power sector in tanzania
DESCRIPTION
Power Sector in Tanzania. Recent Developments, Current Crisis, Issues, Challenges and Solutions. AGENDA. Recent Developments Current Crisis Issues Challenges Solutions. Recent Developments. Power System Characteristics - PowerPoint PPT PresentationTRANSCRIPT
1
Power Sector in Tanzania
Recent Developments, Current Crisis, Issues, Challenges and
Solutions
2
AGENDA
• Recent Developments
• Current Crisis
• Issues
• Challenges
• Solutions
3
Recent Developments
1) Power System Characteristics• Installed generation capacity of 947 MW (Hydro
562 MW, Diesel 85 MW, IPPs 295 MW, Imports 5 MW), 550,000 consumers
• 4 IPPs – IPTL, Songas, Kiwira Coal Mine, TANWAT selling power to TANESCO
• Electricity imports from Uganda and Zambia, and exports power to Kenya
• EWURA established – not yet fully operational• Several privately owned generation facilities
mostly for standby
4
Hydropower Resources
5
Mtera Dam Water Levels
686
688
690
692
694
696
698
700
J F M A M J J A S O N D
Month
Lev
el m
.a.s
.l. 2003
2004
2005
2006
MSL
FSL
6
Nyumba ya Mungu Dam Levels
678
680
682
684
686
688
690
J F M A M J J A S O N D
Month
Lev
el m
.a.s
.l. 2003
2004
2005
2006
MSL
FSL
7
Annual Generation - GWh
0
500
1000
1500
2000
2500
3000
3500
4000
2002 2003 2004 2005 To Ap06
Gen
erat
ion
- G
Wh
IPPs
Thermal
NYM
Pangani
Hale
Mtera
Kihansi
Kidatu
8
Current Crisis
• Generation shortage load shedding (power rationing) in February and March, June to October/November
• Severe cash shortage O&M costs financed through overdraft (now TShs 70 billion, expected to increase)
• Under recovering about TSh 8.3 billion per month due to low electricity tariffs
9
Issues
• Shortage of generation• High liquid fuel prices form about US$40/barrell
in 2003 to over US$70/barrell now• High technical and commercial losses• Lack of investments since 1997 when
TANESCO was specified• Low tariffs that under recover O&M costs• Poor quality of supply and service• Conflicting uses for the water and poor
catchment management• Load shedding 1994, 1997, 2000, 2006
10
Issues
• Delays in commissioning of Ubungo units 5 & 6 in 2005
• Outages of Songas’ generating sets and transformer in 2005 and 2006
• Sub-optimal operation of the hydro/thermal system (overuse of hydro system)
• Unsuccessful procurement of emergency power plant in 2004 (IDA funding),
11
Challenges
• Lower than average hydrology (drought)
• High cost of thermal generation
• Financing of future investments
• Overloaded transmission and distribution Unbalanced electricity tariffs – Zanzibar
at TShs 26/kWh (US$0.0211/kWh) much lower than LRMC of US$0.04/kWh
12
Challenges
• Costs about US$1.1 per kWh not served
• TANESCO estimate load shedding to year end to be about 199 GWh
• Cost to the economy estimated to be US$219 million
• In addition, the government will loose VAT on electricity consumption amounting to about US$3 million
13
Solutions
1) Short Term• Procurement of leased gas based generation• Increase electricity tariffs by 25%• Convert IPTL to natural gas firing• Purchase of the IPTL power plant• Demand side management• Hydro/thermal generation optimization• Negotiate long term gas prices for new plant• Procurement of 100 MW gas based generation
14
Solutions
2) Short Term• Enforcement of water rights, catchment's
management and protection, prohibit agro activities close to rivers, proper environmental management of river basins
• Rehabilitation, reinforcement and expansion of the T&D systems, replace billing system and faulty meters
15
Actions with High Impact on TANESCO’s Financial PerformanceAction Monthly
Impact TShs billion
Target Date
5% tariff increase
1.2 Done
20% fuel levy 5 July 2006, annually if needed
IPTL conversion
5.3 March – Dec 2007
100 MW leased generation
6 Oct/Nov 2006
16
Actions with High Impact on TANESCO’s Financial PerformanceAction Monthly Impact
TShs billionTarget Date
Acquire IPTL 3.2 December 2006
Hydro resource management
2.8 June 2006
Refinance Unit 5&6 debt
0.4 July 2006
17
Solutions
3) Short Term – Studies and TA• Long Term Power Master Plan (2007-2032)• Demand Side Management• Capacity building• IPP Strategy and standardized bidding
documents• Hydro/thermal generation optimization• Grid extension to Kigoma, and mines• Preparation of a new Sector Reform Strategy
18
Solutions
4) Short to Medium Terms
• Demand side management: Replace incandescent lamps (ILs) with compact fluorescent lamps (CFLs) – less wattage on equivalent light output
• Benefits to both the consumers (reduced energy consumption) and the utility (reduction of demand)
19
Comparisons CFLs and ILs on Equivalent Light Output
ILs CFLs Savings
40 W 9W 31 W
60 W 15 W 45 W
100 W 25 W 75 W
20
Comparisons CFLs and ILs on Equivalent Light Output
• On equivalent light output, replacement of 23 @ 60 W ILs with 15 W CFLs would reduce the peak demand by about 1 kW
• Consumers would save TShs 23 per day in electricity charges for every 60 W IL replaced (assuming usage of 5 hours/day)
• Replacing just 2 ILs per consumer for the 550,000 consumers, would reduce the peak demand by 50 MW and the energy demand by 90 GWh annually (assuming usage of 5 hours/day)
21
Solutions
1) Medium to Long Term• TANESCO;s capital investments needs
2006 to 2010 TShs 1.3 trillion for:a) New generation additions 345 MW b) Transmission and distribution system
rehabilitation and expansionc) Increasing access to electricity in rural
areasd) Interconnections – EAC and SADC
22
Comparison of Tanzania’s Electricity Tariffs with selected African and OECD
Countries US$ cents per kWh