power sector financing project report

57
ACKOWLEDGEMENT It is with a sense of gratitude, I acknowledge the efforts of entire hosts of wellwishers who have in some way or other contributed in their own special ways to the success and completion of this project. First of all, I express my sage sense of gratitude and indebtedness staff of NTPCSAIL Power Company (P) Ltd (NSPCL), Bhilai from the bottom of my heart, for their immense actions, support, and faith. I sincerely thank my project guide Shri J.R Sikidar, Sr.Manager (F&A), NSPCL Corporate Center, New Delhi for his valuable suggestions, motivation and encouragement through out this project. Also, I also express my sincere thankfulness to NSPCL Finance & accounting team, HR–Training and Development cell for extending their timely support. . B. SatyaGopi MP072453801

Upload: satyagopi

Post on 29-Apr-2017

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Power sector Financing Project Report

 

 

ACKOWLEDGEMENT

It  is with  a  sense  of  gratitude,  I  acknowledge  the  efforts  of  entire  hosts  of well‐

wishers who have in some way or other contributed in their own special ways to the success 

and completion of this project. 

First of all, I express my sage sense of gratitude and indebtedness staff of NTPC‐SAIL 

Power Company  (P)  Ltd  (NSPCL), Bhilai  from  the bottom of my heart,  for  their  immense 

actions, support, and faith. 

I  sincerely  thank  my  project  guide  Shri  J.R  Sikidar,  Sr.Manager  (F&A),  NSPCL 

Corporate Center, New Delhi for his valuable suggestions, motivation and encouragement 

through out  this project.   Also,  I also express my sincere  thankfulness  to NSPCL Finance & 

accounting team, HR–Training and Development cell for extending their timely support. 

 

B. SatyaGopi 

MP‐072453801 

 

 

 

Gopi
Text Box
i
Page 2: Power sector Financing Project Report

 

 

Contents

                      Page no. 

Acknowledgements                i 

Certificate of originality                ii  

Proforma for approval of project proposal          iii 

Executive summary & Synopsis              vi   

1.0 Introduction                 1   

2.0 Power Sector ‐ Emerging Scenario          3 

  2.1  Power Industry structure in India          4   

3.0 Role of NTPC/NSPCL (A Jv of NTPC & SAIL) in Indian Power sector   7 

4.0 Power sector & issues              

  4.1  Generation                11 

  4.2  Transmission                 12 

  4.3  Distribution                 13 

  4.4 Demand Supply Position              14 

  4.5 Financing Requirements              15 

5.0  Power Project Life Cycle              17 

  5.1 Project Finance                 17 

  5.2 Operational Agreements             18 

Page 3: Power sector Financing Project Report

 

 

  5.3 Project Development               19 

6.0 Project Economics                22 

  6.1 Fuels Supply                 22 

  6.2 Capital costs                23 

  6.3 Wholesale Tariff Structure             24 

7.0 Power Project Financing              26 

  7.1 Types and Sources of Finance           26 

  7.2 Trends in Power Sector Financing          31 

  7.3 Major Financiers in Power Sector          31 

8.0 Budgeting in Power Plants;            32 

  8.1 Types of budget heads in power plant;        32 

9.0   Capital Budgeting for dummy Power project;        36 

9.1 Projections for a 500MW unit.          37 

9.2 Projections for a 2x250MW unit          46 

10.0 Conclusions & Recommendations          52 

 

References/Bibliography 

 

 

 

 

Page 4: Power sector Financing Project Report

 

 

1

1.0 Introduction 

Power is the critical infrastructure for the growth of economy. Acceleration in the growth of 

economy will depends upon a financially & commercially viable power sector that is able to attract 

fresh investments. Even though India ranks 5th in the world in terms of total installed capacity; it is 

one of the lowest in terms of per capita consumption of power. India has continuously experienced 

shortages in energy and peak power requirements.  

According to the Central Electricity Authority's ("CEA") monthly review of the power sector 

("CEA Monthly Review") published in April 2012, the total energy deficit and peak power deficit for 

March 2012 was approximately 8.5% and 10.1%, respectively. Along  it, the Indian Power sector  is 

among  the  least  efficient  in  the  world  in  terms  of  output  units  of  electricity  per  unit  of  fuel 

(coal/gas/oil). Even if we compare India with other developing nations like China and Korea, India is 

far behind in terms of generation efficiency. 

As per the recent statement given to a question in Rajya Sabha on 07/05/2012 by Minister 

of  State  for  Power Shri K.C.  Venugopal ,  “As  per  the  18th Electric  Power  Survey  Report,  Peak 

Demand of 1,99,540 MW and Energy Requirement of 13,54,874 BU has been estimated at the end 

of Twelfth  Five Year Plan  i.e. 2016‐17. At  the end of 11th Five year Plan i.e. 2011‐12  the country 

was facing Peak Shortage of 13815 MW (10.6 %) & Energy Shortage of 79313 MU (8.5 %).”   

The Working Group  on  Power  constituted  by  the  Planning  Commission  to  formulate  the 

12th Five Year Plan for the Power sector has submitted  its report to the Planning Commission. As 

per  the  report  of  this  Working  Group,  capacity  addition  requirement  during  the  12th Plan  is 

75,785MW  on  all  India basis.  The  Sector‐wise  and  fuel‐wise  break  up  of  12th Plan  capacity 

Page 5: Power sector Financing Project Report

 

 

2

addition programme as per the report of the Working Group on Power is as under:     (In MW) 

  Hydro  Thermal Nuclear Total 

Central  5632  11426  2800  19858 

State  1456  12340  0  13796 

Private  2116  40015  0  42131 

Total  9204  63781  2800  75785 

 Source: Press information Bureau Dtd. 07/05/2012 

The target for new capacity additions has created a platform for approximately 150 billion 

USD of investments across different segment of the generation sector. Although, the system is still 

in a transitory phase, deepening reforms and a new policy framework have to create an optimistic 

outlook.   

Therefore, there are following goals of this project 

A brief Study of Power sector & Power Industry structure in India 

Identifying the demand & supply gaps in Generation. 

Role of NTPC/NSPCL (A Jv of NTPC & SAIL) in Indian Power sector.  

Identifying various steps involved & study of Project life cycle of a power project.  

Study of various sources of power project financing & Investment patterns. 

Study of various costs involved, long term Capital Requirement & capital budgeting for the 

Power Generation by taking a 500MW & 250MW model power projects. 

 

 

Page 6: Power sector Financing Project Report

 

 

3

2.0 Power Sector Scenario & Industry Structure. 

India has a total installed capacity of 200 GW as on April 2012.  Even though India has been 

the 5th largest producer of Electricity in the world, it continuously facing acute shortages during the 

peak hours. The following table shows the preceding years Demand & deficit of Electricity. 

Years  Peak Deficit % Energy Deficit % 

           

2000‐01  13  7.8    Actual Power demand­Supply Position 2001‐02  11.8  7.5    Requirement  Availability  Surplus/deficit (+/‐) 2002‐03  12.2  8.8   

Fiscal year  (MU)  (MU)  (MU)    

2003‐04  11.2  7.1    2005  591373  548115  ‐43258  ‐7.3 2004‐05  11.7  7.3    2006  631544  578819  ‐52725  ‐8.3 2005‐06  12.3  8.4    2007  690587  624495  ‐66092  ‐9.6 2006‐07  13.3  9.6    2008  737052  664660  ‐72392  ‐9.8 2007‐08  16.6  9.8    2009  777039  691038  ‐86001  ‐11.1 2008‐09  11  11.1    2010  830594  746644  ‐83950  ‐10.1 2009‐10  12.7  10.1    2011  861591  788355  ‐73236  ‐8.5 2010‐11  9.8  8.5    2012  933741  837374  ‐96367  ‐10.3 2011‐12  12.9  10.3             

                 MU denotes Million Unit             Source: CEA Reports             

  

Considering  the  importance  of  development  of  power  sector  for  the  overall  growth  of 

economy, planning commission has given due importance in the previous & current five year plans. 

Indian Government has  set ambitious  target  to achieve “Power  to all  “as per national electricity 

plan.  To  revamp  the  Power  Sector, Government  of  India  have  taken,  number  of  path  breaking 

initiatives  in  the  recent past, both  in  terms of policy pronouncements and programmes,  ranging 

from  bringing  increasing  efficiency  in  generation  segment  through  introduction  of  super  critical 

technology, penetration of  commercial energy  in  the  rural  areas  and  consolidation of electricity 

Page 7: Power sector Financing Project Report

 

 

4

delivery systems  Indian Government has brought various structural changes to achieve the target 

through Indian Electricity Act 2003. 

Indian Electricity Act 2003; 

The  restructuring  of  power  systems  across  the  globe  started with  the  redesigning  of  its 

power markets. In India, electricity reforms started with the re‐evaluation of Indian Electricity Act‐

1910 and  the Electricity Supply Act‐1948, which  led  to  the Electricity Act, 2003.  Indian Electricity 

Act 2003 is the biggest mile stone in the history of Indian Power sector. The Electricity Act 2003 has 

been brought  about  to  facilitate private  sector participation  in  Indian Power  Sector  and  to help 

cash strapped SEBs to meet electricity demand. The Electricity Act‐ 2003 envisages competition in 

electricity market,  protection  of  consumer’s  interests  and  provision  of  power  for  all.  The  Act 

recommends  the  provision  for  National  Electricity  Policy,  rural  electrification,  open  access  in 

transmission, phased open  access  in distribution, mandatory  SERCs,  license  free  generation  and 

distribution, power trading, mandatory metering, and stringent penalties for theft of electricity.  

