powerpoint presentation - sce...utilities commission (cpuc) and the federal energy regulatory...

32
Circuit Reliability Review San Bernardino District 5 2020

Upload: others

Post on 18-Jul-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

Circuit Reliability Review

San Bernardino District 5

2020

Page 2: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

2

• Southern California Edison (SCE) is an Edison International company

• One of the nation’s largest electric utilities

• More than 130 years of history

• Headquartered in Rosemead, California

• Regulated by the California Public Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC)

• 50,000 square miles of SCE service area across Central, Coastal, and Southern California

• 15 million residents in service territory

• 5 million customer accounts in 445 cities and communities

Who We Are

Page 3: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

Our Grid

To deliver power safely, reliably and affordably, we monitor and maintain a vast electricity system.

730,000 Transformers

119,000 Miles of Transmission and Distribution Lines

4,600 Circuits

1.5 Million Poles

50,000 Square Miles

3

Page 4: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

Strengthening and Modernizing the Grid

• Infrastructure reliability – updating underground

cables, poles, switches, and transformers

• Wildfire mitigation – hardening infrastructure,

bolstering situational awareness capabilities, and

enhancing operational practices

• Transmission – connecting renewables, installing

new substations, and updating lines

• Grid readiness – updating the grid for impacts

from new technologies

• Long-term energy policy – supporting energy

storage, electric vehicles, and renewables

SCE plans to spend more than $5B each

year to maintain, improve, and harden

its infrastructure.

SCE’s investments support safe, reliable, affordable, and clean energy for our customers

2019 Capital Investments

179 miles of underground cable replaced

502 miles of overhead conductor replaced for public safety

16.4k distribution poles replaced

4.3k transmission poles replaced

71 underground structure replacements

4

Page 5: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

PATHWAY 2045SCE’S vision to help California achieve a carbon neutral future

Carbon neutrality is achieved through deep decarbonization of

electricity, transportation and building electrification,

and the use of low-carbon fuels

Meeting California’s Climate Change Goals

5

Page 6: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

• SCE filed its second Wildfire

Mitigation Plan in February 2020

• It builds on the progress made

in 2019 to reduce the risk of fire

ignitions caused by utility

infrastructure

• SCE crews will continue to work

to install hi-tech wildfire

mitigation tools and

technologies to make

communities safer, more

resilient, and to help reduce the

number of Public Safety Power

Shutoffs (PSPS)

Addressing Wildfire Risk

6

Page 7: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

• De-energizing power lines to prevent ignitions

• Used during elevated fire conditions

• Primarily impacts circuits in high fire risk areas

• Use of multiple methods to notify people in affected areas before, during and after a de-energization event

Public Safety Power Shutoffs (PSPS)

7

4-7 DAYS AHEAD

3 DAYSAHEAD

2 DAYSAHEAD

1 DAY AHEAD POWER SHUTOFF

POWER RESTORATION

PLANNING AND MONITORING OUTAGE

*Erratic or sudden onset of conditions may impact our ability to provide advanced notice to customers.

Forecast Weather & Fire

Conditions

SCE Incident Management Team on Alert

County Operational Areas

informed of potential activation

SCE Incident Management

Team Activated

1st Notification PSPS Possible sent

to agencies and customers

2nd Notification PSPS

Possible

3rd Notification Power Shutoff

4th Notification Power Restored After Inspection

Page 8: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

Reliability Overview

8

Page 9: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

What is Reliability?

• In simplest terms:

Having dependable electricity when you need it.

• Outages:

• Maintenance outages (aka planned outages)

• Repair outages (aka unplanned outages)

• Sustained Outage = An outage lasting > 5 minutes

• Momentary Outage = An outage lasting ≤ 5 minutes

9

Major Event Day (MED) : A day in which the daily system SAIDI exceeds a threshold value. For the purposes of calculating daily system SAIDI, any interruption that spans multiple calendar days is accrued to the day on which the interruption began. Statistically, days having a daily system SAIDI greater than a threshold value are days on which the energy delivery system experienced stresses beyond that normally expected (such as severe weather).

Public Safety Power Shutoff (PSPS) : An operational protocol that SCE implements under extreme weather conditions in order to minimize the threat of wildfires and keep communities safe from potentially dangerous situations. These types of sustained outages are temporary and usually involve situations where high fire areas are experiencing adverse weather or public safety is at risk.

Page 10: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

How Do We Measure Reliability?

SAIDI SAIFI MAIFI CAIDI

10

Page 11: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

CityList1Cities /Areas in San Bernardino District 5

COLTON

SAN BERNARDINO

BLOOMINGTON

GLEN HELEN

MUSCOY

RIALTO

FONTANA

SAN BERNARDINO INTERNATIONAL AIRPORT

11

Page 12: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

*”Exclusions” are days which utilities are allowed to remove from their metrics because the outages on those days were caused by a severe acts of nature.**In the columns showing “Rank,” lower numbers indicate poorer performance.

12

Page 13: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

CircuitList1Overview of San Bernardino District 5There are 48 circuits that serve San Bernardino District 5 1

Circuit Type Customers Circuit Type Customers Circuit Type Customers Circuit Type Customers

AVANTI(12KV) 1,580 REDBALL(12KV) 314 - -

BADGER(12KV) 2,084 ROCHHOLTZ(4.16KV) 719 - -

BOBBER(12KV) 2,102 ROI-TAN(12KV) 2,827 - -

BOMBAY(12KV) 105 SLOVER(12KV) 997 - -

BURGUNDY(12KV) 1,678 SPIKE(12KV) 1,194 - -

CACTUS(12KV) 7 STOCKCAR(12KV) 2,447 - -

CALSTATE(12KV) 610 STREAMLINER(12KV) 1,099 - -

CARMELITA(12KV) 2,267 SUSAN(12KV) 1,464 - -

CHARLIE(12KV) 1,255 TAMPICO(12KV) 964 - -

CLUB OAKS(33KV) 2 TENDER(12KV) 1,437 - -

DERBY(12KV) 561 TURNTABLE(12KV) 749 - -

DOMIC(12KV) 1,311 VERDEMONT(33KV) 11 - -

DRAGON(12KV) 341 WARM CREEK(12KV) 521 - -

DUROX(12KV) 689 WATERMAN(12KV) 1,169 - -

FLATCAR(12KV) 870 WHITLOCK(4.16KV) 409 - -

FLEETWOOD(12KV) 322 WIGWAG(12KV) 2,144 - -

FRISBIE(12KV) 1,554 ZAPATA(12KV) 1,089 - -

HEATHER(12KV) 1,847 CHEVELLE(12KV) 2,942 - -

HIGHBALL(12KV) 1,643 - - -

HOLLY VISTA(12KV) 1,366 - - -

HOPPER(12KV) 1,774 - - -

IRONHORSE(12KV) 216 - - -

IRVINGTON(12KV) 591 - - -

KIMBERLY(2.4KV) 50 - - -

LARCH(33KV) 3 - - -

LIMONITE(33KV) 2 - - -

LYTLE(12KV) 92 - - -

MACY(4.16KV) 665 - - -

NORTHPARK(12KV) 2,188 - - -

POWER(4.16KV) 821 - - -

Grand Total 51,092

13

Page 14: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

BarChart

SCE SYSTEMWIDE

**Data is as of 02/14/2020, data

can be slightly different due to

outage data validation process

San Bernardino District 5

Reliability History of Circuits Serving San Bernardino District 5 (No Exclusions)

**“Exclusions” are days which

utilities are allowed to

remove from their metrics

because the outages on

those days were caused by

acts of nature.

