power losses

23
Revolutionary Concept of Power management For a clean and green planet… With NO energy shortage… 

Upload: jaythakar8887

Post on 14-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 1/23

Revolutionary Concept of Power management

For a clean and green planet… 

With NO energy shortage… 

Page 2: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 2/23

Can India be energy surplus in two

years – remember the green

revolution?

Yes

Our strategies and focus can help India to:1. Become an energy surplus state within

two years with zero additional

generation.

2. Earn a very large number of Carbon

Points

Page 3: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 3/23

India 2006 – The Power scenario

Power Shortage is a major problem for India -leads to compounded problems with Lowfrequency, tripping of generators and Load

shedding in nearly all parts of the country.

Poor power factor, a feature of poor qualityequipment, leads to low voltage. Use of equipments to correct voltage further compounds the problem.

Page 4: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 4/23

India 2006 – The Power scenario,

contd. Power shortage/quality thus leads to large scale

use of Voltage Stabilisers, Inverters, Generators,UPS Systems, etc.

Such Electrical Equipments, which requireunwanted investments, in turn not only lead toenhanced shortage in the overall situation butalso cause air and soil pollution by burning of 

coal, diesel, etc. Widespread use of lead-acid batteries in these

equipments further causes pollution of soil andwater.

Page 5: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 5/23

What is the effect of Stabilisers?

Voltage Stabilisers don’t have efficiencies better than80%. While a 1.5 Tr AC consumes 2 units; its stabiliser consumes 0.4 units; it even consumes power if left ONwhen AC is OFF.

Assuming we have 10 Million ACs in India; on accountof stabilisers for ACs alone we lose around 4 millionunits, even during peak hours, which is double the

power generated by many large generating stations.

Assuming an AC runs for 5 hours in a day, this means aloss of 20 million units per day.

Page 6: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 6/23

What is the effect of Inverters?

The average efficiency of the domestic inverters is

50% and unlike fuel-based generators, inverters

don’t generate power. 

There is an estimated 50 million inverters being

used for domestic purposes each consuming say

250W/day or 0.25 units. The power drain by

inverters is thus to the tune of 12.5 million units.

Further, inverters use lead-acid batteries which

severely pollute the environment.

Page 7: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 7/23

Other equipments-how they

affect

UPS systems being like inverters

cause power wastage and pollution

by use of lead-acid batteries.

Diesel/Kerosene gensets not only

cause pollution but also deplete

scarce natural resources. 

Page 8: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 8/23

Power Generation in India

The total installed capacity in the

country is 1,26,000 MW.

Assuming a plant load factor of 0.7,

the generation is 2,116.8 million

units/day.

Page 9: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 9/23

Power loss – Pumps & Motors

Pumps/Motors consume roughly 20% of totalelectricity in India. An estimated 75% of this isconsumed by the pumps for agricultural sector 

mainly for water/irrigation. The balance is for other motor applications.

Most Indian pumps operate at 33% efficiency whilemotors have an average efficiency of 40%. Thesecause heavy loss of electrical energy.

Taking usage of 4 units at 4 hours/day, theconsumption in this category is over 250 millionunits/day and the estimated loss is 160 millionunits/day.

Page 10: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 10/23

Power Generated – How does it

flow? Where does it go?

Transmission System – 4% losses

Unavoidable Distribution

Losses - 15%

Pilferage -35% losses

29 units

Billed to consumer  – 

53 units

Energy usefully consumed – 

42 units (max.)

100 units

96 units

82 units

Generating Station

20% loss

Page 11: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 11/23

Pilferage

Pilferage (Power theft) in India is

responsible for the disappearance of 

29% of electricity generated.

In energy terms this amounts to

613.87 million units/day.

