powergem power grid engineering & markets 1 new york congestion costs experience and plans...
TRANSCRIPT
PowerGEMPower Grid Engineering & Markets
1
New York Congestion CostsExperience and Plans
FERC OfficesApril 14, 2005
James Mitsche
PowerGEMPower Grid Engineering & Markets
2
Meeting Topics• Congestion
– It’s Nature– Analysis Tools– NYISO Activities
• NYISO Congestion Analysis– Congestion Measures– Congestion Analysis Approach– Historic Congestion Results– Sensitivity Studies
• Congestion Planning• PowerGEM Observations
PowerGEMPower Grid Engineering & Markets
3
Remember
• Numbers– Average 4 Simultaneous Constraints Every Hour in NY– NY Congestion Impact: 2003 = $85 Million; 2004 = $72 Million
• Observations from a Planning Perspective– Congestion Occurs at All Load Levels– Most Congestion Impact is Due To Chronic Events, Not Price Spikes– Bottleneck Relief Is Not as Cost Effective as Generally Believed– Analysis of Large Persistent Transmission Constraints is Reasonable
PowerGEMPower Grid Engineering & Markets
4
Congestion
• The Cost of Committing or Running Generating Units Out of Merit Order
• Caused By Combination of– Insufficient Transmission, Requiring Local More
Expensive Supply to Maintain Load/Generation Balance– Generator Characteristics (e.g. min run time, ramp rate,
unit MW minimum) • Unit Commitment Process Commits/Decommits Units to
Minimize BPC, but Increases Congestion
PowerGEMPower Grid Engineering & Markets
5
Nature of Congestion Cost
New York 2004
Congestion Impact $ / MW Range % Hours
% Congestion Impact
= $0.00 0.0% 0.0% $0.00 to $1.00 84.2% 79.4% $1.00 to $2.00 9.7% 14.2% $2.00 to $3.00 2.2% 2.2% $3.00 to $4.00 1.4% 1.1% $4.00 to $5.00 1.0% 0.9% $5.00 to $6.00 0.7% 1.1% $6.00 to $7.00 0.4% 0.6% $7.00 to $8.00 0.2% 0.1%
> $8.00 0.1% 0.4%
Congestion is:
Persistent
Usually Not Dramatic
At All Load Levels
New York 2004
Load Level Range % Hours% Congestion
Impact12,000 to 13,000 6.9% 1.4%13,000 to 14,000 9.1% 2.2%14,000 to 15,000 9.4% 3.3%15,000 to 16,000 10.1% 5.1%16,000 to 17,000 8.8% 5.0%17,000 to 18,000 11.8% 8.8%18,000 to 19,000 12.6% 11.7%19,000 to 20,000 11.1% 15.4%20,000 to 21,000 7.8% 14.9%21,000 to 22,000 4.8% 10.1%22,000 to 23,000 3.8% 10.0%23,000 to 24,000 2.2% 6.6%24,000 to 25,000 1.2% 3.4%25,000 to 26,000 0.3% 1.4%26,000 to 27,000 0.1% 0.5%27,000 to 28,000 0.0% 0.2%28,000 to 29,000 0.0% 0.0%
Average $0.59 / MW
New York 2004 Statewide $ Congestion Impact / MW at Hourly Load Level
$0
$1
$2
$3
$4
$5
$6
$7
$8
$9
$10
12000 17000 22000 27000
NY System Load
NY
$ B
PC
Ch
ang
e C
on
ges
tio
n
Imp
act
/ MW
(In
effi
cien
cy M
easu
re)
PowerGEMPower Grid Engineering & Markets
6
How Often are There Simultaneous Transmission Constraints?
