.6 (1)Bananas (wheeled)
2.60.8 (1)Aggregate
3573 vessel/1 bargePetroleum Terminals648Cruise Terminals
Port Everglades Master Plan Update 2006
August 28, 200719
10Year Vision Plan
NN
Port Everglades Master Plan Update 2006
August 28, 200720
10Year Vision Plan – Master Plan Projects– Northport Terminal Improvements Project Cost ($ million)
• CT 4 Parking Garage 37• Slip 2 Expansion 90• Petroleum Barge Slip 24
– Midport Terminal Improvements• Construct Midport Cruise Intermodal Facility Phase I 80• Expand Container Terminal Area 15• Construct Berth; Fill Tracor Basin 25• Crane Procurement for Berths 2829 (four 100gage cranes) 40• Realign FPL Discharge Canal 10• Construct CT27 35• Demo CT29 1
– Southport Terminal Improvements• Phase 2 Turning Notch Expansion 60• Relocate Banana and Other General Cargoes 10• Construct ICTF Track and Storage Yard 50
TOTAL $ 477
Port Everglades Master Plan Update 2006
August 28, 200721
10Year Vision Development ProgramYear 2013 to 2016
Cost ($ million)
– General Infrastructure Improvements 20
– Master Plan Projects 477
– ACOE Dredging Program 160
– Other Port Capital Improvements 100(Maintenance, Renewal and Replacement)
________
TOTAL $757
Port Everglades Master Plan Update 2006
August 28, 200722
20Year Vision Plan Goals
892.9 (3)700RORO (wheeled)
Container Terminals
NonContainer Cargo Terminals
10001200900750
700900
650
1000
BerthLength
(FT)
Terminal Area(gross acres)
BerthsRequired(rounded)
8.31.7 (2)Cement8.81.5 (2)General Cargo
5.20.6 (1)Bananas (wheeled)
1406.8 (7)RTG Operations
4.20.9 (1)Aggregate
3573 vessel/1 bargePetroleum Terminals648Cruise Terminals
Port Everglades Master Plan Update 2006
August 28, 200723
20Year Vision Plan
NN
Port Everglades Master Plan Update 2006
August 28, 200724
20Year Vision Plan – Master Plan Projects
– Northport Improvements Project Cost ($ million)• Reconfigure Slips 1 and 3 140
– Midport Improvements• Construct Midport Cruise Passenger Skyway 80• CT 24/25 Expansion 40
– Southport Improvements• Begin RTG Terminal Conversions 30• Extend Berth 33A 20• Crane Procurement for Berth 33A 10• DCC Ro/Ro Development 50
TOTAL $370
Port Everglades Master Plan Update 2006
August 28, 200725
20Year Vision Development ProgramYear 2017 to 2026
Cost ($ million)
– General Infrastructure Improvements 20
– Master Plan Projects 370
– ACOE Dredging Program 160
– Other Port Capital Improvements 280(Maintenance, Renewal and Replacement) ________
TOTAL $830
Port Everglades Master Plan Update 2006
August 28, 200726
PROJECT DECISION MATRIXCRUSHED ROCK (AGGREGATE) FACILITY
CRUISE TERMINAL 18 EXPANSION
$44 M26%$37.4 M
NetPresentValue
ROITotalConstructionCost
15,857172,127
LowMidHighPermitRequired
LowMidHighTaxes
($1,000)
JobsTotal Income
($1,000)
Customer /Regulatory Need
Environmental ImpactEconomic Impact
x x3,844
$8.4 M13.7%$63.4 M
NetPresentValue
ROITotalConstructionCost
x6,9951,21576,035
LowMidHighPermitRequired
LowMidHighTaxesJobs
Customer /Regulatory Need
Environmental ImpactEconomic Impact
x x
Total Income
($1,000)