portfolio committee on small business...
TRANSCRIPT
Strategy for Rolling out Solar Energy Geysers
5 November 2014
Portfolio Committee on Small
Business Development
Contents
1. Overview
2. Background
3. Approach
4. Commercial Strategy
5. Localisation Strategy for NSWHP
6. Partners & Stakeholders
7. Supplier and SMME Development for NSWHP
8. Supplier And SMME Development Eskom wide
9. Summary
2
Overview
3
Solar Water Heater is a complete operating system that uses the sun to
produce hot water and comprises of collector, hot water storage tank whether
supported by supplementary energy source or not, and all necessary
interconnecting pipes and functional components.
The SWH consist of two systems:
- Low Pressure system: It uses gravity to feed the water into system
- High Pressure system: It uses direct pressure from the interconnected point
Background
• The SWH programme started in 2008, and to date approximately 400 000 units installed in residential areas.
• The funds were appropriate through NERSA, Division of Revenue Act, (DORA) & DoE.
• Over 90% of the installed SWH were imported which resulted in 2012, the Department of Trade & Industry(dti) introducing SATS 1286 to drive local content & production of SWH.
• Two Low Pressure (LP) programmes were discontinued in December 2012 and May 2013 respectively due to local content requirements.
• The High Pressure (HP) programmed is still running.
4
Approach
• There are over 270 municipalities in SA, however the 1st phase of the SWH programme will rolled-out to approximately sixty (60) municipalities as provided by DoE.
• The municipalities will select the beneficiaries of the SWH units.
• Eskom as the implementing agent will undertake the following by scopes of work: Feasibility Studies, Manufacture, Project Management Installation,
Technical Audits and Maintenance.
5
Commercial Strategy
• There is a Memorandum of Agreement (MoA) signed between Eskom and DoE guides the implementation and contracting criteria.
• An amount of R4.3 billon has been allocated for the National Solar Water Heaters programme through the Department of Energy (DoE).
• The planned demand for SWH is 350 000 units for the next 3 years until 2018, as per Medium Term Expenditure Framework.
• The dti’s South African Technical Specification (SATS) 1286 guides the appointment of manufacturers.
• The Preferential Procurement Policy Framework Act (PPPFA) will be used.
• The SABS Mark of approval documents will be the gatekeeper to ensure quality of the procured systems.
• The open tender mechanism will used for the multiple contracts placement to ensure broader participation.
6
Localisation Strategy NSWHP
Eskom’s SWH Strategy focuses on the following SMME aspects:
Skills Development
The following are proposed skills development targets for SWH:
SWH Installation
- Welders - Plumbers
- Fitters - Safety Officer
- Boiler Makers - Logistics
Job Creation
• Comparatively There are limited number of job opportunities within the manufacturing industry of SWH.
• Large number of jobs (local to site ) to be created in the installation and maintenance phase of the programme
• Approximately 3000 job opportunities will be created during the installation phase and additional 1000 during the 5 year maintenance period.
Local Manufacturing / Production
• The introduction of SATS: 1286 encourages high local production content and growing the local economy and creating jobs..
7
Partners & Stakeholders for the Contracting Framework
8
Description
1 DoE-Eskom Funding Agreement (MoA) with all the conditions imposed on Eskom as the
Implementing Agent
2 DoE-SABS
Provision of services such as technical audits, independent measurement and
verification of local content; etc.
3 Eskom-Local Manufacturers Agreement, with a duration of up to 3 years, for the supply of designation-
compliant SWH systems, signed after following a competitive bidding process,
and subject to entering into an Implementation Agreement with the DoE
4 Local Manufacturers-Installers Service Level Agreement regarding the training of successful installers by
Local Manufacturers on the installation of their SWH systems
5 DoE-Local Manufacturers Implementation Agreement which, among other things, enforces compliance
with industry designation requirements and other pre-defined economic
development objectives, with recourse (including contract termination) in the
event of breach. Most importantly Manufacturers will need to commit to a
schedule that ramps up local production taking into account their lead times
for setting up manufacturing facilities. In this regard the DoE launched a
Request for Registration and Information (RFRI) process to sound the local
market.
