Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 1 of 59
REPLIES TO THE QUERIES OF BIDDERS – 2X55 MW COAL FIRED POWER PROJECT AT SUNDER INDUSTRIAL ESTATE LAHORE
Sr. No.
Specification
Volume
Clause No./Section No.
Clause and Reference Deviations /Clarifications PPDCL’s Response
1.GENERAL Layout
1.
Volume IV Drawings in PDF
MMD-345023-C-DR-02-00-0003-Borehole Location Layout.pdf
Borehole Location Layout The coordinates system in drawing Borehole Location Layout is inconsistent with the coordinates system in drawing PLOT PLAN. Please check and provide the correct coordinates of the boreholes.
Borehole locations are shown for providing preliminary information on soil of the project site. Coordinates of bore hole location and grid line of plot plan cannot be correlated.
Volume IV Drawings in PDF
MMD-320682-Z-DR-02-00-0002.pdf
PLOT PLAN
2. Volume IV Drawings in PDF
MMD-320682-Z-DR-02-00-0002.pdf
PLOT PLAN 1. The coordinates of power plant boundary should be some mistake. For example, The coordinate of the power plant northwest corner is N 346346.461, but the coordinate adjacent grid line is N 3463500. Please check and provide the correct coordinates of power plant boundary. 2. Please provide the AutoCAD format of the drawing.
Coordinates of grid line under revision. The soft copy of Drawing in AutoCAD format will be provided.
2 .MECHANICAL
3. Volume II Part A P1 1.4 Climate The major Meteorological data from the nearest meteorological station is as follows:
As bidder understanding, meteorological data in the table 1.1 is not for guarantee condition. Please provide the ambient parameter (e.g. temperature (dry bulb), relative humidity and barometric pressure) for
Ambient air temperature of 27 °C & RH of 60% has been specified for guarantee of Boiler efficiency and auxiliary power condition. Wet bulb
temperature of 28 ℃ shall be considered for design and guarantee of cooling water system
![Page 2: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/2.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 2 of 59
performance guarantee condition. and turbine cycle heat rate.
4. Volume II Part A P1 Part B P5&6
1.4 Climate The major Meteorological data from the nearest meteorological station is as follows: Monthly Mean Maximum Temperature 41.8 °C Monthly Mean Minimum Temperature 6.9 °C 1.22 Draft fan – FD Fan Design
basis Fan inlet air temp 50°C … 1.24 Primary Air Fan Fan inlet air temp 50°C …
The inlet air temperature of FD fan and PA fan should equal the environment temperature. It is changed with the environment temperature.
Please comply with temperature specified for FD and PA fan design.
5. Volume II Part B Section B1 P1 Part B Section B P1
Steam pressure at SH outlet bar absolute (Tentative) 110 bar Steam generators will be of semi outdoor type, sub critical pressure, natural circulation, non-reheat and dry bottom type Circulating Fluidized Bed Combustion (CFBC)
110bar is high pressure parameter not subcritical, they are contradictory. Bidder recommends high pressure parameter steam generator for this project.
110 bar (tentative) has been specified. This value is aligned with sub-critical parameter. Bidder may quote higher parameter if it proven for this capacity of Boiler and Turbine offered by the Bidder.
![Page 3: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/3.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 3 of 59
units designed to burn 100% imported coal and 100% local coal.
6. Volume II Part B Section B1 P6
1.26 Steam Coil Air Pre-Heaters (SCAPH)
SCAPH outlet air temperature with maximum air flow corresponding to
oil firing condition 100 ℃
SCAPH outlet air temperature is
determined by manufacture
requirement. Bidder will design
according to the manufacture
requirement.
Please follow the specification requirement. Bidder may follow manufacturer’s requirement if it is more stringent than specification requirement
7. Volume II Part B Section B1 P7
1.32 Seal Air Fans Number per SG unit 2 x 100%
Seal air fan is not required for
circulating fluidized bed unit, and
the sealing air will be provided from
primary air system.
Bidder’s proposal shall be evaluated during detailed engineering.
8. Volume II Part B Section B1 P11
Condenser design pressure 0.1 Kg/cm2 (abs) at 33 deg. C cooling water temperature
As bidder understanding, 0.1Kg/cm2 (abs) is applied to physical design of the condenser, but not back pressure for performance guarantee case. Please kindly confirm that.
Condenser pressure of 0.1Kg/cm2 (abs) at at 33 deg. C cooling water temperature shall be guaranteed by the bidders
9. Volume II Part B Section B1 P13
6 Condenser Design cold water temperature 33 deg C when CT is designed for 32 deg. C outlet temperature
The condenser inlet CW temperature shall be the same as CT outlet CW temperature which is 32 deg. C.
Bidder to comply with specification requirement Margin has been considered in CW temperature at condenser inlet and cooling water temperature at cooling tower outlet to take care of temperature rise in CW pump and degradation in performance with time.
10. Volume II Part B Section B1 P14
6 Condenser Tube thickness 22 BWG
Tube thickness shall as per OEM optimization.
Bidder may offer higher thickness
11. Volume II Part B Section B1 P14
6 Condenser Corrosion allowance in water boxes and tube plates minimum 3.2 mm
Corrosion allowance shall as per OEM standardized proven design.
Bidder may offer higher thickness
![Page 4: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/4.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 4 of 59
12. Volume II Part B Section B1 P14
6 Condenser Minimum CW temperature rise across condenser at condenser design condition 10 deg.C
This requirement is not reasonable, since Owner has already asked condenser design pressure of 0.1kg/cm2(a) at 33 deg.C, if CW temperature rise is more than 10deg.C, the condenser TTD will be less than 2.4 deg.C which does not comply with HEI requirement. Thus, CW temperature rise will as per Bidder optimization/design.
Bidder to comply with specification requirement. Bidder may bring out the contradiction with HEI requirement in its proposal.
13. Volume II Part B Section B1 P14
7 Condenser Air Evacuation system Design of air removal section to cool the air and vapour mixture corresponding to 25.4mm Hg (abs) 4.17°C below saturation temperature
Shall as per HEI. Bidder to comply with the specification requirement. Bidder may bring out the HEI requirement in their proposal
14. Volume II Part B Section B1 P15
9 Heat Exchangers type (HP and LP Heaters) Material of tube stainless steel type 316
Material of tube will be TP304 or equivalent as per Bidder optimization.
Bidder to comply with the specification requirement.
15. Volume II Part B Section B1 P15
10 Feed Water Heating Plant (HP and LP Heaters) Corrosion allowance on each heater shell and water box 3.2 mm
Corrosion allowance shall as per OEM standardized proven design and HEI.
Bidder to comply with the specification requirement.
16. Volume II Part B Section B1 P18
4.1 Velocity Limits for calculating the inside pipe diameter are as follows:
Fluid velocity shall as per Bidder optimization/design.
Bidder to comply with the specification requirement.
17. Volume II Part B Section B1 P41
10.2 Self-Cleaning Strainers 4 Material Of Construction Strainer screen / section SS 316. Shaft SS 316. Supporting cage SS 316. Differential Measuring System SS 316. Flushing / Backwashing Unit SS 316
Material shall be TP304 or as per Bidder optimization/design.
Bidder to comply with the specification requirement.
![Page 5: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/5.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 5 of 59
Any other internal hardwares / pipes, etc. SS 316
18. Volume II Part B Section B1 P42
10.3 Induced Draft Cooling Tower Cooling range (
oC) 10
oC
The CT cooling range shall match CW temperature rise which shall as per Bidder optimization/design.
Bidder to comply with the specification requirement.
19. Volume II Part B Section B1 P42
Splash Fill PVC Please confirm is film fill can be used or not.
Bidder to comply with the specification requirement.
20. Volume II Part B Section B1 P43
10.4 DMCW Pumps for both units Operating Range 40% to 120 % 0f rated flow
DMCW pump flow is not regulable. Flow control has not been specified but pump characteristic should meet the specification requirement. Flow may vary depending on number of coolers in service and flow in coolers.
