Environmental Monitoring Report Project No: 42378-016 Loan No-BAN: 3087 July 2018 Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Part B 2: Increased South Dhaka Distribution Network January – June 2018 Prepared by: Dhaka Power Distribution Company Limited(DPDC) for the Asian Development Bank for People’s Republic of Bangladesh.

Upload: others

Post on 12-Mar-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Environmental Monitoring Report

Project No: 42378-016 Loan No-BAN: 3087 July 2018

Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Part B 2: Increased South Dhaka Distribution Network

January – June 2018 Prepared by: Dhaka Power Distribution Company Limited(DPDC) for the Asian Development Bank for People’s Republic of Bangladesh.

This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

DHAKA POWER DISTRIBUTION COMPANY LIMITED

EVIRONMENTAL SAFEGUARD IMPACT MONITORING

REPORT

of

CONSTRUCTION OF NEW 132/33 KV & 33/11 KV

SUBSTATION & CONSTRUCTION & EXPANSION OF

DISTRIBUTION NETWORK OF NORTH SOUTH ZONE

PROJECT UNDER DPDPC

18 JULY 2018

SUBMITTED BY

DHAKA POWER DISTRIBUTION COMPANY LIMITED

1 | P a g e

Table of Content

(Environment)

Table of Content ...................................................................................................................... i

List of Tables ............................................................................................................................ ii

List of Figures ............................................................................................................................ ii

Abbreviations and Acronyms ..................................................................................................... iii

Executive Summary................................................................................................................... iv

1. Introduction............................................................................................................................ 1

1.1 Objective ................................................................................................................................... 1

1.2 Project Location ........................................................................................................................ 2

1.3 Scope of Work of the Projects .................................................................................................. 2

1.4 Monitoring Policy Standard ..................................................................................................... 3

1.5 ADB loan covenants with the DPDC......................................................................................... 4

1.1.1 Implementation arrangement ............................................................................................ 4

1.1.2 Environment ....................................................................................................................... 4

1.6 Safeguards-related provisions in bidding documents of works and work contacts .................. 5

1.7 Safeguard monitoring and reporting ......................................................................................... 5

1.8 Labour standards ...................................................................................................................... 5

1.9 Project reviews .......................................................................................................................... 6

1.10 Occupational Health &Safety…………………………………………………………………………………………………6

2. Methodology............................................................................................................................ 9

3. Monitoring Results .................................................................................................................. 12

4. Consultations........................................................................................................................... 19

5. Institutional arrangement for monitoring and compliance ........................................................20

6. Site Specific Environmental Management Plan ......................................................................... 22

6. 6 Grievance Redress Mechanism……………………………………………………………………………………….…………23

7. Consultation and Recommendation......................................................................................... 62

List of Tables Table 1.1: Location of the sub-stations ................................................................................ 2

Table 1.2: SLECTED IESCs Parameter .................................................................................... 3

Table-2.3: Protective equipment of risky limb in Human Body ........................................... 9

Table-3.1: Project Implementation Status ............................................................................ 12

Table: 3.2: Compliance status with the ADB loan convenants ............................................. 13

Table 3.3: Matrix of Monitoring Results .............................................................................. 16

2 | P a g e

List of Figure

Fig. 5.: Institutional Arrangement for Monitoring and Compliance. ................................... 20

3 | P a g e

ACRONYMS & ABBREVIATIONS

A&P Appraisal and Preparation

ARAP Abbreviated Resettlement Action Plan

BMDF Bangladesh Municipal Development Fund

CBO Community Based Organization

CIP Capital Investment Plan

GoB Government of Bangladesh

GRC Grievance Redress Committee

IDA International Development Association

IP Indigenous People

IPP Indigenous Peoples Plan

LGD Local Government Division

LGED Local Government Engineering Department

M&S Management & Supervision

MGSP Municipal Governance and Services Project

MOLGRDC Ministry of Local Government, Rural Development & Cooperatives

MSP Municipal Services Project

O&M Operation and Maintenance

OD 4.30 Operational Directive 4.30 on Indigenous Peoples

PAH Project Affected Household

PAP Project Affected Person

RP Resettlement Plan

RTIP Rural Transport Improvement Project

SA Social Assessment

SMF Social Management Framework

SMP Social Management Plan

SSE Social Safeguards Expert

TP Tribal People

TPP Tribal People Plan

ULB Urban Local Body

WLCC Ward Level Coordination Committee

WB World Bank

4 | P a g e

EXECUTIVE SUMMARY

Environmental Social Safeguard Monitoring has been executed at the 14 nos. of construction

of new 132/133 kv and 33/11 kv sub-stations and construction and expansion of distribution

network of North South Zone project under DPDC, financed by ADB. Monitoring has been

executed based on ADB Environmental and safeguard’s policy, the laws and the National

Policies of Bangladesh and loan covenants between ADB and Government of Bangladesh.

Construction works of all the sites has been ongoing and environmental expert observed Air

quality, water quality, noise, ecosystem, biodiversity and social environmental status of the

construction sites following the ADB guidelines. Environmental expert also consulted with

sites manager, labors and others who are involved with the construction activities and

observed regarding environmental and social aspects such as Health and Safety, working

condition, services facilities like labor sheds, toilet facilities, Drinking water, Kitchen,

Washroom etc. and gender status and opportunities among the workers.

At all the sites environmental expert was examined noise level and observed it was within in

limit i.e, no noise pollutions were occurred. Expert also collect sample’s of water and

examined Air’s parameters and after laboratory test, found all of those were in limit.

During field visit, it was observed that water is being sprayed to control dusts and other

particles.

Solid waste management was partially satisfactory, waste from kitchen and other sources

must be managed properly such as use dustbin and for disposal, disposal site must be located

by the contractor.

The working environment in the sub-station was partially good but must be improve.

Environmental expert suggested at all the sites for complying every aspects using safety

equipment’s for avoiding accidental cases and managed every matter properly during

construction works.

5 | P a g e

1. INTRODUCTION:

Bangladesh is one of the most densely populated country in the world. Bangladesh is a

South Asian Riverine country. A total of 238 rivers cross the country among them 75 are

trans boundary [54 with India and 3 with Myanmar).

Dhaka is the capital city of Bangladesh which is also most densely populated capital city

in the world and Narayanganj is commercially important city which is also densely

populated and DPDC Area is within two city. With rapid industrialization and

urbanization of the two city, the demand of Electricity has increased tremendously.

Electricity plays an important and vital role in every days actualities of life activities. To

maintain the industrial growth with better socio-economic development, a sustainable

power distribution is very important from the proper power distribution point of view,

DPDC initials to modernize the existing distribution system i.e, construction and

expansion of distribution network of north south zone and also construction of New

132/33 kv and 33/11 kv sub-station under DPDC Area. The construction works of this

project has been ongoing and environmental expert has been monitoring environmental

aspects of all the sites based on ADB environment policy, the laws and the Nation polices

of Bangladesh and loan conversant between ADB and government of Bangladesh.

1.1 OBJECTIVES

Objective of the DPDC project is to monitor environmental aspects according to the

guidelines of DoE and Asian Development Bank with standard engineering practices,

Safeguard, procurement rules, Health and safety and environmental issues at all the

construction sites.

the specific objectives of environmental monitoring are as follows:

a) Monitoring noise, water and air quality during construction of as all he sites.

b) waste management system

c) Monitoring working condition, occupational health and safety of workers all the sites.

MONITORING THE ENVERONMETAL COMPLIANCE OF THE PROJECT

DURING CONSTRUCTION WORKS

Environmental and safeguard monitoring according to the laws and policies of

Government of Bangladesh.

6 | P a g e

Monitoring Plan of environmental and social safeguard management described in the

environmental impact assessment (EIA) report as well as in the action plan in

guidelines with ADB’s requirements.

Provide environmental compliance monitoring report

1.2 Project Location

Table 1.1: Location of the sub-stations

Sl.

No

Name of the

proposed 33/11 Kv

Sub-Station

Location of the land Area of

land

Property Remarks

1. Mugadapara

Hospital

South-East corner of 500

bed General Hospital,

Muddpara, Khilgaon

6.85

decimal

Land belongs to

employer

Surrounded by

boundary wall

2. Banasree Block-E, Plot No. E-14,

Banasree, Rampura, Dhaka

8.25

decimal

Land belongs to

employer

Surrounded by

demarcation wall

3. Dhapa S.A-820, R.S-957, Khatian-

3476, Jot No. 3475, Dhapa,

Idrakpur, Fatulla,

Narayanganj

9.89

decimal

Land belongs to

employer

Demarcated by clear

demarcation

4. Mondalpara S.A-574, R.S (717/1176),

Khatian-2706,

NarayanganjSadar,

Narayanganj

12.68

decimal

Land belongs to

employer

Existing 33/11 Kv

sub-station

5. Nandalapur Adjacent to Prime Textile

Mill

A part of

20 Katha

Land

Land belongs to

employer

Demarcated by clear

demarcation

6. Laxmi Narayan

Cotton Mills

North-West side of Laxmi

Narayan Cotton Mills

Compound, Narayanganj

5.78

Katha

Land belongs to

employer

Surrounded by

demarcation wall

7. Dhaka Medical

College (DMC)

right side of the entrance of

Shaheed Dr. Milon

Auditorium)

8.25

decimal

Land belongs to

employer

Surrounded by

demarcation wall

8. Kamolapur Kamolapur Sub-Station,

Kamalapur, Dhaka

Land belongs to

employer

Surrounded by

demarcation wall

1.3 SCOPE OF WORKS

Scope of works according to the guidelines of DoE, the EIA report including potential

impacts of the project sites activities on the environmental components of the project area.

