power sector in tanzania

22
1 Power Sector in Tanzania Recent Developments, Current Crisis, Issues, Challenges and Solutions

Upload: zorita-lester

Post on 02-Jan-2016

37 views

Category:

Documents


0 download

DESCRIPTION

Power Sector in Tanzania. Recent Developments, Current Crisis, Issues, Challenges and Solutions. AGENDA. Recent Developments Current Crisis Issues Challenges Solutions. Recent Developments. Power System Characteristics - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Power Sector in Tanzania

1

Power Sector in Tanzania

Recent Developments, Current Crisis, Issues, Challenges and

Solutions

Page 2: Power Sector in Tanzania

2

AGENDA

• Recent Developments

• Current Crisis

• Issues

• Challenges

• Solutions

Page 3: Power Sector in Tanzania

3

Recent Developments

1) Power System Characteristics• Installed generation capacity of 947 MW (Hydro

562 MW, Diesel 85 MW, IPPs 295 MW, Imports 5 MW), 550,000 consumers

• 4 IPPs – IPTL, Songas, Kiwira Coal Mine, TANWAT selling power to TANESCO

• Electricity imports from Uganda and Zambia, and exports power to Kenya

• EWURA established – not yet fully operational• Several privately owned generation facilities

mostly for standby

Page 4: Power Sector in Tanzania

4

Hydropower Resources

Page 5: Power Sector in Tanzania

5

Mtera Dam Water Levels

686

688

690

692

694

696

698

700

J F M A M J J A S O N D

Month

Lev

el m

.a.s

.l. 2003

2004

2005

2006

MSL

FSL

Page 6: Power Sector in Tanzania

6

Nyumba ya Mungu Dam Levels

678

680

682

684

686

688

690

J F M A M J J A S O N D

Month

Lev

el m

.a.s

.l. 2003

2004

2005

2006

MSL

FSL

Page 7: Power Sector in Tanzania

7

Annual Generation - GWh

0

500

1000

1500

2000

2500

3000

3500

4000

2002 2003 2004 2005 To Ap06

Gen

erat

ion

- G

Wh

IPPs

Thermal

NYM

Pangani

Hale

Mtera

Kihansi

Kidatu

Page 8: Power Sector in Tanzania

8

Current Crisis

• Generation shortage load shedding (power rationing) in February and March, June to October/November

• Severe cash shortage O&M costs financed through overdraft (now TShs 70 billion, expected to increase)

• Under recovering about TSh 8.3 billion per month due to low electricity tariffs

Page 9: Power Sector in Tanzania

9

Issues

• Shortage of generation• High liquid fuel prices form about US$40/barrell

in 2003 to over US$70/barrell now• High technical and commercial losses• Lack of investments since 1997 when

TANESCO was specified• Low tariffs that under recover O&M costs• Poor quality of supply and service• Conflicting uses for the water and poor

catchment management• Load shedding 1994, 1997, 2000, 2006

Page 10: Power Sector in Tanzania

10

Issues

• Delays in commissioning of Ubungo units 5 & 6 in 2005

• Outages of Songas’ generating sets and transformer in 2005 and 2006

• Sub-optimal operation of the hydro/thermal system (overuse of hydro system)

• Unsuccessful procurement of emergency power plant in 2004 (IDA funding),

Page 11: Power Sector in Tanzania

11

Challenges

• Lower than average hydrology (drought)

• High cost of thermal generation

• Financing of future investments

• Overloaded transmission and distribution Unbalanced electricity tariffs – Zanzibar

at TShs 26/kWh (US$0.0211/kWh) much lower than LRMC of US$0.04/kWh

Page 12: Power Sector in Tanzania

12

Challenges

• Costs about US$1.1 per kWh not served

• TANESCO estimate load shedding to year end to be about 199 GWh

• Cost to the economy estimated to be US$219 million

• In addition, the government will loose VAT on electricity consumption amounting to about US$3 million

Page 13: Power Sector in Tanzania

13

Solutions

1) Short Term• Procurement of leased gas based generation• Increase electricity tariffs by 25%• Convert IPTL to natural gas firing• Purchase of the IPTL power plant• Demand side management• Hydro/thermal generation optimization• Negotiate long term gas prices for new plant• Procurement of 100 MW gas based generation

Page 14: Power Sector in Tanzania

14

Solutions

2) Short Term• Enforcement of water rights, catchment's

management and protection, prohibit agro activities close to rivers, proper environmental management of river basins

• Rehabilitation, reinforcement and expansion of the T&D systems, replace billing system and faulty meters

Page 15: Power Sector in Tanzania

15

Actions with High Impact on TANESCO’s Financial PerformanceAction Monthly

Impact TShs billion

Target Date

5% tariff increase

1.2 Done

20% fuel levy 5 July 2006, annually if needed

IPTL conversion

5.3 March – Dec 2007

100 MW leased generation

6 Oct/Nov 2006

Page 16: Power Sector in Tanzania

16

Actions with High Impact on TANESCO’s Financial PerformanceAction Monthly Impact

TShs billionTarget Date

Acquire IPTL 3.2 December 2006

Hydro resource management

2.8 June 2006

Refinance Unit 5&6 debt

0.4 July 2006

Page 17: Power Sector in Tanzania

17

Solutions

3) Short Term – Studies and TA• Long Term Power Master Plan (2007-2032)• Demand Side Management• Capacity building• IPP Strategy and standardized bidding

documents• Hydro/thermal generation optimization• Grid extension to Kigoma, and mines• Preparation of a new Sector Reform Strategy

Page 18: Power Sector in Tanzania

18

Solutions

4) Short to Medium Terms

• Demand side management: Replace incandescent lamps (ILs) with compact fluorescent lamps (CFLs) – less wattage on equivalent light output

• Benefits to both the consumers (reduced energy consumption) and the utility (reduction of demand)

Page 19: Power Sector in Tanzania

19

Comparisons CFLs and ILs on Equivalent Light Output

ILs CFLs Savings

40 W 9W 31 W

60 W 15 W 45 W

100 W 25 W 75 W

Page 20: Power Sector in Tanzania

20

Comparisons CFLs and ILs on Equivalent Light Output

• On equivalent light output, replacement of 23 @ 60 W ILs with 15 W CFLs would reduce the peak demand by about 1 kW

• Consumers would save TShs 23 per day in electricity charges for every 60 W IL replaced (assuming usage of 5 hours/day)

• Replacing just 2 ILs per consumer for the 550,000 consumers, would reduce the peak demand by 50 MW and the energy demand by 90 GWh annually (assuming usage of 5 hours/day)

Page 21: Power Sector in Tanzania

21

Solutions

1) Medium to Long Term• TANESCO;s capital investments needs

2006 to 2010 TShs 1.3 trillion for:a) New generation additions 345 MW b) Transmission and distribution system

rehabilitation and expansionc) Increasing access to electricity in rural

areasd) Interconnections – EAC and SADC

Page 22: Power Sector in Tanzania

22

Comparison of Tanzania’s Electricity Tariffs with selected African and OECD

Countries US$ cents per kWh