Power Control for Data Centers Ming Chen Oct. 8 th , 2009 ECE 692 Topic Presentation

Upload: kimn

Post on 24-Feb-2016

60 views

Category:

Documents


5 download

DESCRIPTION

ECE 692 Topic Presentation. Power Control for Data Centers. Ming Chen Oct. 8 th , 2009. Why power control in Data Centers?. Power is one of the most important computing resources. Facility under-utilized Cost of power facilities Economically amortize investment. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Power Control for Data Centers

Power Control for Data Centers

Ming ChenOct. 8th, 2009

ECE 692 Topic Presentation

Page 2: Power Control for Data Centers

2

Why power control in Data Centers?

Power is one of the most important computing resources.

Facility over-utilized− Dangerous− System failure and overheating− Power below the capacity

Facility under-utilized− Cost of power facilities− Economically amortize investment.− Provision to fully utilize power

facility.

Page 3: Power Control for Data Centers

3

Xiaorui Wang, Ming Chen University of Tennessee, Knoxville, TN

SHIP: Scalable Hierarchical Power Control for Large-Scale Data Centers

Charles Lefurgy, Tom W. Keller IBM Research, Austin, TX

Page 4: Power Control for Data Centers

4

Introduction

Power overload may cause system failures.− Power provisioning CANNOT guarantee exempt of overload.

− Over-provisioning may cause unnecessary expenses.

Power control for an entire data center is very necessary.

Data centers are expanding to meet new business requirement.− Cost-prohibitive to expand the power

facility.− Upgrades of power/cooling systems

lag far behind.− Example: NSA data center

Page 5: Power Control for Data Centers

5

Challenges

Scalability: One centralized controller for thousands of servers?

Coordination: if multiple controllers designed, how do they interact with each other?

Stability and accuracy: workload is time-varying and unpredictable.

Performance: how to allocate power budgets among different servers, racks, etc.?

Page 6: Power Control for Data Centers

6

State of The Art Reduce power by improving energy-efficiency : [Lefurgy],

[Nathuji], [Zeng], [Lu], [Brooks], [Horvath], [Chen]− NOT enforce power budget.

Power control for a server [Lefurgy], [Skadron], [Minerick], a rack, [Wang], [Ranganathan], [Femal]− Cannot be directly applied for data centers.

No “Power” Struggles presents a multi-level power manager. [Raghavendra] − NOT designed based on power supply hierarchy− NO rigorous overall stability analysis− Only simulation results for 180 servers

Page 7: Power Control for Data Centers

7

What is This Paper About?

SHIP: a highly Scalable Hierarchical Power control architecture for large-scale data centers− Scalability: decompose the power control for a data center

into three levels− Coordination: hierarchy is based on power distribution

system in data centers. − Stability and accuracy: theoretically guaranteed by Model

Predicative Control (MPC) theory. − Performance: differentiate power budget based on

performance demands, i.e. utilization.

Page 8: Power Control for Data Centers

8

Power Distribution Hierarchy

A simplified example for a three-level data center

− Data center-level− PDU-level− Rack-level

Thousands of servers in total

Page 9: Power Control for Data Centers

9

PMRPC

PMRPC

UtilizationMonitor

FrequencyModulator

UM FM

UM FM

UM FM

Power Monitor

Rack PowerController

PDU PowerController

PDU-LevelPower Monitor

Rack-level PDU-level Data center-levelControlled variable

The total power of the rack

The total power of the PDU

The total power of the data center

Manipulated variable

The CPU frequency of each server

The power budget of each rack

The power budget of each PDU

Control Architecture

HPCA08 paper This paper

Page 10: Power Control for Data Centers

10

PDU-level Power Model System model:

Uncertainties:)()( kbrgkpr iii

gi is the power change ratio .

Actual model:

)(...

)(]...[)()1(

1

1

kbr

kbrggkppkpp

N

N

:)(kpp the total power of PDU :)(kpri the power change of rack i

:)(kbri the change of power budget for rack i

)()()1(1

kprkppkppN

ii

Page 11: Power Control for Data Centers

11

Model Predictive Control (MPC)

Design steps:− Design a dynamic model for the controlled system.− Design the controller.− Analyze the stability and accuracy.

Control objective:

2

}1|)({))1((min sNjkbr

Pkppj

s

jjjj

Pkpp

NjPkbrkbrPtosubject

)1(

)1()()(: max,min,

Page 12: Power Control for Data Centers

MPC Controller Design

12

Least Squares Solver

ReferenceTrajectory

Cost Function

ConstraintsSystemModel

21

0

2)(

1

||||||)|()|(||)( R(i)maxPk)|ibr(kk)|iΔbr(k

M

iiQ

P

ikikrefkikppkV

Power budget

Measured power

)(...