One more welcome  step  the  Indian electricity market has  seen  is  the  implementation of 

Availability  Based  Tariff  (ABT)  which  brought  about  the  effective  day‐ahead  scheduling  and 

frequency sensitive charges for the deviation from the schedule for efficient real‐time balancing.  

2.1 Industry Structure 

Public  sector  institutions  continue  to play  the dominant  role  in  the electricity  supply and 

delivery chain  in  India, primarily  through central and state  level government owned utilities. The 

following figure depicts the  interactions between the various players  in the  Indian power market. 

Page 8: Power sector Financing Project Report

 

 

5

The Ministry  of  Power  (MoP)  is  the  Central  government  institution  responsible  for  overseeing 

India’s electricity  industry. Several authorities and agencies operate under the MoP, among them 

the Central Electricity Authority (CEA), assists the MoP on technical and economic issues.  

 

Figure 2.2: Indian Power Market Institutional/Operational Framework 

The Central Electricity Regulatory Commission (CERC) is an independent statutory body with 

quasi‐judicial powers. The CERC has a mandate to regulate interstate tariff related matters, advise 

the central government on formulation of the national tariff policy and promote competition and 

efficiency  in the electricity sector. The CERC regulates Central government owned utilities both  in 

generation  and  transmission.  The  State  Electricity  Regulatory  Commissions  (SERCs)  have 

Page 9: Power sector Financing Project Report

 

 

6

jurisdiction  over  state  utilities  in  generation,  transmission  and  distribution.  Independent  Power 

Producers  (IPPs) are  regulated by CERC  / SERC depending on whether  they  sell power  to one or 

more  states.  Regional  Load  Dispatch  Centers  (RLDCs)  are  responsible  for managing  the  central 

transmission  system, whereas  State  Load  Dispatch  Center  (SLDCs) manages  the  intra‐state  and 

some  inter‐state  systems.  Central  generating  stations  are  contracted  to  state  utilities  and  are 

dispatched by RLDCs. State owned generating  stations  sell power  to  their own  state distribution 

licensee and are dispatched by SLDCs. Distribution licensees can also buy power from mega power 

projects,  IPP,  traders and  through  the power exchange. The  central government,  through public 

companies, owns and operates one‐third of total generation capacity and  interstate transmission 

lines. At the state level, SEBs own and operate most of the remaining two‐thirds of the generation 

capacity, as well as the majority of intrastate transmission and distribution systems.  

To  promote  power  trading  in  a  free  power  market,  Central  Electricity  Regulatory 

Commission  (CERC)  approved  the  setting  up  of  Indian  Energy  Exchange  (IEX) which  is  the  first 

power  exchange  in  India.  IEX  has  been modeled  based  on  the  experience  of  one  of  the most 

successful  international  power  exchanges,  “Nordpool”.  The  exchange  has  been  developed  as 

market based institution for providing price discovery and price risk management to the electricity 

generators, distribution licensees, electricity traders, consumers and other stakeholders.  

 

 

 

Page 10: Power sector Financing Project Report

 

 

7

3.0 Role of NTPC/NSPCL (A Jv of NTPC & SAIL) in Indian Power sector.  

NTPC Limited (formerly known as National Thermal Power Generation Limited),  India's  largest 

power  company,  was  set  up  in  1975  with  a  vision  “A  world  class  integrated  power  major, 

powering  India’s  growth with  increasing  global presence"  to  accelerate  power development  in 

India.  It has emerged as an  “Integrated Power Major”, with a  significant presence  in  the entire 

value chain of power generation business. NTPC  is a Government owned entity with 89.5% of  its 

paid‐up capital contributed by the Government and the balance of 10.5% being held with foreign 

institutional  investors,  financial  institutions, banks, and  the general public. NTPC  is awarded with 

“MAHARATNA” PSU status by Government of India. NTPC is primarily involved in constructing and 

operating  power  stations.  It  is  among  the world’s  largest  and most  efficient  power  generation 

companies. NTPC has installed capacity of 37514 MW as on April 2012. It has 

16 coal based power stations (29,195 MW), 

7 gas based power stations (3,955 MW) and 

7 power stations in Joint Ventures (4,364 MW). 

The company has power generating  facilities  in all major  regions of  the country.  It plans  to be a 

75,000  MW  company  by  2017.  NTPC  is  pursuing  expansion  of  its  business  activities  into 

hydroelectric generation, coal mining, gas exploration, and participation in the liquefied natural gas 

value chain, which supplements and supports its core power generation activities. 

  NSPCL is a Joint venture of two Maharatna companies “NTPC & SAIL” was incorporated on 

7th March  2011, with  50:50  equity  participation  of  both  promoter  companies.  Primarily  it was 

started to own, operate and maintain the captive power plants of Steel Authority of India Ltd (SAIL) 

at Rourkela, Durgapur  and Bhilai.  The  company  has been on the growth path since then.  

Page 11: Power sector Financing Project Report

 

 

8

Initially  it  started  with  an  installed  capacity  of  314MW  combined  of  all  three  power  plants 

supplying  captive  power  to  respective  SAIL  Units.  Going  in  expansion mode,  it  added  further 

capacity of 500MW (2X250) at Bhilai in the year 2009, taking the total capacity to 814 MW. Now it 

supply power not only to SAIL, but beyond the captive mode it also supplies power to Chhattisgarh 

Dadra Nagar Haveli, Daman & Diu  

Expansion project of Bhilai funded by Rural Electrification Corporation (REC) ‐1285Cr, Union 

bank 444Cr and IDBI ‐200Cr as a debt. 

The company  is poised for further capacity addition to the tune of 1725 MW as per  latest 

corporate plan besides  it  is  in the process of finalized  it  long term corporate plan to chart out  its 

ambitious growth path up  to 2022 with a view  to emerge   as significant contributor  to country’s 

economic development. 

Salient Features of NSPCL: 

• The Net Worth of the Company is steadily increasing over the past 5 years. 

• During the past 5 years (FY06 to FY10), the Net worth has increased from Rs389 Cr to Rs1135 

Cr. In the year FY07, out of Rs. 868 Cr of Net Worth, Rs. 781 Cr is Share Capital and Rs. 87 Cr is 

Reserves & Surplus. During this year the promoters had infused equity of Rs. 450 Cr for Bhilai 

Expansion Power Project (2 x 250 MW). 

• As on March 31, 2010, out of the total Share Capital of Rs. 951.50 Cr, Rs. 117.30 Cr of equity is 

towards existing plants at Durgapur and Rourkela, Rs. 33.20 Cr pertains to existing plant (CPP‐

II) of Bhilai and the balance Rs. 800 Cr of equity is towards Bhilai Expansion Power Project (2 x 

250 MW). 

• The operational performance of NSPCL has  improved consistently from FY02 to FY10. This  is 

owing  to  the  renovation & modernization  initiative  taken by NSPCL and better operational 

Page 12: Power sector Financing Project Report

 

 

9

management.  NSPCL,  Bhilai  PP‐  IIs  are  old  plants  with  dated  technology.  However,  with 

renovation  &  modernization  initiatives  taken  by  NSPCL  the  plants  are  running  at  high 

operational parameters.  

• There was a significant improvement in Durgapur and Bhilai plant in terms of units generated, 

PLF and availability factor. 

• Outages,  auxiliary  power  consumption,  specific  oil  consumption  and  heat  rate  have 

significantly decreased from the time of take over to FY10 for all the three Units. 

• The  PLF  of  the  plant  till  September2010  is  89.91%  as  against  the Normative Annual  Plant 

Availability Factor of 85% as per the tariff order. 

• The Gross Station Heat Rate for the Plant is 2399Kcal/kWh which is lower than Gross Station 

Heat Rate as per the CERC Regulations. 

• The Secondary fuel oil consumption for the plant is close to half as against CERC order. 

• The Auxiliary Consumption for the Plant  is  less than auxiliary consumption prescribed  in the 

CERC Regulations for tariff computation. 

• The return on equity is as per the CERC Regulations. 

Opportunity Areas for NSPCL going forward 

• Aggressive growth plans of SAIL which would need 4600 MW of captive requirement by 2020 

• SAIL’s vision of entering  the  thermal power business as part of  their Lakshya2020  initiative 

through NSPCL.  

• Huge demand for power generation capacity in India 

• Taking over the PP1 plants of SAIL 

• Taking over and turning around of DVC plants in Bokaro. 

• Potential amendment of clause on minimum 51% power consumption by the promoter of the 

captive power plant. 

Page 13: Power sector Financing Project Report

 

 

10

• Leveraging  existing  land  bank  of  SAIL  for  projects, which would  result  in  lower  gestation 

periods Constructing and operating Captive power plants for other bulk consumers/ industrial 

clusters / groups 

• Supply through open access 

−Supply to other SAIL plants through CTU 

−Supply to Bulk and other industrial consumers 

• Venturing into Power trading 

• Entry into managed distribution (Eg: SAIL townships) 

• Offering O&M and other consultancy services 

• Investing in Renewable energy 

• Investment for ash utilization 

Key Threats and Challenges 

• Heavy dependence on a single consumer (SAIL). 

• Rapidly evolving technology  

• Fuel Security 

• Dependence on NTPC for manpower and technical know‐how 

• Availability of skilled manpower in the market 

• Gradual phasing out of cross‐subsidy (which would lead to convergence of IPP & CPP) 

• Likely  cheaper  power  from  UMPPs  and  super  critical  power  plants may  be  a  threat  in  a 

competitive market scenario. 