Environmental Management and environment monitoring plan suggested in the EIA

report in line with the action plan proposed by ADB.

7 | P a g e

Environmental monitoring framework and work plan specifying the indicators,

method, location, time, frequency of monitoring provided in the EIA that should be

followed by the contractor.

Monitoring of construction activities, their compliance with national Environmental

and social regulations, and ADB’s Performance Standards on Social and

Environmental sustainability.

Monitoring of implementation of environmental monitoring activities as specified in

the environmental monitoring plan.

Monitoring of different activities of contractors regarding analysis of air quality,

water Quality, noise levels measurement, waste management etc. in connection with

the environmental monitoring plan.

Monitoring of socio-economic issues like community safeguard due to pollution,

hazards and employment opportunity.

Maintain the close co-operation with the project director and all site contractors.

Submit monitoring report at the end of six (6) months according to the reporting

requirement of ADB satisfying equator principles.

1.4 Monitoring Policy Standard

As per the Bangladesh government Policy Standard Environmental compliance

monitoring is one of the most important parts that would be initiated following the

Environment compliance monitoring guidelines by DoE and the agreement between

ADB and Government of Bangladesh based on the ADB loan covenants. DPDC has

taken initiatives to construction of new 132/133 kv and 33/11 kv sub-station and

construction and expansion of Distribution network of North South zone project under

DPDC financed by ADB. Now the purpose of the environmental monitoring is to

monitor whether the construction activities are preforming based on the EMP or is

creating any environmental impacts or any adjustment is required in safeguard

measures.

COMPLIANCE WITH NATIONAL

ENVIRONMENTALAW

The environmental legislation of GOB gives importance to reduce the negative impacts of

infrastructures development project and give priority for the enhancement of positive

impacts due to the project implementation. It conforms the National Environmental Policy

1992. Based on the agenda 21 of Rio conference and subsequent enactment of the

Bangladesh environmental conservation Act (BECA) 1995 and Bangladesh

Environmental Conservation Rules (BECR) 1997.

8 | P a g e

Table 1.2: SLECTED IESCs Parameter

IESCs Parameters

Air Suspended particle maters (SPM), 22 ,, NOCOSO

Waste Waste generation and proper waste disposal

Noise ADB (Decibel) a unit at Both Day and Night

Water BODP H , Arsenic etc.

Biodiversity Habitat conversion and fragmentation

Health and Safety Safety measures with in the construction sites, emergency plan.

Resettlement Livelihood challenges, restoration process, compensation process, any

complaints from affected people.

The results of the monitoring are needed to compare the established benchmark/baseline and

compliance status and help to identify the areas where adverse environmental and social

adverse impacts are still occurring. It would be helpful to formulate the corrective actions

accordingly and in a timely manner.

1.5 ADB Loan covenants with DPDC.

According to the loan covenants DPDC should carry out the project with the due

diligence and efficiency and conformity with sound administrative, financial,

Engineering, Environmental and power sector practices for the execution of project

following criteria should be followed.

1.1.1 Implementation Arrangement:

DPDC should ensure the project implementation in accordance with the detailed

arrangements set forth in the PAM. Besides, it is responsibility of DPDC to ensure

their project management staff who have the qualification to undertake necessary

tasks of procurement, construction, supervision, inspection and testing of equipment,

payments to the contractors, monitoring environmental and social safe guards due

diligence and reporting progress relevant to the components under their responsibility.

1.1.2 Environment:

DPDC should ensure that the preparation, design, construction and operation of the

project and all project facilities comply with

9 | P a g e

All applicable laws and regulation of the relating to environment, Health and safety.

The environmental safeguard

EARF

All measures and requirements set forth in the respective IEE and EMP and any

corrective or preventive action set forth in a safeguard monitoring report.

Compensation and other entitlements have been provided to affected people in

accordance with the RP (Resettlement Plan).

1.6 Safeguards related provisions in bidding documents of works and work

contracts.

DPDC should ensure the following compliance in relation to contract or bidding

during the project implementation.

a) Comply with the measures and requirements relevant to the contractors set forth in

the IEE, EMP and RP (if required) any small ethnic community peoples plan and

any corrective or preventive actions set out in a safeguard monitoring report.

b) Make available budget for all such environmental and social measures.

c) Provide the borrower with a written notice of any unanticipated environmental

resettlement or small ethnic community peoples plan.

d) Adequately record the condition of roads, agricultural land and other

infrastructure prior to starting to transport materials and construction.

e) Completely reinstate pathways, other infrastructure and agricultural land to at

least their pre-project condition upon the completion of construction.

1.7 Safeguard monitoring and reporting

DPDC should comply the following section:

Submit safeguards monitoring reports to ADB and disclose relevant information from

such reports to the affected person.

a) Any anticipated environmental and social as well as impacts arise during the

construction, implementation or operation of the project that were not considered

in the IEE, the EMP or the RP promptly inform ADB of the occurrence of such

risks and impacts with detailed description of the events and proposed corrective

action plans.

b) Reporting would be completed based on the any potential beach of compliance

with the measures and requirements set forth in the EMP.

10 | P a g e

1.8 LABOUR STANDARDS:

Labor standards should be followed as per ADB loan covenants are as follows:

a) Comply with all applicable law and related international treaty obligations of the

borrower and do not employ child labor as defined under the Bangladesh Law.

b) Provide safe working condition for male and female workers.

c) Carryout HIV/Aids and human trafficking prevention and awareness campaigns in

the campsites and corridor of influence.

d) Engage women workers as wage laborers depending on their skill.

e) Provide equal wage for equal works between men and women.

1.9 PROJECT REVIEWS:

a) The project progress should be reviewed by the ADB with necessary mid-course

corrections.

b) The assistance should be provided by the executing agency, DPDC.

The environmental monitoring will assess the compliance that has been suggested under the

laws of government of Bangladesh, policies and national standards (i.e, air noise and water

quality) and ADB loan covenants.

The results of the monitoring will compared with the established benchmark/baseline and

compliance status and help to identify the areas where adverse environmental and social

adverse impacts are still occurring. It will help to formulate the corrective actions accordingly

and timely manner.

1.10 Occupational Health & Safety:

Construction workers will be faced occupational health hazards such as minor or

major injuries due to lack of general safety requirements and precautions applicable

for such sites, malfunctioning equipment, careless use of equipment and vehicles etc.

At the construction camps for all large sized project packages, houses will be

constructed for temporary accommodation for about 100 workers. Poorly designed

11 | P a g e

temporary camps and sanitation facilities may pose a health threat and nuisance to the

workers. Uncontrolled vending of food and drinking water on the work site may also

pose a risk with respect to the distribution of contagious diseases like Typhoid,

Diarrhea, Malaria, Dengue, etc. Construction workers will be required to handle

hazardous materials for the construction works.

A proper Occupational H&S Plan should be prepared prior to start construction by the

Contractors & follow it to avoid health hazard of the workers. Fast Aid Box and

Personnel Protective Equipment (PPE) such as ear plugs, helmets, hand gloves, safety

shoes and belts, goggles, raincoats (during rains) etc. should be provided for the

workers for all construction sites of the DPDC. The safety belts and harnesses must

be worn by the workers, working at heights (such as OHTs, buildings etc.) at all times

and safe anchorage points provided. In case of major accident, transport should be

made available to take the patient to the nearest hospital in Dhaka & Narayangonj

Cities. The H&S Manager should be engaged for the construction period of the

project. The workers operating the equipment and drivers driving the construction

vehicles at construction site should be skilled. Proper H&S signboards and

appropriate information to the local people about the construction activities should be

provided.

Occupational Health, Safety, accident and training upon those.

As mentioned earlier, a considerable staff will be involved with O&M of the WS

activities. There could be H&S risks of the staff that may occur during the stay of

workers at the working places these are mainly:

- Fire hazards from loose electric lines/cooking stoves/ careless handling of

materials that can generate fire;

- Inadequate lighting and ventilation in and outside the WS complexes;

- Frequent load shading of power due to inadequate power supply ;

- Lack of daily cleaning and regular maintenance of the WS complexes;

- Noise pollution due to electro mechanical equipment;&

- Use of hazardous chemicals by the workers for purification of water.