123.0

175.7

127.4

188.4

134.5 139.7 136.8

178.0

0.0

50.0

100.0

150.0

200.0

2016 2017 2018 2019

SAIDI

(average

minutes of

sustained

interruptions)

0.9

1.6

1.3

1.9

1.11.2

0.91.0

0.0

0.5

1.0

1.5

2.0

SAIFI

(average

frequency of

sustained

interruptions)

1.5

1.7 1.7 1.71.6

1.8

1.4 1.4

0.0

0.5

1.0

1.5

2.0

MAIFI

(average

frequency of

momentary

interruptions)

14

Page 15: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

SAIDIChart

SAIDI = the cumulative amount of time the average customer is interrupted by “sustained” outages each year.

Causes of Repair Outages in San Bernardino District 5

2019

3rd Party

4.1%

Equipment Failure

36.5%

Operation

13.7%

Other

20.1%

Vegetation /Animal

2.3%

Weather /Fire

/Earthquake

2.1%

PSPS

21.2%

Contributions to SAIDI by Outage Cause

3rd Party

Equipment Failure

Operation

Other

Vegetation /Animal

Weather /Fire /Earthquake

PSPS

Equipment Failure

e.g., in-service failure of transformer, switch, or conductors

Vegetation/Animale.g., tree branch, rodent, or bird

causing a short circuit between conductors

Othere.g., patrolled but no cause found,

PSPS Operations

e.g., urgent maintenance w/o 3-daynotice

3rd Party e.g., balloon, car hit pole, dig-in

PSPS

e.g., Public Safety Power Shutoff

15

Page 16: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

SAIFIChart

SAIFI = the number of times the average customer is interrupted by “sustained” outages each year

Causes of Repair Outages in San Bernardino District 5

2019

3rd Party

10.9%

Equipment Failure

36.5%

Operation

7.3%

Other

28.7%

Vegetation /Animal

14.0%

Weather /Fire

/Earthquake

1.1%PSPS

1.4%

Contributions to SAIFI by Outage Cause

3rd Party

Equipment Failure

Operation

Other

Vegetation /Animal

Weather /Fire /Earthquake

PSPS

Equipment Failure

e.g., in-service failure of transformer, switch, or conductors

Vegetation/Animale.g., tree branch, rodent, or bird

causing a short circuit between conductors

Othere.g., patrolled but no cause found

Operationse.g., urgent maintenance w/o 3-day

notice 3rd Party

e.g., balloon, car hit pole, dig-in

PSPS

e.g., Public Safety Power Shutoff

16

Page 17: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

17

Page 18: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

18

Page 19: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

Back-up Slides

Reliability Histories of Circuits Serving San Bernardino District 5

Updated through Dec 2019

19

Page 20: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

CitySummary

SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI

123.0 0.9 1.5 175.7 1.6 1.7 127.4 1.3 1.7 17.0 0.2 0.2 31.3 0.4 0.9 37.8 0.5 0.2 102.3 0.7 0.3 188.4 1.9 1.7

3rd Party 29% 36% 24% 18% 19% 18% 29% 31% 36% 16% 34% 60% 5% 9% 25% 3% 4% 18% 3% 9% 19% 4% 11% 28%

Equipment Failure 17% 17% 23% 46% 30% 12% 51% 35% 16% 69% 58% 23% 70% 50% 23% 83% 43% 4% 4% 16% 13% 37% 36% 19%

Operation 11% 16% 2% 11% 17% 3% 8% 18% 7% 3% 1% 1% 10% 14% 0% 6% 3% 17% 19% 8% 14% 14% 7% 5%

Other 13% 15% 30% 9% 18% 38% 11% 15% 34% 11% 4% 9% 16% 27% 46% 0% 0% 60% 30% 60% 49% 20% 29% 43%

Vegetation/Animal 13% 3% 5% 0% 0% 20% 0% 0% 3% - - - - - 6% 8% 49% - 1% 1% 5% 2% 14% 4%

Weather/Fire/Earthquake 17% 13% 16% 16% 16% 9% 1% 1% 3% 1% 2% 8% - - - - - - 4% 2% - 2% 1% 1%

PSPS - - - - - - 0% 0% - - - - - - - - - - 39% 4% - 21% 1% -

SCE SYSTEMWIDE 134.5 1.1 1.6 139.7 1.2 1.8 136.8 0.9 1.4 28.1 0.3 0.4 18.9 0.2 0.4 31.8 0.2 0.3 99.3 0.3 0.3 178.0 1.0 1.4

Average Reliability of 48 Circuits Serving San Bernardino District 5

4th Qtr 2019 20192016 2017 2018 1st Qtr 2019 2nd Qtr 2019 3rd Qtr 2019

48 Circuits Serving San Bernardino District 5 --

Total Customers: 51,092

Notes:

No outages are excluded from the metrics.

Outage Causes: Other: e.g., patrolled but no cause could be foundOperations: e.g., urgent maintenance w/o 3-day notice to customers3rd Party: e.g., balloons, car hit pole, dig-inVegetation/Animal: e.g., tree branch, rodent, or bird causing short circuit across conductorsPSPS: e.g., Public Safety Power Shutoff

SAIDI (minutes) = the cumulative amount of time the average customer is interrupted by “sustained” (longer than 5 minutes) outages.

SAIFI (interruptions) = the number of times the average customer is interrupted by “sustained” outages.

MAIFI (interruptions) = the number of times the average customer is interrupted by “momentary " (lasting 5 minutes or less) outages.