 

 

 

 

Page 14: Power sector Financing Project Report

 

 

11

4.0 Power sector & issues  

4.1 Generation 

The  current  installed  capacity  is  approximately 200 GW with  coal being  the primary  fuel 

source. Despite  significant  recent additions,  there  is a  significant  stock of aging plants  that have 

poor  performances.  The  sector  also  suffers  from,  fuel  shortages,  inadequate  transmission 

evacuation  system,  regulatory  uncertainty  and  payment  security  concerns.  Concerns  about  the 

sector paved the path for reforms. Of this the central and state sector accounted for approximately 

89% [MOP, 2012]. The statistics point to high perception of risk  lack of enthusiasm on part of the 

private sector with regard to power generation in India.  

In the Central Sector, National Thermal Power Corporation (NTPC)  is a player of global scale. The 

State  Electricity  Boards  also  operate  generation  facilities  to  serve  their  demand.  Private  Sector 

comprises  of many  players  like  Tata  Power Company, Reliance  Energy, GVK, GMR  etc.   Despite 

reforms introducing private participation in the early 1990s, India’s electricity sector has remained 

dominated  by  the  state  owned  entities  and  has  been  unable  to  attract  adequate  private 

investments. Electricity Act 2003 introduced another wave of liberation aimed at create a legal and 

structural framework for a competitive market.   

 

 

 

 

Page 15: Power sector Financing Project Report

 

 

12

To maintain the projected economic growth, India needs to add 75 GW of new capacity by 

2017. The growth  in capacity must be matched with efforts  to  i) optimize utilization of unevenly 

distributed  fuel  resources with proper evacuation  system;  ii) diversify  fuel  sources with  cheaper 

and  cleaner  fuel  from  huge  hydro  and  other  renewable  energy;  iii)  build  raw  material  and 

infrastructural  support;  iv)  adopt  new  generation  technologies;  and  v)  renovate  and modernize 

program of existing plants.  

 

The  total  funds  requirement  for  the  generation  segment  during  the  12th  Plan  has  been 

estimated to be approximately `1372580 Cr, of which central sector requirement is 49%. However, 

lack of financing and higher interest rates are likely to impede funds mobilization. But at the same 

time  interest  from  foreign  investors  and  the  renewed  interest  of multilateral  agencies  in  the 

electricity sector has been strong. There has been resurgence of international interest in the Indian 

power sector.  

4.2 Transmission  

Transmission plan  in  India has always been generation based.  It  is  therefore not going  to 

help because there are bound to be imbalances. Even today, CTU and STU’s are very conservative 

Page 16: Power sector Financing Project Report

 

 

13

in  agreeing  to  create  more  than  the  desired  transmission  capacity  and  freely  allowing 

interconnectivity.  Investments  in  the  Transmission  sector  have  been  therefore  been  inadequate 

due to the heavy emphasis on generation capacity. In most states, the existing distribution network 

has  been  formed  by  expanding  and  connecting  smaller  and  disjointed  networks.  Consequently, 

there are  several deficiencies  in  the Transmission  system, such as high  losses and  low  reliability. 

The major player  in  this  sector  is  the government owned Power Grid Corporation of  India.   The 

total transmission system  in  India at 765/HVDC/400/230/220 kV corresponding to 1,32,329 Mega 

Watts  (MW)  of  installed  generation  capacity  at  the  end  of  March  2007  was  198,089  circuit 

kilometers of transmission lines, 251,439 MVA of AC substation and 8,200 MW of HVDC substation 

capacity.  

4.3 Distribution  

India’s distribution sector has traditionally been a leaking bucket with the holes deliberately 

crafted and the leaks carefully collected as economic rents by various stakeholders that control the 

system. The  logical  thing  to do would be  to  fix  the bucket  rather  than  to persistently emphasize 

shortages of power and forever make exaggerated estimates of future demands for power. Most 

initiatives  in  the power  sector  (IPPs and mega power projects) are nothing but ways of pouring 

more  water  into  the  bucket  so  that  the  consistency  and  quantity  of  leaks  are  assured.  The 

Distribution arm of the Power Sector had been the domain of the SEBs for a very long time which 

gave rise to financial problems due to lack of collection of dues. The SEB’s financial difficulties led 

to  problems  in  the  upstream  for  power  generation.  To  alleviate  this  situation  Distribution 

Companies are beginning to be privatized  in some states, most notable among them being Delhi. 

Page 17: Power sector Financing Project Report

 

 

14

Reliance Energy and Tata Power Company were the first private sector players to make a foray into 

power distribution in the country.  

4.4 Demand Supply Position  

The  steady  increase  in  electricity  demand  is  attributed  to  the  country’s  rapid  economic 

growth.  Over  and  above  India’s  visible  electricity  demand  growth,  there  is  significant  latent 

demand that remains under‐represented.  The following table shows the preceding years Demand 

& deficit of Electricity. 

Years  Peak Deficit % Energy Deficit % 

           

2000‐01  13  7.8    Actual Power demand­Supply Position 2001‐02  11.8  7.5    Requirement  Availability  Surplus/deficit (+/‐) 2002‐03  12.2  8.8   

Fiscal year  (MU)  (MU)  (MU)    

2003‐04  11.2  7.1    2005  591373  548115  ‐43258  ‐7.3 2004‐05  11.7  7.3    2006  631544  578819  ‐52725  ‐8.3 2005‐06  12.3  8.4    2007  690587  624495  ‐66092  ‐9.6 2006‐07  13.3  9.6    2008  737052  664660  ‐72392  ‐9.8 2007‐08  16.6  9.8    2009  777039  691038  ‐86001  ‐11.1 2008‐09  11  11.1    2010  830594  746644  ‐83950  ‐10.1 2009‐10  12.7  10.1    2011  861591  788355  ‐73236  ‐8.5 2010‐11  9.8  8.5    2012  933741  837374  ‐96367  ‐10.3 2011‐12  12.9  10.3             

                 MU denotes Million Unit             Source: CEA Reports             

The  demand  projections  have  discounted  the  Places  where  electricity  cables  have  not 

reached yet and  industries  that would come up  if supply of electricity  is guaranteed. Shortage  is 

likely  to be a major driver  for new capacity development  in  future. Energy demand deficits have 

increased from 7 percent to 10 percent in the past five years, indicating that a high latent demand 

for electricity exists in India. This latent demand increases the potential for demand to grow even in 

periods of slow economic growth.   

Page 18: Power sector Financing Project Report

 

 

15

As  the  figure below  shows,  India has  constantly been plagued with a demand  supply gap  in  the 

Power sector. Such a gap is a major hindrance to the growth of a developing economy like India. 

 

4.5 Financing Requirements  

The Working Group on Power has estimated  that Rs. 1372580 Cr will be  required by  the 

Power  sector  to meet  the  target  of  75785 MW  capacity  additions  and  development  of  related 

transmission and distribution infrastructure by the end of XII plan (FY 2012 ‐ FY 2017).  

Overall Investment Requirement in 12th plan (2012‐2017) 

  Particulars  Fund Requirement in Cr 

1  Generation  638600 2  R&M  31887 3  Captive  65000 4  Renewable Energy sources  135100 5  Transmission  180000 6  Distribution  306235 7  R&D  4168 8  DSM &EE  7482 9  HRD  4108   Total Fund Requirement  1372580 

Source: Planning Commission of India 

The question of generating this huge amount of funds therefore assumes prime importance. 

Page 19: Power sector Financing Project Report

 

 

16

The planned additions  in all  the  three sectors will be missed  if significant steps are not  taken  to 

ensure a more congenial environment in the sector to bring in more investments. The investment 

in generation,  transmission, distribution and  rural electrification  should  ideally be  in  the  ratio of 

4:2:1:1.  This  implies  for  each  rupee  invested  in  generation  a  similar  investment  is  required  in 

Transmission & Distribution  (T&D). Nevertheless,  in practice actual  investment  in T&D so  far has 

been 30 percent. As a result there is a severe gap in transmission capacity at state levels. The ratio 

for Central and State sectors has gradually improved over the various plan periods, but the Private 

Sector remains a gaping hole. The private  investment  in T&D segment has not been enough and 

needs to be roped in for balanced distribution of power across the regions. 

While  this could well be  the  investment needed,  the absorption capacity, availability of  financial 

resources and the viability of utilities are  likely to act as constraints  in realizing these  investment 

projections. Hence the question of generating this huge amount of funds therefore assumes prime 

importance. Significant steps to ensure a congenial environment in the sector for bringing in more 

investments have to be taken up as lack of financing and higher interest rates are likely to impede 

funds mobilization. But at the same time interest from foreign investors and the renewed interest 

of multilateral agencies  in the electricity sector has been strong. There has been a resurgence of 

international interest in Indian Power Sector.   

 

 

 

Page 20: Power sector Financing Project Report

 

 

17

5.0 Power Project Life Cycle 

 A typical Power Project Structure is a web of contracts. The Power Plant Promoters setup a 

project company via the Special Purpose Vehicle (SPV) route  i.e. the project company  is a distinct 

legal entity. The Company enters into two sets of agreements‐ Project Finance and Operational.   

 

Table 3.1: Power Project Structure in India 

5.1 Project Finance  

A Power Plant is financed via the Project Finance route. Project finance is usually defined as 

limited  or  non‐recourse  financing  of  a  new  project  through  the  establishment  of  a 

Page 21: Power sector Financing Project Report

 

 

18

separately incorporated vehicle company.  As of now Indian power sector is permitting debt: equity 

ratio of 70:30. Project  financing will be arranged  from different  finance  institutions & markets  in 

terms of debt & equity. 

5.2 Operational Agreements  

EPC Contract: 

   The  Company  then  enters  into  an  agreement  with  an  Engineering,  Procurement  and 

Construction (EPC) contractor for setting up the physical facility for the Power Plant.  