The above mentioned all H&S risks must be considered adequately during designing

of the DPDC infrastructure and implement accordingly during construction. Full time

first aid facilities and an experienced H&S Manager should be available. Based on the

nature & location of job, provide PPE such as helmet, hand glove, safety shoes, ear

plug, mask, raincoat & safety belt for working above the GL to each worker. Training

on H&S should be provided for all staff. In case of any accidents, the victim must be

sent to nearest city hospital/ health center for proper treatment. Electro-mechanical

equipment must be kept in closed concrete house/chamber.

12 | P a g e

Training:

Contractor`s arrange short training on Health and safety and also on any accident

occurred to take necessary action, such as the victim must be provide Fast Aid and

sent to the nearest Hospital or clinic.

Construction of Power distribution Sites:

No any adverse negative environmental impact occurred at the sites of

construction of power distribution lines.

Statistics of Accident during construction work.

Up to date no any accident occurred at any construction sites.

2. METHODOLOGY:

The compliance monitoring of the project has been carried out following important

environmental and social component during the field investigation. Methodology for the

investigation of each component are given below:

2.1 PHYSICAL ENVIRONMENT:

Ambient Air Quality

To assess the baseline condition of the ambient air in the project area, the air has been

sampled and analyzed at spots, using machine and expert. Ambient Air Quality has

been continuously monitored for xx NOSOCo ,, and particulate matter (PM2.5 and

PM10) and suspended particulate matter (SPM) following the standard method.

NOISE LEVEL

Noise monitoring most important for any big construction activity as excessive noise

may create disturbance to the wild life, indigenous species, fragile ecosystems,

communal stability in case of sudden intrusion and workers due to construction

activities and subsequent increase traffic movement.

The ambient noise level has been monitored monthly sensitive receptors around the

construction sites of this project. Each time noise level has been recorded using

portable noise level meter for a two minutes time span at 5 minutes interval depending

on the site condition. Noise level meter for a two minutes time span at 5 minutes

interval depending on the site condition. Noise level recorded at time only as the

construction works held only at day light hour. A probable increase in noise level in

the same area may provide the tools for assessment of impact on environment.

13 | P a g e

Waste Management

Infrastructure work for any development, usually generate variable quantities and

types of waste materials which have the potential to cause adverse environmental

impacts during generation, storage, transport and disposal. For this reason, the project

aims to implement waste management procedures immediately after the

commencement of the civil works in order to maintain minimum potential impacts to

the environment. The projects sites were observed visually during sites visit to

investigate concerns related to waste disposal.

2.2 Ecosystem and Biodiversity Conservation:

All the sub-station sites and also expansion of distribution network sites are in urban

area of Dhaka and Narayanganj City, so urban ecosystem as well as vegetation and

wild life are major components for ecological monitoring, various types of herbs and

shrubs are observed in this area but no trees have found in any project sites.

2.3 Socio-Economic Environment:

Livelihood and living

Livelihood and employment condition of those primary stakeholders were monitored

through in depth observation, group discussion and key information interview. Local

people stated that the project does not pose any threat to the existing livelihood, rather

it appears as blessing, It will facilitate to install new industries which in turn, would

create scope of employment for local people. The present livelihood and living

condition of surrounded people of project area have been identified and will also be

updated at the next stage of monthly environment compliance monitoring.

COMMUNITY HEALTH, SAFETY AND SECURITY

All the contractor will develop a first aid medical center for immediate treatment. in

case of emergency the patient will be transferred to the nearest hospital by the

contractor.

Labour and their working condition

During construction labor and their working condition was monitored based on

observation and consultation with labors and others like that whose are involved with

the construction works.

At the stage of construction work such as. cast in situ pilling, basement, Frame

structural works, slab casting etc. are very tough works for the labors and supervision

staff, congenial and standard engineering working practices were practiced at the sites

14 | P a g e

however the contractor committed to commence standard engineering practices at all

the working sites.

Attempts were made to identify socio-economic constraints and environmental issues

related to sub-stations and expansion of distribution network construction.

It is essential to draw the attention on ensuring adequate accommodation facilities

using safe drinking water, hygienic sanitation and proper medical facilities for labors,

Living, sanitation and bathing facilities (inside the project side). The project authority

stated that all these facilities will be improved, but senario of the above mentioned

facilities remain unchanged whereas working is now in the middle stage. So it is a

matter of concern of the project priority to pursue the contractors as well as sub-

contractors to ensure standard accommodation facilities for the laborers.

Numbers of safety signboards are found in all the project sites which is good

measures for decreasing accidental occurrences. Workers are also found to use

personal safety equipment (PSE). All of the workers stated that the contractor and

project authority strictly monitored this issue. For ensuring laborers safety and

security, following protective. Laborers safety and security, following protective

equipment should be provided as per their requirement and working activity.

Present practice in the project sites is specified in separate coloumn in the following

table 2.3

Table-2.3: Protective equipment of risky limb in Human Body

Risky limbs of

Human Body

Protective Equipment Practice

in Project

Site

Remarks

Eye Safety spectacles/goggles Complied

Ear Ear Plugs Not Complied

Head and Neck Safety Helmets Complied

Hands and Arms Gloves, gavntlets and sleeves that

covers part or all of the Arm

Complied

Partially

Legs and Feet Safety boots and shoes Complied

Lungs Half and full marks filtering dust Complied

15 | P a g e

The labor of the construction sites are satisfied by their wages. The wage rate of

unskilled/semi-skilled laborors varies from BDT 400 to 500 in the project sites while for the

skilled workers wage up to BDT 700 for the respective works.

16 | P a g e

3. MONITORING RESULTS:

Monitoring results based on field visits at all the sub-Stations project sites under the

i.e, the project name: “CONSTRUCTION OF NEW 132/33KV AND 33/11 KV SUB-

STATIONS & CONSTRUCTION & EXPANSION OF DISTRIBUTION

NETWORK OF NORTH-SOUTH ZONE PROJECT UNDER DPDC”. The

monitoring results considered the social safeguard issues related to the above

construction activities.

Monitoring consultant found that construction activities at all the sites of this project

has been continuing, construction status are presented in the following table 3.1

Table-3.1: Project Implementation Status

Name of Sub-Station Activities Status

Mugdapara Hospital Civil construction, Electrical

work is ongoing

ongoing

Banasree Building construction,

Electrical work is ongoing

ongoing

Dhapa Civil construction, Electrical

work is ongoing.

ongoing

Mondalpara Civil construction &

Electrical work ongoing

ongoing

Nandalpara Building construction&

Electrical work ongoing

Building construction is

continuing

Laxminarayan Cotton Mills. Building construction and at

the same time electrical line

setup ongoing

Dhaka Medical College Building constriction work is

ongoing

Working progress is very

good

Kamalapur Pilling work Pilling work completed

Expasion and distribution

network of North South

zone

Construction work of all the

sites of North South zone is

ongoing.

Progress is very good.

3.1 COMPLIANCE STATUS WITH ADB LOAN COVENANTS.

Compliance status with the ADB loan covenants have been monitored according to the

indicators provided in the ADB loan covenants. The findings for compliance status with

the ADB loan covenants presented in the following table 3.2.

17 | P a g e

Table: 3.2: Compliance status with the ADB loan covenants

Indicators Issues Activities Compliance

Status

Remarks

Implementation

Arrangement

Arrangement is

set forth in the

PAM

Environmental

Expert Engaged

for

Environmental

monitoring

Complied The

implementation

arrangement

followed the

ADB loan

covenants

Environment,

Health and

Safeguard

All the laws and

regulations

related to the

environment

health and safety

is applicable.

All measures and

requirement a set

forth in the

respective IEE

and EMP and

corrective or

preventive

actions set forth

in a safeguard

monitoring report

Review of

existing laws

and regulation

(National and

ADB safeguard

policy)

The

environmental

expert prepared

monitoring

result and CAP

based on EMP

Complied The

environmental

expert is

preparing the

monitoring

result based on

EMP and

reviewing

existing laws

and regulations

Human and

financial

resources to

implement

safeguard

requirements

DPDC should

make available or

cause the project

executing agency

to make available

necessary

budgetary and

human resources

to completely

implements the

EMP.

DPDC made

contract with the

contractor which

have available

manpower,

budget and other

resources for the

implementation

of EMP

Complied Human and

financial

resources

management

follows the

ADB and

safeguard

requirements

Bidding

documents of

works and work

contract

Comply with the

measures and

requirements

related to the

contractor set

forth in the EIA

and EMP, make

available budget

for all such

environmental

and social

measures.

The

environmental

expert and

DPDC monitor

through monthly

visit where the

construction

activities

ongoing

Complied All safeguard

related

provisions

incorporated in

bidding

document of

works and work

contracts.