New York 2004 Average Simultaneous Constraints by Day-of-the-Week
0.0
1.0
2.0
3.0
4.0
5.0
Sun Mon Tue Wed Thu Fri Sat
Ave
rag
e #
of
Sim
ult
aneo
us
Co
nst
rain
ts
New York 2004 Average Simultaneous Constraints by Hour-of-the-Day
0.0
1.0
2.0
3.0
4.0
5.0
6.0
00:
00
01:
00
02:
00
03:
00
04:
00
05:
00
06:
00
07:
00
08:
00
09:
00
10:
00
11:
00
12:
00
13:
00
14:
00
15:
00
16:
00
17:
00
18:
00
19:
00
20:
00
21:
00
22:
00
23:
00Ave
rag
e #
of
Sim
ult
aneo
us
Co
nst
rain
trs
New York 2004
Number of Simultaneous Constraints
% of Hours% of Annual Congestion Impact
0 5.8% 0.7%1 9.5% 2.2%2 10.6% 3.8%3 11.2% 9.7%4 17.4% 22.3%5 18.2% 25.8%6 10.9% 12.0%7 6.6% 7.8%8 4.4% 5.9%9 3.0% 5.1%10 1.4% 2.4%11 0.8% 1.6%12 0.3% 0.6%13 0.0% 0.1%14 0.0% 0.0%
Answer:
Almost Always
Average for NY 4.25, Max 13 in 2004
PowerGEMPower Grid Engineering & Markets
7
Congestion Is an Everyday ThingBid Production Cost Impact
New York 2004 Congestion Impact by Day-of-the-Week
Sun, 7%
Mon, 15%
Tue, 14%
Wed, 16%Thu, 20%
Fri, 18%
Sat, 9%
PowerGEMPower Grid Engineering & Markets
8
Congestion Is an Every Hour ThingBid Production Cost Impact
New York 2004 Congestion Impact by Hour-of-the-Day
0%1%2%3%4%5%6%7%8%
00:
00
01:
00
02:
00
03:
00
04:
00
05:
00
06:
00
07:
00
08:
00
09:
00
10:
00
11:
00
12:
00
13:
00
14:
00
15:
00
16:
00
17:
00
18:
00
19:
00
20:
00
21:
00
22:
00
23:
00
% o
f C
on
ge
sti
on
Imp
ac
t
PowerGEMPower Grid Engineering & Markets
9
What Causes Congestion At Shoulder Load ?
• Unit Commitment Decisions and Restrictions– Unit Minimums
– Ramp Rates
– Minimum Run Times
• Generation Outages• Transmission Outages• Bidding Patterns
PowerGEMPower Grid Engineering & Markets
10
Congestion Terms
• Bid Production Cost– The Total Cost to Serve Demand at the Bid Price (Not Clearing Price)
• Shadow Price – The Incremental Change in Bid Production Cost for an Incremental
Change in Constrained Facility Rating• LMP = Shadow Price x Distribution Factor• LMP Congestion Component
– Difference Between Local and Reference Point LMP (excepting Losses)
• Distribution Factor – Change in Constraint Flow for a Change at a Location, Relative to a
Reference Point• Reference Point
– Assumed Uncongested Location
PowerGEMPower Grid Engineering & Markets
11
Congestion Calculation Tools
• Shadow Prices Result From Optimization Simulations– Security Constrained Unit Commitment– Security Constrained Economic Dispatch
• These Tools Minimize Total Bid Production Cost Subject to Energy Balance, Flow Limits, and Other Constraints
• Payments are Made at the LMP Clearing Price, Not the Bid Price
PowerGEMPower Grid Engineering & Markets
12
NYISO Congestion Analysis
• NYISO has reported historic congestion costs since 2001 • Included in NYISO Market Advisor's annual "State of the
Market" report • Electric System Planning Working Group ("ESPWG") was
formed in 2003 to assist in the development of a Comprehensive Planning Process for the NYISO
• ESPWG efforts have led to a detailed methodology for the analysis of historic congestion costs
• This process is now included in the NYISO Tariff (Attachment Y)
PowerGEMPower Grid Engineering & Markets
13
ESPWG Objectives