Fuel Supply Agreement: 

 The Company also enters into a long term Fuel Supply Agreement (FSA) to ensure fuel availability. 

As the paper explains  later, fuel  is the most  important component  in ensuring the viability of the 

project.  

Power Purchase Agreements:  

Off take of the Power generated by the plant is guaranteed by a Power Purchase Agreement (PPA) 

with a TRANSCO. Some power may be utilized for merchant sales to industrial houses.  

Government Clearances:  

The Company also has to get the requisite clearances for the government with regard to property 

rights, permits and environmental concerns.  List of Major clearances required as follows; 

Page 22: Power sector Financing Project Report

 

 

19

 

5.3 Project Development  

From a planning and financing perspective, there are essentially three stages of independent power 

project  (IPP)  development:  development,  construction,  and  operation.  The  sources  of  funds,  in 

general, are different  for each stage. The  risks associated with  the completion of each stage are 

also different and hence, the cost of the capital is different.  

5.3.1 Development Period  

During  the  development  stage,  one  cannot  be  certain  that  a  "financeable"  project  will 

result. The project must first be defined in terms of the buyer's needs, the site, the fuel availability 

and  the  permitting  requirements.  Then  the  feasibility  work  is  done.  This  generally  consists  of 

engineering, cost estimation and environmental work, as well as  the development of preliminary 

Page 23: Power sector Financing Project Report

 

 

20

project proformas. The developer must  then obtain contracts, secure  the site, and complete  the 

permitting for the plant. The contract that sets the direction for the rest of a project's development 

is the power purchase agreement. It is during the development period that the greatest "value" is 

being created because efficient planning and engineering capability decide on the viability of the 

project and also  the  tariff competitiveness of  the power produced  is decided by  the engineering 

excellence  of  the  plant.  The  source  of  funds  generally  used  during  this  period  is  equity.  The 

developer and owner of the project provide these funds. The sources of financing for independent 

power projects  are  scarce because  the  risks of development  are high. Until  the project  reaches 

financial closing for construction, there are a multitude of risks that could reduce the value of the 

project to zero. These risks include:  

Permitting risk  

Political opposition to the project  

Inability to secure fuel and fuel transportation under long‐term contract  

Inability to obtain a financeable power purchase agreement, either because the power price 

is too low or the terms are not acceptable  

Regulatory disapprovals and Change in law  

5.3.2 Construction Period  

A  project  enters  the  construction  stage when  it  has met  all  the  requirements  necessary  to  put 

together a non‐recourse project financing. This means that all of the contracts are negotiated and 

signed,  the  permits  are  granted,  and  the  technology  and  equipment  are  selected.  There 

Page 24: Power sector Financing Project Report

 

 

21

is limited to no recourse to the developer if there is a problem. This is the nature of non‐recourse 

project  finance. The majority of  the construction  funds are  through debt. The period of greatest 

risk  for  them  is  just  before  the  plant  is  completed,  because  they  have  almost  their  entire  loan 

outstanding and the plant  is still not producing revenues. The Project Cost also  includes provision 

for  Interest  during  construction  and  a  margin  for  working  capital  finance  both  of  which  are 

capitalized. 

5.3.3 Operating Period  

The  primary  financial  management  issue  throughout  the  project  life  cycle  is  to  minimize  the 

financial  and  operating  costs  of  the  project.  Once  a  project  reaches  commercial  operation,  a 

developer/owner  has many  options  in  terms  of  additional  financing.  For  example,  institutional 

buyers such as insurance companies and pension funds, as well as the public markets (which do not 

take construction risk), can now participate. The project now has real operating and financial data 

that can be used to assess the plant's performance and financial expectations. The key is planning 

and constant attention to the project finance debt market 

 

 

 

 

 

Page 25: Power sector Financing Project Report

 

 

22

6.0 Project Economics  

The cost of power generation varies, depending on the type of fuel used. The choice of fuel for a 

power  plant  is  influenced  by  a  number  of  factors  such  as  the  relative  cost  of  generation, 

availability,  transportation  constraints,  and  environmental  hurdles.  The  capital  costs  of  power 

plants also vary significantly, based on the source of energy,  infrastructure, plant size, technology 

and equipment and interest during construction (IDC).  

 

6.1 Fuels Supply  

As pointed out earlier, power plants with the  lowest variable costs  (Coal) should be employed to 

meet the base demand, while those with a higher variable cost (Gas) should be employed to meet 

the peaking demand. This will result in a minimum overall variable cost of power.  

Page 26: Power sector Financing Project Report

 

 

23

Cost:  

The delivered price of any fuel can vary significantly depending on the source of supply (imported 

or indigenous) and the distance of the plant from the source of supply. Power plants located near 

coal mines (pit‐head plants) are able to generate power at a fairly lower rate than plants that need 

to transport coal over long distances.  

Supply: 

 An  interruption  in  the  fuel supply can  lower  the plant’s PLF,  resulting  in a higher overall cost of 

power.  Given  the  fuel  supply  constraints  faced  by  existing  power  plants,  banks  and  financial 

institutions  insist on a regular fuel supply arrangement (FSA) before funding private sector power 

projects,  especially  those  proposed  to  be  funded  on  a  non‐recourse  basis.  As  a  result,  private 

power producers want to have  legally enforceable fuel supply agreements with fuel suppliers and 

fuel  transporters where  the  power  producer would  pay  a  premium on  the  price  of  the  fuel,  to 

ensure its adequate and regular supply and would also guarantee a minimum off take of fuel from 

the fuel supplier.  

6.2 Capital costs; 

Power  projects  are  highly  capital‐intensive  and  have  a  gestation  period  of  4‐6  years.  The  fixed 

component of the power tariff is linked to the capital cost of the project. Hence, the capital cost of 

a power project is a very important determinant of the total cost of generation. The capital costs of 

power  plants  also  vary  significantly,  based  on  the  source  of  energy,  infrastructure,  plant  size, 

technology and equipment and  interest during construction  (IDC). Hence,  it  is not possible to set 

standard  benchmark  costs  for  power  plants. However,  the  capital  costs  of most  projects  in  the 

private  sector  are  assumed  as  shown  in  the  table above 

Page 27: Power sector Financing Project Report

 

 

24

6.3 Wholesale Tariff Structure  

The term Availability Tariff ‐‐ in the Indian context ‐‐ stands for a rational tariff structure for 

power supply from generating stations on a contracted basis. In the Availability Tariff mechanism, 

the  fixed and variable cost components are  treated separately. The payment of  fixed cost  to  the 

generating company is linked to availability of the plant, that is, its capability to deliver MWs on a 

day‐by‐day basis. The  total amount payable  to  the generating company over a year  towards  the 

fixed cost depends on the average availability (MW delivering capability) of the plant over the year. 

In  case  the  average  actually  achieved over  the  year  is higher  than  the  specified norm  for plant 

availability,  the  generating  company  gets  a  higher  payment.  In  case  the  average  availability 

achieved is lower, the payment is also lower. Hence the name ‘Availability Tariff (ABT)’. This is the 

first component of Availability Tariff, and is termed ‘capacity charge’. 

The second component of Availability Tariff  is the  ‘energy charge’, which comprises of the 

variable cost (i.e., fuel cost) of the power plant for generating energy as per the given schedule for 

the day. It may specifically be noted that energy charge (at the specified plant‐specific rate) is not 

based  on  actual  generation  and  plant  output,  but  on  scheduled  generation.  In  case  there  are 

deviations  from  the  schedule  (e.g.,  if a power plant delivers 600 MW while  it was  scheduled  to 

supply only 500 MW), the energy charge payment would still be for the scheduled generation (500 

MW),  and  the excess  generation  (100 MW) would be  remunerated  at  a  rate dependent on  the 

system conditions prevailing at the time. If the grid has surplus power at the time and frequency is 

above 50.0  cycles,  the  rate would be  lower.  If  the excess  generation  takes place at  the  time of 

generation shortage in the system (in which condition the frequency would be below 50.0 cycles), 

the payment for extra generation would be at a  higher rate. Likewise, if a state / customer draws 

Page 28: Power sector Financing Project Report

 

 

25

more power from the regional grid than what  is totally scheduled to be supplied to him from the 

various CGSs at a particular  time,  it has  to pay  for  the excess drawl at a  rate dependent on  the 

system conditions, the rate being lower if the frequency is high, and being higher if the frequency is 

low.  The  deviation  from  schedule  is  technically  termed  as  Unscheduled  Interchange  (UI)  in 

Availability Tariff terminology. Figure 1.13 illustrates how and when the UI mechanism works.   

The  payment  due  to  the  generation  company  by  the  buyer  in  any  year  is  computed  as 

follows: Total payment due = Fixed charges + variable charges + UI charges, where   

Fixed charges comprise:  

• Interest on long‐term debt 

• Depreciation  

• O&M expenses (including insurance expenses) 

• Return on equity  

• Incentive return on equity 

• Interest on working capital  

• Taxes  

Variable charges comprise:  

• Cost of primary fuel 

•  Cost of secondary fuel  

UI charges comprise:  

• Cost of secondary fuel  

Page 29: Power sector Financing Project Report

 

 

26

7.0 Power Project Financing 

The  Indian economy  is poised  for higher economic growth  in  the years  to come. This will 

require  large  investment  in the  infrastructure sectors  including the power sector.   As per the 12th 

plan  ` 1372580Cr  required  for  the  addition  of  75GW  capacity. During  the  1990s,  up  to  80%  of 

power  sector  funding came  from  the public  sector,  followed by  the private  sector  (10–15%) and 

official development assistance (5–10%). Increasingly, both the central and state governments are 

facing the need to meet competing budgeting requirement from other social sectors such as health 

and primary education. The need for enhanced fiscal discipline and macroeconomic stability is also 

placing a limit on borrowing capacity of the government both at central and state level. 