18 | P a g e

Environmental

and social

safeguard

monitoring and

reporting

Any anticipate

results that were

not considered in

the EIA and the

EMP promptly

inform ADB and

proposed for

mitigation in

corrective action

plans.

The monitoring

and the reporting

would be

completed asked

on any potential

beach of

compliance with

the measures and

requirements set

forth in the EMP.

Reviewed the

EMP provided

in the EIA

All compliance

status prepared

based on

selected

indicators

provided in the

check list.

Complied Environmental

and safeguard

monitoring and

reporting

complied

Labour Standard Comply with all

applicable labor

law, treaty

obligations of the

borrowers and

child labor law of

Bangladesh.

Provided safe

working

condition for

male and Female

workers.

Carry out

HIV/Aids and

Human

trafficking

presentation and

awareness

complains in the

campsites and

corridor of

influences.

Engage women

labors as wage

laborers

depending on

Compliance

status monitored

through site

specific visit by

DPDC and

environmental

expert.

Complied Suggestions for

achieving full

compliance

suggested in the

CAP.

19 | P a g e

their skill,

provide equal

wage for equal

works between

men and women.

Project Reviews The project

progress would

be reviewed by

the ADB with

necessary mid-

course correction

All submitted

report reviewed

by ADB

Complied All comment

form the ADB

incorporated and

submitted to

DPDC.

3.2 Social Safeguard Compliance Status:

3.2.1 Compensation

DPDC has not needed to paid any compensation for the land, because they has own

land for the construction of 22 nos. of sub-station (8 nos. sub-stations, ADB Financed)

and construction and extension of distribution network of North South zone project.

3.2.2 Livelihood and Employment:

Social safeguard expert during monitoring found that 5% workers are from the

locality involved in the construction work, so it is very good information that the

project has generated employment opportunity for local people through construction

activities. The working condition was not very good inside the sub-stations, because

social safeguard expert during monitoring found that almost all labors were not using

safety equipment as the safety equipment was not sufficient for all workers.

3.2.3 Occupational Health, safety and security

Contractors of all the construction sites, were and security of all the laborers. In any

case of emergency there were no any specific arrangement of doctor’s, ambulance

service to carry the injured person to nearby hospital or clinic, for better treatment.

3.2.4 Labor and working condition

The social safeguard expert during monitoring found that in all the construction sites

labor’s facilities were not upto mark. Contractors were not providing sufficient safety

equipment, adequate labors sheds drinking water, toolbox (First Aid) etc. It should be

improved.

20 | P a g e

Table 3.3: Matrix of Monitoring Results

Environmental

& social

component

Potential

Components

Monitoring

measures

Status Corrective Action

Plan (CAP)

Ambient Air

Quality

Emission of

fugitive dusts due

to construction

activities can

accelerated the air

pollution

Spraying water

in the

construction site

to control

fugitive dusts

Water spraying

carried out

once in a day

Water can be sprayed

tarice in a day for

controlling fugitive

dusts.

Construction

materials to be

kept covered

Party complied

some sites

Construction materials

should be kept covered

by polythene during

dry weathers so that

strong wid cannot blow

away.

Noise Level Disturbance to

ecosystem and

workers at work

site due to

construction

activities of the

project site.

Using modern

law noise

generation

machineries

with silencers.

Complied in all

sites

The contractor has been

advised to relocate the

generator in one corner

of the project and cover

the machine with noise

proof hood to make the

noise free from noise

hazard

Providing ear

plug to the

workers.

Not Complied Generator in one corner

of the project and cover

the machine with noise

proof hood to make the

area free from noise

hazard.

Solid waste

management

An efficient

municipal solid

waste

management

system may

create serious

negative impacts

like spread of

infectious

diseases, land and

water pollution,

obstruction of

drains and loss of

bio diversity.

Ear marking

specific sites for

waste disposal.

Complied

partly

Facilitate garbage bin

for solid wastes

disposal, construction

wastes need to be

collected and disposed

in a particular site

inside the project

boundary.

Livelihood and

employment

Livelihood may

be disturbed due

to the

development

Causing no

threat in the

livelihood of

local peoples

Contractor is

hiring local

labors.

N/A

21 | P a g e

activities prioritizing local

labors in

employment.

Providian

separate water

facilities for

workers

No negative

impacts was

found

Occupational

health safety and

security

Health, safety and

security would be

affected during

construction

phase of the

project

Construction of

boundary wall

and fence

around the

project area.

Consider

community

health and safety

in designing

infrastructure

and equipment.

Practicing safe

management for

hazardous

materials which

may pose threat

to the

community.

Site specific

HSE manager

would be

required for

regular

monitoring

availability of

contingency

plan for natural

hazards.

Training and

instruction to the

security

personnel about

their behavior

and

communication

with the local

people.

Safety trainings

The contractors

were following

standard

occupational

health, safety

and securities

practices in any

of the sites

The contractors need to

facilitate the following

arrangement.

Personal protective

equipment

Needed to

arrangement of tool

box training to the

workers twice in a

week.

Displaying

emergency contact

numbers should be

in Bengali language

(Hospital, Fire

service, police

station etc.)

Display of

construction sites

safety signs in

Bengali inside and

around the project

boundary.

Permanently

engage HSE

manager in each

sites.

No smoking

instruction should

be displayed in

Bengali.

The kitchen should

have to be need and

clean

Needed basket or

dust bin in all sites

for disposal and

non-disposal

wastes.

Ensure to clear the

dustbin after out of

22 | P a g e

for workers (i.e.)

fire control,

working at

height, working

in heat, first aid

etc.

Increased

awareness

among the

workers and

employees and

conduct health

awareness.

order.

The safety and

healthy water

supply (For

drinking) should

have to be readily

accessible to the

workers.

The bath reservoir

should have to be

lean by weekly.

Accidental or injury

log book should be

put into display.

Site specific EHS

plan must be

implemented

The insurance

policy should be

cover the accident

or injuries of the

labours.

All electric

distribution lines at

the project site

required to be

fixed.

Labor and

working

condition

Community

dwellers may feel

that they are

giving substantial

share in project

related job

opportunity

Adequate fire

precautions in

place (For

example, fire

extinguishers,

escape routes).

Documentation

and reporting of

occupational

accidents,

Compliance of

projects labor

policy with the

national labor

law. No child

labor and forced

labor.

The contractor

is complying

HSE’s issues

properly

The contractors needed

to facilitate the

following arrangement:

Develop and

refurnish the labor

sheds.

The sanitation

facilities need to be

improved

Fire extinguisher

needed at the

workers sheds.

5 minutes

awareness speech

should be delivered

to the workers at

every morning.

23 | P a g e

4. CONSULTATION:

Consultation meeting were held with the DPDC’s personnel’s and contractor’s

managers, engineers and others in all the sites, the participants expressed their opinion

regarding construction works and other aspects which are related with sites activities.

The environmental expert recorded all the information delivered in the meeting.

Consultation Output:

DPDC’s Engineers gave an overall scenario about construction of new 132/33 kv and

33/11 kv sub-station & construction and expansion of distribution network of North

South zone project under DPDC. According to them no lands were acquired for eight

sub-stations and also distribution network of North South projects. They also reported

that about 5 to 10% labors are local people.

Contractors of all the sites provides health, safety and security services for the

construction labors. Contractors of all the sites also arranged short training

programme regarding tool box and job related for the labors health, safety and

security.

24 | P a g e

5. INSTITUTIONAL ARRANGEMENT FOR MONITORING AND COMPLIANCE.

The organogram provided by the DPDC is responsible to monitor environmental

compliance during the construction of the projects. The superintending engineer,

executive engineer, asst. engineer are working under the supervision of the project

director and chief engineer for the compliance monitoring of construction of New

132/33 kv and 33/11 kv sub-stations & construction and expansion of distribution

network of North South zone project under DPDC financed by ADB. The project

director is responsible to supervise and guide the whole work regarding monitoring

and compliance. The following figure 5.1 shows the institutional arrangement those

who responsible to ensure monitoring and compliance in accordance with laws of

government of Bangladesh and ADB’s loan covenants.

Fig. 5.: Institutional Arrangement for Monitoring and Compliance.

Office Asst.

Chief Engineer &

Project Director

Superintending

Engineer

Manager

Finance

Superintending

Engineer

Executive Engineer Executive Engineer

Asst. Engineer

(Two Nos)

Computer Operator Asst. Engineer

(Two Nos)

Peons

25 | P a g e

6. SITE SPECIFIC ENVIRONMENTAL MANAGEMENT PLAN :

The characteristics of the 22Nos. of Sub-stations (9nos. ADB Financed) are of the

same nature and so the EMPs provided in the EIA report are same, therefore the

SFMP suggested in this section would cover all EMPs for all the 8 nos. of sub-

stations.

