power scenario
TRANSCRIPT
-
7/29/2019 Power Scenario
1/69
POWER SCENARIO
IN
INDIA
http://www.studygalaxy.com/
-
7/29/2019 Power Scenario
2/69
POWER or ELECTRICITY critical infrastructuralcomponent for multidimensional growth and basichuman need
Reliable and quality power at competitive rates toIndian industry - important for global competition.
Clean and Green Sustainable Power
need of the day.
Energy Security
POWER SCENARIO
-
7/29/2019 Power Scenario
3/69
EVOLUTION OF POWERSECTOR
-
7/29/2019 Power Scenario
4/69
POWER SECTOR-AN OVERVIEW
Electricity - Concurrent Subject: jointresponsibility of State and Central
Governments.
Bulk of transmission and distribution
functions with State Utilities.
Private sector - small presence inDistribution and making entry into
Transmission.
-
7/29/2019 Power Scenario
5/69
POWER SECTOR-AN OVERVIEW
Conventional Generation - blend of thermal, hydroand nuclear sources.
Coal based thermal power plants and in some regions
hydro power plants - mainstay of electricity generation.Oil, natural gas and nuclear power accounts for
smaller proportion of power.
Emphasis also on non-conventional energy sources
i.e. solar, wind, biogas and tidal. Captive power plants being encouraged to supply
surplus power to Grid.
-
7/29/2019 Power Scenario
6/69
GROWTH OF INSTALLED GENERATING CAPACITY IN
INDIA
'47 '55 '61 '66 '74 '80 '85 '90 '95 '02 '03 '04 '06 '07 '12
(Projeced)
Thermal Nuclear
Hydro Renewable
1,
362
2,
695
4,
653
9,
027
16,
664
28
,448
42,
585
81,
171
63,
636
1,
05,
046
1,
07
,877
1,1
8,
426
1
,24,
287
2,
24,
907
*
1,
32,
329
Source: CEA
(figs. in MW)
* Total generation as on 30-06-2011 is
1,76,990 MW
-
7/29/2019 Power Scenario
7/69
535759
61
68
7173
69
2000 2003 2005 2008
Year
% of Coal basedCapacity in TotalGenerating Capacity
% of Coal based
Generation in TotalGeneration
Share
in %
(app.)
COUNTRYS SHARE OF COAL IN
TOTAL POWER GENERATION AND
INSTALLED CAPACITY OVER YEARS
-
7/29/2019 Power Scenario
8/69
ALL INDIA PLF (%) OF THERMAL POWER STATIONS
(COAL AND LIGNITE BASED)
Source: CEA
-
7/29/2019 Power Scenario
9/69
MAJOR LEGISLATIVE / POLICY INITIATIVES
OF GOVERNMENT 1998- Electricity Regulatory Commission Act
1998 - Electricity Laws (Amendment) Act
2001- Electricity Conservation Act
2003- Electricity Act
February ,2005- National Electricity Policy
January 2006- National Tariff Policy
August 23, 2006 - Rural Electrification Policy
August 2006- Integrated Energy Policy.
January 2007- Report submitted by Working Group on Power for 11th Plan constitutedby Planning Commission.
August,2007 - National Electricity Plan notified.
-
7/29/2019 Power Scenario
10/69
Access to electricity for all households in next 5years.
Availability of power on demand to be fully met by2012
Energy shortage and peaking shortage to beovercome by providing adequate spinningreserves
Reliability and quality of power to be supplied in
efficient manner . Electricity Sector to achieve financial turnaround
and commercial viability
Consumersinterests to be accorded top priority.
NATIONAL ELECTRICITY POLICY THE WAY FORWARD
-
7/29/2019 Power Scenario
11/69
NATIONAL ELECTRICITY POLICY - ENCOURAGING PRIVATE
PARTICIPATION
Competition encouraged - to bring significant benefit toconsumers
Guidelines for competitive bidding issued by Government inJanuary,2005.
Role of private participation in generation, transmission anddistribution to become increasingly critical in view of rapidlygrowing investment needs.