21. Volume II Part B Section B1 P44
10.5 Plate Type Heat Exchangers Heat Transfer plate SS-AISI-316
Heat transfer plate shall be TP304 or as per Bidder optimization/design.
Bidder to comply with the specification requirement.
22. Volume II Part B Section B1 P45
11.1 Specification Requirement Schedule for Plant Water System 1 Raw Water Intake system Capacity M3/hr 435 or process requirement whichever is higher
Capacity shall as per Bidder design. Bidder to comply with the specification requirement.
23. Volume II Part B Section B1 P45
11.1 Specification Requirement Schedule for Plant Water System 1 Raw Water Intake system Margin in pump flow over continuous requirement 20%
5% flow margin is to be considered; otherwise high margin will make the pump not operate at high efficiency point during Plant normal operation.
Bidder to comply with the specification requirement. Bidder clarification generally applicable to continuously running pumps without limited storage capacity in the system. But the explanation given by bidder is not applicable for River water intake system in view of storage capacity available in Raw water reservoir.
![Page 6: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/6.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 6 of 59
24. Volume II Part B Section B1 P45
11.1 Specification Requirement Schedule for Plant Water System 1 Raw Water Intake system Impeller and shaft SS316 Fastener SS316
Material shall be TP304 or as per Bidder optimization/design.
Bidder to comply with the specification requirement.
25. Volume II Part B Section B1 P45
4 In plant Raw Water Pumps Rated pump head m As per process requirement with 10% margin.
5% head margin is to be considered; otherwise high margin will make the pump not operate at high efficiency point during Plant normal operation.
Bidder to comply with the specification requirement.
26. Volume II Part B Section B1 P46
Material of clarifier shaft and Paddle, Flash mixer agitator SS316
Material shall as per Bidder optimization/design.
Bidder to comply with the specification requirement.
27. Volume II Part B Section B1 P47
12 Material of Construction of Pumps handling Clarified, Filtered, UF, Potable and Service Water Impeller SS316 Shaft SS316 / SS410
Material shall be TP304 or as per Bidder optimization/design.
Bidder to comply with the specification requirement.
28. Volume II Part B- Section B-Mech Specification
5.6.1.2 Unit Gross Heat Rate Unit Gross Heat rate in KJ/KWhr under rated steam conditions at 0.1 Kg/cm2 (abs) design condenser pressure with zero make up at 100% TMCR, 80% TMCR and 60% TMCR unit load while firing performance coal.
Since there is already guarantee for Unit Net Heat Rate (weighted), Unit Gross Heat Rate for each case shall not be guaranteed otherwise there will be reduplicative guarantee.
Incorrect section of specification has been referred. It seems, clarification refers to Volume-II Part-A. Please refer to clause 5.3 of Volume-II Part-A. Net heat rate is being computed from gross heat rate and hence gross heat rate shall be demonstrated and net heat rate shall be calculated from the demonstrated Gross Heat Rate.
29. Volume II-Part B- Section B-Mech Specification
6.1 system description
The coal shall be transported to the project site through trucks.
Please provide the truck transport distance.
Transport of coal to the project site is responsibility of Owner.
30. Volume II-Part B- Section B-Mech
6.1.1 Truck Unloading Facilities
Capacity of each truck will be 50 Tonnes
Does the truck is Dump truck or not? Please provide the truck shape parameter, including the truck width,
Truck tippler design should take care of various types of truck available in the market up to 50 T capacity
![Page 7: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/7.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 7 of 59
Specification
length, height during normal mode and unloading mode.
31. Volume II-Part B- Section B-Mech Specification
6.1 system description
Coal flow diagram has been depicted in Drawing no MMD-345023-M-DR-02-00-012
Please provide the coal flow diagram which in drawing NO. MMD-345023-M-DR-02-00-012
Already provided to prequalified bidders.
32. Volume II-Part B- Section B-Mech Specification
6.1.2 Conveying, Crushing and Bunker Feeding System
The coal from surge hoppers SH-1/2 is fed into the crushers CR-1/ 2 through vibrating feeder 2A/B .Crushed Coal from crushers is fed to screens SCR-1/2 in screen house to screen out (-) 6 mm coal present in the feed. The (+) 6 mm coal from the screens will be recycled and will be fed to the crushers CR-1/ 2 by conveyors BCN-3A/3B for crushing it down to (-) 6 mm size.
We suggest canceling the surge hoppers, to make the crusher house elevation lower, and set the crushers and screens capacity larger than the conveyor belt system capacity. Please confirm. And please provide the type of conveyors BCN-3A/3B.
Bidder proposal shall be evaluated during detailed engineering
33. Volume II-Part B- Section B-Mech Specification
6.1.2 Conveying, Crushing and Bunker Feeding System
The motor operated travelling tripper TR-1/2 provided on conveyors BCN-5A/5B will fill the coal into the bunkers.
Considering the economy and easy operation, Bidder recommended using plough unloaded to replace the tripper conveyors. Up to now, the information about plough unloader we get from the running power plant shows that, the plough unloader is reliable and easily operated / maintained. please confirm
Bidder to comply with the specification requirement. However bidder may bring it as deviation in the proposal with price of withdrawal for this deviation.
34. Volume II-Part B- Section B-Mech Specification
6.3.1 Mechanical Equipment / System
Deck plate of minimum 3.15 mm thickness shall be provided for full length of all conveyors.
Head cleaner device and return belt cleaner will be provided to avoid the spillages go into the tail pulley and take-up pulley, so we suggest canceling the full length deck plate, or provide the deck plate under the loading area only. Please confirm.
Bidder to comply with the specification requirement.
![Page 8: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/8.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 8 of 59
35. Volume II-Part B- Section B-Mech Specification Volume 1 Contractual 1
6.1.3 Coal Feed from Stockyard 6.3.1 Mechanical Equipment / System 2 Project Description
The coal in two stockyard shall have adequate storage for at least 30days coal consumption The capacity of coal stockyard shall be adequate for storing coal for 20 days maximum continuous requirement (MCR). Coal storage 45 days.
These three descriptions are different, please indicate which is correct.
Please follow the requirement given in clause 6.1.3 of Volume II-Part B- Section B-Mech Specification
36. Volume II-Part B- Section B-Mech Specification
7.1 System Description
The lime of maximum Lump Size (-) 25 mm shall be transported to the project site through trucks.
Does the truck is Dump truck or not? Please provide the truck shape parameter, including the truck width, length, height during normal mode and unloading mode.
37. Volume II-Part B- Section B-Mech Specification
7.1 System Description
Lime flow diagram has been depicted in drawing no MMD-345023-M-DR-02-00-015.
Please provide the limestone flow diagram which in drawing NO. MMD-345023-M-DR-02-00-015.
This drawing has been provided to prequalified bidder
38. Volume
II-Part B-
Section
B-Mech
Specificati
on
9.1.1 Bed Ash
Handling
System
The silo shall be of RCC type
construction
Bidder recommended use steel
structure silo to instead of RCC type
construction.
For the bed ash is only a little, the
steel structure is suitable for bed
ash storage.
Bidder may provide steel silo for
bed ash.
![Page 9: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/9.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 9 of 59
39. Volume II-
Part A-
General
Technical
Requirem
ent
Sundar
5.6.2.2 Steam
Generator
Efficiency
Efficiency of the steam generator at
100% TMCR, 80% TMCR and 60%
TMCR at 27deg C ambient
temperature and 60% RH while
firing the performance coal at rated
steam parameters, and rated
excess air.
The steam generator efficiency of
60% TMCR cannot guaranteed by
OEM, so bidder can guaranteed for
100% TMCR, 80% TMCR only.
Bidder to comply with specification requirement.
40. Volume
II-Part B-
Section
B-Mech
Specificati
on
1.3.15 Auxiliary
Steam System To meet the continuous and startup
auxiliary steam……
Please confirm whether new
auxiliary boiler is required or not,
Please confirm.