7.1 Types and Sources of Finance  

7.1.1 Debt  

Given  the  capital‐intensive  nature  of  power  projects, mobilization  of  long‐term  debt  becomes 

critical to the development of power projects. Project finance debt is generally secured by projects 

assets  such  that after paying operating expenses, debt and debt  service  is paid  from cash  flows. 

Debt typically constitutes up to 70% of the power project costs  in  India. The type of debt used  in 

power projects finance structures has been varied. The following are some of the sources of debt 

available to power projects developers:  

Government:  

Traditionally, the main source of debt has been the government. Both the central and state 

governments  lend the money to utilities from time to time for expansion plans or working 

capital. They extend  loans  for  longer  tenure and at  lower  interest  rates  than  commercial 

Page 30: Power sector Financing Project Report

 

 

27

rates.  

Commercial Banks and Financial Institutions; 

Commercial  banks  and  Financial  Institutions  (FIs)  have  consistently  increased  lending  to 

power  sector  in  the  last  4‐5  years. Most  of  the  lending  has  been  skewed  towards  the 

generation  segment.  With  the  opening  up  of  the  T&D  segment  to  the  private  sector, 

commercial  lending  is  likely  to  increase  in  future.  For  generation  projects,  the  standard 

tenure of loans is 13‐14 years, which included construction period and repayment period of 

10 years.   Earlier the  lending use to be under recourse financing, but  in the  last 4‐5 years, 

the  lending  institutions  have  become  more  liberal  and  comfortable  with  lending  to 

bankable power projects. Although,  commercial banks  and  FIs  continue  to  increase  their 

exposure to the power sector,  individual exposure of banks to the sector remains  limited. 

This  is  mainly  because  they  are  still  constrained  by  financing  limits  as  per  prevalent 

prudential norms prescribed by the Reserve Bank of India (RBI).   

Niche Institutions; 

There  are  also  niche  institutions  such  as  Power  Finance  Corporation  (PFC)  and  Rural 

Electrification Corporation  (REC), which  provide  loans  specifically  to  power  sector. While 

PFC provides  loans for all kinds of  investments, REC focuses mainly on rural electrification. 

The  state  sector’s  reliance  on  these  institutions  for  debt  is  very  high mainly  due  to  the 

competitive rates and liberal terms and conditions offered by them. In the recent past, due 

to their experience and expertise in the sector, these institutions have been competing with 

commercial banks. Moreover, since  issues  like asset‐liability mismatch and exposure  limits 

are not applicable to PFC and REC, it is easier for these institutions to lend to the sector. 

Page 31: Power sector Financing Project Report

 

 

28

Insurance Companies; 

Insurance  companies  like  the  Life  Insurance  Corporation  of  India  (LIC),  General  Insurance 

Corporation of  India  (GIC) have extended  financial  support  to  the power  sector. There are 

limits on the investments prescribed by the Insurance Regulatory and Development Authority 

of  India  (IRDA). Life  insurance and general  insurance companies have to  invest at  least 15% 

and 10% of the fund respectively to the infrastructure and social sectors.  

External Commercial Borrowings; 

External  commercial borrowings  (ECBs) were quite  a popular means  to  raise  finances until 

some  time  back,  especially  for  large  projects  funding.  These  loans  are  raised  at  Libor‐plus 

rates, which are generally  lower  than  the  interest  rates  in  the domestic market. ECBs have 

declined of late due to RBI restrictions on foreign funds flows for rupee expenditure and due 

to an increase in borrowing costs as a result of the sub‐prime effect.  

Export Credit Agencies; 

Loans from export credit agencies are cheaper than commercial loans and are generally used 

when equipment needs  to be  imported  from  a particular  country.  These  are  likely  to  gain 

importance in the medium term mainly fuelled by the requirement of importing super‐critical 

units in the eleventh and Twelfth plan periods, and until this demand is met by the domestic 

market.  

Bonds; 

Several utilities and state power corporations have resorted to  issuing bonds to raise funds. 

These  are  generally  subscribed  by  provident  and  pension  funds,  gratuity  trusts,  insurance 

companies, mutual funds, individual, etc. These bonds typically have tenure of 7‐8 years.  

Page 32: Power sector Financing Project Report

 

 

29

7.1.2 Equity  

The  equity  in  power  projects,  like  in  other  projects,  is  driven  by  the  rate  of  return  that  is 

expected  from the  investment apart  from acting as a cushion to project  finance.  In the power 

sector, the return on equity  is fixed at 15.5% on 30% of the equity  investment. The sources of 

equity  are  promoter’s  equity,  internal  accruals,  equity  funds  and  strategic  equity  investors. 

Raising funds from capital markets is also becoming increasingly popular. The following are some 

of the sources of equity available to power project developers:  

Promoter’s Equity and Internal Accruals ; 

Most project developers invest some amount of the total project cost as promoter’s equity 

to be able to earn the minimum return on equity and raise the required debt. Many CPSUs, 

including National Thermal Power Corporation  (NTPC) are  increasingly  relying on  internal 

accruals for investing equity in new projects. 

Primary/Capital Markets; 

In  recent  times,  power  sector  companies  have  been  raising  funds  from  primary markets 

through Initial Public Offerings (IPOs). Almost all IPOs of power companies in the last two to 

three  years  have  met  with  an  overwhelming  response  from  investors  or  have  been 

performing well in the stock markets. Some of the successful IPOs have been those of CPSUs 

like NTPC, and PGCIL, private developers  like Suzlon Energy, JP Hydro and Reliance Power 

and  infrastructure  companies  like  GMR,  GVK  and  Lanco.  Many  power  companies  are 

expected to launch their IPOs in the coming years. NTPC is also planning to come out with a 

follow‐on public offer.  

 

Page 33: Power sector Financing Project Report

 

 

30

Qualified Institutional Placements; 

Another source of equity, which is increasingly being tapped by power sector companies, is 

private  placement  with  qualified  institutional  investors.  For  instance,  GVK  Power  & 

Infrastructure  Limited  (GVKIL)  and  Kalpataru  Power  Transmission  raised USD  300 million 

and  USD  85 million  respectively  through  this  route  in May  2007  and  September  2006 

respectively. PTC India also raised around USD 29 million through this route in January 2008 

by allotting shares to institutional buyers like LIC and Morgan Stanley, among others.  

Equity Funds  

Specialized equity  funds  such  as  India Development  Fund by  Infrastructure Development 

Finance  Company  (IDFC)  have  been  set  up  to  invest  in  equity  in  private  sector  power 

sectors.  India  Infrastructure  Finance  Company  Limited  (IIFCL),  Citigroup,  Blackstone  have 

also  instituted  a  USD  5  billion  India  infrastructure  financing  initiative  for  investing  in 

infrastructure  projects.  The  Anil  Dhirubani  Ambani  Group  and  Singapore’s  Temasek 

Holdings  constituted  the  Reliance  India  Power  Fund  with  equal  contributions.    Others 

planning  to  set up  infrastructure  funds, which would pick up equity  in power projects as 

well, include a USD 2 billion infrastructure by ICICI bank, the USD 1 billion Macquarie India 

Infrastructure  Opportunities  Fund  by  Macquarie  and  International  Finance  Corporation 

(IFC), a USD 1 billion India focused infrastructure private equity fund by Standard Chartered 

and IL&FS Investment Managers and a USD 2 billion India Infrastructure Fund by JP Morgan 

and Chase Company. PTC India’s investment arm PTC Financial Services also plans to pick up 

equity in power projects through an Energy Equity Fund.   

 

Page 34: Power sector Financing Project Report

 

 

31

7.2 Trends in Power Sector Financing 

• Increased investor confidence resulting in commitment and disbursement of more funds  

• IPP revival triggered by increased investor confidence  

• Gradually increasing interest rates leading to increased project costs  

• Increased availability of longer‐term debt  

• Skew towards investment in generation continues  

• External Commercial Borrowings (ECB) loses sheen as RBI tightens norms  

• As local capital market mature, more companies are opting for IPOs  

• Lenders no longer demand government guarantees, counter guarantees.  

• Bankable and competitively priced projects are able to raise funds easily.  

• Project financing criteria relaxed by financiers for new types of projects. 

• Promoter’s track record is a important consideration 

7.3 Major Financiers in Power Sector 

1) Power Finance Corporation  

2) Rural Electrification Corporation  

3) World Bank  

4) International Finance Corporation  

5) Asian Development Bank  

6) Japan Bank for International Cooperation  

7) Department of International Development  

8) India Infrastructure Finance Company Limited  

9) Infrastructure Development Finance Company  

10) Life Insurance Company  

11) Commercial banks  like State Bank of  India, Punjab National Bank  ,  IDBI Bank,  ICICI 

Bank, SBI Capital Markets. 

Page 35: Power sector Financing Project Report

 

 

32

8.0 Budgeting in Power Plants; 

8.1 Types of budget heads in power plant; 

1. Direct capital outlay 

2. Commissioning Expense 

3. Construction materials 

4. Technical consultancy 

5. Training & Recruitment 

6. Incidental expenditure during construction 

I. Employee cost 

II. Other establishment expenses 

7. Miscellaneous brought out Assets (MBOA) 

8. Interest during construction (IDC) 

9. Working Capital margin 

10. Capital Expenditure not represented by assets 

11. Township and social overheads. 

1. Directly Capital Outlay ; 

This  represents  all  cost  directly  identifiable with  capital work  and  includes  cost  of  land  , 

infrastructural  facilities, and mechanical, electrical works  ,  township  ,MGR and construction 

facilities. The budget provision is to be made against each budget head listed. 