Central and State Governments to develop workable andsuccessful models for public private partnership.
Special mechanisms to be created to encourage private investment
in transmission sector
-
7/29/2019 Power Scenario
12/69
NATIONAL ELECTRICITY POLICY - ENCOURAGING PRIVATE
PARTICIPATION
Private Sector participation in distribution encouraged forachieving requisite reduction in T&D losses and improvingquality of service to consumer
Multi Year tariff framework- important structural incentiveto minimize risks for utilities and consumers, promoteefficiency and rapid reduction of system losses.
Competition through concept of multiple licensees in same
area through their independent distribution system
-
7/29/2019 Power Scenario
13/69
Electricity Act & National Electricity Policy mandatesnon-discriminatory open access in transmission and, inphases in distribution.
Respective State Regulatory Commissions to
facilitative framework for open access. Well planned and strong transmission and distribution
system to ensure optimal utilization of transmissioncapacities
Would facilitate achieving objective of cost effectivedelivery of power.
Distribution reform - key to long term sustainability of
the power sector.
OPEN ACCESS IN TRANSMISSION AND DISTRIBUTION
-
7/29/2019 Power Scenario
14/69
PRESENT POWER SCENARIO
-
7/29/2019 Power Scenario
15/69
INSTALLED CAPACITY IN THE
COUNTRY (as on 31st August, 2008)
TOTAL IC-1,45,627 MW
. . .,12195
8.4%
NUCLEAR
4120
2.8%
THERMAL
93115
64%
HYDRO,
36198,
24.8%
CENTRAL ELECTRICITY
-
7/29/2019 Power Scenario
16/69
EVOLUTION OF UNIT SIZE OFCOAL BASED POWER PLANTS
Largest unit size in 1950-30 MW
First re-heat unit of 82.5 MW in 1966 at
Bandel TPS
First 200 MW unit at Obra TPS in 1977
First 500 MW unit at Trombay in 1984
Committee constituted by CEArecommended 800 to 1000 MW unit size in
future
In 11
th
Plan 800/660 MW units planned
CENTRAL ELECTRICITY
AUTHORITY
MINISTRY OF POWER
GOVERNMENT OF INDIA
CENTRAL ELECTRICITY
-
7/29/2019 Power Scenario
17/69
Unit Size MS. Pr MS/RH Temp Gross
Efficiency(HHV )
kg/cm2 oC (%)
30-50 60 482 ~3160-100 90 535 32-33
110/120/140 130 535/535 35-36
210 150 535/535 37.8250 150 535/535 38.4
500 170 538/538 38.6
PREVAILING UNIT SIZES IN
INDIA
210/250 & 500 MW Units Constitute Over 80% of the TotalCapacity
CENTRAL ELECTRICITY
AUTHORITY
MINISTRY OF POWER
GOVERNMENT OF INDIA
D t il f IC f bl
-
7/29/2019 Power Scenario
18/69
Details of IC of renewable energy
sources(As on 31.03.2008)
Sources / Systems Installed Capacity ( MW)
Wind Power 7666.84
Biomass Power &Biomass Gasifiers
1325.63
Small Hydro Power 2034.07Solar power & others
87.87Total 11,125.41
TRANSMISSION & NATIONAL GRID
-
7/29/2019 Power Scenario
19/69
TRANSMISSION & NATIONAL GRID
Development in a phased manner commensurate withgeneration / load growth.
Economy in generation through efficient transmission
Conservation of Right-of-Way
In forest areas with rich flora & fauna, construction of
lines with high towers / high voltage rating leading
to reduced forest cutting.