To Better Understand Congestion Costs & Causes – Define congestion – Analyze causes of congestion – Provide better information for the market
– Consider implications for NYISO Comprehensive Planning Process
Characterize Historic Congestion – Measures & Metrics
– Magnitude
– Location• Zones• Constraints
PowerGEMPower Grid Engineering & Markets
14
Congestion Measures
• Market Impact Measures– Change in BPC– Incremental BPC Impact (Patton Method)
• Payment Impact Measures– Congestion Payments– Demand and Supply Payments
PowerGEMPower Grid Engineering & Markets
15
New York Congestion Impact Metrics Summary Metric 2003 Result
$ Millions Description
Bid Production Cost $85 Primary Metric Actual Constrained – Unconstrained Measures Economic Inefficiency Societal Impact
Congestion Payments $821 Sum of (Congestion LMP Change) *
(Demand Affected) w/o Transmission Constraints
Ignores Energy Change w/o Constraints Accounting Impact Measure Power Alert Number
TCC Hedging $528 TCC MW owned times the LMP difference between the TCC contract point of withdrawal (POW) minus point of injection (POI)
Unhedged Congestion Payments
$293 Congestion Payments – TCC Hedging Accounting Impact Measure
Demand Payments $392 Sum of (Total LMP Change) * (Demand
Affected) w/o Transmission Constraints Includes Energy Response w/o
Constraints Bills Impact Measure
TCC Hedging $528 TCC MW owned times the LMP difference between the TCC contract point of withdrawal (POW) minus point of injection (POI)
Unhedged Demand Payments -$136 Actual Bills Impact After Hedging Supply Payments -$136 Sum of (Total LMP Change) * (Supply
Affected) w/o Transmission Constraints Includes Energy Response w/o
Constraints
Amount Paid to Suppliers Due to Congestion
Patton Figure $688 Incremental Bid Production Cost Change
PowerGEMPower Grid Engineering & Markets
16
David Patton’s 2003 NYISO Markets Report
• Defines Congestion as:– The difference between total congestion payments from loads and
payments to generators and imports; plus– Congestion costs collected from physical bilaterals
• Utilizes a “marginal cost” definition: – “Shadow price” x Power flowing across congested interface
• Includes both Day-Ahead and Real-Time congestion components• Relative, Not Absolute Measure
• Total for 2003: $688 Million
PowerGEMPower Grid Engineering & Markets
17
BPC Congestion Impact and Patton Number
• Both Numbers are Extreme Cases– BPC Impact Removes All Transmission Constraints (Big Change)– BPC Represents the Maximum Savings Possible– Patton Number is for a Small Incremental Change Only
• Better Approach– BPC Change for Discrete Grid Improvements or Other “What If”
Tests– It is Believed That Both Methods Should Converge When Looking
at Discrete Situations
PowerGEMPower Grid Engineering & Markets
18
Comparison of 2004 Totals By Different Metrics,
Metric 2004 Total
$ Millions
Positive Means Negative Means Interpretation of Actual 2004 Result
BPC Change $ 71.3 Market Inefficiency Not Possible Maximum that Can be Saved (Not Shifted) from Eliminating Congestion
Demand Payments After TCC Hedging
- $ 181.2 Congestion Increased Energy Bills
Congestion Decreased Energy Bills
NY State as a Whole Benefited from Congestion
(Viewed Differently at Zonal Level)