As per CERC Tariff Regulation 2009 Capital cost for a project shall include:  

a) the  expenditure  incurred  or  projected  to  be  incurred,  including  interest  during 

construction and financing charges, any gain or loss on account of foreign exchange risk 

Page 36: Power sector Financing Project Report

 

 

33

variation during construction on the loan ‐ (i) being equal to 70% of the funds deployed, 

in the event of the actual equity in excess of 30% of the funds deployed, by treating the 

excess equity as normative  loan, or (ii) being equal to the actual amount of  loan  in the 

event  of  the  actual  equity  less  than  30%  of  the  funds  deployed,  ‐  up  to  the  date  of 

commercial operation of  the project, as admitted by  the Commission, after prudence 

check;  

b) Capitalized initial spares subject to the ceiling rates  as specified by CERC; and  

c) Additional  capital  expenditure  determined  under    special  circumstances  like  (i)  Un 

discharged liabilities; (ii) Works deferred for execution; (iii) Procurement of initial capital 

spares within the original scope of work, (iv) Liabilities to meet award of arbitration or 

for compliance of the order or decree of a court; and (v) Change in law: 

2.  Commissioning expenses 

All  direct  expenses  for  running  of  individual  units  up  to  date  of  commercial  operation, 

including fuel costs, startup power chemicals & lubricants consumption and anticipated sale 

of energy during trail run are to be indicated. 

3. Construction Materials; 

Provision  should be made  for  accretion or decretion of  stock of  construction of  stock of 

construction  materials  such  as  structural  steel,  reinforcement  steel  cement  and  other 

materials. This consumption of materials should be valued at budget cost  represented by 

difference between  the  issue price  and  contract price  should provide  for  indirect  capital 

outlay. 

 

Page 37: Power sector Financing Project Report

 

 

34

4. Technical Consultancy; 

Payment  to  technical consultants  identifiable with  system  such as main plant, MGR, Coal 

Handling plant, & other  are  to be  included  in  this head.  TA,  lodging  expense payable  to 

consultants based on contractual obligations and  income  tax provisions  in  respect of  tax‐

free foreign consultancy payments should also be provided under this head. 

5. Training & Recruitment Expenditure; 

The first part of this budget consists of expenses for training executives/non‐ executives and 

trainees,  including stipends,  faculty  fee, course material  for  trainees, rent  for  training hall 

and expenses for management development courses. Second part consists of expenses for 

recruitment, interview expenses, TA to candidate etc. 

6. Incidental Expenses during Construction 

a) Employee Costs;‐  These  comprise  salaries, wages,  allowances,  contribution  to PF  and 

other funds , welfare expenses. Any other provision for arrears of salary/DA or incentive 

should be shown separately. 

b) Other Establishment Expenses:  ‐ Expenses  incidental to construction and capital works 

not  traceable directly  to  any  capital  activity  are  chargeable  to  incidental  expenditure 

during  construction  repair  and  maintenance  of  buildings,  construction  equipment. 

Vehicle running expenses, official rent, LC charges, cost of drawing, travelling expenses, 

advertising for tenders are major items falling in this category. 

7. Miscellaneous Brought out Assets‐  

Furniture  and  other  office  equipments, medical  and  hospital  equipments, miscellaneous 

assets of Township and loans to employees figure in this subject  budget. 

Page 38: Power sector Financing Project Report

 

 

35

8. Interest during Construction; 

Interest to be paid and capitalized during construction period on loans has to to be included 

in this budget. 

9. Working Capital Margin 

The accretion to working capital comparison inventory of fuel, spares, consumables etc plus 

cash  expenses  on  operation  and  maintenance  less  cash  realization  anticipated  during 

budget period is to be financed to the extent of 25% by way of working capital margin from 

budgets and the balance from cash credit etc. 

10. Capital Expenditure Not Represented by Assets: 

This  includes  capital  expenditure  on  assets  belonging  to  their  agencies  for  example, 

construction  of  approach  roads,  canal,  and  lining  etc.  on  property  belonging  to  local 

authorities/SEBs. These  items should be  included under respective budgets head  in direct 

capital  outlay  budget  and  these  should  also  be  presented  separately  in  the  format  for 

capital expenditure not  represented by assets  to  facilitate  identification and  control  such 

works.  The  budget  proposals  for  these  should  be  supported  by  specific  approval  from 

competent authority. The relevant  information  in respect of details of agreement and the 

date of transfer etc.  

11. Township and Social overheads; 

This  is  an  analysis  of  provision  already  in  the  IEDC  budgets  pertaining  to  the  cost  of 

administration and maintenance of Permanent Township and income from township. Other 

social  overheads  comprising maintenance  of  schools,  hospitals,  sub‐sided  transport  etc. 

should also be indicated. 

Page 39: Power sector Financing Project Report

 

 

9.0 Capital Budgeting for dummy Power project; 

A dummy power project was given with the life of 25 years starting from April‐2011. Some assumptions 

for  the  input  values  were  taken  from  NTPC/NSPCL  standards  (shown  in  the  table  below).  Using  these 

assumptions following parameters were calculated: 

a) Primary and Secondary Fuel Cost 

b) Depreciation, return on equity and Operations & Management (O&M) Cost 

c) Working Capital and Interest on working Capital 

d) Term Loan and Interest 

e) Average fixed cost 

f) Tariff 

g) Profit and Loss statement 

h) Cash Flow statement and NPV, IRR 

 

Gopi
Text Box
36
Page 40: Power sector Financing Project Report

 

 

 

Gopi
Text Box
37
Page 41: Power sector Financing Project Report

 

 

 

Gopi
Text Box
38
Page 42: Power sector Financing Project Report

 

 

 

Gopi
Text Box
39
Page 43: Power sector Financing Project Report

 

 

 

Gopi
Text Box
40
Page 44: Power sector Financing Project Report

 

 

 

Gopi
Text Box
41
Page 45: Power sector Financing Project Report

 

 

 

Gopi
Text Box
42
Page 46: Power sector Financing Project Report

 

 

 

 

Gopi
Text Box
43
Page 47: Power sector Financing Project Report

 

 

 

Gopi
Text Box
44
Page 48: Power sector Financing Project Report

 

 

45

 

Since, the value of NPV is positive also the value of IRR is more than WACC, so NSPCL should 

accept this project. 

 

 

 

 

 

Page 49: Power sector Financing Project Report

For the year ended March 31,  2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023

Installed Capacity  MW 2x250 2x251 2x252 2x253 2x254 2x255 2x256 2x257 2x258 2x259 2x260 2x261 2x262Plant Load Factor 80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 80.00%Income Units generated million kWh 2044 3504 3504 3504 3504 3504 3504 3504 3504 3504 3504 3504 3504Less: Auxiliary Consumption million kWh 184 315.36 315.36 315.36 315.36 315.36 315.36 315.36 315.36 315.36 315.36 315.36 315.36Units sold  million kWh 1860 3189 3189 3189 3189 3189 3189 3189 3189 3189 3189 3189 3189Tariff for the year Rs.  2.14 2.16 2.24 2.36 2.31 2.26 2.21 2.16 2.11 2.06 2.01 1.67 1.49Total Sales Rs. Crore 398 687 713 752 736 720 704 688 673 657 642 533 476

ExpenditureRaw Material Rs. Crore 128 219 219 219 219 219 219 219 219 219 219 219 219O & M expenses Rs. Crore 31 55 58 60 63 66 68 71 74 78 81 85 88water charges 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00Total Expenditure 159 274 277 279 282 285 287 290 294 297 300 304 307

PBDIT 239 413 437 473 454 436 417 398 379 360 341 229 169

Depreciation Rs. Crore 80 138 138 138 138 138 138 138 138 138 138 138 138

Interest‐ Term Loan Rs. Crore 106 186 170 151 132 113 94 75 57 38 19 2 0‐ Working Capital Rs. Crore 9 14 14 15 15 15 15 15 15 15 15 14 13

PBT 44 76 115 170 170 170 170 170 170 170 170 76 18

Gross Cash Accruals Rs. Crore 125 214 253 308 308 308 308 308 308 308 308 214 156

For the year ended March 31,  2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035

Installed Capacity  MW 2x257 2x257 2x257 2x257 2x257 2x257 2x257 2x257 2x257 2x257 2x257 2x257Plant Load Factor 80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 80.00%Income Units generated million kWh 3504 3504 3504 3504 3504 3504 3504 3504 3504 3504 3504 3504Less: Auxiliary Consumption million kWh 315.36 315.36 315.36 315.36 315.36 315.36 315.36 315.36 315.36 315.36 315.36 315.36Units sold  million kWh 3189 3189 3189 3189 3189 3189 3189 3189 3189 3189 3189 3189Tariff for the year Rs.  1.51 1.52 1.53 1.55 1.56 1.58 1.59 1.61 1.63 1.65 1.67 1.69Total Sales Rs. Crore 480 484 489 493 498 503 509 514 520 526 532 538

ExpenditureRaw Material Rs. Crore 219 219 219 219 219 219 219 219 219 219 219 219O & M expenses Rs. Crore 92 96 100 104 109 113 118 123 128 134 139 145water charges 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00Total Expenditure 311 315 319 323 328 332 337 342 347 353 358 364

PBDIT 169 169 170 170 170 171 171 172 172 173 173 174

Depreciation Rs. Crore 138 138 138 138 64 0 0 0 0 0 0 0

Interest‐ Term Loan Rs. Crore 0 0 0 0 0 0 0 0 0 0 0 0‐ Working Capital Rs. Crore 13 14 14 15 15 15 16 16 17 17 18 18