High capacity lines (HVDC & 765 kV)
EVOLUTION OF ELECTRIC GRID
-
7/29/2019 Power Scenario
20/69
National
Grid
1950-60s
1970-80s
2000 onwards
Local
1950s
EVOLUTION OF ELECTRIC GRID
State
Grids by
SEBs
Regional Gridswith ATS of
Central
Generation
Shift from
Regional self
sufficiency
concept to
National level
Planning
Interconnecting
Regional Gridswith HVDC
1990s
Towards National Grid System
BENEFITS OF NATIONAL GRID
-
7/29/2019 Power Scenario
21/69
16441
22526
30000
23134
0
5000
10000
15000
20000
25000
30000
35000
2004-05 2005-06 2006-07 2007-08
Energy Traded
EnergyinMillonUnits
1129 % increase in number of
approved transactions in Short-term
Open Access at Inter State level
82% increase in volume of energy
traded in Short-term Open Access at
Inter State level
Encourage Competition and Choice by facilitating electricitytrade
BENEFITS OF NATIONAL GRID
(Contd. .)
BENEFITS OF NATIONAL GRID (Contd )
-
7/29/2019 Power Scenario
22/69
Security and Reliability enhanced by reduction in number of grid
disturbances
Grid Disturbances
74
53
7 2 1 0 03 4 0 0 0 0 0
0
20
40
60
80
100
2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08
Year
Nos.
Minor Major
BENEFITS OF NATIONAL GRID (Contd. .)
-
7/29/2019 Power Scenario
23/69
Development of Transmission
Voltages Levels
132 kV Highest level at the time of
Independence
Iintroduction of 220 kV in 1960
400 kV in 1977
HVDC back-to-back link in 1989,
500kV, HVDC bi-pole line in 1990 765 kV transmission line from 2000
onwards.
-
7/29/2019 Power Scenario
24/69
-
7/29/2019 Power Scenario
25/69
119,290
150,477
197,927 209,072
293,210
1997 2002 2007 2008 ( upto
Feb )
2012 (proj.)
GROWTH OF HIGH VOLTAGE TRANSMISSION LINKS
Source: CEA
Cumulative HT Lines 220 KV and above (in ckm)
-
7/29/2019 Power Scenario
26/69
PER CAPITA CONSUMPTION OF ELECTRICITY IN INDIA
Source: CEA
176
348
559632 672
704
1000
613
1980-
81
1990-
91
2000-
01
2004-
05
2005-
06
2006-
07
2007-
08
2011-
12
kWh/year
(Projected)
As per UN Methodology (Gross Electrical Energy Availability /
Population)
Growth Pattern
STATUS OF POWER SECTOR
-
7/29/2019 Power Scenario
27/69
Country facing energy shortage of 9.8% andpeak shortage of 16.6% (2007-08).
As per Census 2001, only about 56% of
households have access to electricity, with ruralaccess being 44% and urban access about
82%.
Annual per capita consumption about 704 kWhas against world average of about ~2400 KWh.
STATUS OF POWER SECTOR
-
7/29/2019 Power Scenario
28/69
ACTUAL POWER SUPPLY POSITION OF
THE COUNTRY (2007-08)
Peak (MW) Energy (MU)
Requirement 1,08,886 7,37,052
Availability 90,793 6,64,660
(-)Shortage/(+)Surplus
(-)18,093 (-)72,392
(%) (-)16.6 (-)9.8
-
7/29/2019 Power Scenario
29/69
ACTUAL POWER SUPPLY POSITION OF
THE COUNTRY (April,08-August,08)
Peak (MW) Energy (MU)
Requirement 1,06,922 3,18,813
Availability 91,363 2,84,861
(-)Shortage/
(+)Surplus
(-) 15,559 (-)33,952
(%) (-) 14.6 (-) 10.6
-
7/29/2019 Power Scenario
30/69
CAPTIVE POWER
National Electricity Policy stipulates liberalprovisions for setting up captive power plants
Installed Capacity if Captive plants- 22,335 MW
(10th Plan end)
Open Access to be made effective
Efforts underway to resolve crucial issues, which
are Cess on captive power generation not to be imposed.
Wheeling charges for transfer of surplus power may not exceed 7%of the generation cost within the state.
-
7/29/2019 Power Scenario
31/69
Captive Power
Very high electricity duty imposed on captive powergeneration by some states.
Very high cross subsidies surcharge levied by somestate. To be brought down
Fixation of reasonable tariff by State RegulatoryCommission for surplus power available from CPPs.