If required please confirm the fuel of
auxiliary boiler.
Auxiliary boiler shall be provided if it
is required for commissioning of
boilers and startup of boiler after
long shutdown. HSD shall be used
as fuel if Auxiliary Boiler is provided
41. Volume
II-Part B-
Section
B-Mech
Specificati
on
1.3.17 Draft
Plant
b) Induced Draft Fans
Two ID fans (2 x 60% BMCR) shall
be provided and they shall be of the
radial backward curved type with
renewable liners and variable
frequency drive.
The ID fan is radial type with guide
vane control and considering the
economy and easy operation,
Bidder not recommended use
variable frequency drive, please
confirm
Bidder to comply with specification
requirement
42. Volume
II-Part B-
Section
B-Mech
Specificati
on
1.3.20.1 Coal
bunkers The effective bunker live storage
capacity for each boiler shall give
16 hours operation of the boiler at
BMCR, taking 15% filling factor
considering Coal as worst fuel firing.
Bidder recommended the effective
storage capacity of bunker is 12
hours operation of the boiler at
BMCR with design coal, please
confirm.
Bidder to comply with specification
requirement.
43. Volume
II-Part B-
Section
1.1 Type of
Steam
Generator
Steam generators will be of semi
outdoor type, sub critical pressure,
natural circulation, and non-reheat
Please confirm the steam generator
is out door type or semi outdoor
type.
Steam generators will be of semi
outdoor type
![Page 10: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/10.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 10 of 59
B-Mech
Specificati
on
and dry bottom type Circulating
Fluidized Bed Combustion (CFBC)
units designed to burn 100%
imported coal and 100% local coal.
Provision to fire HSD during start-up
and stabilization will also be made.
The steam generators shall be top
supported, Circulating Fluidized
Bed Combustion (CFBC), balanced
draft, outdoor type with all
auxiliaries, integral piping and
elevators.
44. Volume
II-Part B-
Section
B-Mech
Specificati
on
9.1.1 Bed Ash
Handling
System
The bed ash collected in the
Denseveyor shall be conveyed to
bed ash silo through MS pipes by
pressure conveying.
In our experience, Mechanical
transporting system is better than
pneumatic system for bottom ash
conveying.
We advise using bucket-chain
conveyer and bucket elevator
convey and lift the bottom ash into
the bottom ash silo.
Bidder to comply with specification
requirement as mechanical
conveying will create dusty
environment. However bidder may
bring this proposal as deviation with
price of withdrawal for this
deviation.
45. Volume
II-Part B-
Section
B-Mech
Specificati
on
9.1.3 HCSD
Disposal
System
There is a large number of calcium
oxide (CaO) in the ash of CFBC
boiler, when meeting water, the
ash will harden quickly, stick in the
pipeline. So the HCSD system is
not suitable for CFBC boiler ash.
Bidder to comply with specification
requirement. However bidder may
bring this proposal as deviation with
price of withdrawal for this
deviation.
Decision shall be taken after
discussion with all the Bidders
![Page 11: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/11.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 11 of 59
We advise that Cancel HCSD
system, the ash from fly ash silo
and bottom ash silo will be
transported to ash disposal area by
truck.
during post bid discussion.
46. Volume II-Part B- Section B-Mech Specification
7.1 System Description
Size above 0.25mm after separating from Separators will be fed again to Mills by Screw conveyors SC-1/2 by further crushing to size below 0.25 mm. Lime size below 0.25 mm will be fed to Product hoppers-1/2.
Bidder will set the limestone mill outlet size as the requirement of boiler manufacturer. Please confirm.
Boiler manufacturer’s requirement shall be brought out in the proposal. Decision shall be taken in post bid discussion.
47. Volume II-Part B- Section B-Mech Specification
6.1.2 Conveying, Crushing and Bunker Feeding System
The (+) 6 mm coal from the screens will be recycled and will be fed to the crushers CR-1/ 2 by conveyors BCN-3A/3B for crushing it down to (-) 6 mm size.
Bidder will set the coal crusher and screen outlet size as the requirement of boiler manufacturer. Please confirm.
Boiler manufacturer’s requirement shall be brought out in the proposal. Decision shall be taken in post bid discussion.
48. Volume II Part B Section B1 P5
Margin over 100% BMCR pressure requirement 44%
According to relevant standard and project experience, the margin with 20% is recommended by bidder.
Bidder to comply with specification requirement.
49. Volume II Part B Section B1 P2 Part B Section B P19
1.8 Combustor … In bed Sulphur Capture (for range of coal) 90% minimum Crushed Lime stone storage bunker of 16 hrs storage capacity at 100% BMCR for the range of coal specified along with feeding arrangement to each boiler considering at least 95% Sulphur capture for the range of coal specified and considering highest sulphur content in coal with redundancy in feeding system.
As bidder understanding, sulphur capture efficiency is not key point. Bidder will meet the environmental requirements of owner.
Sulfur capture efficiency, lime stone utilization, and SO2 emission for each type of coal specified shall be brought out in the Proposal.
![Page 12: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/12.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 12 of 59
3. WATER SUPPLY & CHEMICAL
50. Volume II Part A- General Technical Requirement Sundar
1.12 Raw Water Source
Plant water requirement shall be met form the Kahna Minor that flows in front and parallel to the plant site at a distance of about 20m. Besides annual maintenance closures of Kahna Minor, the extended/ unforeseen closures of the canal are expected during floods in respective rivers during monsoon season to protect the canal from bank breaches/ overflows/ other possible damages etc. To meet the raw water requirement during canal closure a backup arrangement shall be made for underground water at Kahna Minor canal bank by ins telling deep bore well pumps.
As there is not enough hydrogeololgy information about the canal, design scheme is based on that the water intake and discharge will not influence the water quality and hydrologic condition of canal. After the hydrogeololgy information about the canal received, the design base on it will be updated with cost. Waste water after treatment from the plant will be discharged into the canal during drought period of canal, assuming minimum dilution 1:10 ratio (one cubic meter treated water have 10 cubic meter canal water). Please kindly confirm if there is existing deep well which can be used for the project. And provide the data (capacity, depth, diameter, influence radius, quantity, location, etc..) about the deep well.
No cost update is permitted after submission of Bid. Bidder may visit the canal and satisfy itself regarding the design requirement. All study required for the design is in the scope of Bidder. Waste water shall not be discharged to canal. Please comply with the specification requirement regarding discharge of waste water. Bore well as specified in Clause 11.1.1, Volume II Part B is in the scope of Bidder. All study required for the design is in the scope of Bidder.
51. Volume II Part A- General Technical Requirement Sundar
3.2.1.9 Water System
Raw Water reservoir for 20 days water storage
Water reservoir for 20 days water storage will be really huge, please give the explanation about the storage period design.
Bidder to comply with specification requirement. Adequate storage space has been identified in the Plot Plan to cater this requirement.
52. Volume II Part A- General Technical Requirement
5.6.12 DM water consumption
Make-up water shall be evaluated based on actual DM water make-up required for the station for 15 days while maintaining the boiler steam quality at recommended levels. Percentage of DM water
The quality of DM makeup water cannot be guaranteed for 15 days. DM water storage will be designed to satisfy the requirement of water consumption for one maximum boiler start-up, or the 2h~3h steam
Bidder to comply with specification requirement
![Page 13: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/13.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 13 of 59
Sundar Volume II Part B- Section B1 - Mech Technical Specification Schedule
11 Plant Water System
consumption shall be computed based on average percentage of throttle steam flow during the test period of 15 days. For the purpose of tests unit load shall be maintained between 60% and 100% of rated values. DM Water Storage Tank No Two (2) Total Storage Capacity 500 m3 or system requirement, whichever is higher.
flow in BMCR.