20

Page 21: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

CircuitHistory1

SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI

AVANTI(12KV) - Customers: 1,580 9.7 0.0 - 38.7 0.6 0.1 2.4 0.3 1.1 - - - - - - 103.8 1.5 - 458.8 2.0 - 562.6 3.5 -

3rd Party 28% 90% - 11% 71% - - - - - - - - - - - - - - - - - - -

Equipment Failure 33% 5% - - - - 100% 100% 7% - - - - - - 89% 17% - - - - 16% 7% -

Operation - - - 89% 29% - - - - - - - - - - 2% 16% - - - - 0% 7% -

Other - - - - - 100% - - 93% - - - - - - - - - 100% 100% - 82% 58% -

Vegetation/Animal - - - - - - - - - - - - - - - 10% 67% - - - - 2% 28% -

Weather/Fire/Earthquake 39% 5% - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

BADGER(12KV) - Customers: 2,084 13.1 0.0 1.0 71.0 1.0 0.0 8.8 0.1 1.0 5.2 0.0 - - - - 12.4 1.0 - 36.3 1.0 - 53.9 2.0 -

3rd Party - - - - - - - - - - - - - - - - - - - - - - - -

Equipment Failure - - - 93% 96% - 100% 100% - - - - - - - - - - 11% 0% - 7% 0% -

Operation 92% 76% - 6% 3% - - - - 100% 100% - - - - - - - - - - 10% 2% -

Other 5% 23% 100% 1% 1% 86% - - 100% - - - - - - - - - 89% 100% - 60% 49% -

Vegetation/Animal 2% 1% - - - - - - - - - - - - - 100% 100% - - - - 23% 49% -

Weather/Fire/Earthquake - - - - - 14% - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

BOBBER(12KV) - Customers: 2,102 41.7 0.1 1.0 183.9 2.1 4.4 36.0 1.0 - 50.6 0.2 - - - 1.9 5.5 0.0 - - - - 56.2 0.2 1.9

3rd Party - - - 3% 1% 23% - - - - - - - - 48% - - - - - - - - 48%

Equipment Failure 27% 62% - 62% 50% 10% 80% 4% - 26% 7% - - - - 93% 50% - - - - 33% 10% -

Operation 0% 5% - 3% 1% - 20% 96% - - - - - - - 7% 50% - - - - 1% 4% -

Other - - 100% 33% 48% 44% - - - 74% 93% - - - 52% - - - - - - 67% 86% 52%

Vegetation/Animal - - - - - 23% - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake 73% 33% - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

BOMBAY(12KV) - Customers: 105 - - 1.0 53.8 1.0 1.0 4.7 0.0 - 16.4 1.0 - - - 1.0 - - 1.0 - - - 16.4 1.0 2.0

3rd Party - - 100% - - - - - - - - - - - - - - - - - - - - -

Equipment Failure - - - 100% 100% - 100% 100% - 100% 100% - - - - - - - - - - 100% 100% -

Operation - - - - - - - - - - - - - - - - - - - - - - - -

Other - - - - - - - - - - - - - - 100% - - 100% - - - - - 100%

Vegetation/Animal - - - - - 100% - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

Reliability Histories for Individual Circuits Serving San Bernardino District 5 - 1 of 12

2016 2017 2018 1st Qtr 2019 2nd Qtr 2019 3rd Qtr 2019 4th Qtr 2019 2019

21

Page 22: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

CircuitHistory2

SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI

BURGUNDY(12KV) - Customers: 1,678 73.6 1.1 2.3 25.6 0.1 1.0 187.6 2.0 1.1 5.8 0.1 - 17.6 0.1 1.0 1.4 0.0 - 6.8 0.6 0.4 31.6 0.8 1.4

3rd Party 2% 1% - - - - 91% 74% 25% - - - - - 100% 47% 32% - - - - 2% 0% 73%

Equipment Failure 27% 3% 12% 70% 40% - 6% 4% - 94% 96% - - - - - - - 74% 98% 100% 33% 89% 27%

Operation 46% 91% - - - - 3% 22% 75% 6% 4% - 99% 99% - - - - 26% 2% - 62% 10% -

Other - - 44% 10% 21% - - - - - - - 1% 1% - - - - - - - 0% 0% -

Vegetation/Animal 16% 4% 44% 19% 39% - - - - - - - - - - 53% 68% - - - - 2% 1% -

Weather/Fire/Earthquake 9% 1% - - - 100% - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

CACTUS(12KV) - Customers: 7 - - 1.0 144.0 0.7 1.0 - - 1.0 - - - - - - - - - - - - - - -

3rd Party - - - - - - - - 100% - - - - - - - - - - - - - - -

Equipment Failure - - - - - - - - - - - - - - - - - - - - - - - -

Operation - - - - - - - - - - - - - - - - - - - - - - - -

Other - - - - - 100% - - - - - - - - - - - - - - - - - -

Vegetation/Animal - - - - - - - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - 100% 100% 100% - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

CALSTATE(12KV) - Customers: 610 186.7 0.5 - 73.5 1.0 1.0 23.1 0.0 1.0 0.6 0.0 0.0 - - - 19.7 1.0 - 3085.9 3.1 - 3106.1 4.2 0.0

3rd Party 0% 3% - - - - - - - - - - - - - - - - - - - - - -

Equipment Failure 76% 45% - 89% 98% - - - - 100% 100% - - - - - - - - - - 0% 0% -

Operation 23% 51% - - - - - - - - - - - - - - - - - - - - - -

Other - - - - - 100% 31% 50% 100% - - 100% - - - - - - 1% 33% - 1% 25% 100%

Vegetation/Animal - - - - - - - - - - - - - - - 100% 100% - - - - 1% 24% -

Weather/Fire/Earthquake - - - 11% 2% - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - 69% 50% - - - - - - - - - - 99% 67% - 98% 51% -

CARMELITA(12KV) - Customers: 2,267 46.2 0.3 1.0 23.2 0.2 - 44.1 0.5 2.6 - - - 34.2 0.1 - 17.1 1.4 - 435.4 2.8 - 486.7 4.2 -

3rd Party - - 100% 4% 6% - 17% 4% - - - - - - - - - - 6% 13% - 6% 9% -

Equipment Failure 9% 2% - 34% 26% - 56% 17% - - - - - - - 6% 0% - 2% 37% - 2% 24% -

Operation 22% 42% - - - - - - - - - - 99% 96% - 6% 0% - 85% 14% - 83% 11% -

Other 69% 55% - 50% 66% - 7% 75% 62% - - - 1% 4% - 2% 0% - 7% 36% - 6% 24% -

Vegetation/Animal - - - - - - - - - - - - - - - 87% 100% - - - - 3% 33% -

Weather/Fire/Earthquake - - - 13% 3% - 20% 5% 38% - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

Reliability Histories for Individual Circuits Serving San Bernardino District 5 - 2 of 12

2016 2017 2018 1st Qtr 2019 2nd Qtr 2019 3rd Qtr 2019 4th Qtr 2019 2019

22

Page 23: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

CircuitHistory3

SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI

CHARLIE(12KV) - Customers: 1,255 9.1 1.0 1.1 28.9 0.1 3.3 84.2 0.5 2.0 78.5 1.1 1.1 - - - 49.8 1.1 - - - - 128.3 2.2 1.1

3rd Party - - - - - - 19% 69% 50% - - - - - - - - - - - - - - -

Equipment Failure 16% 1% 100% 100% 100% - 81% 31% - 97% 99% 100% - - - 96% 100% - - - - 97% 99% 100%