DPDC’s appointed all the contractors of all the site are very much committed (as per

bidding documents of works and work contract) achieving excellent results in their

HSE performances at their working sites. Their commitment to HSE must not be

compromised to achieve other business objectives like the way they manage Quality,

cost and schedule. All the contractors must always be proactive in identifying existing

and potential Hazards and work towards eliminating and or mitigating the impact of

Hazards regarding the EMP provided in EIA report of this projects. Responsibility of

HSE falls on everyone in the workplaces which includes employees, customers,

contractors, visitors etc.

6.1. HSE Implication.

Promote good safety, culture and Behavior through positive communication and co-

operation we work towards incident free-zero accident, zero loss no harm to people,

excellent result in HSE performance, HSE would not compromised cultivating HSE

excellence as a core value, manage HSE like we do quality, cost and schedule, no

operation will have greater importance over HSE and no damage to the environment.

6.2. Site Training and meeting for Safety.

Daily conducted tool Box meeting.

a) Monthly mass meeting to be arranging.

b) Specific safety training needs providing the employees.

c) Mock Drill to be arranged at sites once in 6month.

d) Conduct Firefighting raining program sessions.

6.3. Environmental protection.

a) Only licensed disposal collect or shall engaged to carry out the disposal.

b) The hazarders material, liquids or chemicals shall be disposed in designated bin in

collection point, separated from other form of waste such as rubbish or scraps.

c) All garbage, refuse, waste, debris etc. shall be disposed in designated Bins or

containers.

26 | P a g e

6.4. IN-HOUSE RULES AND REGULATIONS:

In house rules and Regulations are:

a) Smoking is only allowed at designated smoking points.

b) No cigarettes, lighter and matches are allowed near the O2, C2H2 & LPG bay.

c) Drugs or substance abuse are strictly prohibited.

d) Personnel found consuming or in possession of drugs will be handed over to the local

authority.

e) Alcohol consumption during working hours are strictly prohibited.

6.5. General site safety and environmental Guidelines.

a) The factory act and regulation (Bangladesh Government) Permission held and strictly

following the CP (Code Purchase)

b) Work place must be indicated the emergency assembly points, evacuation and rescue

plant contacts by immediate in charge of project.

c) Emergency First AID Box and Quality first Aides appointed.

d) First Aider should be qualifying on CPR & AED.

e) safety Awareness and safety articles are available at the work place.

f) All inflammable material are stored separates in an open shed with proper

barricading, caution Boards like “No” smoking etc. are displayed.

g) Firefighting facilities was provided like sand bucket, fire extinguisher.

h) Safety talk/Tool Box meeting was conducted daily before start of work to create

safety awareness about the hazards in the particular job to avoid accidents.

i) Nobody is allowed to work without wearing certified safety Helmet, Goggles,

fluorescent jacket & safety shocks and other DPE, as required.

j) Usage of protection when works without wearing certified safety Helmet.

k) Usage of eye protection when works man one engaged for grinding, chipping welding

and gas cutting.

l) Emergency contact numbers like ambulance, Fire station, local police station Nos.

was displayed at site office or sites.

m) Emergency vehicle stand by deployed at site.

27 | P a g e

n) All excavated pits barricaded and barricaded maintained fill the back filling is done.

o) Adequate lighting facilities such as flood-lights, hand lights and area lighting was

provided at the working sites.

p) Pilling zones, erection zones and dismantling zone has been barricaded.

q) Scaffoldings/work platforms are used sound proof materials.

r) Flagman was deployed during movement of heavy vehicles.

s) Fall arrestor was used while working at heights.

t) Daily manpower report, accidents/near miss report submitted.

u) Safety meeting hold at regular intervals.

v) To be submitted organization chart with contact nos.

w) Medical certificate should be kept before engaging workman.

x) Safety audit compliance prepared by contractor on daily basis.

y) Name and blood group was reflected on helmet and new employees was updating on

daily basis.

6.6 GRIEVANCE REDRESS MECHANISM

6.6.1 General

Experience from past projects shows that project implementation is a complex process

involving numerous interested and aggrieved parties giving rise to likely instances of conflict,

allegations, etc. Most of the conflicts and allegations appear not to be of a serious nature but

may snowball into a bigger issue if not given adequate attention from the beginning itself.

Some of the potential points that could give rise to grievances could be related to

compensation payment, improper estimation of affected assets, failure to fulfill commitments,

poor management of construction activities, inappropriate planning of vehicle movement, and

cultural conflicts between migrant workers and local communities etc.

Therefore, it is imperative to have an internal mechanism in place where the aggrieved

party/s can lodge their complaints and get it amicably settled prior to approaching the formal

mode of solution available to them i.e. access to legal system through courts. In order to

provide a formal forum to the aggrieved parties to deal with issues arising out of project, it is

proposed that a joint grievance redress mechanism be instituted for both environmental and

social related issues.

28 | P a g e

The proposed Grievance Redress mechanism (GRM) will be developed for the Project in

order to settle as many disputes as possible through consultations. Such a mechanism is

important as it is expected that most cases, if not all, would be resolved amicably; and the

process, as a whole, will promote dispute settlement through mediation to reduce litigation.

However, the options of legal recourse will not be restricted in any way by the project

proponent.

6.6.2 Objectives of Grievance Redress Mechanism

The basic objective of the GRM shall be to provide an accessible mechanism to the affected

people, community and any stakeholder(s) having stake in the project to raise their issues and

grievances as well as concerns. The Grievance Redress Cell (GRC) shall be officially

recognized “non-judicial” body that will seek to resolve non-judicial disputes arising out of

various matters related to the implementation of the ESMP, as well as other aspects of the

project, as may deemed fit to be raised before the GRC.

The fundamental objective of GRM is to resolve any resettlement and environmental related

grievances locally in consultation with the aggrieved party to facilitate smooth

implementation of the EMP. Another important objective is to democratize the development

process at the local level and to establish accountability towards the stakeholders.

6.6.3 Composition of GRC and ULC

A grievance redress mechanism (GRM) is an arrangement for receiving, evaluating, and

facilitating resolution of affected persons concerns, complaints, and grievances about social

and environmental performance at the project level. The GRM is a trusted way to voice and

resolve concerns linked to the project, and an effective way to address affected persons’

concerns. The GRM for the Project is outlined below and consists of three levels with time-

bound schedules for addressing grievances.

The first level and most accessible and immediate venue for the fastest resolution of

grievances is the PMU, chiefly through the PMU Environmental Officer and Project Director,

with assistance from the Environmental Specialist (National) of the design and supervision

consultant (DSC). The contact phone number of the PMU will be posted in public areas in the

project area and construction sites. Grievances will be resolved through continuous

interactions with affected persons and the PMU will answer queries and resolve grievances

regarding various issues including contractor performance, environmental impacts of the

Project (noise, air, traffic, etc.), land acquisition, structures acquisition, livelihood impacts,

entitlements, and assistance. Corrective measures will be undertaken at the field-level itself

within seven (7) days. All grievances will be documented with full information of the person

(name, address, date of complaint, etc.) and the issue.

29 | P a g e

Should the grievance remain unresolved, the PMU's Project Director, will activate the second

level of the GRM by referring the issue (with written documentation) to the local Grievance

Redress Committee (GRC) of the DPDC, who will, based on review of the grievances,

address them in consultation with the PMU Resettlement Officer and Project Director and

affected persons. The local GRC will consist of the following persons:

i. Project Director, DPDC;

ii. Executive Engineer, DPDC;

iii. Affected person or representative of the affected person(s);

iv. Representative of the local District Commissioners office;

v. Representative of the Department of Environment’s (DOE) divisional office, Dhaka.

vi. DSC Environmental Specialist.

A hearing will be called with the GRC, if necessary, where the affected person can present

the concern/issues. The process will promote conflict resolution through mediation. The local

GRC will meet as necessary when there are grievances to be addressed. The local GRC will

suggest corrective measures at the field level and assign clear responsibilities for

implementing its decision within fifteen (15) days.

The functions of the local GRC are as follows:

provide support to affected persons on problems arising from land acquisition

(temporary or permanent); asset acquisition; and eligibility for entitlements,

compensation and assistance;

record grievances of affected persons, categorize and prioritize them and provide

solutions fifteen (15) days; and

report to the aggrieved parties about developments regarding their grievances and

decisions of the GRC.