6 Municipalities – Eskom Memorandum of Agreement outlining roles and responsibilities
Supplier and SMME Development NSHWP
Increased SMME opportunities:
• Multiple contracts and work packages will be used as opposed to the previous turnkey approach increasing SMME opportunities.
• The expected local content on the SWH as designated by the Department of Trade and Industry has a threshold of 70% for both the storage tank and solar collector.
At least 70% of storage tank and solar collector shall be locally procured.
Contracts for both Manufacturers and Installers will be placed with local entities.
• Non-black manufactures will be require to demonstrate that 30% of black owned businesses participate in the whole value chain.
• PPPFA framework special condition : Black-owned companies for all installations.
• Manufacturing contracts to be separated from installation – this closes the import opportunity and forces local manufacture.
• The DoE will be responsible for the development black manufacturers in the SWH industry.
• Black installers will be trained by the SWH Manufacturers to become competent for the installation and maintenance phase.
• Individuals from communities will be further trained and given necessary skills and support through the incubation programme.
9
SUPPLIER AND SMME DEVELOPMENT
10
Supplier Development’s role is to increase the capacity and capability of local suppliers across Eskom’s value chain
Please note: Emphasis is on Black Owned Suppliers to accelerate transformation
Focus is on opportunities identified in Primary and Secondary Plant; Primary Energy and Capex
Source: Extract from the Supplier Development Strategy document; Team analysis
Strategic imperatives Description
Create an
enabling
environment for
new suppliers
• Identification of priority and high
impact commodities with no local
supplier (BO) presence
• Creation of an enabling
environment for the development of
new suppliers to do business with
Eskom
Develop and grow
existing emerging
suppliers
• Source EMEs and QSEs (BOs)
from the data base and through
industry analysis for development to
increase capacity and capability to
contract with Eskom in high impact
areas
Grow emerging
suppliers into
sustainable LMEs
• Ensure QSEs (BOs) are developed
and provided with sufficient,
sustainable business to become
established LMEs
• Clear linkage to priority/high
impact spend areas with a
focus on Primary Energy,
Primary and Secondary Plant
and Capex
• Thorough understanding of
supplier types, their growth
trajectories and related needs
• Strong integration and
collaboration with internal
Eskom departments
• Establishment of strategic
external partnerships
• Range of suitable
intervention mechanisms
How will this be achieved
A strong and capable localised energy supply chain will benefit Eskom, benefit local industry and benefit South Africa as a whole
Source: CSDP; IPAP2; Group Technology and Commercial
Driving economic development... Will benefit….
Enhanced
industrialisation
Localised
energy
industry
Accelerated
job
creation
Greater local
skills base
The South African economy:
• Reduced cost of doing business
• Investment in plant and
technology
• Greater export potential
• Reduced unemployment and
poverty
• Larger and more skilled
workforce
• Increased diversity in work
• Improved quality of life
Eskom operations:
• Reduced supply chain costs
• Greater security of supply
• Shorter lead times
• Improved efficiencies and quality
• Co-development of solutions for
operation specific problems with
manufacturers
Investment in
building local
communities
12
Eskom proactively drives socio-economic
development
13
Source: Eskom Group Technology and Commercial Department
Su
pp
lie
r D
eve
lop
me
nt,
Lo
ca
lis
ati
on
an
d T
ran
sfo
rma
tio
n
Te
ch
no
log
y
Strategic
Sourcing
• Drives TCO, risk & local development through
long-term sustainable spend
Tactical
Sourcing
• Looks for opportunities to maximise value from
transactional (once-off) procurement activities
Identifies opportunities to design for local to drive
development of local industry
Identifies and integrates local development opportunities into
once-off, strategic commodity and project contracts
Project
Sourcing
• Capital procurement excellence
• Incorporates technology and SD&L to drive local
industry development while maintaining the project
