POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS PROJECT UPDATES THURSDAY JUNE 11, 2015

Upload: others

Post on 28-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS PROJECT UPDATES

THURSDAY JUNE 11, 2015

Page 2: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

AGENDA

A. Introduction

B. Rules of the Road

C. Agenda

• School Construction Update • Building C Addition – August 2015 Completion • Building B Renovation – June 2015 Start, August 2015 Completion • Building D Addition – Fall 2015 Start, pending funding

• Parking Lot Site Plan • Twin Oaks Community Garden Update

D. Next Steps

E. Questions & Answers

Elevating the Quality of Life in the District

Page 3: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

SITE OVERVIEW

Page 4: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

School Budget and Twin Oaks North Garden

Total Budget is $39.8 Million

Elevating the Quality of Life in the District

Powell ES School

Twin Oaks Gardens - SOUTH

Twin Oaks Gardens - NORTH

Page 5: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

SCHOOL SITE PLAN

Page 6: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

BUILDINGS A, B, C and D: 1ST FLOOR MASTER PLAN

Page 7: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

BUILDINGS A, B, C and D: 2ND FLOOR MASTER PLAN

Page 8: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

BUILDING ELEVATIONS

North Elevation – Upshur Street View

South Elevation – 14th Street View

Page 9: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

BUILDING A INTERIOR

Building A Typical Classroom Finishes

Building A Classroom Portal

Page 10: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

BUILDING B INTERIOR

Building B Typical Classroom Finishes

Building B Corridor / Welcome Center

Page 11: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

BUILDING C INTERIOR

Building C Typical Classroom Finishes

Building C 2-Story Atrium

Page 12: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

BUILDING C EXTERIOR PROGRESS PHOTOS

Page 13: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

BUILDING C INTERIOR PROGRESS PHOTOS

Page 14: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

BUILDING D INTERIOR AND EXTERIOR

Building D Typical Classroom Finishes

Building D Elevations

Page 15: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

BUILDINGS A, B, C and D: SITE OVERVIEW

Page 16: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

BUILDING D EXTERIOR PARKING LOT

Page 17: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

TWIN OAKS GARDEN SITE OVERVIEW

Page 18: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

TWIN OAKS GARDEN SITE LOCATION

Behind Upshur Park Soccer Field

Page 19: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

TWIN OAKS GARDEN PLOT LAYOUT

Page 20: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

TWIN OAKS GARDEN RENDERING

Page 21: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

Elevating the Quality of Life in the District

TWIN OAKS GARDEN PROGRESS PHOTOS

Page 22: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

NEXT STEPS

A. School Construction 1. August 2015 – Completion of Building C and Renovation of Building B 2. September 2015 – Building D Construction Start Date, pending funding 3. August 2016 – Completion of Building D, pending funding

B. Community Garden Construction 1. Late May – Early June 2015 – Site work start date, four (4) month construction duration 2. Late September 2015 – Relocation of Twin Oaks North Garden 3. October 2015 – Twin Oaks North Garden site will be turned over as material

staging area for Building D construction

Elevating the Quality of Life in the District

Page 23: POWELL ELEMENTARY SCHOOL & TWIN OAKS GARDENS … · AGENDA A. Introduction B. Rules of the Road C. Agenda • School Construction Update • Building C Addition – August 2015 Completion

QUESTIONS & ANSWERS

Elevating the Quality of Life in the District