53. Volume II Part A- General Technical Requirement Sundar Volume II
5.6.1.3 Unit Auxiliary Power Consumption 10.3 Induced Draft Cooling Tower
The auxiliary power consumption for all the equipment and system covered under the scope of this contract that are required for continuous unit operation a t 100% TMCR, 80% TMCR, and 60% TMCR load under rated steam conditions at condenser pressure of 0.1 Kg/cm2 (abs) with 0% make-up and with ambient air temperature of 27 °C & RH of 60% while firing performance coal shall be guaranteed.
Design ambient wet bulb temp.(℃) 28.0 (including recirculation allowance - 0.5 )
With ambient air temperature of 27 °C & RH of 60%, the wet bulb temperature is 21.3°C. Please confirm the design wet bulb temperature of cooing tower is 21.3°C or 28°C.
Wet bulb temperature of 28 ℃ shall be considered for design and guarantee of cooling Tower.
![Page 14: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/14.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 14 of 59
Part B- Section B1 - Mech Technical Specification Schedule
54. Volume II Part B - Section A Civil
11.6 C.W. Ducts
CW ducts from C.W. pump house up to condensers and from condensers up to cooling towers shall be steel pipe encased in concrete.
Bidder clarify that CW duct should be steel pipe encased in epoxy resin, which is more corrosive resistant and easier to construct.
Bidder to comply with technical specification. However Bidder may bring this proposal as deviation with price of withdrawal for this deviation.
4.ELECTRICAL
55. Volume II- Part A- General Technical Requirement Sundar
3.2.2.2
Generator Main
Connections
One (1) set of isolated
three-phase bus duct from
generator phase
terminals/phase
segregated terminal adaptor
box to the generator circuit
breaker and from generator
Circuit breaker terminals to
generator transformer terminals
with current transformers.
For a 55MW power unit, SEPCOIII recommend SPB or NSPB for generator main connections
For Generator main connections please use isolated Phase duct.
56. Volume II- Part A- General Technical Requirement Sundar
3.2.2.16 132kV Transmission Line
4.7 km long 132kV double circuit line with ‘RAIL’ conductor. The transmission line shall run from the outdoor gantry of the 132kV Switchyard at the Power Plant to the outdoor gantry of the 132kV switchyard at the Sunder Industrial estate. The length is indicative and the actual route length will be determined by the
Please provide the location of the sunder Industrial estate substation.
It is located within the Sundar Industrial estate.
![Page 15: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/15.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 15 of 59
EPC Contractor through detailed survey.
57. VolumeII-C Electrical Technical Specification
1.4.1 AC Auxiliary Power Distribution System
2 Low Voltage Power 3-Phase,4-wire 50Hz solidly earthed 3 Low Voltage Emergency Power supply 400V(±10%), 3-Phase,3-wire,50Hz, unearthed
SEPCOIII recommend LV emergency power supply 3-ph,4-wires same as LV normal power supply system.
The LV emergency POWER SUPPLY is derived from the emergency DG which is 3 wire source. Hence, all emergency consumers shall be 3 phase, 3 wire
58. VolumeII-C Electrical Technical Specification
3.3.1 Generator Circuit Breaker (GCB)
The circuit breaker (CB) shall be three single-pole, sulphur hexaflouride (SF6) type.
SEPCOIII recommend vacuum type circuit breaker used for GCB.
Bidder bring this proposal as deviation with price of withdrawal for this deviation. Decision shall be taken during post bid discussion.
59. VolumeII-C Electrical Technical Specification
6.3.1 Construction features
The switchgear enclosure shall conform to the degree of protection IP-43.The LV compartment shall conform to IP-52.
The MV switchboard will be located in a clean room, degree of protection IP41 is enough.
Please follow the specified Degrees of protection
60. Volume IV Drawings
3. MMD-345023-C-DR-02-00-0003-Borehole Location Layout
In this drawing, the generator transformers and auxiliary transformers are located in the switchyard, SEPCOIII recommend remove these transformers to the front of steam turbine hall.
Please refer Plot Plan MMD-345023-z-DR-02-00-0002 for location of transformer. Bidder’s proposal meets the requirement.
61. VolumeII-C Electrical Technical Specification
1.4.3 DC supply system
Each set comprises 2x100% batteries, 2 x 100% float-cum-Boost-charger and one DC distribution board.
Further, distribution of DC system
shall be through a number of fuse
boards being distributed in various
areas.
1. Rated 55MW generator is so small, each set comprises 1x100% batteries, 1 x 100% float-cum-Boost-charger and one DC distribution board is safe and reliable enough and this scheme comply with Chinese standards and is successful in many engineering practice. Please confirm. 2. Please confirm that DC breaker boards can be used instead of fuse
1. Please follow the specification requirements. 2. Can be reviewed at detail engineering stage.
![Page 16: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/16.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 16 of 59
boards as alternative.
62. VolumeII-C Electrical Technical Specification
1.7 System Control, Metering and Protection
The protection of the major electrical equipment i.e., generator, generator transformer, unit auxiliary transformers, station auxiliary transformers shall be effected through redundant (2 x 100%) numerical/Microprocessor based Digital Protection Relays.
As per Chinese standards, Protection of rated and above 100MW generator with generator transformer, Protection of rated and above 220kV transformers shall be effected through redundant (2x100%) numerical/Microprocessor based Digital Protection Relays. Please allow us supply 1x100% numerical/microprocessor based digital protection relay for this project 55MW generator, generator transformer, unit auxiliary transformers, station auxiliary transformers. This scheme is safe and reliable enough and successful in many engineering practice. Please confirm.
Please follow the specification requirements.
63. VolumeII-C Electrical Technical Specification
6.3.1.7 Relays Auxiliary transformer buchholz protection and winding temperature initiated trip/alarm shall be interfaced with the numerical protection relays.
Bidder understands this clause requirement is applicable only for oil filled transformers, not for dry transformers. Please confirm.
Dry type Transformers shall not have buchholz relay but are to be provided with Winding temperature detector.
64. VolumeII-C Electrical Technical Specification
6.3.1.20 AC and DC power supply
The following power supplies shall be made available to each switchgear: a. AC supply : 400V Single Feeder b. DC supply : 220V Double Feeder Isolating switch fuse units shall be provided at each switchgear for the incoming supplies, 4-pole, single throw for AC and 2-pole, double throw for DC Moulded case circuit breaker (MCCB) shall also be
For avoiding circular current produce, it is not permit two DC power parallel in DC end distribution board, so please allow us supply single 220V DC supply feeder and use MCCB as an alternative instead of isolating switch fuse unit.
Double throw is specified to not permit DC powers supply paralleling. Hence no change is needed.
![Page 17: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/17.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 17 of 59
accepted as an alternative for AC circuit only.
65. VolumeII-C Electrical Technical Specification
6.3.1.23 Auto bus transfer (ABT) panel
Panel enclosure shall be fabricated from 2 mm thick sheet steel and the same shall be IP 52 protected.
Because ABT panel is placed in a neat room, for make well heat emission, Please allow us use IP32 instead of IP52.
IP42 may be acceptable in Air conditioned room ie Equipment room
66. VolumeII-C Electrical Technical Specification
7.3.1.10 Measuring instruments
For incomers to PCC/PMCCs and Air Circuit Breaker operated outgoing feeders Digital Multi-function meters with communication facility with DDCMIS system shall be provided. Digital Multifunction meters shall be of accuracy class 0.5 for incomers and 1.0 for outgoing feeders. Transducers shall be provided in MCC/ACDBs to display voltage/current/power values on DDCMIS. Transducers shall be DC operated and shall have dual output signal wired to DDCMIS/remote panel.
Since MCC/ACDBs equipment is not as important as PCC/PMCCs, it is not necessary to provide transducers in MCC/ACDBs to display voltage/current/power values on DDCMIS. Please allow us provided Voltage meter, current meter in MCC/ACDBs for local monitoring as per design requirement.
To be decided during detail engineering.