Operation 84% 99% - - - 9% - - 50% 3% 1% - - - - - - - - - - 2% 0% -

Other - - - - - 91% - - - - - - - - - 4% 0% - - - - 1% 0% -

Vegetation/Animal - - - - - - - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

CHEVELLE(12KV) - Customers: 2,942 - - - - - - - - - - - - - - - - - - 36.4 0.3 0.1 36.4 0.3 0.1

3rd Party - - - - - - - - - - - - - - - - - - - - - - - -

Equipment Failure - - - - - - - - - - - - - - - - - - 24% 25% - 24% 25% -

Operation - - - - - - - - - - - - - - - - - - 55% 49% - 55% 49% -

Other - - - - - - - - - - - - - - - - - - 21% 25% 100% 21% 25% 100%

Vegetation/Animal - - - - - - - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

CLUB OAKS(33KV) - Customers: 2 22.0 1.0 2.0 - - 3.0 591.8 1.6 2.2 66.5 0.5 - - - - - - 1.1 8196.3 6.5 4.4 8262.9 7.1 5.5

3rd Party - - 50% - - - 2% 67% 50% - - - - - - - - - - - - - - -

Equipment Failure 100% 100% - - - - 98% 33% - - - - - - - - - - 0% 17% - 0% 15% -

Operation - - - - - 33% - - - 100% 100% - - - - - - - 28% 33% 25% 29% 38% 20%

Other - - 50% - - 67% - - - - - - - - - - - 100% - - 75% - - 80%

Vegetation/Animal - - - - - - - - 50% - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - 12% 17% - 12% 15% -

PSPS - - - - - - - - - - - - - - - - - - 59% 33% - 59% 31% -

DERBY(12KV) - Customers: 561 256.4 1.0 - 147.1 1.1 2.0 60.7 0.1 1.0 1.0 0.0 - 0.7 0.0 - 11.5 0.0 - 17.3 0.1 1.0 30.6 0.2 1.0

3rd Party 99% 96% - - - 50% - - - - - - - - - - - - 74% 93% 100% 42% 60% 100%

Equipment Failure - - - 4% 3% - 28% 23% - 100% 100% - 100% 100% - 100% 100% - - - - 44% 36% -

Operation 1% 4% - - - - - - - - - - - - - - - - 26% 7% - 14% 4% -

Other - - - - - 50% 72% 77% 100% - - - - - - - - - - - - - - -

Vegetation/Animal - - - - - - - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - 96% 97% - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

Reliability Histories for Individual Circuits Serving San Bernardino District 5 - 3 of 12

2016 2017 2018 1st Qtr 2019 2nd Qtr 2019 3rd Qtr 2019 4th Qtr 2019 2019

23

Page 24: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

CircuitHistory4

SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI

DOMIC(12KV) - Customers: 1,311 352.0 3.1 9.6 313.5 3.9 4.4 88.0 2.2 4.2 57.1 1.0 0.8 - - - 5.0 0.0 1.0 7.3 1.0 - 69.3 2.1 1.8

3rd Party 0% 0% 8% - - 37% - - 23% 91% 99% 100% - - - - - 100% 78% 99% - 83% 98% 100%

Equipment Failure 0% 0% - 32% 21% - 57% 52% 26% 9% 1% - - - - 99% 98% - - - - 15% 2% -

Operation - - - 27% 53% - 7% 43% - - - - - - - - - - 16% 0% - 2% 0% -

Other 58% 64% 39% - - 41% 37% 5% 26% - - - - - - 1% 3% - 5% 1% - 1% 0% -

Vegetation/Animal - - - - - - - - 26% - - - - - - - - - - - - - - -

Weather/Fire/Earthquake 41% 36% 52% 42% 26% 22% - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

DRAGON(12KV) - Customers: 341 - - - - - 1.0 7.8 1.0 - 0.6 0.0 - - - - - - - - - - 0.6 0.0 -

3rd Party - - - - - - - - - - - - - - - - - - - - - - - -

Equipment Failure - - - - - - - - - 100% 100% - - - - - - - - - - 100% 100% -

Operation - - - - - - 100% 100% - - - - - - - - - - - - - - - -

Other - - - - - - - - - - - - - - - - - - - - - - - -

Vegetation/Animal - - - - - 100% - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

DUROX(12KV) - Customers: 689 101.7 1.4 0.6 536.3 1.3 - 141.5 2.0 - 6.5 0.3 0.7 - - - - - - - - - 6.5 0.3 0.7

3rd Party 100% 100% 100% - - - 48% 49% - 100% 100% 100% - - - - - - - - - 100% 100% 100%

Equipment Failure - - - 89% 75% - 52% 51% - - - - - - - - - - - - - - - -

Operation - - - 11% 25% - - - - - - - - - - - - - - - - - - -

Other - - - - - - - - - - - - - - - - - - - - - - - -

Vegetation/Animal - - - - - - - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

FLATCAR(12KV) - Customers: 870 29.0 0.1 1.0 127.8 1.0 3.0 35.8 0.9 1.0 - - - 14.0 1.0 1.0 31.4 0.5 0.5 188.6 1.5 2.0 234.1 3.0 3.5

3rd Party - - - - - 33% - - - - - - - - - 13% 2% - - - - 2% 0% -

Equipment Failure 95% 51% - 4% 1% - 55% 97% 100% - - - - - - 87% 98% 100% 53% 66% 50% 54% 49% 43%

Operation 5% 49% - 2% 2% - - - - - - - - - - - - - - - - - - -

Other - - 100% - - 33% - - - - - - 100% 100% 100% - - - - - - 6% 33% 28%

Vegetation/Animal - - - - - 33% - - - - - - - - - - - - 47% 34% 50% 38% 17% 28%

Weather/Fire/Earthquake - - - 94% 97% - 45% 3% - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

Reliability Histories for Individual Circuits Serving San Bernardino District 5 - 4 of 12

2016 2017 2018 1st Qtr 2019 2nd Qtr 2019 3rd Qtr 2019 4th Qtr 2019 2019

24

Page 25: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

CircuitHistory5

SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI

FLEETWOOD(12KV) - Customers: 322 130.2 3.0 1.0 127.6 3.0 4.6 295.7 4.8 6.9 110.7 1.0 2.0 - - - - - - 0.2 0.0 - 110.9 1.0 2.0

3rd Party 89% 34% - 39% 33% - 10% 14% 43% 100% 100% 50% - - - - - - - - - 100% 100% 50%

Equipment Failure 6% 33% 100% 48% 65% 57% 22% 22% - - - - - - - - - - - - - - - -

Operation - - - 3% 1% - 50% 42% - - - - - - - - - - 100% 100% - 0% 0% -

Other 5% 33% - 10% 1% 43% 3% 1% 57% - - 50% - - - - - - - - - - - 50%

Vegetation/Animal - - - - - - - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - 16% 21% - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

