power purchase agreements · 10/7/2015 · output for a short period (e.g., 1 mw for 1 hour) for...
TRANSCRIPT
Edward Kee
Power Purchase Agreements
Oct 2015 ANL/IAEA
The NECG slides that follow are not a complete record of this presentation and discussion. The views expressed in these slides and the discussion of these slides may not be comprehensive and may not reflect the views of NECG’s clients or the views of my colleagues.
© 2015 NECG
Oct 2015 1ANL/IAEA
Electricity industry structure important– My session earlier today covered this in more detail– In some cases, a PPA may be possible
PPA offers options– Alternative to self-build/ownership– Off balance sheet financing by buyer– Attract outside investors– Manage nuclear project risks
Oct 2015 2ANL/IAEA
Overview & Context
PPA approach not without risks
PPA may be more expensive than direct ownership
PPA details reflect competing demands– Requirements of lenders and investors– Potential for delays and cost overruns– Requirements of power buyer/user– Grid and system operations – over life of PPA
Oct 2015 3ANL/IAEA
Overview & Context (cont.)
Oct 2015 4ANL/IAEA
Government utility
TRANSMISSION
$
MWh
RETAIL SERVICES
DISTRIBUTION
Government
governmentsubsidies
CONSUMERS
$
System Dispatch
Nuclear ProjectElectricityMinistry
Ultimate credit sourceInvestors
PPA
Nuclear Plant
Investors
Oct 2015 5ANL/IAEA
Regulated utility
TRANSMISSION
RETAIL SERVICES
CONSUMERS
DISTRIBUTION
Investors
System Dispatch
Nuclear Project
$
MWh
IRP & rate-making process
Utility Regulator
Ultimate credit source
PPA
Nuclear Plant
Oct 2015 6ANL/IAEA
Electricity markets
GeneratorGenerator
Generator
GeneratorGenerator
GeneratorGenerator
GeneratorGenerator
GeneratorGenerator
GeneratorGenerator
GeneratorTRANSMISSION
$
MWh
RETAIL SERVICESCONSUMERS
DISTRIBUTION
Electricity Market
Utility regulator
Market oversight
Ultimate credit source
InvestorsNuclear Project
Generator
Hedgecontract
14 Oct 2015 7Middle East Nuclear Power Briefing 2015
Cooperative model
TVOU.S. G&T Coops
Member agreements + long-term projected demand
Cooperative members
CONSUMERS
Nuclear Project
Costs
MWh
Ultimate credit source
Electricitymarket
PPA = alternative to nuclear plant ownership
Costs and benefits of ownership should be compared to PPA outcomes
Nuclear project finance tightly linked to PPA– Guarantees of payments/obligations may be needed– PPA details must be crafted to meet
lender/investor/sponsor requirements
Oct 2015 8ANL/IAEA
PPA
Longer development/construction period
Greater risk in development and construction
Longer term/tenor (high capital + long asset life)
Low-probability, high-impact nuclear events
Externalities (Decom, SNF, TPL insurance)
Nuclear regulatory cost issues
Nuclear fixed/variable costs & dispatchOct 2015 9ANL/IAEA
Nuclear PPAs ≠ conventional PPAs
Short-run marginal cost - key power plant attribute
Difference in total cost due to small change in output for a short period (e.g., 1 MW for 1 hour)
For fossil fuel units, SRMC is fuel cost (maybe some variable O&M)
For wind, solar, run-of-river hydro, SRMC = ZERO
For most nuclear power plants, SRMC = ZERO
Oct 2015 10ANL/IAEA
SRMC
Batch refueled light water reactors (PWR/BWR)
Plants operate as much as possible during 18 to 24 months between refueling outages
Refueling outages involve maintenance activity in addition to fuel change – not easily rescheduled
Nuclear fuel cost incurred before fuel is loaded
Only a very large/long outage might result in delay of refueling outage
Oct 2015 11ANL/IAEA
Nuclear SRMC = ZERO
100% 100%
0%
70%
Nuclear Fossil fuel
Total costMarginal cost
Oct 2015 12ANL/IAEA
Illustrative – marginal cost comparison
Utility meets time-varying demand by dispatch
Fossil-fueled units– Large part total generating cost = fuel (marginal cost)– Change output levels significantly in short time– Able to shut down overnight or in off-peak seasons– Avoid large part of total costs by shutting down
Nuclear plant costs all fixed – no benefit to operator/owner from operating at less than 100%
Oct 2015 13ANL/IAEA
Dispatch issues
Oct 2015 14ANL/IAEA
SRMC Dispatch (unit 1 = nuclear)
X Generator SRMC
2 3 4 5 6 7
Demand Supply
Short-run Marginal Cost (SRMC) 1
All payments for power on $/MWh basis
Transforms PPA price into SRMC for buyer
Buyer dispatch with PPA based on this SRMC– May mean lower operation of unit in PPA– Lower revenue for PPA seller– Typically leads to PPA terms that require buyer “must
take” power (i.e., no dispatch)– Issues for all plants, not just nuclear
Oct 2015 15ANL/IAEA
“Single Price” PPA
Oct 2015 16ANL/IAEA
Single-price PPA – turns fixed costs into marginal costs for power buyer
Nuclear costs (all
fixed)
Nuclear costs (all marginal)
PPA with one-part pricing; all revenue is obtained when power is sold at $/MWh
Nuclear operator
sees costs that are all
fixed
Utility power buyer sees
costs that are all marginal
Approach used in more mature PPAs– Fixed capacity payment ($/MWe/month) – based on
project fixed costs– Variable payment ($/MWh) – based on project
variable/marginal costs
Allows PPA dispatch similar to owned units
Avoids need for “must-run” PPA provisions
Typically includes availability tests to qualify for fixed capacity payments
Oct 2015 17ANL/IAEA
“Two-Price” PPA
A nuclear PPA with a pricing approach tied to project costs suggests a single fixed payment (the opposite of the single variable payment approach)
PPA provisions related to operating effectiveness and incentives for performance– Financial incentives/penalties– Based on capacity factor over month or year– Risk for owner/operator may be issue– Exceptions for regulatory requirements?
Oct 2015 18ANL/IAEA
Nuclear PPA – capacity payments?
Ownership equivalents– Cooperative arrangements– Regulatory participation agreements– Pass-through PPA between affiliates
Other– Stipulated price agreements – conventional PPA– Tolling agreement (power buyer pays for fuel)– Hedge Agreement / Contract for Differences (CfD) in
electricity markets
Oct 2015 19ANL/IAEA
High-level PPA approaches
PPA Issues and Approaches
Pricing and payment structure– Performance incentives and risks– Financial incentives and penalties– Plant operating schedules & outages
Contract timing & term/tenor
Spent nuclear fuel & decommissioning fees
Contract re-openers/contingencies
Oct 2015 20ANL/IAEA
Participation agreements– Buyer takes all available power and pays all costs on a
pro rata basis)– TVO, Palo Verde, SERI (Entergy), Vogtle 3&4
US merchant nuclear PPAs (part of sale)
Exeltium & Blue Sky (European fwd power sales)
UK EMR – Hinkley Point C CfD
Oct 2015 21ANL/IAEA
Nuclear PPA examples
© Copyright 2015 NECGAll rights reserved.
Edward Kee
Nuclear Economics Consulting Group+1 (202) [email protected]
22