Supply Payments After TCC Hedging
- $ 181.2 Suppliers Benefited from Congestion
Suppliers Were Paid Less Because of Congestion
NY Generators as a Whole Were Hurt by Congestion
(Viewed Differently at Zonal Level)
Unhedged Congestion Payments
$ 316.0 Congestion Increased this Component of Total Energy Payments
Congestion Decreased this Component of Total Energy Payments
Congestion Was about 3% of Total NY State Energy Payments
PowerGEMPower Grid Engineering & Markets
19
Congestion Reporting Posting(www.NYISO.com)
Total and Zonal Congestion Metrics
Congestion Payments By ConstraintAnnual Totals Monthly Totals Daily Totals
A Monitored Element Totals x xB Monitored Element /Contingency Pair x
Annual Totals Monthly Totals Daily Totals4 Metrics Mitigated Bids NYCA x x x4 Metrics Mitigated Bids Zonal x x xConstrained Quantities xUnconstrained Quantities x
Annual Totals Monthly Totals Daily TotalsMonitored Element Totals x xMonitored Element /Contingency Pair x
PowerGEMPower Grid Engineering & Markets
20
Metrics Calculated Using PROBE Software
• PROBE (PoRtfolio Ownership Bid Evaluation) Software– A “Study Mode” for the NYISO SCUC– Day Ahead Market Only– Driven by Same Data as the SCUC
• Bids (real and virtual, load and generation), Hourly Network Models, Business Rules, TCC
– Market Optimization• All Markets (Generation, Price Capped Load, Virtual Load & Generation, Imports, Exports,
Wheels, Ancillary Service)• Full Security Constrained Unit Commitment and Dispatch• Includes Mitigation • Produces Same Hourly Results as SCUC (LMP’s, dispatch, flows, etc.) + Insights
– 2 Modes• SCUC Viewer• Simulation
• Used Since January 2002• NYISO Market Monitoring & Performance Unit Uses Routinely• Used for Daily PJM Market Advice and Economic Planning
PowerGEMPower Grid Engineering & Markets
21
Simulation Tool
PROBE
Hourly Network Models (24)
Generator Bids
Virtual Load & Gen Bids
Fixed Load & Price Capped Load Bids
PAR Settings
Imports & Export Bids
Unit Characteristics (Status, Min Up & Down Time, Ramp Rates)
Monitored Branches, Interfaces Limits,
Contingencies
Zonal Factors
TCC Contracts
Daily Security Constrained Unit Commitment
Daily Security Constrained Dispatch
Energy & Congestion $ for All Bid Types
•Generators
•Fixed Load
•Price Capped Load
•Virtuals
•Imports & Exports
Shadow Prices & LMP’s
Branch Flows
Marginal Bids
Congestion Impact on Bidders
Excel Spreadsheets
NYISO Supplied Daily
Relatively Static or Derived Data
User Controls
•Ramp Rate Handling
•Bids to Optimize
•PAR Handling
PowerGEMPower Grid Engineering & Markets
22
Important Assumptions
• The Congestion Impact Calculation is the Difference of the “As Given” Network and a Totally Unconstrained System. Removing All Constraints is Not Truly Practical, but Quantifies the Maximum Possible Savings
• Bids are Assumed to Be Mitigated and Unchanged for All Calculations
• Bilateral Market Hedging is Not Included
• TCC Hedging Attributed Totally to Load. No Inclusion of TCC Auction Cost
• Virtual Load, Virtual Generation, and Price Capped Load Assumed to be Fixed MWHr in the Unconstrained Case ($ Payments Change)
• No Adjustment for “Unusual Events”
• PAR’s Fixed at SCUC Supplied Setting