To make available additional fuel required by CPPs
SERCs to promote arrangements between co-generator and concerned distribution licensee forpurchase of surplus power from cogeneration plants.
MAJOR PROBLEMS OF POWER
-
7/29/2019 Power Scenario
32/69
MAJOR PROBLEMS OF POWER
SECTOR
Inadequate power generation capacity
Lack of optimum utilization of the existing
generation capacity
Inadequate inter-regional transmission
links
Inadequate and ageing sub-transmission
& distribution network
Cont..
MAJOR PROBLEMS OF POWER SECTOR
-
7/29/2019 Power Scenario
33/69
High T&D losses, large scale theft and skewed
tariff structure
Slow pace of rural electrification
Inefficient use of electricity by end consumer
Lack of grid discipline
MAJOR PROBLEMS OF POWER SECTOR
-
7/29/2019 Power Scenario
34/69
CAPACITY ADDITION PLANNINGFOR 11TH AND 12TH PLAN
10TH PLAN TARGET AND ACTUAL
-
7/29/2019 Power Scenario
35/69
10TH PLAN TARGET AND ACTUAL
CAPACITY ADDITION
6
(MW)
Original Target 41,110
Capacity Slipped / Dropped 21,281
Net Capacity Addition from Original Target 19,829
Additional Projects identified during the Plan 8,320
Capacity Slipping from additional projects 6,969
Net Capacity Addition from additional Projects 1,351
Net Capacity added during 10TH Plan 21,180*
* Thermal -12,114 MW, Hydro 7,886 MW, Nuclear 1180 MW
MAJOR REASONS FOR SLIPPAGES FROM 10th PLAN (MW)
-
7/29/2019 Power Scenario
36/69
S.No Major Reasons for Slippage
Original Plan Additional
Projects-
ThermalThermal Nuclear Hydro
1 Delay in supplies/erection by suppliers/ contractors 2670 220 679 3350
2 Delay in tie-up super critical technology by BHEL (one
unit at Sipat and one at Kahalgaon were replaced by 500
MW units)
3960
3 Non-availability of Gas 1713 1450
4 Delay in award of works mainly in state sector/NLC 1423 222 835
5 Projects not taken up/Escrow cover not given/financialclosure not achieved/funds not tied up
5278 23
6 Delay in clearance/investment decision (Hydro projects) 2391
7
Hydro Project - delay in environmental clearance,
geological surprises, natural calamities, R&R issues,
delay in signing of MoU, Court Cases
3155
8 Law & Order Problems 500 60
9Nuclear projects included on best effort basis(otherwise
scheduled for XI plan)1220
10 Adjustment due to change of size - 990 91
Total 14554 220 6507 6969*
MAJOR REASONS FOR SLIPPAGES FROM 10th PLAN (MW)
Total slippage: 21,281MW* Out of a total additional capacity of 8320 MW identified during MidTerm Review
-
7/29/2019 Power Scenario
37/69
Major Steps of Integrated approach
Capacity Addition from Conventional fuel based plants
complemented by Renewable Energy based plants toextent possible.
National Electricity Plan based on Conventional EnergySources with priority to Hydro and Nuclear plants
Strategies/ Initiatives being taken/ required to be takenfor low carbon growth i.e. Introduction of Clean CoalTechnologies (Supercritical Technology, Ultrasupercritical technology, IGCC),
Other measures to reduce pollution i.e. Reduction in T&D
losses, R&M of Old thermal power projects, Retirementof old and small size generating units, Coal qualityimprovement
POWER GENERATIONCENTRAL ELECTRICITY
AUTHORITY
-
7/29/2019 Power Scenario
38/69
POWER GENERATION - STRATEGY
Large emphasis on hydro development.Constraints restricting progress are large gestationperiod, high capital cost, Issues such as R&R, law &order etc. New Hydro Policy to encourage private
participation in hydro power generation. Limited dependability on gas based capacity -
Availability of gas at reasonable rates being aconstraint for gas based projects. During 11th Plan
only about 6,843 MW gas based capacity envisaged. Active steps to harness Nuclear energy on a larger
scale being taken but contribution minor as yet.