67. VolumeII-C Electrical Technical Specification
7.3.1.21 AC and DC auxiliary power supplies
Necessary 400/230V AC and 220V DC power supplies as required for control and service shall be arranged inside the Switchgear. Single supply shall be arranged for AC supply and duplicate feeder shall be arranged for DC supply.
Please allow us supply single 220V DC supply, reason see item 4.5.
Refer our reply as above at 4.10
68. VolumeII-C Electrical Technical
8.3.1 Construction features
The Back-up Control Panel and the Relay Panels shall be totally enclosed, floor mounted, free-standing, dead-front
Because relay panels is placed in a neat room, for make well heat emission, please allow us use IP32 instead of IP52.
Refer our reply at 4.11
![Page 18: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/18.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 18 of 59
Specification
assemblies conforming to IP-52 degree of protection.
69. VolumeII-C Electrical Technical Specification
8.3.1.13 Relays The design of the integrated generator protection and transformer protection shall be based on numerical techniques. 2x100% integrated numerical protection along with other standard protections shall be provided. Separate numerical relay shall be provided for overall differential protection (87OA) of generator, generator transformer, unit transformers and station transformer.
Please allow us supply 1x100% numerical/microprocessor based digital protection relay for 55MW generator with generator transformer of this project. Reason please see item 4.2
Please follow the specification requirements.
70. VolumeII-C Electrical Technical Specification
9.2.2.3 Float-cum-boost charger (SCR Control)
The triggering of the thyristors is controlled by electronic voltage/current regulator unit which senses feedback from both output voltage and current.
Please allow us use high speed switch IGBT type charger instead of thyristors type charger.
Accepted.
71. 00. Drawing List for 2x55 MW Lahore
MMD-345023-E-DR-02-00-0002 SLD Generator, GT, UT, ST, Metering & Protection MMD-345023-E-DR-02-00-0003 SLD Metering and Protection Scheme for 132kV GIS MMD-345023-E-DR-02-00-0004 Functional Block Diagram of 220V DC Power Supply MMD-345023-CI-DR-02-XX-0002 Single Line Diagram for UPS
These drawing is missing, please offer if any.
Already provided to the prequalified bidders.
72. Volume II Part B Section D
7.1 General Requirements
The Bidder shall furnish separate parallel redundant industrial grade UPS System for DDCMIS Package
Since 55MW is a small generator, for reduce project investment, we suggest single UPS system instead
Please follow the specification requirement
![Page 19: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/19.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 19 of 59
-Technical Specification for C&I
UPS system shall be separate for each unit.
of parallel redundant UPS system. Please confirm.
73. Volume II- Part A- General Technical Requirement Sundar.pdf
Page-27 3.2.2.2 Generator Main Connections One (1) set Generator Circuit Breaker (GCB)
The GCB is not required for this small unit, the startup power will be from the station auxiliary transformer.
Please follow the specification requirement
74. VolumeII-C Electrical Technical Specification-Lahore_Final-31 Jan 2015.pdf
Page-1 1.2 Environmental Conditions
The equipment shall be installed in hot, humid and tropical atmosphere. Unless otherwise specified all electrical equipment shall be designed for continuous operation. Design ambient for all electrical equipment installed indoors, shall be taken as 50
OC.
The maximum temperature is 41.8
OC. So the electrical equipment
installed indoors shall be taken as 40
OC, and 45
OC for outdoor.
Please follow the specification requirement
75. VolumeII-C Electrical Technical Specification-Lahore_Final-31 Jan 2015.pdf
Page-3 1.4.2 Emergency Power supply
System
Diesel Generator (DG) sets shall be
provided to supply emergency
power to the plant.
According to Chinese standards and experience, the DG will only be provided for the unit more than 200MW. There will no DG for this project.
Please follow the specification requirement.
76. VolumeII-C Electrical Technical Specification-Lahore_Final-31 Jan 2015.pdf
Page-179 17.10.3 Dead-end, Angle, three
post, self-supporting with Tension
Strings
Dead-end tower of 132kV will be made of angle and steel pole? The tower section will be triangle? As bellow
Noted.
![Page 20: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/20.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 20 of 59
77. VolumeII-C Electrical Technical Specification-Lahore_Final-31 Jan 2015.pdf
Page-185 17.11.1.1 Shop test on Tower
In addition to material tests and
inspections identified in the
approved QAP, Prototype Towers
shall be full scale load tested (Type
test) at a reputable tower testing
facility. The testing shall be
conducted on the tallest towers of
each type.
This transmission line is only about 4.7 km, and there would be about fifteen towers in total, but there are four tower type. Prototype Towers shall be full scale load tested, so In my opinion there would be four towers which need a full-scale load test according to IEC 60652 Loading Tests on Overhead Line Towers. Please conform.
Noted.
5.C&I
78. Volume II-
Part B
Section D
-
Technical
Specificati
on for
C&I.pdf
4.2.6.2
Redundancy in
Input/output
Modules
(1)Hot standby 100% redundancy
shall be provided for all input/output
cards where inputs/outputs are
used for critical loops like Steam
Drum level control, main steam
temp Control, feed water flow
control, Turbine bypass control,
furnace draft control and
combustion control etc. DO cards
shall be redundant for each HT
(1)The DCS will have redundancy in
following levels – Main processor,
Network interface module,
communication cable and power
supply.
For important signal, the
instruments will be triple or dual
redundancy, and these redundant
signals will be sent to different I/O
modules of DCS. Any one of
Bidder to comply with the tender specification.
![Page 21: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/21.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 21 of 59
drive and critical LT drives, as
applicable to the plant.
(3)Wherever redundant sensors are
employed each sensor shall be
wired to redundant input modules
so that even if one input module
fails,the signal will be available from
the other input module.
redundant I/O module fails, other
signals resident un-failure I/O
module can also be used.
So the redundancy I/O module will
not be provided.
(2) DO cards will not be redundant.
(3)For redundant sensors, each
sensor will be wired to different I/O
modules(one sensor to one input
module, not one sensor to two or
three input module). Even if one
input module fails, other signals will
be available from the other input
module.
79. Volume II-
Part B
Section D
-
Technical
Specificati
on for
C&I.pdf
4.2.17.1
Electro-Hydrauli
c Governor
Control
Alternative – I
Alternative – II
Steam Turbine Generator Control
System will be provided as per
turbine manufacture standard
design.
Bidder’s response not clear with respect to which type of alternative proposed in the specification is applicable for the bidders provided steam turbine.
80. Volume II-
Part B
Section D
-
Technical
4.2.17.2
Turbine
Protection
System (TPS)
(c) ........ The trip coils shall be
monitored continuously for
healthiness and failure shall be
alarmed.
According to the turbine
manufacturer’s design, for the
solenoid valve, the state of the trip
coils cannot be monitored, and the
state of the solenoid valve will be
Bidder to comply with the tender specification however this shall be evaluated during bid evaluation.
![Page 22: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/22.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 22 of 59
Specificati
on for
C&I.pdf
monitored. The power supply status
can be monitored continuously.
81. Volume II-
Part B
Section D
-
Technical
Specificati
on for
C&I.pdf
4.2.17.3
Turbine
Supervisory
System (TSS)
ii) Absolute as well as relative
shaft vibration measurement, of
each bearing in both X and Y
direction (both for Turbine and
Generator bearing).
v) Absolute bearing vibration
measurement of each bearing in
both X and Y directions (both for
turbine and generator bearings).
vi) Stator winding vibration
measurement in radial and
tangential directions.
vii) Axial shift of the rotor, (three
sensors).
As per the turbine manufacture's
design,
ii) the shaft absolute vibration will
not be provided, only provided the
X/Y direction for shaft relative
vibration.
v) Absolute bearing vibration
measurement of each bearing in
vertical directions (both for turbine
and generator bearings).
vi) Stator winding vibration
measurement will not be provided.
vii) Axial shift of the rotor, two or
three sensors, different
manufacture has different design for
the number of axial shift sensor.