PowerGEMPower Grid Engineering & Markets
23
SCUC – PROBE Results Comparison
Conclusion: Overall Revenue and Bid Production Cost is Being Reproduced by PROBE With Acceptable Precision
Revenue SCUC - PROBE Difference
15-Jul 22-Sep 3-Dec 12-Dec 15-Dec 18-Dec 19-DecNew York Generation -1.1% -0.7% 0.5% 0.1% -1.6% 0.2% 0.4%Price Capped Load -1.7% -2.9% 0.6% 0.6% 0.4% 2.8% 1.8%Imports -0.6% 11.8% -1.4% -0.8% -3.9% -0.1% -2.4%Exports -0.5% -0.1% 0.9% 0.6% -2.5% 0.7% 2.9%
Mitigated Bid Production Cost SCUC - PROBE Difference
Generation & Imports -1.5% -0.3% -1.7% -0.5% 2.6% -1.2% -1.0%
Grayed Areas are Differences >2%
Note: Sept. 22 Imports were very small (5% of Gen+import Revenue); a small SCUC/PROBE difference results in a larger than normal % difference. All dates in 2003
PowerGEMPower Grid Engineering & Markets
24
2003 & 2004 Summary
New York Congestion Impact(Bid Production Cost Impact)
$71.7
$84.6
$0
$10
$20
$30
$40
$50
$60
$70
$80
$90
2003 2004
Co
ng
esti
on
Imp
act
in $
Mill
ion
s
PowerGEMPower Grid Engineering & Markets
25
2003 & 2004 SummaryComparative Cumulative Congestion -- BPC impact
$0
$30
$60
$90
1/1 4/1 7/1 10/1
$ M
illio
ns
2003 2004
Not all Constraints Shown. 95% of 2003, 90% 0f 2004
2003 vs 2004 Unhedged Congestion Payments by Constraint
0% 5% 10% 15% 20% 25% 30%
DUNWODIE 345SHORE_ RD1 345
CENTRAL EAST -VC
RAINEY __ 138VERNON __1 138
LEEDS ___ 345N. SCTLND1 345
RAINEY __ 345 DUNWODIE 1 345 or2
UPNY CONED
E179 THST 138HELLGT_ E1 138
W49TH_ ST 345SPRNBRK _ 1 345 or2
VALLYSTR 138 EGRDNCTY1 138
PLSNTVLY 345LEEDS ___1 345
% of Annual Total Positive Congestion Impact
2004
2003
PowerGEMPower Grid Engineering & Markets
26
2003 Totals
2003 Total Congestion Impact Mitigated Bids ($ Millions)
Zone BPC mitig Unhedged Cong Gener pay Unhedged load payCAPITL -$6.10 $5.66 -$20.64 -$20.64CENTRL -$39.70 -$2.88 -$124.88 -$124.88DUNWOD $0.00 $6.39 -$0.42 -$0.42GENESE -$2.51 $1.24 -$18.02 -$18.02HQ -$43.97 $2.17 -$51.17 -$51.17HUDVL -$25.57 -$13.32 -$59.62 -$59.62LONGIL $95.70 $135.98 $177.42 $177.42MHKVL -$7.82 -$2.30 -$16.97 -$16.97MILLWD -$0.14 -$10.22 -$45.26 -$45.26N.Y.C. $230.19 $163.48 $319.96 $319.96NORTH $0.39 $2.60 -$29.93 -$29.93NPX -$5.52 $1.85 -$10.19 -$10.19OH -$13.21 $0.17 -$37.23 -$37.23PJM -$79.46 $6.75 -$123.67 -$123.67WEST -$17.74 -$4.13 -$95.52 -$95.52NYCA Total $84.55 $293.43 -$136.12 -$136.12
+ Number Means Congestion Increases Supplier Production Cost
+ Number Means Congestion Increases Load Cost
- Number Means Congestion Decreases Load Payments
Negative Number Means Gen Payments Congestion Hurt Gens
PowerGEMPower Grid Engineering & Markets
27
2003 TotalsUnhedged Congestion Impact by Constraint
(Price Increasing Impact only) Monitored Facility % of Total Cum % of TotalDUNWODIE 345 SHORE_RD 345 1 26.5% 26.5%CENTRAL EAST - VC 19.5% 46.0%RAINEY__ 138 VERNON__ 138 1 16.1% 62.1%LEEDS___ 345 N.SCTLND 345 1 11.2% 73.3%RAINEY__ 345 DUNWODIE 345 1 8.0% 81.3%RAINEY__ 345 DUNWODIE 345 2 3.7% 85.0%UPNY CONED 3.6% 88.6%E179THST 138 HELLGT_E 138 1 3.1% 91.7%W49TH_ST 345 SPRNBRK_ 345 1 1.7% 93.4%VALLYSTR 138 EGRDNCTY 138 1 1.4% 94.8%W49TH_ST 345 SPRNBRK_ 345 2 1.4% 96.1%PLSNTVLY 345 LEEDS___ 345 1 0.8% 96.9%JAMAICA_ 138 VALLYSTR 138 1 0.5% 97.5%FRESHKLS 138 WILLWBRK 138 1 0.5% 98.0%VERNON__ 138 KENTAVE_ 138 1 0.3% 98.3%ROSLYN__ 138 EGRDNCTY 138 1 0.2% 98.5%HELLGATE 138 E179THST 138 1 0.2% 98.7%BUCHAN_N 345 EASTVIEW 345 1 0.2% 98.9%NEWBRDGE 138 EGRDNCTY 138 1 0.2% 99.0%