life cycle
Elevates tactical commodities through
standardisation and aggregation of demand
Enhances long-term view by pooling the
demand of project and strategic commodities
13
Socio-economic transformation pillars
B-BBEE
NGP
NDP
Programmes
ASGI-SA
NIPF
IPAP
CSDP
NIPP
Skills
Develo
pm
en
t
Development objectives
Jo
b c
reatio
n
Lo
calis
atio
n
Ind
ustria
lisatio
n
Source: Introduction to the Competitive Supplier Development Programme; B-BBEE Act 53 of 2003; ESKADAAT6
• All of this is underpinned by getting previously disadvantaged into the
mainstream and fighting inequalities, poverty and unemployment
Su
pp
lier/E
nte
rpris
e
Develo
pm
en
t
PPPFA
Op
era
tio
na
l
Priority focus
areas
▪ Boiler Maintenance
▪ Primary Energy
▪ Cables and Conductors
▪ Metering
▪ Valves
▪ Protection Schemes
▪ Grinding Elements
▪ Pumps
▪ ICT
▪ Vessel (Containers)
▪ Generators
▪ Switchgear
▪ Generation Spares
▪ Fabric Filter Bags
▪ Transformers
▪ Turbines
▪ Control systems
▪ Ash & Stockpile Handling
▪ Pipes
▪ Rotors
▪ Conveyor
▪ Tubes
▪ Air Heater Pack
▪ Economiser
▪ Capacitor Bank
▪ DC Equipment
▪ MV Motors
▪ CSP
▪ Solar PV
▪ Wind
▪ Gas CCGT
▪ Nuclear New Build
▪ Tx Line Construction
▪ Biomass
▪ Network Strengthening
▪ Substation construction
and refurbishing
▪ Koeberg Nuclear
▪ Electrification of homes
▪ Civil Construction
▪ Fabric Filter Plant
Retrofit
▪ Steel
▪ Building and Build
maintenance
42 operational and project spend focus areas making up ~89% of our procurement spend
Pro
jec
ts a
nd
New
Bu
ild
IR
P2
01
0
Source: Eskom SD&L Plan and Analysis
Other
Total
Spend
42 Focus
Areas
Total forecasted 5
year spend, R’billion
Provide a platform for sustained demand
through our operational and project spend
15
Acceleration socio-economic development
transformation
b Enhancing our Strategic
Sourcing process
• Integrating technology and SD&L
into the process
c Creating our SD&L Plan • Following a strategy to drive
development through our spend
d Making transformation a
key focus
• Accelerating the development of
black industrialists, SMMEs and
Cooperatives
e Including SD&L and
collaboration in all our
transactions
• Implementing our SD&L plan through
our strategic sourcing activities
• Changing the way we strategically
work with our suppliers - Developing
collaborative, long-term relationships
a Embedding SD&L into
our organisation
• Ensuring SD&L becomes an
integral part of our operations
Source: Eskom Supplier Development and Localisation Department 16
SD&L Key Performance Indicators
KPA KPIs 2014/15 2015/16
Localisation Percentage of B-BBEE attributable spend against TMPS 75% 80%
Percentage of BO attributable spend against TMPS 12.5% 40%
Percentage of BWO attributable spend against TMPS 6% 12%
Percentage of BYO attributable spend against TMPS 2% 2%
Percentage of BPLwD attributable spend against TMPS 1% 2%
Percentage of QSE attributable spend against TMPS 10% 15%
Percentage of EME attributable spend against TMPS 10% 15%
Percentage of Local Content Contracted in New Build 65% 65%
Percentage of Local sourcing in procurement 65% 65%
Skills
Development Investment in skills developed by suppliers SPC SPC
Youth Development through suppliers network 2500 2500
Jobs Creation Jobs creation by suppliers 16 334 8 317
Industrialization Investment in plant by suppliers SPC SPC
Technology Transfer (Rand Value) RVPC RVPC
Export Promotion (Rand Value) RVPC RVPC
Enterprise/
Supplier
Development
Suppliers developed (number of suppliers) RVPC RVPC
Payment duration to black owned QSE/EMEs 14 days 14 days
SPC = Set Per Contract
RVPC = Rand Value Per Contract
17
MEDUPI
• Up-skilling opportunity of local business owners through Eskom Contractors Training Academy
which is a registered programme offered in partnership with the University of Limpopo
• A consortium, made up of 46 local BWO companies , takes pride in feeding Medupi’s construction
workers
• A wholly Black Owned business doing general maintenance at Medupi
KUSILE
• Bulk Earthworks
o A SMME employs 89 local people from the Mpumalanga Province and this contract enabled
the contractor to increase its CIDB level from grade 5CE to grade 8CE
• Rock Crushing Contract
o Joint Venture engaged for Rock Crushing at Kusile
o The purpose was to give local entities an opportunity to participate in tenders whose scope of
work needed a higher CIDB grading.