FRISBIE(12KV) - Customers: 1,554 6.7 0.0 - 34.4 0.7 - 56.9 0.1 1.9 104.3 1.0 0.4 - - 1.0 - - - 12.0 0.1 - 116.3 1.0 1.4

3rd Party - - - 3% 2% - 76% 53% 100% - - - - - 100% - - - - - - - - 69%

Equipment Failure 49% 36% - 72% 93% - 21% 29% - 100% 100% 100% - - - - - - - - - 90% 94% 31%

Operation 51% 64% - 25% 5% - - - - - - - - - - - - - 100% 100% - 10% 6% -

Other - - - - - - - - - - - - - - - - - - - - - - - -

Vegetation/Animal - - - - - - 4% 18% - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

HEATHER(12KV) - Customers: 1,847 57.7 0.1 - 81.3 1.0 1.0 84.9 2.8 3.3 48.1 0.7 1.0 - - 1.0 28.8 0.0 1.0 - - - 76.9 0.7 3.0

3rd Party 1% 5% - 1% 0% 100% 50% 62% 40% - - 100% - - - - - - - - - - - 33%

Equipment Failure 84% 58% - 10% 1% - 50% 38% 60% 100% 100% - - - - 100% 100% - - - - 100% 100% -

Operation 14% 36% - 0% 0% - - - - - - - - - - - - - - - - - - -

Other - - - - - - - - - - - - - - 100% - - 100% - - - - - 67%

Vegetation/Animal - - - - - - - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - 89% 99% - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

HIGHBALL(12KV) - Customers: 1,643 212.1 1.0 - 1149.9 2.2 1.5 527.1 1.6 1.8 33.2 1.6 1.8 58.3 0.4 1.0 258.0 2.3 1.0 1.2 0.0 - 350.6 4.3 3.7

3rd Party 93% 97% - 29% 45% - 1% 1% - 23% 49% 100% - - - - - - - - - 2% 18% 47%

Equipment Failure 0% 0% - 70% 53% 35% 88% 93% 100% 49% 49% - 100% 100% - 100% 100% - 75% 61% - 95% 81% -

Operation - - - 2% 2% - 11% 5% - - - - 0% 0% - 0% 0% - 25% 39% - 0% 0% -

Other 7% 2% - - - - 0% 1% - 28% 3% - - - 100% - - 100% - - - 3% 1% 53%

Vegetation/Animal - - - - - 65% - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

Reliability Histories for Individual Circuits Serving San Bernardino District 5 - 5 of 12

2016 2017 2018 1st Qtr 2019 2nd Qtr 2019 3rd Qtr 2019 4th Qtr 2019 2019

25

Page 26: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

CircuitHistory6

SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI

HOLLY VISTA(12KV) - Customers: 1,366 1.0 0.0 1.0 93.6 1.3 2.0 325.3 3.3 3.9 2.5 0.0 - 14.4 0.1 - 1.7 0.0 - 12.6 0.1 1.0 31.2 0.2 1.0

3rd Party - - - - - 51% 96% 99% 60% - - - - - - - - - 92% 93% - 37% 58% -

Equipment Failure 100% 100% 100% 0% 0% - 1% 0% 26% 100% 100% - - - - 94% 86% - 8% 7% - 17% 15% -

Operation - - - 2% 1% - 2% 0% 14% - - - - - - 6% 14% - - - - 0% 1% -

Other - - - - - 49% 0% 0% - - - - 100% 100% - - - - - - 100% 46% 27% 100%

Vegetation/Animal - - - - - - - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - 98% 99% - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

HOPPER(12KV) - Customers: 1,774 175.3 0.6 0.4 206.0 0.5 3.7 148.4 2.8 - 13.8 0.4 0.3 2.6 0.0 1.0 0.5 0.0 - - - 1.0 16.9 0.4 2.3

3rd Party - - - - - - - - - - - - - - - - - - - - 100% - - 44%

Equipment Failure 1% 1% - 83% 64% 19% 95% 99% - 100% 100% 100% - - - - - - - - - 81% 96% 12%

Operation 6% 6% - 13% 19% - 5% 1% - - - - - - - 100% 100% - - - - 3% 1% -

Other - - - 3% 16% 27% - - - - - - 100% 100% 100% - - - - - - 15% 3% 44%

Vegetation/Animal - - - - - 27% - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake 93% 94% 100% 1% 1% 27% - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

IRONHORSE(12KV) - Customers: 216 0.8 0.0 - 14.2 0.4 4.0 286.4 1.9 4.2 6.2 0.0 0.3 60.0 0.3 1.7 119.0 0.5 1.0 5.9 0.0 - 191.0 0.9 3.0

3rd Party - - - 23% 77% - 60% 83% 100% - - - 100% 100% 40% - - - - - - 31% 40% 22%

Equipment Failure - - - - - - 36% 9% - - - - - - - 5% 3% - - - - 3% 2% -

Operation 100% 100% - - - - 4% 9% - 100% 100% 100% - - - 95% 97% 100% - - - 62% 57% 44%

Other - - - - - 50% - - - - - - - - 60% - - - 100% 100% - 3% 2% 34%

Vegetation/Animal - - - 77% 23% 50% - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

IRVINGTON(12KV) - Customers: 591 2.6 0.0 1.3 11.0 0.1 3.0 - - 2.0 205.2 1.0 0.2 - - - 11.1 1.0 - 60.4 2.0 - 276.6 4.0 0.2

3rd Party - - - - - - - - 50% - - - - - - - - - - - - - - -

Equipment Failure 89% 67% 100% - - - - - - 100% 100% 100% - - - - - - - - - 74% 25% 100%

Operation 11% 33% - 100% 100% - - - - - - - - - - - - - - - - - - -

Other - - - - - 100% - - 50% - - - - - - - - - 100% 100% - 22% 50% -

Vegetation/Animal - - - - - - - - - - - - - - - 100% 100% - - - - 4% 25% -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

Reliability Histories for Individual Circuits Serving San Bernardino District 5 - 6 of 12

2016 2017 2018 1st Qtr 2019 2nd Qtr 2019 3rd Qtr 2019 4th Qtr 2019 2019

26

Page 27: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

CircuitHistory7

SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI

KIMBERLY(2.4KV) - Customers: 50 401.4 2.0 2.0 17.4 0.0 2.0 1138.0 2.0 2.0 120.6 1.0 - 39.1 0.1 - - - 1.0 5386.6 6.0 2.0 5546.3 7.1 3.0

3rd Party - - 50% - - - 1% 50% 49% - - - - - - - - - - - - - - -

Equipment Failure 27% 50% - 100% 100% - 99% 50% - - - - 99% 83% - - - - 0% 17% - 1% 16% -