Page 12: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 12/23

Simple Mathematics –  

No rocket science

Power Generation capacity: 1,26,000 MW

Power available/day: 2116.80 MU

Power con sum ed/day -Transmission line: 84.67 MU

Unavoidable distribution losses: 296.35 MU

Pilferage: 613.87 MU

Used by consumer (max.): 889.06 MU

Wasted by consumer (min.): 232.85 MUMU – Million units/day

Page 13: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 13/23

Power Loss Summary Table

Equipment  Power   Inst. Base  Loss Million  Loss Loss  Units/day  (Cr. Rs./year) 

Stabiliser   20%  10 Million  20.00 2,190.00

Inverter/UPS  50%  50 Million  12.50 1,368.75

Pumps  66%  11 Million  116.16 12,719.52

Motors  60%  5 Million  48.00 5,256.00

Others  -  -  36.19 3,962.81

Pilferage  29%  -  613.87 67,218.77

Total=>  846.72 92,715.85 

Page 14: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 14/23

Investment at consumer and

national level

Each element of this loss means additional

equipment leading to mind-boggling capital

expenses by the Nation & the Consumer 

PLUS

Higher energy costs and use of scarce fuel

resources.

Page 15: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 15/23

Impact of wastage

At the national level all this wastage adds up

to 850 Million units/day against a capacity of 

2,116.8 Million Units/day.

The cost of setting up a 1000 MW power 

plant entails a capital cost of approx 5000

Cr. Considering a plant load factor of 0.7, itgenerates about 16.8 Million Units/day .

Transmission cost is another about 3000 Cr.

Page 16: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 16/23

Cost of wastage

Wastage of 16.8 Million Units/day,

requires a capital outlay to the tune

of Rs. 8,000 Cr.

Wastage of 850 Million Units/day implies a

wasteful capital blockage of over Rs.

4,00,000 Crores with a recurring daily loss

of over Rs. 250 Cr. and an annual loss of over Rs. 90,000 Cr !

Page 17: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 17/23

Delhi’s Power shortage woes 

Delhi’s peak power requirement is 3268

MW. A mere shortage of 160 MW has

created havoc during July first week with

heavy load shedding in the city.

Further requirement stated is an additional

2000 MW to be added by 2010.

Hindustan Times in its article on 11.7.06

declares that Delhi’s problem can’t be

solved before 2010 in any case. Not true!

Page 18: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 18/23

Are Delhi’s power problems big? 

Delhi’s power requirements look

small in comparison to what we waste

by mismanagement of power.

Adding generation is slow and long

term as compared to power savingwhich can be done fast.

Page 19: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 19/23

National Level Statistics-T&D

India has the reputation of having thehighest distribution losses in the worldwith a figure of nearly 47%, rankingabove Burma with 36 % losses andBangladesh at 33 %.

How do we bring these losses downand become an energy surplus Nation?

Page 20: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 20/23

National Level Statistics-Generation

All India Peak Load requirement for 2006~07 is 1,30,944MW. Installed capacity is 1,26,000 MW.

For the 10th Five year plan the capacity is to be

enhanced by 34,000 MW. Powerful energy management ideas can thus yield

saving of over 40,000 MW (1MU/day translates to around60MW) placing us years ahead in our march to energyavailability, sufficiency and increased efficiency of natural resource management plus lower pollutions.

We can thus very comfortably realize the governmentsdeclared goal of total self sufficiency of power by year 2012, much earlier.

Page 21: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 21/23

Detrimental Environmental/

Financial effects

Unwanted increase in emissions of smoke andgas from burning of coal.

Increased lead pollution from use of lead-acidbatteries in Inverters and UPS systems.

Increased emission of smoke and gas fromgensets on account of burning of diesel/kerosene to take care of power shortages.

Rapid depletion of resources like petroleum and

coal. Besides the higher tariffs which the consumer 

pays, the country also loses valuable foreignexchange.

Page 22: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 22/23

 

Is there a solution to all this wastage and chaos?

 YES !

We have the solution…. 

Page 23: Power Losses

7/27/2019 Power Losses

http://slidepdf.com/reader/full/power-losses 23/23

Our Commitment

Whereas we are capable of achieving

savings of over 20,000 MW, we can help

save 5,000 MW in the first instance,provided a commitment is made to:

1. Implement the solutions nation-wide

2. Take care of our interests, commensuratewith the gains.