Bidder to comply with the tender specification
82. Volume II-
Part B
Section D
-
Technical
Specificati
on for
C&I.pdf
4.2.21 PLC
Configuration
The complete MIS system including
hardware, software, cables etc, as
required shall be provided.
There is not detailed function
description for MIS in owner's
tender document, please provide.
So that bidder can consider this
system.
The functional description of MIS is attached in Annexure I
![Page 23: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/23.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 23 of 59
83. Volume II-
Part B
Section D
-
Technical
Specificati
on for
C&I.pdf
4.5 Vibration
Monitoring for
HT Motors
Vibration monitoring for all HT
motors and its associated pumps,
fans, drives etc. for X, Y and Key
Phasor ......
Vibration monitoring for most HT
motors and its associated pumps,
fans, drives etc, will be provided,
the detailed rotation device list
which will be provided the vibration
measuring will be submitted to
owner for reviewing.
Noted.
84. Volume II-
Part B
Section D
-
Technical
Specificati
on for
C&I.pdf
6.1.3
Termination/Mar
shalling
Cabinets and
Interposing
Relay Panels
Marshalling/Termination cabinets
for the system shall be supplied as
part of DDCMIS/PLC
cabinets/panels for terminating
all cables originating from the
field, MCC/SWGR or any other
source of signal and for
distributing the signals to different
functional panels and cubicles.
I/O cards and terminals will be
integrated in one cabinet, no
dedicated Marshalling/Termination
cabinets to be provided.
Noted.
85. Volume II-
Part B
Section D
-
Technical
Specificati
on for
C&I.pdf
13.5 Ambient Air
Quality
Monitoring
(AAQMS
AAQMS shall include monitoring of
the following pollutant
gases/parameters. However, any
other gases/parameters
recommended by relevant central
and state regulatory agencies shall
also be provided.
Method of measurements and
standards shall be as per pollution
control boards (PCBs) norms.
Please provide the PCB norms for
bidder reference,
As per EIA already supplied to the prequalified bidders as part of feasibility study report.
![Page 24: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/24.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 24 of 59
There shall not be any cost
implication for the same to Owner
86. Volume II-
Part B
Section D
-
Technical
Specificati
on for
C&I.pdf
8.7.1.2 Control
Cables
Solenoid valve Power supply cables
shall be minimum 2.5sq.mm
Solenoid valve Power supply cables
shall be maximum 1.5sq.mm due to
the lower voltage and current.
Bidder to comply with the tender specification
6.CIVIL
87. Volume
II-partB
Section A Civil 2.2.1 b) All foundations shall be
designed in accordance with
provisions of the relevant parts of
the latest revisions of British
Standards.
2.2.3 Pile Foundations: Type and
size of the Pile foundation shall be
based on the recommendation in
detailed geotechnical investigation
report and subsequent established
by initial pile load test at site and
shall be designed as per relevant
part of American and British
standards.
3.6 Basic Design Concepts for
Design of Structural Steel Work:
According to the tender document,
the bidder will make overall design
according to American standard.
Please clarify.
Refer Clause 1.1 – Last Paragraph
![Page 25: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/25.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 25 of 59
Structural steel design shall be
carried out as per structural steel
design code AISC 12th Edition,
BS 5950 and other relevant code
unless noted otherwise.
3.8 Codes & Standards: The
engineering & execution of all Civil,
Structural & Architectural works
shall be based on the latest edition
or revision of the applicable portion
of the following Codes and
Specifications. List of some of
applicable codes and standards are
given in Appendix-A for ready
reference. In case any particular
aspect of work is not covered by
those Standards, other standard
specifications, as may be specified
by the Engineer, shall be followed.
d) American Codes and standards
(ASTM, ACI,)
88. Volume II-partB
Section A Civil 3.4.18 Seismic Load
The project site is in Zone – IIA as
per Pakistan seismic code.
According to the Pakistan seismic code, the earthquake acceleration (PGA) of Zone-IIA is range of 0.08g~0.16g. Please provide the accurate earthquake acceleration (PGA) in this project area.
0.16g shall be used.
![Page 26: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/26.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 26 of 59
89. Please clarify: Can Chinese steel materials be used for steel structures?
Steel materials confirming to British and American code shall be used.
90. Volume
П-Part
B-Section
A Civil
P55-10.3
P59-11.1
Superstructure of Pump house shall
be of RCC with brick cladding./The
superstructure of all pump houses
shall consist of structural steel
frames, side metal sheet cladding
and RCC roof over permanent
shuttering desk sheets.
The documents have a different
description of structure form for the
pump house, whether the
superstructure of pump house can
use steel structure uniformly.
Please follow the stipulation of technical specification
91. Volume П-Part B-Section A Civil
P74-12.3.2.3 The following factors of safety shall be considered for stability of foundation and underground structures. Stability against uplift : 1.25
According to the American or BS code, Ring plate type foundation dose not allow to produce uplift force in the working load combination and allow uplift of ring plate foundation which central angle is less than 30 degrees under the computational load combination. So we think the coefficient of uplift is enough which is 1.2.
Please follow the stipulation of technical specification
92. Volume П-Part B-Section A Civil
P76-14.1.5 These shall be of RCC construction, water tight and above ground.
Please consider using steel water tank.
Please follow the stipulation of technical specification
93. Volume П-Part B-Section A Civil
P78-15.3 The ash dyke height shall be designed and constructed considering design life of power plant as 30 years.
Considering the demand and cost in the prior period, Whether primary dam can design according to the amount of ash storage for 3~5 years? Later can increase the height of dam to meet the future requirement. Please confirm.
Ash dyke height shall be 6 m including 750 mm free board.
94. Volume П-Part B-Section
P79-15.6 No protection is required 1m below FBL for for U/S slope since it will be submerged under water/ash most of
Please consider protection measures of whole U/S slope.
Bidder’s proposal if superior to specification requirement shall be considered.
![Page 27: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/27.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 27 of 59
A Civil the time.
95. Volume II
- Part -
Section A
Civil
17.5 Work Shop It shall be of RCC structure with
steel truss framing with brick
cladding and roof metal decking
with minimum built up of 2000 m2.
We think the area is large. We
suggest area may be 1000 m2 and
it is enough. Please confirm.
Please follow the stipulation of technical specification
96. Volume II - Part B - Section A Civil
17.6 Permanent Stores
Permanent Stores shall be of RCC
framed structure with brick cladding
with minimum built up of 2000 m2.
We think the area is large. We
suggest area may be 1000 m2 and
it is enough. Please confirm.
Please follow the stipulation of technical specification
97. Volume II - Part A-General Technical Requirement Sundar Volume II - Part B - Section A Civil
1.6 Geology Appendix-B. Details of Boreholes
As per soil investigation report of
Sunder, Lahore project site, soil is
having minimum bearing capacity of
around 15.0 T/sq.m at a depth of
3.0 m.
According to the soil profiles, the
value of SPT is larger than 30 at a
depth of 3.0m.Therefore, it can be
envisaged that the bearing capacity
should be more than 15.0 T/sq.m at
3m depth. Please confirm the same
and provide a final value for design.
Refer Appendix B – 2nd last Paragraph - last line.