PowerGEMPower Grid Engineering & Markets
28
2004 Totals
2004 Total Congestion Impact Mitigated Bids ($ Millions)
Zone BPC mitig Unhedged Cong Gener pay Unhedged load payCAPITL -$23.12 $3.37 -$46.87 -$46.87CENTRL -$50.75 -$3.11 -$132.52 -$132.52DUNWOD $0.00 $9.91 -$1.08 -$1.08GENESE -$1.93 $0.02 -$18.62 -$18.62HQ -$30.40 -$0.10 -$31.85 -$31.85HUDVL -$19.58 -$5.12 -$71.47 -$71.47LONGIL $118.69 $137.81 $168.82 $168.82MHKVL -$4.75 -$0.95 -$13.16 -$13.16MILLWD -$0.03 -$10.68 -$40.54 -$40.54N.Y.C. $187.86 $187.09 $250.48 $250.48NORTH $0.06 $0.04 -$29.02 -$29.02NPX -$13.28 $1.08 -$14.05 -$14.05OH -$11.48 -$0.11 -$25.95 -$25.95PJM -$66.01 -$0.51 -$79.14 -$79.14WEST -$13.56 -$2.71 -$96.21 -$96.21NYCA Total $71.73 $316.04 -$181.18 -$181.18
+ Number Means Congestion Increases Supplier Production Cost
+ Number Means Congestion Increases Load Cost
- Number Means Congestion Decreases Load Payments
Negative Number Means Gen Payments Congestion Hurt Gens
PowerGEMPower Grid Engineering & Markets
29
2004 TotalsUnhedged Congestion Impact by Constraint
Monitored Facility % Cum %DUNWODIE 345 SHORE_RD 345 1 26.4% 26.4%
RAINEY__ 345 DUNWODIE 345 1 or 2 21.2% 47.7%RAINEY__ 138 VERNON__ 138 1 15.2% 62.9%
CENTRAL EAST - VC 9.5% 72.4%PLSNTVLY 345 LEEDS___ 345 1 4.9% 77.3%
W49TH_ST 345 SPRNBRK_ 345 1 or 2 4.8% 82.0%UPNY CONED 4.8% 86.8%
VALLYSTR 138 EGRDNCTY 138 1 2.7% 89.5%SHORE_RD 345 SHORE_RD 138 1 2.0% 91.5%
E13THSTA 345 W49TH_ST 345 1 1.3% 92.8%VERNON__ 138 KENTAVE_ 138 1 1.1% 93.9%SPRNBR49 345 EGRDNCTY 345 1 0.9% 94.9%FRESHKLS 138 WILLWBRK 138 1 0.7% 95.5%
E179THST 138 HELLGT_E 138 1 0.6% 96.1%HUDS_AVE 138 JAMAICA_ 138 2 0.6% 96.7%
QUENBRDG 138 VERNON__ 138 1 0.5% 97.2%LEEDS___ 345 ATHENS__ 345 1 0.5% 97.8%PLSNTVLY 345 ATHENS__ 345 1 0.5% 98.2%
SPR/DUN-SOUTH 0.4% 98.6%NE - NY 0.3% 98.9%
MILLWOOD 345 EASTVIEW 345 1 0.2% 99.1%LEEDS___ 345 N.SCTLND 345 1 0.0% 99.1%JAMAICA_ 138 VALLYSTR 138 1 0.0% 99.1%
PowerGEMPower Grid Engineering & Markets
30
Congestion Impact By Day2003 NY Daily Congestion
$0.0
$0.5
$1.0
$1.5
$2.0
$2.5
1/1 4/1 7/1 10/1
BP
C I
mp
ac
t in
$ M
illi
on
s
2004 NY Daily Congestion
$0.0
$0.5
$1.0
$1.5
$2.0
$2.5
1/1 4/1 7/1 10/1
BP
C i
mp
ac
t in
$ M
illi
on
s
PowerGEMPower Grid Engineering & Markets
31
Observations• 2004 Congestion Impact Not Dramatically Different than 2003, but is Lower• After a Congested January, Summer 2004 Congestion was Lower then 2003• The Upstate/Imports to Zone J and K Congestion Impact Divide Continues• Individual Constraints 2003 vs 2004
– Consistent• Dunwoodie – Shore Rd 345• Rainey – Vernon 138 kV
– Up• Dunwoodie – Rainey 345 • Pleasant Valley – Leeds 345 kV • Sprainbrook – 49th Street
– Down• Central East Interface
PowerGEMPower Grid Engineering & Markets
32
“Release Constraints in Sequence” Test
Assumes No Network Impedance or Connection Change
Scenario (Constraints Ignored for
Next Scenario) Monitored Element Contingency
Base DUNWODIE 345 SHORE_RD 345 1 Base Case RAINEY__ 345 DUNWODIE 345 1 SCB: SPBK (RS-4): M52 99941
