DESIGN AND CONSTRUCTION OF A
DRAINAGE IN A RURAL COMMUNITY
ACMK Construction Company
Alex E. Obi-UgboKarel Jie Tjoe Foek
Carlton NgMajid Almas
![Page 2: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/2.jpg)
Introduction■ This designing and construction project became necessary due to
numerous complaints of flooding in the area of 500 km square. The area has a population of 150,000 people where 20% of the population are attributed to children between the ages of 4-13 years old.
![Page 3: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/3.jpg)
Problem Statement■ Objectives• Using the SMART analysis:SPECIFIC• Construction would be in phases which
includes from start-to-finish of the project.
MEASURABLE• Our progress will be measured on a
weekly basis whereby we plan to excavate 50km square in trenches so as to pour the concrete mixtures before the pipes are been laid.
ASSIGNABLE• Project manager: Meetings, Resources,
Preparation of final reports
• Concrete Experts: All aspects of concrete for the project and analysis of results.
• Procurement; Ordering of all materials for the project
• Scheduling: Construction scheduling timeline and excavation
REALISTIC• The pipes come in standard form of 20
meters long. 20 pieces of pipes are produced every 6-hrs which comes out to be 80 pieces/day. A total of 381 pipes would be produced at an approximation of 5 days .
TIME RELATEDDuration of project is 9-months.
![Page 4: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/4.jpg)
Scope (Constraints, Assumptions, Limits, Exclusion, & Inclusion)
■ Scope: The project consists of the design, permitting and construction, pollution control structures, water control structures, A or B Manhole 48” Diameter (up to 4’ deep), and 12 catch basins. System maintenance and repair will be done only up to one month after final inspection.
■ Assumptions: Steady & Uniform gravity flow, company personnel have adequate knowledge to carry out project, design will follow health, safety, quality, & performance requirements, all research information can be obtained from open sources. Etc.
■ Limits: We would be limited for only one month after inspection, Future modification or structural changes would not be the company’s responsibility.
![Page 5: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/5.jpg)
Significance (Merit, Profit, and/ or Benefit)
■ Significance: The continuous flow of storm water which is caused by excess rainfall created flooding, erosion and transportation of potential pollutants to the local bodies of water in the rural area.
■ Benefit: • Erosion Control• Standardized Drainage for neighboring communities• Elimination of death rate between the ages of 4-13 years old.
![Page 6: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/6.jpg)
Proposed ApproachSolution Approach
■ Dig the trenches in segments whereby we pour the concrete base before laying the first segment of pipes and connect all necessary fittings.
■ While digging the second segment, the previous segment would be backfilled which will work simultaneously for other sub-segments of the solution approach.
■ Less expensive
Work Breakdown Structure
■ Place Order■ Receive Procured Order■ Remove Existing Drainage■ Excavation of Trenches■ Pour Concrete■ Lay Pipes■ Backfill Trenches■ Asphalt■ Inspection
![Page 7: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/7.jpg)
Proposed ApproachWBS
![Page 8: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/8.jpg)
Contractual Aspects■ ACMK will hire consultants to provide an overall assessment of the
surrounding areas■ This aspect will facilitate the needs of the community while ensuring efficient
and effective project initiative■ The consultant will create line of communication with the community in order
to gain feedback and address unplanned issues that may arise during the length of the project
■ Field workers will meet the demand based on the timeframe of the project■ Contract with equipment company to provide all construction equipment
needs
![Page 9: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/9.jpg)
ResourcesResource Name Group Hours Cost
Project Manager Administration 1440 $27,000
Civil Engineer Administration 1440 $27,000
Project Engineer Administration 1440 $27,000
Plumber Administration 1440 $27,000
Labor Personnel Field Workers 1080 $18,000
Labor Personnel Field Workers 1080 $18,000
Labor Personnel Field Workers 1080 $18,000
Labor Personnel Field Workers 1080 $18,000
Labor Personnel Field Workers 1080 $18,000
Labor Personnel Field Workers 1080 $18,000
Labor Personnel Field Workers 1080 $18,000
Labor Personnel Field Workers 1080 $18,000
Labor Personnel Field Workers 1080 $18,000
Labor Personnel Field Workers 1080 $18,000
![Page 10: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/10.jpg)
Cost■ The linear meters of the total area where the pipes would be laid is 7,620 meters
which gives us a number of 381 pipes of 20 meters long.■ The total cost of the project is one million, four hundred and eighteen thousand,
five hundred and forty eight thousand dollars only ($1,418,548).■ A or B Manhole 48” Diameter (up to 4’ deep) would be installed at every 40-
meter for cleanup and future services.■ Since the project is a cost-plus proposal, it includes all materials and installation,
hiring of heavy duty equipment’s unless otherwise noted. The notation TDB = To Be Determined which indicates that it would be an industry accepted estimate as a standard cost-plus price has not be established.