Renewables.
POWER GENERATION -STRATEGY
AUTHORITY
MINISTRY OF POWER
GOVERNMENT OF INDIA
POWER GENERATIONCENTRAL ELECTRICITY
AUTHORITY
-
7/29/2019 Power Scenario
39/69
POWER GENERATION - STRATEGY
Renewable energy sources to be madeeconomically viable- At present can playdominant role in meeting remote locateddemands where not economic to extend the
grid. Coal based power projects expected to be mainstay of Indian Power Sector for next 50-70 years.Continuous efforts directed at generating
maximum energy from each tonne of coal withminimum effect on environment
POWER GENERATION- STRATEGY
AUTHORITY
MINISTRY OF POWER
GOVERNMENT OF INDIA
-
7/29/2019 Power Scenario
40/69
Development of Hydro Power projects
Plan Period Hydro Capacity
Addition (MW)
Total Hydro Capacity
at the end of plan
(MW)
11
th
Plan (2007-08 to2011 - 12) 15627 50280
12th Plan (2012-13 to
2016-17)
30000 80280
13th Plan (2017 - 18
to 2021-22)
31000 111280
14th Plan (2022-23 to
2026 - 27)
36494 147774
-
7/29/2019 Power Scenario
41/69
DEMAND AND CAPACITY REQUIREMENT
Year Energy
Requirement
(BU)
Peak Demand
(MW)
Proposed Capacity
Addition during 5
year plan (MW)
Generation
growth rate
(CAGR)
2011-12 1038 1,52,000 77,070*
( 11th Plan)
9.5% (over2006-07)
2016-17 1470 2,18,209 94,000
(12th Plan)
7.4% (over2011-12)
* Feasible capacity as per latest assessment
-
7/29/2019 Power Scenario
42/69
26,783 MW36,874 MW
15,043 MW
CENTRAL SECTORSTATE SECTOR
PVT SECTOR
47%(34%)
19%
Total 78,700 MW
CAPACITY ADDITION TARGETTED FOR 11th
PLAN (SECTORWISE)
-
7/29/2019 Power Scenario
43/69
FEASIBLE CAPACITY ADDITION FOR
11th PLAN 77,070* MW
Thermal 58,183 MW( Coal 48,609 MW, Gas- 7,293 MW, Lignite- 2,280 MW)
Additional capacity expected : New Renewables 14,000 MW: Captive 12,000 MW
* Feasible capacity as per latest assessment
NUCLEAR,
3,380MW, 4.3%
THERMAL,
58,183MW,
75.5%
HYDRO,
15,507MW,
20.2%
-
7/29/2019 Power Scenario
44/69
11TH PLAN TARGET AND STATUS 10th Plan capacity addition only 21,180 MW. About 11,000 MW
slippages due to causes attributable to equipment suppliers and
contractors.
11th Plan 77,070 MW
- 11,404 MW capacity already commissioned (Till date)
- 65,666 MW (83%) under construction
- 85% hydro capacity under construction- Coal Linkage available for 96% of projects
- All gas based projects under execution or gas tied upfrom local sources
Additional 3,720 MW thermal projects under best effort category.
Additional 13,000 MW gas based projects if gas available atreasonable price
INTERNATIONAL CONCLAVE ON KEY
-
7/29/2019 Power Scenario
45/69
INTERNATIONAL CONCLAVE ON KEY
INPUTS
On 4th-5th July,2007 organized by
CBIP/MoP/CEA.
Purpose-To discuss issues to be addressed to
ensure timely Implementation of projects
during 11th Plan and beyond .
MAJOR ISSUES AND CONSTRAINTS TO
-
7/29/2019 Power Scenario
46/69
MAJOR ISSUES AND CONSTRAINTS TO
BE ADDRESSED
Manufacturing Capability/ Availability ofMain Plant and
Balance Of Plant Equipment
Constraints in supply of main equipment forthermal capacity as well as in supply of balanceof plant like Coal Handling plant, Watertreatment plants, Ash Handling, CW Pumps etc.