7.HVAC
98. Volume II- Part A- General Technical Requirement Sundar
19 of 222 1.4 Climate
The major Meteorological data from
the nearest meteorological station is
as follows:
Table 1.1: Meteorological Data
Parameter Values
The data quoted in the left is not
applicable for HVAC system design,
The following data might be
considered to be taken as outdoor
design conditions of HVAC system
during the tendering phase, please
Bidders understanding regarding
use of ASHRE, Metrological data for
HVAC system design is correct. Any
site specific data that is more
stringent than ASHRE Metrological
![Page 28: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/28.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 28 of 59
Monthly Mean Maximum
Temperature °C 41.8
Monthly Mean Minimum
Temperature °C 6.9
Average Annual Rainfall mm 288
Recorded in July 2010
Maximum ambient humidity % 100
Average Relative Humidity over 4
years % 70
confirm
(Quoted from ASHRAE ,
Meteorological data of LAHORE city
which latitude is31.52N and
longitude is 74.40E):
1) Dry-bulb temperature
corresponding to 0.4% /1%annual
cumulative frequency of occurrence
(warm conditions) and mean
coincident wet-bulb temperature;
43.2°C/23.2°C, 41.8°C/23.5°C,
2 ) Dry-bulb temperature
corresponding to 99.6% /99% annual cumulative frequency of occurrence and outdoor design
relative humidity(cold conditions)3.9°C /5.0°C
3) Evaporation wet-bulb temperature corresponding to 0.4% /1%annual cumulative frequency of occurrence and mean coincident
dry-bulb temperature ;42.3°C/34.2°C, 28.7°C/33.6°C,
Please provide extreme (maximum and minimum) temperatures used for HVAC system design.
data shall also be considered.
99. Volume II-Part B- Section
176 of 235 15.1.1.2 Water Cooled Packaged
Units
The ESP cum VFD Control Buildings and fly Ash Equipment Building Control room are far away
Water cooled air-conditioning
system has been considered due to
![Page 29: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/29.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 29 of 59
B-Mech Specification
Water Cooled Packaged Units
(Precision Type) shall be provided
for air conditioning of the ESP cum
VFD Control room in ESP cum VFD
Control Buildings. No separate
cooling tower have been envisaged
for this system. Condenser cooling
water shall be supplied to these
buildings
from the ACW system
Water Cooled Packaged Units
(Precision Type) shall be used for
air conditioning of the Fly Ash
Equipment Building Control room
(One No. common for both the
units). Water for condenser cooling
of such PAC units shall be tapped
from ACW supply system. Hot water
after condenser cooling shall be
returned to the ACW return line for
its cooling in the Main Cooling
Towers of the Power Station.
from central refrigeration station and considering simplifying the system and convenience for operation and maintenance, we consider that air cooled air conditioner shall be provided for these rooms, please confirm.
better efficiency, more stable
cooling in extreme hot condition,
and relatively high heat load in the
ESP cum VFD control room
building.
Bidder to comply with specification
requirement.
100. Volume II-Part B- Section B-Mech Specification
183 of 235 15.4.2 Ventilation System
For all the mechanically ventilated
areas, the supply air fans/louvers,
filters and exhaust air fans/roof
extractors or combination shall be
According to ASHRAE, The dry
ventilation system for each area
shall be sized based on a maximum
room temperature of 6°C
(maximum) above design ambient
Comply with specification
requirement. The requirement is
aligned with high ambient
temperature during summer
![Page 30: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/30.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 30 of 59
provided as required. The
ventilation system for each area
shall be sized based on a maximum
room temperature of 3°C
(maximum) above design
ambient temperature during
summer considering all heat loads
or 10 (ten) air change rate/hour (for
general areas) and 15 (fifteen) air
change rate /hour (for battery
rooms), whichever is higher.
temperature during summer
considering all heat loads or 10
(ten) air change rate/hour (for
general areas) and 15 (fifteen) air
change rate /hour (for battery
rooms), whichever is higher.
The relative humidity is not controlled
months.
101. Volume II-Part B- Section B1 - Mech Technical Specification Schedule
63 of 98 1 Temperature
Dry Bulb Temperature to be
maintained in manned area (24+
1.0) ºC
Dry Bulb Temperature to be
maintained inside the Control rooms
(22+ 1.0) ºC
2 Relative Humidity
Max Relative Humidity As per site
requirement
Min Relative Humidity As per site
requirement
Relative Humidity to be maintained
inside of building 50% ± 5%
According to ASHRAE, center
control room and Electronic
equipment room will be maintained
constant temperature as follows:
Summer Temperature 24±1°C
Winter Temperature 22±1°C, the
humidity shall be maintained at
30%~65%;
Local control rooms, Offices and
personnel areas shall be
maintained at:21~26℃, relative
humidity is no more than 65%;
The battery room shall be
maintained at25℃, relative humidity
is not controlled.
According to electrical code IEC,
indoor condition of switchgear
Bidder understanding regarding use
of ASHRE code for design of
Air-conditioning system is correct.
Further detail shall be considered
during detail engineering.
![Page 31: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/31.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 31 of 59
rooms shall be maintained at no
more than +35℃, relative humidity
is not controlled.
Please confirm.
102. Volume II-Part B- Section B-Mech Specification
182 of 235 15.1.2 Ventilation
Two types of ventilation system
namely evaporative cooling system
(i.e. Air washer system) and dry
mechanical system shall be
employed in various areas of the
plant for the purpose of ventilation.
The areas to be ventilated by
evaporative cooling system are as
follows:
d) Battery Room in main plant
Because the air washer system can't maintain the Battery Room
indoor temperature at 25℃, Battery Room in main plant will be provided with air conditioning system.
Bidder may provide air conditioning
system in Battery Room as per
requirement.
103. Vol 1 Bid Security With reference to "Form of Bid
Security" Item 2 (c) (ii); if bidder
fails to sign 'Contract Agreement"
the bid bond will be forfeited.
Even though we have sincerest
intentions to achieve financial
close within shortest possible time
with the support of the employer; it
will be unjust to make EPC contractor
solely responsible and liable for the
achievement of financial close.
We suggest this time limitation of 120
days for achieving financial
close shall either be removed from
It is a presumption that successful
bidder will sign contract and furnish
performance security within a
prescribed time period after
achievement of financial close which
eventually ensure accomplishment of
commercial operation date of project
during desired time period.
Therefore, clause 19.1 (c) is
imperative to ensure steadfast
adherence with time driven project
milestones including signing of
![Page 32: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/32.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 32 of 59
Further elaborated in ITB clause
44.1, Signing of Contract will be
subject to the achievement of
Financial Close which shall be
within 120 days from the date of
Notification of Award.
ITB 44.1.
contract and submission of
performance security .
The complete text of clause 44.1
addresses the concerns of SEPCO III
regarding financial close within 120
days and responsibility of PPDCL
for financial close. The clause 44.1 is
re-produced for clarity purposes;
Signing of Contract will be
subject to the achievement of
Financial Close which shall be
within 120 days from the date of
Notification of Award. However,
the Employer and Bidder may
mutually agree to extend the
period to achieve Financial Close.
The Employer shall fulfill all the
requirements deemed necessary
to achieve Financial Close as per
the terms and conditions
prescribed by the Financial
Institution. Upon achievement of
Financial
Close, The Employer will send
the Bidder the form of Agreement
![Page 33: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/33.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 33 of 59
incorporating all agreements
between the Parties.
So in the light of clause 44.1 the
following explicit conclusions
can be drawn;
1. Period for financial close can
be extended with mutual
agreement between
successful bidders and
PPDCL
2. Employer (PPDCL) takes
full responsibility to fulfill
all the requirements which
are essential to achieve
financial close such as Letter
of Interest, Generation
License, approval of tariff
from NEPRA, Letter of
Support, Power Purchase
Agreement, Implementation
Agreement and Coal Supply
Agreement.
104. ITB 14.7: The Bidder shall provide a
detailed Financial Model
Which should include the
following:
We understand that preparation of
financial model is generally the
responsibility of the Employer. In the
clarification issued on 22 May 2015,
we were referred to NEPRA's upfront
Contract will be awarded on the basis
of robust evaluation of quoted
CAPEX (EPC cost), Operational &
Maintenance services cost and
offered financing.
![Page 34: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/34.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 34 of 59
a) The underlying Assumptions
and Parameters as per
guidelines issued by
NEPRA.
b) CAPEX
c) Schedule of O&M Costs
d) Debt Amortization
Structure
e) Tariff Model (Levelized)
Projected Financial Statements
tariff
(NEPRA/TRF-ITTC/2013/7195-7197
) for the assumptions. We would like
to highlight here that the minimum
size of plant considered in NEPRA's
UFT is 220MW (gross) and the
assumptions given in UFT are
almost irrelevant to a 2x55MW Plant.