■ This is an industry accepted and current estimate for any materials that are approved and permitted by the City but not included in this document.
■ Cost for manholes are assumed to be precast, unless otherwise noted. This is accepted and current estimate for any structures that are poured in place.
![Page 11: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/11.jpg)
Cost Cost Breakdown
Demolition, Utility Adjustment and Relocation $18,000 Sediment Control and Earthwork $35,000
Storm water Management and Stream Restoration $25,000 Strom Drainage $43,000
Water and Sewer $45,000 Paving $15,000 Pipe (381pipes * 600) $228,600
A or B Manhole 48” Diameter (up to 4’ deep) (190pieces * 1500) $285,000 Pipe Brackets (380pieces * 78) $29,640
Elbows (380pieces *78) $29,640 Tees (380pieces *78) $29,640
Concrete (1000 cubic ft.) $80,000 Welding Torch (Rent for 4-month) $10,000
Argon gas (300 lbs.) $37,000 Staffing (2000 * 10persons * 9mths) $180,000
Administration ($3000 * 4persons * 9mths) $108,000 Other Expenses $25,000
Insurance $70,000 Total $1,233,520
15% Contingency plan $185,028.00 Overall Total $1,418,548.00
![Page 12: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/12.jpg)
SchedulePlace Order
Receive Procured Order
Remove Existing Drainage
Excavation of Trenches
Pour Concrete
Lay Pipes
Backfill Trenches
Asphalt
Inspection
1/4/16 2/8/16 3/14/16 4/18/16 5/23/16 6/27/16 8/1/16 9/5/16
![Page 13: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/13.jpg)
Budget
![Page 14: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/14.jpg)
PersonnelOrganizational Structure
![Page 15: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/15.jpg)
PersonnelJob Description and Qualifications/Skills
Position Advanced Degree Bachelor Degree Certification Leadership Skills Experience
Project Manager Masters Required PMI Certification Yes 3-5 Years
Civil Engineer Not Necessary Required PE Certification Not Necessary 3-5 Years
Project Engineer Not Necessary Required Not Necessary Yes 2-3 Years
Plumber Not Necessary Not Necessary Plumbers License Not Necessary 4 or more Years
Labor Personal Not Necessary Not Necessary Not Necessary Not Necessary 0-2 Years
Welder Not Necessary Not Necessary Welding Certification Not Necessary 2 or more Years
![Page 16: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/16.jpg)
PersonnelResponsibility Chart
Task
Project Team
Alex Carlton Karel Majid
Attend meetings to make plans R S S S
Determine resources R S S S
Construct schedule timeline S S S R
Order materials S S R S
Excavation S R S S
Concrete S R S S
Lay Pipes S S R S
Plumbing S S R S
Welding S R S S
Drainage S S S R
Asphalt R S S S
Miscellaneous S S S R
Analyze results S R S S
Prepare final report R S S S
![Page 17: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/17.jpg)
Personnel Communication Plan
What Information
Target Audience
When?
Method of Communication
Provider
Milestones Reports Project Manager & Project Engineer Monthly E-mail & hard copy Alex
Project-Daily Status Reports Project Manager & Project Engineer Daily E-mail & hard copy Carlton
Weekly Status Reports Project Manager & Project Engineer Weekly Meeting & hard copy Karel
Outsourcing Performance Project Manager & Project Engineer Weekly Meeting & hard copy Alex
Accept Change Request Owner & Project Manager As required Attention E-mail & hard copy Majid
Issue Report Project Manager & Project Engineer Weekly E-mail & hard copy Majid
Budget Update Project Manager & Owner Monthly E-mail & hard copy Karel
Scheduled Periodic Owner and Management Team Meetings
Management Team & Owner Monthly E-mail & hard copy Carlton
![Page 18: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/18.jpg)
Evaluation Methods■ Defining phase: Designers and Engineers will develop the project according to
the latest Florida Building Codes and create the plans and specifications.■ All submittals for materials and equipment shall be collected prior to the
execution and presented to the city for approval. ■ Executing phase: During construction of the project, regular inspections shall be
performed for certain work by a respective City Inspector.■ Inspectors shall make sure that the work being done is according to the plans
and specification■ Inspection = Pass → Work can continue as planned■ Inspection ≠ Pass → Work is stopped until necessary changes have been met
and pass re-inspection
![Page 19: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/19.jpg)
Potential Problems
■ Weather
■ Utilities
■ Traffic
■ Site
![Page 20: Power Point Presentation for (Advance Project Management)](https://reader035.vdocument.in/reader035/viewer/2022062522/5873b60f1a28abbc788b47ed/html5/thumbnails/20.jpg)
Questions