)(1

kbr

kbr

N

Budget changes

sP

)(kppIdeal trajectoryto track budget

Tracking error Control penalty

Page 13: Power Control for Data Centers

13

StabilityLocal Stability

− gi is assumed to be 1 at design time.− gi is unknown a priori.− 0 < gi < 14.8: 14.8 times of the allocated budget

Global Stability− Decouple controllers at different levels by running them in different time scales.− The period of upper-level control loop > the settling time of the lower-level− Sufficient but not necessary

Page 14: Power Control for Data Centers

14

System Implementation Physical testbed

− 10 Linux servers− Power meter (Wattsup)

• error: • sampling period: 1 sec

− Workload: HPL, SPEC− Controllers:

• period: 5s for rack, 30s for PDU Simulator (C++)

− Simulate large-scale data centers in three levels.− Utilization trace file from 5,415 servers in real data centers− Power model is based on experiments in servers.

%5.1

Page 15: Power Control for Data Centers

15

Precise Power Control (Testbed)

0 800 1600 2400600

800

1000

1200

PDU

Time (s)

Pow

er (W

)

0 800 1600 2400200

240

280

320

360

Budget Rack 1Rack 2 Rack 3

Time (s)

Pow

er (W

)

Power can be precisely controlled at the budget.

The budget can be reached within 4 control periods.

The power of each rack is controlled at their budgets.

Budgets are proportional to .maxP

Tested for many power set points (See the paper for more results.)

Page 16: Power Control for Data Centers

16

0 800 1600 2400200

230

260

290

320

Rack1 Rack2

Time (s)

Pow

er b

udge

t (W

)

Power Differentiation (Testbed)

Capability to differentiate budgets based on workload to improve performance

Take the utilization as the optimization weights. Other differentiation metrics: response time,

throughput

Budget allocation proportional to estimated max consumptions;

Budgets differentiated by utilization;CPU: 100%CPU: 80%

CPU: 50%

Page 17: Power Control for Data Centers

17

Simulation for Large-scale Data Centers

0 2 4 6 8 10 12 14400

500

600

700

800

Data centerSet point

Time (control period)

Pow

er (k

W) 6 PDU, 270 racks

Real data traces 750 kW

Randomly generate 3 data centers Real data traces

600 620 640 660 680 700 720 740 760 780500

600

700

800

900

Data center 1 Data center 2Data center 3 Set point

Power set point (kW)

Pow

er (k

W)

Page 18: Power Control for Data Centers

18

Budget Differentiation for PDUs

1 2 3 4 5 6 7 8 9 10 11 12 13 140

5

10

15

PDU1 PDU2 PDU3PDU4 PDU5 PDU6

Time (control period)

CPU

utili

zatio

n (%

)

1 2 3 4 5 6 7 8 9 10 11 12 13 140

8

16

24

32

40

PDU1 PDU2 PDU3

PDU4 PDU5 PDU6

Time (control period)

Diffe

renc

e (k

W)

Power differentiation in large-scale data centers;− Minimize the difference with estimated max power consumption.− Utilization is the weight.− The difference order is consistent with the utilization order.

PDU5

PDU2

Page 19: Power Control for Data Centers

19

Execution time of the MPC controller Vs. the # of servers

Scalability of SHIP

0 500 1000 1500 2000 2500 30000

3000

6000

9000

12000

0.09 (50)0.39 (100)

65.9452.1

3223.6

10997.5

Number of servers

Exec

utio

n tim

e (s

ec)

Centralized SHIPLevel One level Multiple

Computation overhead Large Small

Communication overhead Long Short

Scalability NO YES

Overhead of SHIP The max scale

of centralized

Page 20: Power Control for Data Centers

20

Conclusion SHIP: a highly Scalable HIerarchical Power control architecture for large-scale data centers

− Three-levels: rack, PDU, and data center− MIMO controllers based on optimal control theory (MPC)− Theoretically guaranteed stability and accuracy− Discussion on coordination among controllers

Experiments on a physical testbed and a simulator− Precise power control− Budget differentiation− Scalable for large-scale data centers

Page 21: Power Control for Data Centers

21

Xiaobo Fan, Wolf-Dietrich Weber, Luiz Andre Barroso

Power Provisioning for a Warehouse-sized Computer

Acknowledgments: The organization order and contents of some slides are based on Xiaobo Fan’s slides in pdf.

Page 22: Power Control for Data Centers

22

Introduction

Strong economic incentives to fully utilize facilities− Investment is best amortized.− Upgrades without any new power facility investment

Power facilities

$10-$20/watt

years

utilization

~10 ~18

Electricity < $0.8/watt-year

Run risk of outages or costly violations of SLA. Power provisioning given the budget

0.85

0.5

Page 23: Power Control for Data Centers

23

Reasons for Facility Under-utilization

Staged deployment− new facilities are rarely fully populated

Fragmentation Conservative machine power rating (nameplate) Statistical effects

− Larger machine population, lower probability of simultaneous peaks

Variable load

Page 24: Power Control for Data Centers

24

What is This Paper About? Investigate over-subscription potential to increase

power facility utilization.− A light-weight and accurate model for estimating power− Long-term characterization of simultaneous power usage of a large number of machines

Study of techniques for saving energy as well as peak power.− Power capping (physical testbed)− DVS (simulation)− Reduce idle power (simulation)

Page 25: Power Control for Data Centers

25

Data Center Power Distribution

Transformer

Main Supply

ATSSwitchBoard

UPS UPS

STSPDU

STSPDU

Panel

Panel

Generator

1000 kW

200 kW

50 kW

Rack

Circuit

2.5 kWRack level

40-80 servers

PDU level20-40 racks

Data center level5-10 PDUs

Page 26: Power Control for Data Centers

26

Power Estimation Model

Model is predicted for each family of machines. Greater interest is for a group of machines.