Operation - - - - - - - - - 100% 100% - 1% 17% - - - - 1% 34% 50% 3% 42% 33%

Other - - 50% - - 100% - - - - - - - - - - - 100% - - 50% - - 67%

Vegetation/Animal - - - - - - - - 51% - - - - - - - - - - - - - - -

Weather/Fire/Earthquake 73% 50% - - - - - - - - - - - - - - - - 18% 17% - 17% 14% -

PSPS - - - - - - - - - - - - - - - - - - 82% 33% - 80% 28% -

LARCH(33KV) - Customers: 3 - - 4.0 156.7 2.3 3.0 1610.8 5.0 6.3 - - - - - 2.0 - - 1.0 - - 1.0 - - 4.0

3rd Party - - 50% - - - 30% 20% 16% - - - - - 50% - - - - - - - - 25%

Equipment Failure - - - - - - 61% 40% 32% - - - - - - - - - - - - - - -

Operation - - - 100% 100% - - - - - - - - - - - - 100% - - - - - 25%

Other - - 25% - - 100% 0% 20% 37% - - - - - 50% - - - - - - - - 25%

Vegetation/Animal - - - - - - - - 16% - - - - - - - - - - - 100% - - 25%

Weather/Fire/Earthquake - - 25% - - - 9% 20% - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

LIMONITE(33KV) - Customers: 2 324.3 1.0 1.0 - - - 703.0 2.0 1.0 110.0 1.0 2.0 - - - - - - - - - 110.0 1.0 2.0

3rd Party - - - - - - - - 100% 100% 100% 50% - - - - - - - - - 100% 100% 50%

Equipment Failure - - 100% - - - - - - - - - - - - - - - - - - - - -

Operation - - - - - - 100% 100% - - - - - - - - - - - - - - - -

Other 100% 100% - - - - - - - - - 50% - - - - - - - - - - - 50%

Vegetation/Animal - - - - - - - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

LYTLE(12KV) - Customers: 92 41.6 0.2 2.0 231.5 4.4 0.0 746.3 4.2 0.5 - - - 14.8 0.2 0.1 - - - 39.4 0.3 0.0 54.2 0.5 0.2

3rd Party - - - 39% 22% 100% 0% 0% - - - - - - - - - - - - - - - -

Equipment Failure 61% 44% - 9% 10% - 88% 76% 100% - - - 51% 78% 100% - - - - - - 14% 30% 75%

Operation 39% 56% - 0% 0% - 0% 0% - - - - - - - - - - 2% 14% - 1% 8% -

Other - - 50% 52% 67% - 12% 24% - - - - 49% 22% - - - - 98% 86% 100% 85% 61% 25%

Vegetation/Animal - - - - - - - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - 50% - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

Reliability Histories for Individual Circuits Serving San Bernardino District 5 - 7 of 12

2016 2017 2018 1st Qtr 2019 2nd Qtr 2019 3rd Qtr 2019 4th Qtr 2019 2019

27

Page 28: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

CircuitHistory8

SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI

MACY(4.16KV) - Customers: 665 459.8 3.3 2.7 340.7 5.0 4.9 67.2 2.0 4.0 8.7 0.0 - 15.8 1.1 3.0 167.7 1.0 - 7.6 1.0 1.0 199.9 3.1 4.0

3rd Party 78% 92% 36% 37% 60% 60% - - 25% - - - - - - - - - - - - - - -

Equipment Failure 2% 1% - 1% 0% 20% 2% 1% - 100% 100% - 81% 97% 67% 99% 98% - - - - 94% 67% 50%

Operation 20% 7% 27% - - - 67% 50% - - - - - - - 1% 2% - - - - 0% 1% -

Other - - 36% 13% 20% 20% 32% 50% 75% - - - 19% 3% - - - - 100% 100% 100% 5% 33% 25%

Vegetation/Animal - - - - - - - - - - - - - - 33% - - - - - - - - 25%

Weather/Fire/Earthquake - - - 49% 20% - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

NORTHPARK(12KV) - Customers: 2,188 116.4 1.7 1.7 207.5 2.4 0.8 48.5 0.5 1.3 5.5 0.1 - 59.0 2.2 - 12.0 1.0 0.2 22.2 1.0 - 98.7 4.4 0.2

3rd Party 27% 59% 42% 0% 0% - 4% 0% 20% - - - - - - 3% 3% 100% - - - 0% 1% 100%

Equipment Failure 19% 2% - 33% 43% - 26% 15% - - - - 1% 1% - 2% 0% - 1% 0% - 1% 0% -

Operation 25% 17% - 5% 3% 3% 27% 74% - - - - 20% 53% - 6% 0% - - - - 13% 27% -

Other - - - 46% 33% 97% 34% 8% 80% 2% 1% - 79% 47% - - - - 95% 100% - 69% 46% -

Vegetation/Animal - - - - - - - - - - - - - - - 90% 96% - - - - 11% 23% -

Weather/Fire/Earthquake 29% 22% 58% 16% 20% - 9% 3% - 98% 99% - - - - - - - 4% 0% - 6% 3% -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

POWER(4.16KV) - Customers: 821 243.8 3.0 1.8 496.3 6.0 3.0 36.0 1.1 4.8 2.5 0.0 1.5 30.6 1.0 3.9 193.8 1.0 - 139.6 1.0 1.0 366.5 3.1 6.4

3rd Party 100% 100% 44% 56% 67% 33% - - 20% - - 89% - - 25% - - - - - - - - 36%

Equipment Failure - - - 1% 0% 33% 7% 0% - 100% 100% - 99% 100% 50% 100% 100% - - - - 62% 66% 31%

Operation - - - - - - 19% 6% - - - - 1% 0% - 0% 0% - 2% 2% - 1% 1% -

Other - - 56% 9% 17% 33% 73% 93% 80% - - 11% - - - - - - 98% 98% 100% 37% 33% 18%

Vegetation/Animal - - - - - - - - - - - - - - 25% - - - - - - - - 15%

Weather/Fire/Earthquake - - - 34% 17% - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

REDBALL(12KV) - Customers: 314 340.0 2.9 0.8 - - 2.0 - - - - - - - - 1.0 - - - 235.9 2.0 - 235.9 2.0 1.0

3rd Party - - - - - 50% - - - - - - - - - - - - - - - - - -

Equipment Failure 100% 100% - - - - - - - - - - - - - - - - - - - - - -

Operation - - 100% - - - - - - - - - - - - - - - - - - - - -

Other - - - - - - - - - - - - - - 100% - - - 100% 100% - 100% 100% 100%

Vegetation/Animal - - - - - 50% - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

Reliability Histories for Individual Circuits Serving San Bernardino District 5 - 8 of 12

2016 2017 2018 1st Qtr 2019 2nd Qtr 2019 3rd Qtr 2019 4th Qtr 2019 2019

28

Page 29: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

CircuitHistory9

SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI

ROCHHOLTZ(4.16KV) - Customers: 719 1116.7 3.0 2.0 116.8 3.0 - 332.9 3.1 3.0 10.0 0.0 1.0 13.7 0.1 1.0 0.6 0.0 - 13.4 0.0 - 37.8 0.1 2.0