1 DUNWODIE 345 SHORE_RD 345 1 BUS: NORTHPORT 681 UNIT 3 DUNWODIE 345 SHORE_RD 345 1 BUS: NORTHPORT 677 UNIT 2 RAINEY__ 345 DUNWODIE 345 1 Base Case W49TH_ST 345 SPRNBRK_ 345 2 SCB: SPBK (RS-4): M52 99941 E179THST 138 HELLGT_E 138 1 Base Case
2 RAINEY__ 345 DUNWODIE 345 1 DUNWODIE345_SHORE_RD345_Y50___ ROSLYN__ 138 EGRDNCTY 138 1 SHORE_RD138_GLENWD__138B365___ W49TH_ST 345 SPRNBRK_ 345 1 Base Case VALLYSTR 138 EGRDNCTY 138 1 BUS: LAKSUCSS 368 903
3 CARLPLCE 138 EGRDNCTY 138 1 SHORE_RD138_GLENWD__138A366-1_ W49TH_ST 345 SPRNBRK_ 345 1 SPRNBRK_345_W49TH_ST345_M51___ VALLYSTR 138 EGRDNCTY 138 1 Base Case
4 GLENWDGT 138 ROSLYN__ 138 1 SHORE_RD138_GLENWD__138B365___ VALLYSTR 138 EGRDNCTY 138 1 BUS: E F BARRET 292 459 BA SPR/DUN-SOUTH Base Case
5 JAMAICA_ 138 LAKSUCSS 138 1 DUNWODIE345_SHORE_RD345_Y50___ W49TH_ST 345 SPRNBRK_ 345 1 SCB: DUNW(7): W75 72 GLENWD__ 138 SHORE_RD 138 1 SHORE_RD138_GLENWD__138B365___
Single Day Effect of Sequentially Ignoring Constraints
-$800,000
-$600,000
-$400,000
-$200,000
$0
$200,000
$400,000
$600,000
$800,000
0 1 2 3 4 5
Stage of Constraints Ignored
Co
ng
es
tio
n Im
pa
ct
BPC
Payments
Base
PowerGEMPower Grid Engineering & Markets
33
Economic Planning Example Using PROBE
May 2004• Dunwoodie – Shore Rd. 345 kV was 25% of Congestion
Payments• 2 Tests
– 10% Increase in Dunwoodie – Shore Road Rating
– 600 MW added in Zone K @ $50/MW
Bid Production Cost Savings May 2004
Total Congestion Impact All Congestion Removed $5,258,463
Monthly Decrease in Bid Production Cost ForDunwoodie - Shore Rd. 345 kV Rating Increased 10% $599,442600 MW added to Zone K at $50/MW $14,617,085
PowerGEMPower Grid Engineering & Markets
34
Handling “Unusual Days” Approach
1. Use a Statistical Approach to Identify Days with an Unusual Amount of Congestion Impact
2. Define Congestion Impact Using the Primary Congestion
Measure (Constrained – Unconstrained) Mitigated Bid Production Cost
3. Analyze and Characterize Why the Days Were Unusual
4. Report Congestion Metrics Separately for “Unusual Days”
PowerGEMPower Grid Engineering & Markets
35
Unusual Days Part of the Preliminary 2003 Congestion Metrics
New York 2003Unusual Day Portion of Congestion Metrics
Bid Production Cost Change Impact % of all 200399 % Confident Unusual $9,703,053 13%99% to 95 % Confident Unusual $9,342,245 12%Not Unusual days $58,206,184 75%
Load Payments Impact % of all 200399 % Confident Unusual $45,490,007 11%99% to 95 % Confident Unusual $28,056,635 7%Not Unusual days $342,263,081 82%
Congestion Payments Impact % of all 200399 % Confident Unusual $97,206,520 10%99% to 95 % Confident Unusual $71,247,322 7%Not Unusual days $783,277,256 82%
Generation Payments Impact % of all 200399 % Confident Unusual $3,060,104 -4%99% to 95 % Confident Unusual -$8,817,920 10%Not Unusual days -$81,522,957 93%
PowerGEMPower Grid Engineering & Markets
36
Economic Planning Thoughts Using PROBE
Everyone Agrees “What if” Studies are Worthwhile
Study Approach Questions• Analyze All Hours or a Sample?• Take Out “Unusual Events” in the Base Calculation?• Solution to Each Problem or Multiple Problems ?• What about the “Just Submerged” Constraints ?