Need to develop additional domestic players toadequately meet additional demand andpromote competition.
MAJOR ISSUES AND CONSTRAINTS TO
-
7/29/2019 Power Scenario
47/69
MAJOR ISSUES AND CONSTRAINTS TO
BE ADDRESSED
Construction and Erection Agencies &EquipmentAugmentation required in number of construction agencies
undertaking Civil & E&M works at power plants - Limitedcontractors in erection of cooling towers, Chimneys ,
tunneling, dam construction etc.Serious efforts needed by major power companies to
develop vendors for supply and erection of equipment andfor taking up civil construction.
New technologies and Use of latest construction machineryfor hydro projects required for fast progress in construction.
MAJOR ISSUES AND CONSTRAINTS TO
-
7/29/2019 Power Scenario
48/69
MAJOR ISSUES AND CONSTRAINTS TO
BE ADDRESSED
Fuel Availability Requirement of coal for 11th Plan 550 MT; 40 MT equivalent of 68 MT
of Indian coal to be imported
Requirement of gas (90% PLF) 89 MMSCMD; Availability at present-
36 MMSCMD; gas not sufficient
Transportation for fuel and equipment
Establishment of new rail links for coal evacuation from coal mining
blocks
Railways, Coal , MoP to formulate Fuel Supply Transport Agreement
MAJOR ISSUES AND CONSTRAINTS TO
-
7/29/2019 Power Scenario
49/69
MAJOR ISSUES AND CONSTRAINTS TO
BE ADDRESSED
Transmission & Distribution Equipment Need for capacity building for transmission and distribution system
including supply of equipment and execution of works - Substantialaugmentation inmanufacturing capacity of transformers; Need forindigenous manufacturing capacity for 765 KV voltage level equipment,increasing test facilities, online test facilities and mobile repair facilities.
Strengthening of erection and commissioning teams and development ofnew vendors
Increase in demand of CRGO
Shortage of indigenous materials and Equipment viz. meters, singlephase distribution transformers and switchgears, OLTC and bushings.
Franchisees to be developed in rural areas and local community to betrained.
More agencies required for turnkey execution of projects.
Installation of LT Capacitors to be speeded up.
MAJOR ISSUES AND CONSTRAINTS TO
-
7/29/2019 Power Scenario
50/69
MAJOR ISSUES AND CONSTRAINTS TO
BE ADDRESSED
Critical Key Inputs To encourage domestic steel producers for production of CRGO
Advanced planning for material to be imported
CRGO to be exempt from custom duty
Detailed analysis by Planning Commission to assess requirement ofvarious key input considering requirement of all sectors of economy
Manpower Development & Training
CEA has taken up with project developers and major EPC contractors toadopt ITI in vicinity of projects to build up skilled manpower pool forPower Sector to be utilized by them.
Quick implementation of National Training Policys recommendation -allocation of separate funds of 1.5% of salary budget - gradually increaseto 5% for meeting training needs
Man power requirement during 11th Plan is 1 Million for Constructionand O& M
MAJOR ISSUES AND CONSTRAINTS TO
-
7/29/2019 Power Scenario
51/69
MAJOR ISSUES AND CONSTRAINTS TO
BE ADDRESSED
Delays in clearances Testing facilities to be increased and CPRI to play a proactive
role
R & D
Power Utilities as well as manufacturing units to enhance budgetallocation for R&D
To attract youngtalent
11th Plan tentative targets for grid interactive
-
7/29/2019 Power Scenario
52/69
11th Plan tentative targets for grid interactive
renewable power(Figures in MW)
Sources / Systems Target for 11th
plan
Wind Power 10,500
Biomass Power Baggasse Co-
generation
Biomass Gasifiers
2,100
Small Hydro (up to 25 MW) 1400
Total 14,000
Targets for 12th
Plan likely to be at least 14,000 MW
-
7/29/2019 Power Scenario
53/69
Village Electrification
Number of villages electrified increased
from 3061 in 1950 to about 4,88,655 in
2008 (as on 31.07.08, 82.3% village
electrification).