PBT 18 18 18 18 92 156 156 156 156 156 156 156

Gross Cash Accruals Rs. Crore 156 156 156 156 156 156 156 156 156 156 156 156

2x250MW Project  Profitalibility Projections 

Gopi
Text Box
46
Page 50: Power sector Financing Project Report

For the year ended March 31,  2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023AssetsGross Block 2,645            2,645            2,645            2,645            2,645            2,645            2,645            2,645            2,645            2,645            2,645            2,645                2,645                Less: Depreciation 80                  218                356                494                632                770                908                1,046            1,184            1,322            1,460            1,598                1,736                Net Block 2,565            2,427            2,289            2,151            2,013            1,875            1,737            1,599            1,461            1,323            1,185            1,047                909                   Capital Work in Progress ‐                     ‐                     ‐                     ‐                     ‐                    Current Assets 116                182                188                197                196                196                195                195                195                196                196                181                   175                   Cash and bank balances 141                244                307                425                544                664                783                903                1,022            1,142            1,261            1,385                1,542                

Total 2,821            2,853            2,784            2,772            2,753            2,734            2,716            2,697            2,679            2,660            2,642            2,613                2,626                Liabilities

Share Capital 807                807                807                807                807                807                807                807                807                807                807                807                   807                   Reserves and surplus 44                  120                235                405                575                744                914                1,084            1,254            1,424            1,594            1,670                1,687                Term Loan‐ Rupee borrowing 1,883            1,789            1,601            1,413            1,224            1,036            848                659                471                283                94                  (0)                      (0)                      ‐ FC borrowing 0                     0                     0                     0                     0                     0                     0                     0                     0                     0                     0                     0                       0                       Bank Borrowings 87                  137                141                148                147                147                147                146                147                147                147                136                   131                   Current Liabilities 0                     0                     0                     0                     0                     ‐                     ‐                     ‐                     ‐                     ‐                     ‐                     ‐                        ‐                        

Total 2,821            2,853            2,784            2,772            2,753            2,734            2,716            2,697            2,679            2,660            2,642            2,613                2,626                

Difference 0 0 0 0 0 0 0 0 0 0 0 0 0

For the year ended March 31,  2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036AssetsGross Block 2,645            2,645            2,645            2,645            2,645            2,645            2,645            2,645            2,645            2,645            2,645            2,645               Less: Depreciation 1,874            2,012            2,150            2,288            2,352            2,352            2,352            2,352            2,352            2,352            2,352            2,352               Net Block 771                633                495                357                293                293                293                293                293                293                293                293                  Capital Work in ProgressCurrent Assets 179                184                189                193                199                204                210                216                222                229                236                244                  Cash and bank balances 1,696            1,850            2,005            2,159            2,313            2,468            2,622            2,776            2,930            3,083            3,237            3,391               

Total 2,646            2,667            2,688            2,710            2,805            2,965            3,125            3,285            3,445            3,606            3,767            3,928               Liabilities

Share Capital 807                807                807                807                807                807                807                807                807                807                807                807                  Reserves and surplus 1,705            1,722            1,740            1,757            1,849            2,005            2,160            2,316            2,471            2,627            2,782            2,938               Term Loan‐ Rupee borrowing (0)                   (0)                   (0)                   (0)                   (0)                   (0)                   (0)                   (0)                   (0)                   (0)                   (0)                   (0)                     ‐ FC borrowing 0                     0                     0                     0                     0                     0                     0                     0                     0                     0                     0                     0                      Bank Borrowings 135                138                141                145                149                153                157                162                167                172                177                183                  Current Liabilities ‐                     ‐                     ‐                     ‐                     ‐                     ‐                     ‐                     ‐                     ‐                     ‐                     ‐                     ‐                       

Total 2,646            2,667            2,688            2,710            2,805            2,965            3,125            3,285            3,445            3,606            3,767            3,928               

Difference 0 0 0 0 0 0 0 0 0 0 0 0 0

Balance Sheet

Gopi
Text Box
47
Page 51: Power sector Financing Project Report

For the year ended March 31,  2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 20231 2 3 4 5 6 7 8 9 10 11 12 13

InflowGross Cash Accruals 125               214              253              308              308              308              308                308              308              308              308              214                 156                Increase in equity 201               0                  0                  0                  ‐                  Term Loan Drawls‐ Rupee borrowing 468               0                  0                  0                  ‐                   ‐                   ‐                     ‐                   ‐                   ‐                   ‐                   ‐                      ‐                      ‐ FC borrowing 0                   0                  0                  0                  ‐                   ‐                   ‐                     ‐                   ‐                   ‐                   ‐                   ‐                      ‐                      Increase in Current Liabilities ‐                    ‐                   ‐                   ‐                   ‐                   ‐                   ‐                     ‐                   ‐                   ‐                   ‐                   ‐                      ‐                      Decrease in Current Assets ‐                    ‐                   ‐                   ‐                   1                  0                  0                    0                  ‐                   ‐                   ‐                   15                   6                     Increase in bank borrowings 87                 50                5                  6                  ‐                   ‐                   ‐                     ‐                   0                  0                  0                  ‐                      ‐                      

Total 880               263              258              314              308              308              308                308              308              308              308              228                 162                

OutflowCapital investments 669               0                  0                  0                  ‐                  Repayment‐ Rupee borrowing ‐                    94                188              188              188              188              188                188              188              188              188              94                   ‐                      ‐ FC borrowing ‐                    0                  0                  0                  0                  0                  0                    0                  0                  0                  0                  0                     ‐                      Decrease in Current Liabilities ‐                    ‐                   ‐                   ‐                   ‐                   ‐                   ‐                     ‐                   ‐                   ‐                   ‐                   ‐                      ‐                      Increase in Current Assets 116               66                6                  8                  ‐                   ‐                   ‐                     ‐                   0                  0                  0                  ‐                      ‐                      Decrease in bank borrowings ‐                    ‐                   ‐                   ‐                   0                  0                  0                    0                  ‐                   ‐                   ‐                   11                   5                     

Total 785               161              194              197              189              189              189                188              188              189              189              105                 5                     

Opening Balance 46                 141              244              307              425              544              664                783              903              1,022           1,142           1,261              1,385             Surplus / (Deficit)  96                 103              63                117              120              120              120                120              119              119              119              123                 157                Closing Balance 141               244              307              425              544              664              783                903              1,022           1,142           1,261           1,385              1,542             

Gross Cash Accruals Rs. Crore 114                195                233                284                284                284                284                284                284                284                284                196                   141                  Difference  11                 18                21                24                24                24                24                  24                24                24                24                18                   15                   Discounting factor 9% 0.92 0.84 0.78 0.71 0.65 0.60 0.55 0.51 0.47 0.43 0.39 0.36 0.33NPV 9.66 15.60 15.93 17.11 15.70 14.41 13.22 12.13 11.13 10.21 9.36 6.52 4.88

For the year ended March 31,  2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 203514 15 16 17 18 19 20 21 22 23 24 25

InflowGross Cash Accruals 156               156              156              156              156              156              156                156              156              156              156              156                Increase in equityTerm Loan Drawls‐ Rupee borrowing ‐                    ‐                   ‐                   ‐                   ‐                   ‐                   ‐                     ‐                   ‐                   ‐                   ‐                   ‐                     ‐ FC borrowing ‐                    ‐                   ‐                   ‐                   ‐                   ‐                   ‐                     ‐                   ‐                   ‐                   ‐                   ‐                     Increase in Current Liabilities ‐                    ‐                   ‐                   ‐                   ‐                   ‐                   ‐                     ‐                   ‐                   ‐                   ‐                   ‐                     Decrease in Current Assets ‐                    ‐                   ‐                   ‐                   ‐                   ‐                   ‐                     ‐                   ‐                   ‐                   ‐                   ‐                     Increase in bank borrowings 3                   3                  3                  4                  4                  4                  4                    5                  5                  5                  5                  6                    

Total 159               159              159              159              159              160              160                160              160              161              161              161                

OutflowCapital investmentsRepayment‐ Rupee borrowing ‐                    ‐                   ‐                   ‐                   ‐                   ‐                   ‐                     ‐                   ‐                   ‐                   ‐                   ‐                     ‐ FC borrowing ‐                    ‐                   ‐                   ‐                   ‐                   ‐                   ‐                     ‐                   ‐                   ‐                   ‐                   ‐                     Decrease in Current Liabilities ‐                    ‐                   ‐                   ‐                   ‐                   ‐                   ‐                     ‐                   ‐                   ‐                   ‐                   ‐                     Increase in Current Assets 4                   4                  5                  5                  5                  5                  6                    6                  6                  7                  7                  8                    Decrease in bank borrowings ‐                    ‐                   ‐                   ‐                   ‐                   ‐                   ‐                     ‐                   ‐                   ‐                   ‐                   ‐                     

Total 4                   4                  5                  5                  5                  5                  6                    6                  6                  7                  7                  8                    

Opening Balance 1,542            1,696           1,850           2,005           2,159           2,313           2,468             2,622           2,776           2,930           3,083           3,237             Surplus / (Deficit)  154               154              154              154              154              154              154                154              154              154              154              154                Closing Balance 1,696            1,850           2,005           2,159           2,313           2,468           2,622             2,776           2,930           3,083           3,237           3,391             

Gross Cash Accruals Rs. Crore 141                141                141                141                141                141                141                141                141                141                141                142                  Difference  15                 15                15                15                14                14                14                  14                14                14                14                14                  Discounting factor 9% 0.31 0.28 0.26 0.24 0.22 0.20 0.18 0.17 0.15 0.14 0.13 0.12NPV 4.47 4.09 3.75 3.43 3.14 2.88 2.63 2.41 2.20 2.02 1.84 1.69