PowerGEMPower Grid Engineering & Markets
37
Economic Planning Thoughts Using PROBE
“Cost Effectiveness”• Measured by the Change in Bid Production Cost with the
Upgrade (Economic Efficiency Improvement)• Whole State Net Benefit Viewpoint• 10 Year Planning Horizon• “Benefit” is Present Worth of Production Cost Improvement
Net of– Cost of the Transmission Upgrade– Cost of the Upgrade Outage
PowerGEMPower Grid Engineering & Markets
38
Chronic Congestion May Be Viewed As:– All Monitored Elements that contributed to the
top X% of unhedged congestion payments in 2004
99% of Total 2004 Congestion 95% of Total 2004 Congestion 80% of Total 2004 Congestion %DUNWODIE 345 SHORE_RD 345 1 DUNWODIE 345 SHORE_RD 345 1 DUNWODIE 345 SHORE_RD 345 1 26.4%
RAINEY__ 345 DUNWODIE 345 1 or 2 RAINEY__ 345 DUNWODIE 345 1 or 2 RAINEY__ 345 DUNWODIE 345 1 or 2 21.2%RAINEY__ 138 VERNON__ 138 1 RAINEY__ 138 VERNON__ 138 1 RAINEY__ 138 VERNON__ 138 1 15.2%
CENTRAL EAST - VC CENTRAL EAST - VC CENTRAL EAST - VC 9.5%PLSNTVLY 345 LEEDS___ 345 1 PLSNTVLY 345 LEEDS___ 345 1 PLSNTVLY 345 LEEDS___ 345 1 4.9%
W49TH_ST 345 SPRNBRK_ 345 1 or 2 W49TH_ST 345 SPRNBRK_ 345 1 or 2 4.8%UPNY CONED UPNY CONED 4.8%
VALLYSTR 138 EGRDNCTY 138 1 VALLYSTR 138 EGRDNCTY 138 1 2.7%SHORE_RD 345 SHORE_RD 138 1 SHORE_RD 345 SHORE_RD 138 1 2.0%
E13THSTA 345 W49TH_ST 345 1 E13THSTA 345 W49TH_ST 345 1 1.3%VERNON__ 138 KENTAVE_ 138 1 VERNON__ 138 KENTAVE_ 138 1 1.1%SPRNBR49 345 EGRDNCTY 345 1 SPRNBR49 345 EGRDNCTY 345 1 0.9%FRESHKLS 138 WILLWBRK 138 1 0.7%
E179THST 138 HELLGT_E 138 1 0.6%HUDS_AVE 138 JAMAICA_ 138 2 0.6%
QUENBRDG 138 VERNON__ 138 1 0.5%LEEDS___ 345 ATHENS__ 345 1 0.5%PLSNTVLY 345 ATHENS__ 345 1 0.5%
SPR/DUN-SOUTH 0.4%NE - NY 0.3%
PowerGEMPower Grid Engineering & Markets
39
PowerGEM Observations
• More Comprehensive Calculation Significantly Lowers Congestion Impacts– Cost Shifting Rather than Savings – Effect on Energy Markets– Another Constraint is Usually in Hiding
• Studies to Date Have Not Shown Instances Where Transmission Development Lowers Cost Enough to Justify the Investment on a Purely Economic Basis
• Reliability Upgrades Affect Congestion• Diligence is Justified
– Persistent High Impact Constraints– Low Cost Transmission Investments
PowerGEMPower Grid Engineering & Markets
40
PowerGEM Observations
• LMP Based Rewards for Transmission Investment are Weak– LMP’s are Volatile– Congestion is Shifty and Difficult to Predict – Small Changes Can Make a Large Local Difference– Upgrades Remove the Source of Reward– Free Rider Issues
• LMP’s Are Strong Indicators for Generation• Affect on Bid Production Cost is a More Dependable Reward
for Transmission Investment
PowerGEMPower Grid Engineering & Markets
41
PowerGEM Lessons Learned
• Congestion is Persistent• LMP’s are Volatile• Shadow Prices are Even Yet More Volatile• Unit Commitment Has a Major Impact on Congestion Location and
Price• Congestion Cost Measurement Depends on Application• Transmission Upgrades Shift Rather than Reduce Cost to
Customers• Bid Production Cost Change is a More Stable Measure of Upgrade
Merits
PowerGEMPower Grid Engineering & Markets
42
Remember
• Numbers– Average 4 Simultaneous Constraints Every Hour in NY– NY Congestion Impact: 2003 = $85 Million; 2004 = $72 Million
• Observations from a Planning Perspective– Congestion Occurs at All Load Levels– Most Congestion Impact is Due To Chronic Events, Not Price Spikes– Bottleneck Relief Is Not as Cost Effective as Generally Believed– Analysis of Large Persistent Transmission Constraints is Prudent