Renewable Energy Sources during 12th Plan
-
7/29/2019 Power Scenario
54/69
Renewable Energy Sources during 12th Plan
Capacity addition during 12th Plan expected tobe more than 11th Plan due to incentives byMNRE for setting up of Solar and Wind power
plants Considering at least 14,000 MW during 12th
Plan also, by 12th Plan end about 38,000 MWRenewable power expected.
Assuming PLF of 20 %, generation about 67BU.
This energy considered while planning for 12th
Plan
12th Plan Tentative Capacity Addition
-
7/29/2019 Power Scenario
55/69
12th Plan Tentative Capacity Addition
Demand as per 17th EPS Energy Requirement 13,92,066BU; Peak Demand- 2,18,209 MW
Spinning Reserve 5% as per National Electricity Policy.Capacity corresponding to 3000 MW and 1600 MW alsoworked out
25,000 MW Hydro and 8,500 MW Nuclear as must run stations.
As result of studies 12th Plan total Generating capacity 94,431which includes 61,171 MW thermal.(28,190 MW PH, 15,495 MWLC, 14,800 MW Coastal)
Capacity with 1600 MW S.R.- 81,570 MW; 3000MW S.R.82,970 MW
Fuel consumption(2016-17) Coal 815 MT, Lignite 60 MT
All India Studies for 5% S.R: LOLP 0.18%; ENS 0.00%(Norms LOLP-1% & ENS- 0.15%)
13th Plan Tentative Capacity
-
7/29/2019 Power Scenario
56/69
13th PlanTentative Capacity
ExpansionASSUMPTIONS
17th EPS Demand Energy Requirement- 19,14,508MU; Peak Demand- 2,98,253 MW
Spinning Reserve - 5% .
Beginning of 13th
Plan 37,014 MW Coal & Lignitebased capacity more than 27 yrs old. (5,634 MW capacityupto 100 MW unit size and 31,380 MW capacity greater than 100 MW unit
size)
Studies indicate 13th Plan capacity addition-1,05,060MW (Hydro-34,500 MW, Nuclear -8,000 MW, Thermal-62,560 MW including 6000 MW gas)
LOLP-0.18 % and ENS-0.007 %, Reliability Criteria
met.
-
7/29/2019 Power Scenario
57/69
STRATEGIES FOR CLEAN
AND
GREEN ENVIRONMENT
Existing status of CO2 per capita
-
7/29/2019 Power Scenario
58/69
Country
Per capita CO2 emission in 2004
(tonnes/MWhr of CO2)
India 1.2
USA 20.6Australia 16.2
U.K 9.8
Japan 9.9China 3.8
World 4.5
UNDP Human Development report 2007/08
Existing status of CO2 per capita
emission different countries
-
7/29/2019 Power Scenario
59/69
Clean Coal technologies Supercritical Technology 2% efficiency gain possible
Ultra Supercritical Technologyadditional efficiency 0.75% over
800 MW supercritical
Integrated Gasification Technology higher efficiency of 40-
45%
Reduction in T & D losses All India T&D losses- 28.65%in 2006-07. Aim to bring down to 15%
R & M of old thermal power stations Benefits of
CDM to be extended to overcome fund constraints
Energy Efficiency improvement
TECHNOLOGIES USED ATCENTRAL ELECTRICITY
AUTHORITY
-
7/29/2019 Power Scenario
60/69
COMBUSTION STAGE
Adoption of Supercritical technology Ultra supercritical (USC) and advanced USC
technology
Circulating Fluidized Bed Combustion ( CFBC)
Pressurized Fluidized Bed Combustion (PFBC) Integrated Gasification Combined Cycle (IGCC)
In-Situ gasification
Low NOx burners