The PMU Xen will be responsible for processing and placing all papers before the PMU

GRC, recording decisions, issuing minutes of the meetings and taking follow up action to see

that formal orders are issued and the decisions carried out. In the event that a grievance is not

addressed by the PMU or GRC, the affected person can seek legal redress of the grievance in

the appropriate courts, the third level of the GRM. The GRM proposed is depicted in Figure

6.1

30 | P a g e

Figure 6.1Grievance Redress Mechanism

Complain

Second Level of

Grievance

First Level of

Grievance

PMU

Third Level of

Grievance

Local GRC

Higher Authority/

Court of Law

Grievance

Redressed

Grievance

Redressed

Not redressed

Not redressed

7 Days

15 Days

31 | P a g e

Monitoring Checklist

Category Description of

Potential Impacts

Measures/

Indicators

Mugdapara Banasree Dhapa Mondalpara

Com

pli

ed

or

no

t

com

pli

ed

Rem

arks

Co

mp

lied

or

not

com

pli

ed

Rem

arks

Co

mp

lied

or

not

com

pli

ed

Rem

arks

Co

mp

lied

or

not

com

pli

ed

Rem

arks

Noise

Level

Disturbances to

local

communities,

ecosystem and

workers at the

construction site

Use modern low

level producing

machineries

Complied Complied Complied Complied

Providing hearing

protection

equipment for the

workers

Complied Complied Complied Complied

Maintaining noise

level 45 dba at the

reside

Complied Complied Complied Complied

Ensure that all

equipment is in

good condition and

operated in correct

manner

Complied Complied Complied Complied

Air

Quality

Emission of

particulate matter,

SOx and NOx,

Co, SPM due to

construction

activities and

from construction

machinaries

Water spraying

system to control

fugitive dusts

Complied Complied Complied Complied

Construction

material covered

with polythene

Complied Complied Complied Complied

Use good quality

engine/machineries

Complied Complied Complied Complied

Waste

Manage

ment

Solid waste

management

system may

create serious

Negative impacts

like infectious

diseases, land and

water pollution

etc.

Disposal

Quantification

of solid waste

Sanitation

system

Ensure that the

waste

management

such as waste

collection an

disposal are

correctly

implemented

Ensure that the

sites is

regularly

cleaned

Complied

(60%)

Complied

(65%)

Complied

(40%)

Complied

(55%)

32 | P a g e

Livelihoo

d and

living

condition

Livelihood and

living system may

be disturbed due

to construction

activities

Construction of

boundary wall

around the sub-

station sites

Complied Complied Complied Complied

Evaluation for

risks and

impacts on

health and

safety during

construction

activities.

50%

Complied

65%

Complied

40%

Complied

55%

Complied

Availability of

plan for

natural

hazards

40%

Complied

55%

Complied

45%

Complied

50%

Complied

Develop and

implement

emergency

response plan

60%

Complied

65%

Complied

45%

Complied

50%

Complied

Practice of

tool box.

meeting and

reporting

75%

Complied

70%

Complied

60%

Complied

60%

Complied

Providing of

Health service

facilities.

50%

Complied

50%

Complied

50%

Complied

50%

Complied

Working

Condition

Community

dwellers may feel

that they are not

giving substantial

share in project

related job

opportunity

Adequate fire

precautions in

place such as fire

extinguisher,

escape routs etc.

60%

Complied

65%

Complied

55%

Complied

40%

Complied

Documentation

and reporting of

occupational

accidents, discases

and incidents.

60%

Complied

65%

Complied

55%

Complied

40%

Complied

Regular safety

checks and

maintenance

50%

Complied

50%

Complied

55%

Complied

45%

Complied

33 | P a g e

Monitoring Checklist

Category Description of

Potential Impacts

Measures/

Indicators

Dhaka Medical

College

Komolapur

Station

Nandalalpur Lakshi Narayan

Cotton Mill

Com

pli

ed

or

no

t

com

pli

ed

Rem

ark

s

Co

mpli

ed

or

no

t

com

pli

ed

Rem

ark

s

Co

mpli

ed

or

no

t

com

pli

ed

Rem

ark

s

Co

mpli

ed

or

no

t

com

pli

ed

Rem

ark

s

Noise

Level

Disturbances to

local

communities,

ecosystem and

workers at the

construction site

Use modern low

level producing

machineries

Complied Complied Complied Complied

Providing hearing

protection

equipment for the

workers

Complied Complied Complied Complied

Maintaining noise

level 45 dba at the

reside

Complied Complied Complied Complied

Ensure that all

equipment is in

good condition and

operated in correct

manner

Complied Complied Complied Complied

Air

Quality

Emission of

particulate matter,

SOx and NOx,

Co, SPM due to

construction

activities and

from construction

machinaries

Water spraying

system to control

fugitive dusts

Complied Complied Complied Complied

Construction

material covered

with polythene

Complied Complied Complied Complied

Use good quality

engine/machineries

Complied Complied Complied Complied

Waste

Manage

ment

Solid waste

management

system may

create serious

Negative impacts

like infectious

diseases, land and

water pollution

etc.

Disposal

Quantification

of solid waste

Sanitation

system

Ensure that the

waste

management

such as waste

collection an

disposal are

correctly

implemented

Ensure that the

sites is

regularly

cleaned

Complied

(60%)

Complied

(65%)

Complied

(40%)

Complied

(55%)

34 | P a g e

Livelihoo

d and

living

condition

Livelihood and

living system may

be disturbed due

to construction

activities

Construction of

boundary wall

around the sub-

station sites

Complied Complied Complied Complied

Evaluation for

risks and

impacts on

health and

safety during

construction

activities.

50%

Complied

65%

Complied

40%

Complied

55%

Complied

Availability of

plan for

natural

hazards

40%

Complied

55%

Complied

45%

Complied

50%

Complied

Develop and

implement

emergency

response plan

60%

Complied

65%

Complied

45%

Complied

50%

Complied

Practice of

tool box.

meeting and

reporting

75%

Complied

70%

Complied

60%

Complied

60%

Complied

Providing of

Health service

facilities.

50%

Complied

50%

Complied

50%

Complied

50%

Complied

Working

Condition

Community

dwellers may feel

that they are not

giving substantial

share in project

related job

opportunity

Adequate fire

precautions in

place such as fire

extinguisher,

escape routs etc.

60%

Complied

65%

Complied

55%

Complied

40%

Complied

Documentation

and reporting of

occupational

accidents, discases

and incidents.

60%

Complied

65%

Complied

55%

Complied

40%

Complied

Regular safety

checks and

maintenance

50%

Complied

50%

Complied

55%

Complied

45%

Complied

35 | P a g e

Progress of Work

S/L Site Electrical Installation Civil Works

01. Mugdapara

Hospital.

33 kV GIS and 11 kV AIS

Switchgear installation

work is almost completed.

Transformer installation

work is complete.

Installation of the Control

Panel is almost complete.

Super structure complete.

Interior Finishing 95% Complete.

Exterior Finishing 98%

Complete.

02. Banasree 33 kV GIS and 11 kV AIS

Switchgear installation

work is almost completed.

Transformer installation

work is complete.

Power Cable Connection

work is going on

Super structure complete.

Interior Finishing 95% Complete.

Exterior Finishing 98%

Complete.

03. Dhaka

Medical

College

(DMC)

33 kV GIS and 11 kV AIS

Switchgear installation

work is in progress.

Transformer installation

work is complete.

Control Panel installation

work is on going

Super structure complete.

Interior Finishing 80% Complete.

Exterior Finishing 90%

Complete.

04. Kamlapur

railway

Equipment placement

is in progress,

Super structure complete.

Interior Finishing 80%

Complete.

Exterior Finishing 80%

Ongoing.

05. Dhapa Testing work is ongoing

Super structure complete.

Interior Finishing 98%

Complete.

Exterior Finishing

Complete.

36 | P a g e

06. Mondalpara Civil construction &

electrical work is in

progress,

Super structure complete.

Brick Masonry work

ongoing.

07. Nandalalpur

(prime

textile)

Testing work is ongoing

Super structure complete.

Interior Finishing 98%

Complete.

Exterior Finishing

Complete.

08. Laxmi

Narayan

Cotton Mills

Testing work is finished.

Super structure complete.

Interior Finishing 95%

Complete.

Exterior Finishing Complete.

37 | P a g e

Reporting Period: June-2018

1. Name of the Project : Construction and Expansion of Distribution Network of

North & South

Zone under DPDC (1st Revised).

2. Objectives of the Project :

To maintain the power distribution network of DPDC.

To construct and expand new distribution network.

To ensure quality services to the customers of DPDC.

To keep distribution lines operational with a view to

ensure supply of electricity to customers.

Maintenance of 11/0.4 kV lines to improve the

service quality and reliability of electricity supply.