Direct measurements are not always available.

Input: CPU utilization

Models:− Pidle+(Pbusy – Pidle)u− Pidle+(Pbusy – Pidle)(2u-ur)− Measure and derive <Pidle ,Pbusy

, r>

Page 27: Power Control for Data Centers

27

Model Validation

PDU-level validation example (800 machines) Almost constant offset

− Loads not accounted in the model: networking equipments. Relative error is below 1%.

− EMc

i

ii

McEM

nerror |(|1

Page 28: Power Control for Data Centers

28

Analysis Setup

Data center setup− Pick up more than 5,000 servers for each workload.− Rack: 40 machines, PDU: 800 machines, Cluster: 5000+

Monitoring period: 6 months every 10 mins Distribution of power usage

− Aggregate power at each time interval at different levels.− Normalized to aggregated peak power

Workload Description

Websearch Online servicing correlating with time of dayComputation-intensive

Webmail Disk I/O intensive.

Mapreduce Offline batch jobsLess correlation between activities and time of day

Real data center Randomly pick any machines from data centers

Page 29: Power Control for Data Centers

29

Webmail

65%

92%88%86%

72%

Higher level, narrower range− More difficult to improve facility utilization in lower

levels. Peak lowers as more machines are aggregated.

− 16% more machines can be deployed.

Page 30: Power Control for Data Centers

30

Websearch

45%

98%93%

52%

Peak lowers as more machines are aggregated.− 7% more machines can be deployed.

98% 93%

Higher level, narrower range− More difficult to improve facility utilization in lower

levels.

Page 31: Power Control for Data Centers

31

Real Data Centers

Clusters have much narrower dynamic range compared to racks.

Clusters peak at 72%.− 39% more machines

Mapreduce has the similar results.

Page 32: Power Control for Data Centers

32

Summary of CharacterizationWorkload Avg power Power range Machine increase

Websearch 68% 52%-93% 7%

Webmail 78% 72%-86% 16%

Mapreduce 70% 54%-90% 11%

Real data center 60% 51%-72% 39%

Average power: utilization of the power facilities Dynamic range: difficulty to improve facility utilization Peak power: potential of deployment over-subscription

Page 33: Power Control for Data Centers

33

CDF

1.0Time in power capping

Power

Powersaving

Time

Power CDF1.0

Power

Power Capping

Small fraction of time in power capping Substantial saving in peak power Provide a safety valve when workload is unexpected.

Page 34: Power Control for Data Centers

34

Results for Power Capping

For workload with loose SLA or low priority Websearch and Webmail are excluded; De-scheduling tasks or DVFS

Page 35: Power Control for Data Centers

Motivation− A large portion of dynamic power is consumed by CPU.− DVS is widely available in modern CPUs.

CPU Voltage/Frequency Scaling

utilization

CPU power

threshold

Method− Oracle-style policy− Threshold: 5%, 20%, 50%− Simulation− CPU power is halved when

DVS is triggered.

35

Page 36: Power Control for Data Centers

36

Energy saving is larger than peak power reductions.

Biggest saving in data centers.

Benefits vary with workloads

Results for DVS

Page 37: Power Control for Data Centers

37

Lower Idle PowerMotivation

− Idle power is high. (more than 50% of peak)

− Most of time is in non-peak activity level.− What if idle power is 10% of peak?

keeping peak power unchanged.

− Simulation

utilization

CPU powerPeak

0.6

0.1

Page 38: Power Control for Data Centers

38

Conclusions

Power provisioning is important to amortize facility investment.

Load variation and statistical effects lead to facility under-utilization.

Over-subscribing deployment is more attractive in cluster level than rack level.

Three simple strategies to improve facility utilization: power capping, DVS, and lower idle power

Page 39: Power Control for Data Centers

39

Comparison of the Two PapersSHIP Power Provisioning

Target Power capacity of data centers

Power capacity of data centers

Goal Control power to the budget to avoid facility over-utilization

Give power provisioning guidelines to avoid facility under-utilization

Methodology MIMO optimal control Statistical analysis

Solutions A complete control-based solution

Some strategies suggested based on real data analysis

Experiments Physical testbed and simulation based on real trace files

Detailed analysis on real trace files and simulations

Page 40: Power Control for Data Centers

40

Critiques Paper 1

− Workload is not typical in real data centers.− Power model may include CPU utilization.− No convincing baseline is compared.

Paper 2− Power provisioning Vs. performance violations− Power model is workload-sensitive.− Estimation accuracy in rack-level?− Quantitative analysis on idle power and peak power reduction

Page 41: Power Control for Data Centers

41

Thank you !