Oxy-fuel combustion
Clean coal technologies( CCT) have pollution
abatement in energy conversion process soexternal environmental control equipments not
required
MINISTRY OF POWER
GOVERNMENT OF INDIA
UNIT-WISE DETAILS OF I C (coal +
-
7/29/2019 Power Scenario
61/69
UNIT WISE DETAILS OF I.C (coal +lignite)( as on 31/3/2007)
UNIT SIZE INMW
NO. OFUNITS
CAPACITY(MW) DESIGNEFFICIENCY(%)
ActualOperating
Efficiency(%)
Upto 100 95 5634 28.2 to 31.3
>100 &
upto 199
73 8440 34.4
200/210 157 33,580 35.6 to
37.04
250 17 4,250 38.3
500 36 18,000 38.6
Sub-critical units in 10th, 11th , 12th, 13th
-
7/29/2019 Power Scenario
62/69
Sub critical units in 10 , 11 , 12 13
& 14th Plans
600 MW
(nos)
500 MW
(nos)
250/300
/330
MW
(nos)
200/210
MW
(nos)
125/135
MW
(nos)
Total
Subcritical
MW
10
TH
Plan 0 11 7 9 4 9620
11TH Plan 8 42 62 6 14 45470
12th Plan 7 20 12 0 2 18270
13TH Plan 0 8 0 0 0 4000
14th Plan 0 0 0 0 0 0
Super-critical units in 10th , 11th , 12th ,
-
7/29/2019 Power Scenario
63/69
Super critical units in 10 , 11 , 12 ,
13th & 14th Plans
Total Sub
critical
MW
660 MW
(nos)
800 MW
(nos)
Total
Super
critical MW
Total MW
10TH Plan 9620 0 0 0 9620
11TH Plan 45470 7 1 5420 50890
12th Plan 18270 25 33 42,900 61,170
13TH Plan 4000 36 36 52,560 56,560
14th Plan 0 45 52 71,300 71,300
Comparison of S b critical/S per critical
-
7/29/2019 Power Scenario
64/69
Comparison of Sub-critical/Super critical
Capacity In Various Plans (MW)
9620
45470
18270
400000
5420
42900
52560
71300
0
10000
20000
30000
40000
50000
60000
70000
80000
10th Plan 11th Plan 12th Plan 13th Plan 14th Plan
Sub-Critical Super Critical
ALL INDIA EFFICIENCY AND
-
7/29/2019 Power Scenario
65/69
ALL INDIA EFFICIENCY AND
EMISSION RATES
All India thermal efficiency 32.44% (2006-07)
(coal & lignite based plants)
Present weighted average CO2 emission rate (t CO2
/MWh) (including imports) : 0.80 (2006-07)
Likely Coal Based Capacity Addition & Expected Emission
-
7/29/2019 Power Scenario
66/69
End of
The
Plan
Coal
Based
Capaci
ty
Addition
(MW)
Cumulati
ve
Coal
Base
dCapacity
(MW)
Total
Gener
ation
from
CoalBased
Plants
(BU)
Coal
Consumpti
on
(MT)
Co2
Emissio
n
(MT)
Co2
Emissio
n per
unit of
ThermalGenerati
on
Expected
Ther
mal
Effici
ency
Total Ash
Genera
tion
(MT)
11th Plan 50240 116610 708 492 722 1.02 35.3 182
12th Plan 58485 175095 1164 785 1152 0.99 36.4 278
13th Plan 56500 231595 1542 1028 1507 0.97 36.85 363
14th Plan 72000 303595 2033 1337 1961 0.96 37.3 471
-
7/29/2019 Power Scenario
67/69
Requirement Of Planning Process
Data of Existing PlantsOutage Rate, Heat Rate, Auxiliary Consumption,
Monthly Energy If Hydro Project, Coal Price
Data,Capacity (MW),Life of the plant,Capital Cost, Executing Agency
Candidate Projects
Demand data
Load Curves
Hourly demand data of Past one Year
-
7/29/2019 Power Scenario
68/69
Planning Models In CEA
Integrated System Planning (ISPLAN)
Expansion Generation Electric Analysis
System (EGEAS)
Multysym Model
-
7/29/2019 Power Scenario
69/69
Thank You