3. Implementation Period : a) Original: 01/07/2013 to 30/06/2016

b) Revised: 01/07/2013 to 30/06/2019

4. Location of the Project : Dhaka & Narayanganj under DPDC area.

5. Source of Funding (with amount) : P.A-TK 26085.02 lakh, GOB TK-17616.11 lakh, DPDC-TK

15942.38 lakh

(In lakh Tk)

Total Taka Project Aid (RPA) Agency’s own Physical

Target

51062.72 10763.9

2 34309.99 5988.811 100%

59643.52 17616.1

1 26085.02 15942.38 100%

37890.02 13800.0

0 22572.91 1517.11 75.14%

6994.40 1200.00 1000.00 4794.40 15.68%

1584.51 0.00 72.67 1511.84 0.38%

6998.26 1200.00 1073.67 4724.59 16.27%

- 1200.00 - - -

38 | P a g e

6. Estimated Cost

a) i. Original :

ii. Revised :

b) Cumulative Progress upto last June :

c) Current year allocation and

Physical Target (2017-18) :

d) Progress of current month :

e) Progress upto the current

month of the year :

f) Fund released upto the current month :

7. Quarterly Financial And Physical progress :

(In Lakh Taka)

1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Financi

al

Physic

al

Financi

al

Physic

al

Financi

al

Physic

al

Financi

al

Physic

al

PA 752.63

3.46%

192.78

3.76%

0.00

4.87%

128.26

4.18%

GO

B

300.00 300.00 486.41 113.59

Tota

l

1052.6

3

492.78 486.41 241.85

8. Target and Achievement of the main Components of the Project:

Sl.

No

.

Work components as

per DPP

(With quantity)

Estimated

Cost as

per DPP

Achievement up to last

June-2017

Target of the current year

(2017-18)

Progress up to the month

of June-2018

Financial

Physical

(% of the

componen

t)

Financial

Physical

(% of the

component)

Financial

Physical

(% of the

component)

1

Materials &

Equipments 29360.

18

22572.91 86.25 3000 11.75 2985.65 11.75

2 Installation Cost 8298.2

6

856.74 46.00 2200 32 2175.69 35

3

CD,VAT and Other

Charges 17616.

11

13800.00 81.62 1200 15 1200 15

4 Supply and services

331.25 166.00 48.00 16 5 15.85 7

5 Transport & Vehicle

232.00 118.11 62.00 3.5 1.5 3.31 1.5

6

Salary of officers and

staffs 563.57 235.31 42.00 170 30 206.76 36

7 Repair, Maintenance

37.00 4.68 37.00 3.4 2 3.39 2

8

Office Furniture and

Equipment 29.00 10.27 27.00 1.5 5 1.42 10

9 Income Tax 1144.4

0

95.54 11.50 400 35 406.19 35

39 | P a g e

10

Interest During

Construction 1273.3

6

30.46 3.00 0 0 0 0

11 Contingency

758.38 0.00 0.00 0 0 0 0

12 Total =

59643.52 37890.02 75.14 6994.40 15.68 6998.26 16.27

9. Reasons for the delay of

Project implementation :

Delay in tendering process:

This turn-key project work mainly incorporates tender invitation, material purchase and installation of

the materials according to the survey performed. According to original DPP the project implementation

period was from July-2013 to June-2016. But the project work actually started after the approval from

ECNEC on 19.09.2013. After that, the tender was invited on 27.04.2014 and due to lack of eligible

bidder deadline of the tender submission had been extended twice. Finally the project contract was

signed on 11.06.2015 after the approval of the project financial evaluation report and became effective

on 20 Sep 2015.

10. Existing problems of Implementation of the project:

Because of not receiving road cutting approval from Dhaka South City Corporation (DSCC), 68.587

km 11kV U/G cable installation work under DSCC area cannot be started.

During construction work I observed that no any environmental negative advance impact was occurred.

During construction work there was no any Environmental negative adverse impact not

occurred.

Reference:

(Abul Fazal Md. Badrul Alam)

Project Director

Construction and Expansion of Distribution

Network of North and South Zone under DPDC.

Mobile No: 01713255012

E-mail: [email protected]

40 | P a g e

41 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

Analysis Sheet of Noise (Sound) Monitoring

Banasree Substation Rampura Dhaka

SL.

NO.

SAMPLING

LOCATION

DATE CODE NO. TIME NOISE LEVEL

(dBa)

REMARKS

1 Banasree Substation 02-04-2018 31 5:00pm 65 All the results

are in limit

2. Banasree Substation 02-04-2018 32 5:30pm 45 All the results

are in limit

3 Banasree Substation 02-04-2018 33 6:00pm 53 All the results

are in limit

Bangladesh Standard 75(dBa)

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

42 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

Analysis Sheet of Noise (Sound) Monitoring

Mughdapara Hospital Substation, Dhaka

SL.

NO.

SAMPLING

LOCATION

DATE CODE NO. TIME NOISE LEVEL

(dBa)

REMARKS

1 Mughdapara Substation 03-04-2018 31 2:30pm 52 All the results

are in limit

2. Mughdapara Substation 03-04-2018 32 3:00pm 48 All the results

are in limit

3 Mughdapara Substation 03-04-2018 33 4:00pm 56 All the results

are in limit

Bangladesh Standard 75(dBa)

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

43 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

Analysis Sheet of Noise (Sound) Monitoring

Dhapa Substation FatullaNaryangonj

SL.

NO.

SAMPLING

LOCATION

DATE CODE NO. TIME NOISE LEVEL

(dBa)

REMARKS

1 Dhapa Substation 05-04-2018 31 11:00am 57 All the results

are in limit

2. Dhapa Substation 05-04-2018 32 11:30am 55 All the results

are in limit

3 Dhapa Substation 05-04-2018 33 12:00pm 62 All the results

are in limit

Bangladesh Standard 75(dBa)

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

44 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

Analysis Sheet of Noise (Sound) Monitoring

Nandalalpur Substation, Prime textile mill, Naryangonj

SL.

NO.

SAMPLING

LOCATION

DATE CODE NO. TIME NOISE LEVEL

(dBa)

REMARKS

1 Nandalalpur Substation 16-04-2018 31 11:30am 57 All the results

are in limit

2. Nandalalpur Substation 16-04-2018 32 12:00pm 53 All the results

are in limit

3 Nandalalpur Substation 16-04-2018 33 12:30pm 62 All the results

are in limit

Bangladesh Standard 75(dBa)

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

45 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

Analysis Sheet of Noise (Sound) Monitoring

Laxmi Narayan Cotton Mills Substation Naryangonj

SL.

NO.

SAMPLING

LOCATION

DATE CODE NO. TIME NOISE LEVEL

(dBa)

REMARKS

1 Cotton Mills Substation 16-04-2018 31 3:00pm 68 All the results

are in limit

2. Cotton Mills Substation 16-04-2018 32 3:30pm 52 All the results

are in limit

3 Cotton Mills Substation 16-04-2018 33 4:00pm 48 All the results

are in limit

Bangladesh Standard 75(dBa)

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

46 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

Analysis Sheet of Noise (Sound) Monitoring

Dhaka Medical College Substation Dhaka

SL.

NO.

SAMPLING

LOCATION

DATE CODE NO. TIME NOISE LEVEL

(dBa)

REMARKS

1 DMC Substation 18-04-2018 31 11:00am 56 All the results

are in limit

2. DMC Substation 18-04-2018 32 11:30am 48 All the results

are in limit

3 DMC Substation 18-04-2018 33 11:45am 62 All the results

are in limit

Bangladesh Standard 75(dBa)

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

47 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

Analysis Sheet of Noise (Sound) Monitoring

Kamlapur Substation Dhaka

SL.

NO.

SAMPLING

LOCATION

DATE CODE NO. TIME NOISE LEVEL

(dBa)

REMARKS

1 Kamlapur Substation 18-04-2018 31 1:30pm 65 All the results

are in limit

2. Kamlapur Substation 18-04-2018 32 2:00pm 62 All the results

are in limit

3 Kamlapur Substation 18-04-2018 33 2:15pm 58 All the results

are in limit

Bangladesh Standard 75(dBa)

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

48 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

LABORATORY TEST RESULTS:

Analysis Sheet of Water Quality Monitoring

Mughdapara Hospital Substation, Dhaka

Sl.

No.

Date: Surface Water

(Industrial)

Quality

parameters

Bangladesh

Standard

Concentration

present

Analysis Procedure Remarks

1. 07-05-2018 Total Suspended

Solids (TSS)

150mg/L 109mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

2. 07-05-2018 Total Suspended

Solids (TSS)

150mg/L 116mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

3. 07-05-2018 Total Suspended

Solids (TSS)

150mg/L 127mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

49 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

LABORATORY TEST RESULTS:

Analysis Sheet of Water Quality Monitoring

Banasree Substation, Rampura Dhaka

Sl.

No.

Date: Surface Water

(Industrial)

Quality

parameters

Bangladesh

Standard

Concentration

present

Analysis Procedure Remarks

1. 07-05-2018 Total Suspended

Solids (TSS)

150mg/L 116mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

2. 07-05-2018 Total Suspended

Solids (TSS)

150mg/L 119mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

3. 07-05-2018 Total Suspended

Solids (TSS)

150mg/L 126mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

50 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

LABORATORY TEST RESULTS:

Analysis Sheet of Water Quality Monitoring

Dhapa Substation Fatulla, Naryangonj

Sl.

No.