3rd Party - - - - - - - - 33% - - - - - 100% - - - - - - - - 50%

Equipment Failure 0% 0% - 58% 34% - 86% 66% - 100% 100% - - - - 100% 100% - 68% 57% - 52% 25% -

Operation - - - 9% 33% - 5% 2% - - - - - - - - - - - - - - - -

Other 5% 33% 100% 33% 33% - 9% 32% 33% - - 100% 100% 100% - - - - - - - 36% 69% 50%

Vegetation/Animal 95% 66% - - - - - - 34% - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - 32% 43% - 11% 6% -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

ROI-TAN(12KV) - Customers: 2,827 209.0 2.3 3.7 459.7 3.9 2.7 215.8 3.2 4.0 1.4 0.0 - 163.7 1.4 1.3 227.6 2.3 0.5 190.8 2.8 2.0 583.5 6.5 3.8

3rd Party 20% 26% 26% 11% 7% - 38% 28% 29% - - - 8% 19% - - - - - - - 2% 4% -

Equipment Failure 49% 48% 74% 54% 33% 27% 10% 17% 11% - - - 75% 70% 100% 88% 55% - 0% 0% - 55% 35% 33%

Operation 12% 4% - 22% 28% - 13% 34% - 100% 100% - 1% 1% - 7% 1% 100% - - - 3% 1% 14%

Other 15% 22% - 11% 26% 36% 39% 21% 60% - - - 16% 10% - 0% 0% - 75% 91% 100% 29% 41% 53%

Vegetation/Animal - - - - - - - - - - - - - - - 5% 43% - - - - 2% 15% -

Weather/Fire/Earthquake 5% 1% - 2% 6% 36% - - - - - - - - - - - - 25% 9% - 8% 4% -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

SLOVER(12KV) - Customers: 997 102.5 0.3 - 66.0 3.0 2.0 65.0 1.0 2.0 - - 1.0 0.1 0.0 1.0 3.2 0.0 - - - - 3.3 0.0 2.0

3rd Party 28% 25% - - - 50% 97% 99% 100% - - - 100% 100% - - - - - - - 2% 10% -

Equipment Failure 54% 61% - 46% 33% - 3% 1% - - - - - - - 100% 100% - - - - 98% 90% -

Operation 18% 14% - 9% 33% - - - - - - - - - - - - - - - - - - -

Other - - - - - - - - - - - - - - 100% - - - - - - - - 50%

Vegetation/Animal - - - - - 50% - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - 45% 33% - - - - - - 100% - - - - - - - - - - - 50%

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

SPIKE(12KV) - Customers: 1,194 - - 2.0 3.9 0.1 1.0 4.8 0.0 - - - - 348.0 2.4 1.5 34.6 0.1 - - - - 382.6 2.6 1.5

3rd Party - - 50% - - - - - - - - - - - - - - - - - - - - -

Equipment Failure - - - 7% 2% - 100% 100% - - - - 97% 59% 35% 83% 73% - - - - 96% 59% 35%

Operation - - - 93% 98% - - - - - - - - - - 6% 4% - - - - 1% 0% -

Other - - 50% - - - - - - - - - 3% 41% 65% 10% 23% - - - - 4% 40% 65%

Vegetation/Animal - - - - - 100% - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

Reliability Histories for Individual Circuits Serving San Bernardino District 5 - 9 of 12

2016 2017 2018 1st Qtr 2019 2nd Qtr 2019 3rd Qtr 2019 4th Qtr 2019 2019

29

Page 30: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

CircuitHistory10SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI

STOCKCAR(12KV) - Customers: 2,447 49.7 0.1 1.9 26.2 1.0 1.0 22.5 0.1 1.0 - - - 38.3 1.0 3.2 - - 1.0 6.1 0.4 1.0 44.5 1.4 5.2

3rd Party 79% 73% 100% - - - - - - - - - 19% 38% 31% - - - - - - 16% 27% 19%

Equipment Failure 4% 10% - 40% 2% - 90% 68% - - - - 76% 61% 38% - - - - - - 66% 43% 24%

Operation 17% 17% - 60% 98% - - - 100% - - - 5% 1% - - - - 100% 100% 100% 18% 31% 19%

Other - - - - - - 10% 32% - - - - - - 31% - - 100% - - - - - 38%

Vegetation/Animal - - - - - 100% - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

STREAMLINER(12KV) - Customers: 1,099 132.9 1.1 0.8 17.1 1.0 2.0 120.2 1.0 4.0 - - - 6.5 0.1 1.8 - - - - - - 6.5 0.1 1.8

3rd Party 96% 99% 100% 90% 99% 50% 6% 1% 75% - - - 86% 97% 47% - - - - - - 86% 97% 47%

Equipment Failure - - - 10% 1% - 24% 52% 25% - - - - - - - - - - - - - - -

Operation 4% 1% - - - - 67% 44% - - - - - - - - - - - - - - - -

Other - - - - - - - - - - - - 14% 3% 53% - - - - - - 14% 3% 53%

Vegetation/Animal - - - - - 50% 3% 4% - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

SUSAN(12KV) - Customers: 1,464 121.5 1.4 1.9 133.5 1.0 2.4 30.4 1.2 1.2 9.2 0.9 - 8.4 0.6 0.7 - - - - - - 17.6 1.5 0.7

3rd Party 52% 57% 23% 41% 79% 51% - - 82% 100% 100% - - - - - - - - - - 52% 58% -

Equipment Failure 5% 30% 77% 7% 1% - 0% 0% - - - - 30% 1% - - - - - - - 14% 0% -

Operation 43% 13% - 34% 12% 49% - - - - - - - - - - - - - - - - - -

Other - - - - - - 100% 100% 18% - - - 70% 99% 100% - - - - - - 33% 42% 100%

Vegetation/Animal - - - - - - - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - 18% 8% - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

TAMPICO(12KV) - Customers: 964 129.8 1.1 3.1 16.2 0.0 1.0 221.2 1.5 2.8 5.0 0.0 - 14.6 0.1 2.0 - - - 26.4 0.2 - 46.0 0.3 2.0

3rd Party 1% 0% 32% 16% 24% - - - - 100% 100% - - - 50% - - - - - - 11% 3% 50%

Equipment Failure - - - 82% 71% - 53% 11% - - - - - - - - - - 100% 100% - 57% 74% -

Operation 88% 98% - - - - 1% 1% - - - - 100% 100% - - - - - - - 32% 24% -

Other - - 68% 3% 5% 100% 42% 72% 72% - - - - - 50% - - - - - - - - 50%

Vegetation/Animal - - - - - - - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake 11% 2% - - - - 4% 16% 28% - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

Reliability Histories for Individual Circuits Serving San Bernardino District 5 - 10 of 12