Cashflow Projections

Gopi
Text Box
48
Page 52: Power sector Financing Project Report

DSCR Calculations 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023Numerator‐ Gross Cash Accruals 125 214 253 308 308 308 308 308 308 308 308 214 156‐ Interest on Term Loans 106 186 170 151 132 113 94 75 57 38 19 2 0

231 400 423 459 440 421 402 383 364 346 327 215 156

Denominator ‐ Interest on Term Loans 106 186 170 151 132 113 94 75 57 38 19 2 0‐ Repayment 0 94 188 188 188 188 188 188 188 188 188 94 0

106 280 358 339 320 301 283 264 245 226 207 96 0

DSCR 1.43 1.18 1.35 1.37 1.40 1.42 1.45 1.49 1.53 1.58 2.25

DSCR Calculations 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035Numerator‐ Gross Cash Accruals 156 156 156 156 156 156 156 156 156 156 156 156‐ Interest on Term Loans 0 0 0 0 0 0 0 0 0 0 0 0

156 156 156 156 156 156 156 156 156 156 156 156

Denominator ‐ Interest on Term Loans 0 0 0 0 0 0 0 0 0 0 0 0‐ Repayment 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0DSCR

Maximum DSCR 2.25Average DSCR 1.46Minimum DSCR 1.18  

DSCR and IRR CALCULATIONS

Gopi
Text Box
49
Page 53: Power sector Financing Project Report

IRR CALCULATIONS 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023

Capital Expenditure incl. IDC 320.3 774.1 881.7 668.8 0.0 0.0 0.0 0.0 0.0Less: IDC 12.0 48.5 112.1 63.8 0.0 0.0 0.0 0.0 0.0Capital Expenditure excl. IDC 308 726 770 605 0 0 0 0Current Assets build up 116 66 6 8 ‐1 0 0 0 0 0

Gross Cash Accruals 125 214 253 308 308 308 308 308 308 308Interest (term loan + WC) 115 200 184 165 147 128 109 90 71 52Salvage Value

Net Cash flow ‐308 ‐726 ‐770 ‐482 347 431 465 455 436 417 398 379 360

IRR CALCULATIONS 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035

Capital Expenditure incl. IDCLess: IDCCapital Expenditure excl. IDCCurrent Assets build up 0 ‐15 ‐6 4 4 5 5 5 5 6 6 6

Gross Cash Accruals 308 214 156 156 156 156 156 156 156 156 156 156Interest (term loan + WC) 34 15 13 13 14 14 15 15 15 16 16 17Salvage Value

Net Cash flow 341 244 175 165 165 165 165 165 165 165 166 166

IRR 12.15%

IRR CALCULATION

Gopi
Text Box
50
Page 54: Power sector Financing Project Report

For the year ended March 31,  2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023Components of Fixed TariffDepreciation 55 94 134 188 188 188 188 188 188 188 188 94 36Interest on Term Loan 106 186 170 151 132 113 94 75 57 38 19 2 0O & M expenditure 34 61 63 66 68 71 74 77 80 83 87 90 94Return on equity 66 113 113 113 113 113 113 113 113 113 113 113 113Interest on working capital 9 14 14 15 15 15 15 15 15 15 15 14 13Total Fixed Charges 270 468 494 533 517 501 485 469 453 438 422 314 257

Total variable cost 128 219 219 219 219 219 219 219 219 219 219 219 219Incentive 0 0 0 0 0 0 0 0 0 0 0 0 0

Fixed Tariff  1.45 1.47 1.55 1.67 1.62 1.57 1.52 1.47 1.42 1.37 1.32 0.98 0.81Variable tariff 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69Total Tariff 2.14 2.16 2.24 2.36 2.31 2.26 2.21 2.16 2.11 2.06 2.01 1.67 1.49Discounting factor 0.89 0.80 0.71 0.64 0.57 0.51 0.45 0.40 0.36 0.32 0.29 0.26 0.23Discounted Tariff 1.91 1.72 1.59 1.50 1.31 1.14 1.00 0.87 0.76 0.66 0.58 0.43 0.34Levelised Tariff (Rs / unit) 2.05

For the year ended March 31,  2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034Components of Fixed TariffDepreciation 55 36 36 36 36 36 36 36 36 36 36 36Interest on Term Loan 106 0 0 0 0 0 0 0 0 0 0 0O & M expenditure 34 97 101 105 110 114 119 123 128 133 139 144Return on equity 66 113 113 113 113 113 113 113 113 113 113 113Interest on working capital 9 13 14 14 15 15 15 16 16 17 17 18Total Fixed Charges 270 261 265 270 274 279 284 289 295 301 306 313

Total variable cost 128 219 219 219 219 219 219 219 219 219 219 219Incentive 0 0 0 0 0 0 0 0 0 0 0 0

Fixed Tariff  1.45 0.82 0.83 0.85 0.86 0.88 0.89 0.91 0.92 0.94 0.96 0.98Variable tariff 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69Total Tariff 2.14 1.51 1.52 1.53 1.55 1.56 1.58 1.59 1.61 1.63 1.65 1.67Discounting factor 0.89 0.20 0.18 0.16 0.15 0.13 0.12 0.10 0.09 0.08 0.07 0.07Discounted Tariff 1.91 0.31 0.28 0.25 0.23 0.20 0.18 0.17 0.15 0.13 0.12 0.11Levelised Tariff (Rs / unit) 2.05

Tariff Estimates

Gopi
Text Box
51
Page 55: Power sector Financing Project Report

 

 

9.0  Conclusions and Recommendations  

From the above capital budget projections on a dummy project, it is observed that the IRR 

for 500MW unit  is 11.4% &  for a 2x250MW unit  is 12.15% and  the  levellized Tariff  is `2.51/‐ & 

`2.05/‐  per  unit  respectively. NPV  for  both  the  projects  are  found  positive.    By  comparing  two 

options 2x250MW unit  is  looking more  feasible compared to a single 500MW unit. Of course we 

can’t say this statement is always true. There certain other factors like nature of project whether it 

is a Green  field or Brown  filed, Fuel price, distance  from coal  fields &  type of  transportation etc. 

Installing a single unit has always has a drawback  in terms of  inventory. Single unit requires  large 

percentage  of  investment  in  inventory  like  spares &  other  overheads  compared  to  a multi  unit 

structure. 

The Electricity Act, 2003 aims to bring  in more competition  in the power sector  in India to 

increase the efficiency of the system. It is evident that the deficit in power availability in India is a 

significant  impediment to the smooth development of the economy.  In this context, bridging the 

gap  in  demand  and  supply  has  become  critical  and  consequently,  large  projects  are  being 

undertaken in different segments of the sector; Generation, Transmission and Distribution. As India 

has  not witnessed  such  a  large  scale  of  implementation  before,  there  is  a  need  to  review  and 

enhance project execution capabilities to help ensure targets are met.  

It  is necessary to appreciate that  inspite of all the encouragement and reforms; the power 

sector  is  still  riddled  with  many  gross  uncertainties.  Emerging  economies  such  as  India  has 

therefore much to do and learn about the execution of the reform processes. The reforms process 

should be carried out in gradual steps and the sector should not be left to market forces from the 

Gopi
Text Box
52
Page 56: Power sector Financing Project Report

 

 

very outset.  Government reforms should be investor friendly to attract more investments in Indian 

Power Sector. 

Government  should  pay  more  attention  on  development  of  non  conventional  energy 

sources rather than depending on coal based plants. The Ministry of Power needs to accelerate the 

development of  the National Grid because  the  lack of Transmission capacity  is harming  the cost 

effectiveness of delivered power. As for financing the sector, the Inter‐Institutional Group needs to 

start working on  the Public Private Participation model wherein  the Private entrepreneurial skills 

are  actively  supported  by  public  funds  not  just  in  the  form  of  debt  financing  but  also  equity 

participation.  

 

 

@@@@@@@@@ 

 

 

 

 

 

 

 

 

 

 

Gopi
Text Box
53
Page 57: Power sector Financing Project Report

 

 

References/Bibliography 

Literature References   

Reports & Executive summary on Power Sector from Central Electricity Authority 

(CEA),CERC  

Planning Commission reports on Indian Power Sector( 11& 12th plan Volume3) 

INDIA ‐ Power Sector: Emerging Developments & Critical issues 

Indian Power sector‐ Performance, Challenges & Opportunities by CRISIL  

The Hindu‐ Survey of Indian Industry.

Business report on NSPCL by M/s  Deloitte Touche Tohmatsu India Private Limited.

Power sector Financing Key Issues in INDIA by Power Minsistry 

Investment Opportunities  in  Indian  Power  Sector  and  Cooperation with  International 

Energy Agency ‐R.V. Shahi ,Secretary, Ministry of Power ,Government of India. 

Various  Reports  of  Power  Finance  Corporation  (PFC),  Central  Electricity  Regulatory 

Commission (CERC), Ministry of Power (MoP), Power Finance Corporation (PFC) ,Power 

Grid Corporation of India (PGCIL)  

 Weblinks 

1. Ministry of Power, Govt. of India (powermin.nic.in)  

2. Central Electricity Authority (www.cea.nic.in)  

3. Central Electricity Regulatory Commission (cercind.gov.in)  

4. Infraline (www.infraline.com)  

5. The Associated Chambers of Commerce and Industry in India (www.assocham.org)  

6. Confederation of Indian Industries (www.ciionline.org )  

7. Power Finance Corporation ( www.pfcindia.com )