Date: Surface Water

(Industrial)

Quality

parameters

Bangladesh

Standard

Concentration

present

Analysis Procedure Remarks

1. 08-05-2018 Total Suspended

Solids (TSS)

150mg/L 120mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

2. 08-05-2018 Total Suspended

Solids (TSS)

150mg/L 113mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

3. 08-05-2018 Total Suspended

Solids (TSS)

150mg/L 130mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

51 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

LABORATORY TEST RESULTS:

Analysis Sheet of Water Quality Monitoring

Nandalalpur Substation, Prime Textile Mill, Naryangonj

Sl.

No.

Date: Surface Water

(Industrial)

Quality

parameters

Bangladesh

Standard

Concentration

present

Analysis Procedure Remarks

1. 08-05-2018 Total Suspended

Solids (TSS)

150mg/L 135mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

2. 08-05-2018 Total Suspended

Solids (TSS)

150mg/L 117mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

3. 08-05-2018 Total Suspended

Solids (TSS)

150mg/L 126mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

52 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

LABORATORY TEST RESULTS:

Analysis Sheet of Water Quality Monitoring

Laxmi Narayan Cotton Mills Substaion, Naryangonj

Sl.

No.

Date: Surface Water

(Industrial)

Quality

parameters

Bangladesh

Standard

Concentration

present

Analysis Procedure Remarks

1. 08-05-2018 Total Suspended

Solids (TSS)

150mg/L 127mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

2. 08-05-2018 Total Suspended

Solids (TSS)

150mg/L 134mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

3. 08-05-2018 Total Suspended

Solids (TSS)

150mg/L 136mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

53 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

LABORATORY TEST RESULTS:

Analysis Sheet of Water Quality Monitoring

Dhaka Medical College Substation, Dhaka

Sl.

No.

Date: Surface Water

(Industrial)

Quality

parameters

Bangladesh

Standard

Concentration

present

Analysis Procedure Remarks

1. 10-05-2018 Total Suspended

Solids (TSS)

150mg/L 112mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

2. 10-05-2018 Total Suspended

Solids (TSS)

150mg/L 107mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

3. 10-05-2018 Total Suspended

Solids (TSS)

150mg/L 115mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

54 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

LABORATORY TEST RESULTS:

Analysis Sheet of Water Quality Monitoring

Kamlapur Substation, Dhaka

Sl.

No.

Date: Surface Water

(Industrial)

Quality

parameters

Bangladesh

Standard

Concentration

present

Analysis Procedure Remarks

1. 10-05-2018 Total Suspended

Solids (TSS)

150mg/L 114mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

2. 10-05-2018 Total Suspended

Solids (TSS)

150mg/L 119mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

3. 10-05-2018 Total Suspended

Solids (TSS)

150mg/L 110mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

55 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

LABORATORY TEST RESULTS:

Analysis Sheet of Water Quality Monitoring

Mondalpara Sub-station, NarayanganjSadar, Narayanganj

Sl.

No.

Date: Surface Water

(Industrial)

Quality

parameters

Bangladesh

Standard

Concentration

present

Analysis Procedure Remarks

1. 21-05-2018 Total Suspended

Solids (TSS)

150mg/L 108mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

2. 21-05-2018 Total Suspended

Solids (TSS)

150mg/L 123mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

3. 21-05-2018 Total Suspended

Solids (TSS)

150mg/L 114mg/L USEPA 160.2, SM

2540 B-D

Result is Within

Limit

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

56 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

Analysis Sheet of Air Quality Monitoring

Mugdapara Hospital Substation, Dhaka

SL.

NO

SAMPLING LOCATION DATE CODE

NO.

SPM

3/mg

SOx

3/mg

NOx

3/mg

REMARKS

1. Substation 21-05-2018 425 137.15 22.25 29.10 Result is with in limit

Bangladesh Standard - - 200 80 100

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

57 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

Analysis Sheet of Air Quality Monitoring

Banasree Substation, Dhaka

SL.

NO

SAMPLING LOCATION DATE CODE

NO.

SPM

3/mg

SOx

3/mg

NOx

3/mg

REMARKS

1. Substation 21-05-2018 425 137.20 20.10 24.55 Result is with in limit

Bangladesh Standard - - 200 80 100

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

58 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

Analysis Sheet of Air Quality Monitoring

Dhapa Substation FatullahNarayangonj

SL.

NO

SAMPLING LOCATION DATE CODE

NO.

SPM

3/mg

SOx

3/mg

NOx

3/mg

REMARKS

2. Substation 22-05-2018 425 134.10 19.20 23.36 Result is with in limit

Bangladesh Standard - - 200 80 100

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

59 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

Analysis Sheet of Air Quality Monitoring

Nandalalpur Substation Prime Cotton Mill, Naryangonj

SL.

NO

SAMPLING LOCATION DATE CODE

NO.

SPM

3/mg

SOx

3/mg

NOx

3/mg

REMARKS

1. Substation 22-05-2018 426 135.20 20.25 26.30 Result is with in limit

Bangladesh Standard - - 200 80 100

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

60 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

Analysis Sheet of Air Quality Monitoring

Laxmi Narayan Cotton Mills Substation, Naryangonj

SL.

NO

SAMPLING LOCATION DATE CODE

NO.

SPM

3/mg

SOx

3/mg

NOx

3/mg

REMARKS

1. Substation 21-05-2018 425 139.13 20.20 20.33 Result is with in limit

Bangladesh Standard - - 200 80 100

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

61 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

Analysis Sheet of Air Quality Monitoring

Dhaka Medical College Substation, Dhaka

SL.

NO

SAMPLING LOCATION DATE CODE

NO.

SPM

3/mg

SOx

3/mg

NOx

3/mg

REMARKS

1. Substation 23-05-2018 425 125.20 20.20 25.33 Result is with in limit

Bangladesh Standard - - 200 80 100

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

62 | P a g e

ENVIRONMENTAL DEVELOPMENT AND SURVEY INSPECTION COMPANY

9/C, Motijheel, ShanewazBhaban,

2nd Floor, Room No. 302

Dhaka-1000

Analysis Sheet of Air Quality Monitoring

Banasree Substation, Dhaka

SL.

NO

SAMPLING LOCATION DATE CODE

NO.

SPM

3/mg

SOx

3/mg

NOx

3/mg

REMARKS

1. Substation 23-05-2018 425 138.11 20.36 24.30 Result is with in limit

Bangladesh Standard - - 200 80 100

__________ __________________ _________________________

LAB.ASST. SENIOR CHEMIST ENVIRONMENTAL EXPERT

63 | P a g e

07. CONCLUTIONS AND RECOMMENDATIONS.

The environmental expert has carried out the monitoring activities comprising the

monitoring of implementation of environmental management plan (EMP) and

environmental compliance with the environmental parameters. The sub-stations

Building construction work and construction of Expansion of Distribution Network of

North South Zone under DPDC are going on rabidly. Some related works were

responsible for a number of environmental issues such a spreading of dust, improper

sanitation setup and inadequate medical facilities etc. There is necessity to follow the

measures suggested in recent monitoring period, the environmental due diligence

covers; the Environmental management system and action plan, occupational Health

and safety, workers well being Biodiversity and sustainable Management of Natural

Resources. The Environmental and Social Monitoring Expert suggested

recommendation and guidelines which need to be strictly and seriously followed by

the workers and the contractors of all the sites.

To make the process more smooth and efficient, the following recommendations are

proposed by Environmental Expert to be followed with immediate effect:

The HR policy was found developed as the management of the site specific EHS

programme have been established: Occupation Health and safety policies.

Emergency preparedness and response plan: Fire prevention, protection and control

plan.

With respect to physical environment and social Monitoring expert considered that

Air Quality was quite good. This time the concentration of all the ambient air quality

monitoring parameters (SO4, NO7, CO, SPM) were found to be within the standard

limit set by ECR’97.

Though construction materials like sand and soil were not covered with polythene at

any site. This might cause dust pollution in dry condition. Hence is required to cover

the construction materials properly.

The observed noise level attains at the maximum but not crossed the limit.

It is obligatory to provide hearing protection equipment to the employees who are

exposed to loud noise.

There was no dustbin or specific disposal site in any of the sites. Hence particular

place for waste disposal should be earmarked for maintaining ambient environmental

neatness.

The Level of safety for workers must be enhanced with comprehensive enforcement

on PPE usage and regular health and safety supervision should be carried out.

64 | P a g e

There were no dustbin or specific waste disposal site at any of the construction site.

Heretic mandatory to define a particular place for waste disposal for maintaining an

effective waste management system.

Workers working condition such as accommodation, Drinking water, sanitation and

medical facilities has remained same as it was in earlier phase of monitoring.

The sanitation system for labors must be improved upto a healthy and desirable level.

The labor sheds must be improved upto a comfortable security force.

Recruitment of more local labor in the construction site would certainly improve the

economic condition of local people: Rationalized work permit system and enhanced

medical support at the site should be maintained.

Weekly Tool Box meetings on health and safety as well as the other governing

environmental and social issues should be initiated.