2016 2017 2018 1st Qtr 2019 2nd Qtr 2019 3rd Qtr 2019 4th Qtr 2019 2019

30

Page 31: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

CircuitHistory11SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI

TENDER(12KV) - Customers: 1,437 213.1 2.0 1.0 150.4 2.1 3.0 21.5 0.1 - - - - 70.9 1.1 1.0 0.1 0.0 - - - - 71.0 1.1 1.0

3rd Party 42% 49% - - - - 9% 32% - - - - - - - - - - - - - - - -

Equipment Failure - - - 21% 51% 33% 91% 68% - - - - 96% 99% - 100% 100% - - - - 96% 99% -

Operation 0% 0% - 3% 1% - - - - - - - 4% 1% 4% - - - - - - 4% 1% 4%

Other - - 100% - - 33% - - - - - - - - 96% - - - - - - - - 96%

Vegetation/Animal - - - - - 33% - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake 58% 51% - 76% 48% - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

TURNTABLE(12KV) - Customers: 749 593.3 2.9 1.0 17.4 0.1 1.0 196.6 0.3 2.5 - - - 28.6 0.8 1.2 - - - 57.3 2.0 1.8 85.9 2.8 3.0

3rd Party 22% 6% - - - - 100% 99% 100% - - - - - - - - - 84% 50% 44% 56% 36% 27%

Equipment Failure 2% 35% 100% 98% 90% - 0% 1% - - - - 100% 100% 17% - - - 16% 50% 56% 44% 64% 40%

Operation 4% 2% - 2% 10% - - - - - - - - - - - - - - - - - - -

Other 52% 24% - - - - - - - - - - - - 83% - - - - - - - - 33%

Vegetation/Animal - - - - - 100% - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake 20% 34% 0% - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

VERDEMONT(33KV) - Customers: 11 5254.6 1.6 1.6 1037.5 4.2 2.6 195.4 1.2 4.2 - - - 9.5 1.2 3.0 639.0 1.6 - - - 1.0 648.5 2.8 4.0

3rd Party 7% 88% 25% 34% 33% 23% 92% 17% 29% - - - - - - - - - - - - - - -

Equipment Failure - - - 20% 10% 38% - - - - - - 73% 83% 67% 77% 63% - - - - 77% 71% 50%

Operation - - - 4% 10% - - - - - - - 27% 17% - 23% 38% - - - - 23% 29% -

Other - - 75% 4% 24% 38% 8% 83% 71% - - - - - - - - - - - 100% - - 25%

Vegetation/Animal - - - - - - - - - - - - - - 33% - - - - - - - - 25%

Weather/Fire/Earthquake 93% 13% - 38% 24% - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

WARM CREEK(12KV) - Customers: 521 - - - 518.3 6.4 3.5 18.5 0.1 - 5.4 0.0 - - - - - - - 11.7 0.0 1.0 17.1 0.1 1.0

3rd Party - - - 22% 16% - - - - - - - - - - - - - 78% 83% 100% 53% 37% 100%

Equipment Failure - - - 63% 66% 61% - - - - - - - - - - - - 22% 17% - 15% 7% -

Operation - - - - - 28% 100% 100% - 100% 100% - - - - - - - - - - 32% 56% -

Other - - - - - - - - - - - - - - - - - - - - - - - -

Vegetation/Animal - - - - - - - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - 15% 18% 11% - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

Reliability Histories for Individual Circuits Serving San Bernardino District 5 - 11 of 12

2016 2017 2018 1st Qtr 2019 2nd Qtr 2019 3rd Qtr 2019 4th Qtr 2019 2019

31

Page 32: PowerPoint Presentation - SCE...Utilities Commission (CPUC) and the Federal Energy Regulatory Commission (FERC) •50,000 square miles of SCE service area across Central, Coastal,

CircuitHistory12SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI SAIDI SAIFI MAIFI

WATERMAN(12KV) - Customers: 1,169 82.1 0.6 1.4 48.9 0.2 - 191.5 1.7 1.5 0.3 0.0 - 16.6 0.0 1.0 - - - - - - 16.9 0.0 1.0

3rd Party - - - - - - 91% 95% 100% - - - - - - - - - - - - - - -

Equipment Failure 89% 84% 33% 76% 64% - 9% 5% - 100% 100% - 100% 100% 1% - - - - - - 100% 100% 1%

Operation - - - 24% 36% - - - - - - - - - - - - - - - - - - -

Other 11% 16% - - - - - - - - - - - - - - - - - - - - - -

Vegetation/Animal - - 67% - - - - - - - - - - - 99% - - - - - - - - 99%

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

WHITLOCK(4.16KV) - Customers: 409 97.9 0.3 1.0 476.4 2.0 1.0 - - - - - - - - - - - - 204.4 1.0 - 204.4 1.0 -

3rd Party - - - - - - - - - - - - - - - - - - - - - - - -

Equipment Failure - - - 23% 51% - - - - - - - - - - - - - - - - - - -

Operation 100% 100% 100% - - - - - - - - - - - - - - - 100% 100% - 100% 100% -

Other - - - - - 100% - - - - - - - - - - - - - - - - - -

Vegetation/Animal - - - - - - - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - 77% 49% - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

WIGWAG(12KV) - Customers: 2,144 0.9 0.0 - 82.2 1.0 3.0 62.7 1.0 - - - - 12.1 0.0 1.0 - - - - - - 12.1 0.0 1.0

3rd Party - - - 96% 98% - 100% 100% - - - - - - - - - - - - - - - -

Equipment Failure - - - - - - - - - - - - 100% 100% - - - - - - - 100% 100% -

Operation 100% 100% - 4% 2% - - - - - - - - - - - - - - - - - - -

Other - - - - - 67% - - - - - - - - 100% - - - - - - - - 100%

Vegetation/Animal - - - - - 33% - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

ZAPATA(12KV) - Customers: 1,089 79.0 0.1 3.0 133.8 1.3 - 61.2 1.1 0.0 - - - - - - 70.3 1.2 - - - - 70.3 1.2 -

3rd Party - - - - - - 36% 5% 100% - - - - - - 62% 82% - - - - 62% 82% -

Equipment Failure 100% 100% 33% - - - 5% 3% - - - - - - - - - - - - - - - -

Operation - - - 100% 100% - 59% 92% - - - - - - - 38% 18% - - - - 38% 18% -

Other - - 33% - - - - - - - - - - - - - - - - - - - - -

Vegetation/Animal - - 33% - - - - - - - - - - - - - - - - - - - - -

Weather/Fire/Earthquake - - - - - - - - - - - - - - - - - - - - - - - -

PSPS - - - - - - - - - - - - - - - - - - - - - - - -

Reliability Histories for Individual Circuits Serving San Bernardino District 5 - 12 of 12

2016 2017 2018 1st Qtr 2019 2nd Qtr 2019 3rd Qtr 2019 4th Qtr 2019 2019

32