• Construction of 336 units
o The JV participation ratio was 50:50
SMME development
19
• Eskom has invested R2.3 billion in infrastructure development
o Eskom has built 995 houses and purchased 321 houses
o Eskom and Exxaro jointly invested R180 million on the roads upgrade
o Eskom has upgraded the two sewage plants serving Lephalale
• Eskom invested over R3,8 million in wellness centers and medical equipment to
seven clinics in the local communities
• Hitachi invested R1.2 million in building Segwati crèche
• Eskom invested R8.6 million invested in a paediatric mobile unit for primary
school health care
• Eskom invested R3.5 million in the refurbishment and upgrading of the Seleka
Community Hall and Traditional Offices
• Eskom invested over R620k in refurbishing Itereleng Creche in Marapong
• Eskom refurbished the Olifantsdrift Primary School after it was damaged by
storms
Eskom Investment at Medupi
Increasing the capability and penetration of BO suppliers in priority spend areas requires Eskom to address challenges head-on
Lack of access to
funding
▪ Historically, black people were excluded from accumulating capital making it difficult to start and
sustain businesses
▪ The private sector in SA tends to be risk averse and venture or start-up capital is not readily accessible
▪ DFIs e.g. the IDC, have been set up by government to bridge the funding gap, but their lending criteria
is stringent and they demand security in the form of supplier contracts
▪ The high capital requirements in high impact areas amplifies this challenge
Lack of human
capital and skills
• Human capital is a key asset for any business - managerial and entrepreneurial skills are not well
developed and the overall scarcity of critical skills pits BO companies against established business in
the “war for talent”
• The technical/ engineering driven nature Eskom’s high impact areas requires specialist human capital
up to date with the latest knowledge
Lack of IP
▪ Barriers to entry for BO suppliers in the highly technical and engineering driven fields (Primary Energy,
Primary and Secondary Plant) are sizeable
▪ This limits black owned companies to “easier” general services industries, such as catering, cleaning,
security and certain professional services
Access to work
opportunities
• The technical specifications of tender documents are often set at a prohibitively high level of
complexity, making it impossible for local BO firms to compete with OEMs and established large local
businesses
General difficulty in
doing business in
South Africa
• South Africa has a low tolerance for entrepreneurial failure – people dissociate themselves and
finance institutions tend to black list failed entrepreneurs
• SA has one of the highest failure rates of start-up businesses in the world with almost two-thirds of
start-up businesses failing within the first two years
• This reduces the number of entrepreneurs starting new ventures as failure can easily result in a poor
financial future
Challenges
Source: Eskom Supplier Development Strategy 20
Summary
• The biggest portion of the budget is allocated to the manufacturing supply & delivery of the SWH systems.
• Programme to be implemented applying a multiple contracts approach in order to create opportunities for the SMMEs
• Black Economic empowerment through the special conditions using the PPPFA framework in the installations contracting model.
• Big corporates to outsource or subcontract in order to demonstrate 30% participation in the manufacturing phase.
• Sustainability, Localisation and SMMEs development for the 5 year period during the maintenance phase of the programme
• This is a new industry and an industry of the future, Eskom intends building capacity and capability of local and targeted players. This will be done through focused Enterprise Development initiatives like Subcontracting and Incubation programmes.
21
Thank You