In such conditions it would be almost
impossible to prepare a financial
model without proper inputs and
assumptions. We request you to
kindly share the financial model of the
project with us you have prepared so
we could take further action
accordingly.
The CAPEX, O&M cost and
financing are also integral and
significant components of financial
model. Therefore, PPDCL cannot
share financial model pursuant to
principles of transparency and
relevant regulatory statutes.
However, our financial advisors will
provide guidelines and / or training to
bidders regarding conceptual
modalities of financial model.
Detailed explanation for
SEPCO III ; Financial model is an essential and
imperative document to persuasively
demonstrate the financial viability of
power project before potential
financial institutions / lenders.
Therefore, clause 14.7 on page 9 of
EPC Bidding documents Volume
1-Contractual contains requirement
to submit financial model. The
financial model should contain
following;
a) The underlying Assumptions
and Parameters as per
guidelines issued by
NEPRA.
b) CAPEX
c) Schedule of O&M
d) Debt Amortization Structure
e) A Tariff Model (Levelized)
f) Projected Financial
![Page 35: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/35.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 35 of 59
Statements
Explanation: The Assumptions
and Parameters as per guidelines
issued by NEPRA.
NEPRA explicitly delineate the key
parameters and assumptions in the
upfront tariff for coal fired power
plants vide its letter No.
NEPRA/TRF-ITTC/2013/7195-7197
dated 26 June 2014. The key
parameters and assumptions include;
Plant size
Site of plant
Plant specifications
Auxiliary consumption
Project cost including EPC
cost, Taxes & Duties,
Financing fee and charges,
Insurance during
construction and Interest
during construction
Construction period
Debt Equity ratio
Duration of loan period
Duration of grace period
Interest rates on loans
Duration of Tariff Period
Quality of Imported / Local
![Page 36: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/36.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 36 of 59
Coal; Calorific value of coal
Price of Local and Imported
Coal
Thermal efficiency
Operation and maintenance
cost
Cost of Ash Disposal
Cost of limestone
Exchange rate
Financing fee and charges
Sino sure Fee
Interest during construction
Insurance cost
Interest on working capital
Return on Equity
Explanation: CAPEX (Capital
cost)
The capital cost for coal based power
project includes cost of Main Plant
Equipment System, Boiler including
Auxiliaries, STG .& Auxiliaries,
Balance of Plant Equipment System,
Other Mechanical Equipment
System, Electrical Equipment
System and C&I, Coal Handling
Infrastructure, Engineering & Project
Management, Erection &
Commissioning, land, site
![Page 37: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/37.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 37 of 59
development and civil works,
transportation and evacuation cost up
to inter-connection point.
Explanation: Debt Amortization
Structure
The Debt Amortization Structure
contains information about duration
of repayment period, total amount of
debt, no of loan installments and
Debt Servicing.
Please refer to page 73 of EPC
Bidding document (Volume 1) which
contains prescribed template for debt
amortization structure.
Explanation: Tariff Model
NEPRA designed tariff model for
coal fired power projects vide its
letter No.
NEPRA/TRF-ITTC/2013/7195-7197
dated 26 June 2014. Tariff Model
establishes the selling price of
electricity to power purchaser. Tariff
model comprising of following
components
Energy Purchase Price (Rs/kWh)
Fuel cost component
Cost of Ash disposal
![Page 38: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/38.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 38 of 59
Cost of limestone
Variable Operation &
Maintenance cost (Local &
Foreign)
Capacity Purchase Price
(Rs/kWh)
Fixed Operation &
Maintenance cost (Local &
Foreign)
Insurance cost
Cost of working capital
Return on equity
Interest cost
Principal element of loan
installment
Explanation: Projected
financial statements
Projected financial statements
shall be prepared based on the
tariff model. The projected
financial statements include;
Statement of Financial
Position (Balance sheet)
Statement of Profit and Loss
Account
Statement of Cash Flows
105. Vol-1 Standard form Form of Bank Security (Bank
Guarantee)
On our banks request we would like to
add following as the second last
paragraph of 'Form of Bank Security',
Some banks proposed to add this
provision in the bank guarantee;
however it does not affect the intent of
![Page 39: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/39.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 39 of 59
"Any claim under this guarantee shall
reach our counter by the Expiry Date
after which we shall stand discharged
of our liabilities regardless of whether
this guarantee is returned to us in
original or not"
bank security, hence agreed.
106. Vol-1 Standard form Form of Bid Security Item
2 (b); (2) that in the event of;
(a) The Principal withdraws his
Bid during the period of
validity of Bid, or
(b) The Principal does not
accept the correction of his
Bid Price, pursuant to
Sub--‐ Clause 24.2 of
Instructions to Bidders, or
(c) Failure of the successful
Bidder to(i) furnish the
required Performance
Security, in accordance with
Clause 34 of Instructions to
Bidders,or
(ii) sign the proposed Contract
Agreement, in accordance with
Clause 35 of Instructions to Bidders,
ITB 24 refers to Deadline of
Submission of Bid and sub--‐ clause
24.2 don’t match the context given in
the Form of Bid Security. Please
clarify.
The bid security form included in
bidding document is a sample form
and hence it has to be read as
under:
a) Clause 24.2 is replaced by
Clause 19.6
b) Clause 34 is replaced by
Clause 45.1
c) Clause 35 is replaced by
Clause 44.1
107. Vol-1 Standard form Form of Bid Security Item
2 (c); the sub--‐ clause 2 (c) (i)
(2) that in the event of;
(a) The Principal withdraws his
The ITB clause 34 mentioned doesn't
matches the context. We understand
it should be ITB clause 45 instead of
ITB clause 34; Please confirm.
Repeated. Reply as above.
![Page 40: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/40.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 40 of 59
Bid during the period of
validity of Bid, or
(b) The Principal does not
accept the correction of his
Bid Price, pursuant to
Sub--‐ Clause 24.2 of
Instructions to Bidders, or
Failure of the successful Bidder to
(i) furnish the required Performance
Security, in accordance with Clause
34 of Instructions to Bidders, or (ii)
sign the proposed Contract
Agreement, in accordance with
Clause 35 of Instructions to Bidders,
108. Vol-1 Standard form Form of Bid Security Item 2 (c);
The sub--‐ clause 2 (c) (ii)
(2) that in the event of;
(a) the Principal withdraws his
Bid during the period of validity
of Bid, or
(b) the Principal does not accept
the correction of his Bid Price,
pursuant to
Sub--‐ Clause 24.2 of
Instructions to Bidders, or
(c) failure of the successful
Bidder to
(i) furnish the required
The ITB clause 35 mentioned doesn't
matches the context. We understand
it should be ITB clause 44 instead of
ITB clause 35; Please confirm.
Repeated. Reply as above.
![Page 41: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/41.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 41 of 59
Performance
Security, in accordance with
Clause 34 of Instructions to
Bidders, or
(ii) sign the proposed Contract
Agreement, in accordance with
Clause 35 of Instructions to Bidders,
109. Volume I, ITB, Clause 6. ITB, Clause 6. Qualification of the
Bidder;
Bids submitted by a joint venture of
two or more firms as partners shall
comply with the following
requirements:...
Volume I, ITB, Clause 14.6 Requisite
Financial Documents:
Where the bidder is a Consortium
each member of the Consortium, and
where applicable, their Parent
Companies;
Refer to Pre-Bid Clarification
Meeting, PPDCL to confirm
Consortium with joint and several
arrangement shall also be acceptable.
All the conditions of joint ventures
are applicable to the consortium.
Wherever word consortium appears
in the document, it should be
construed as joint venture.
110. Volume I, ITB, Clause 19. Bid Security;
All bids must be accompanied by a
Bid Security in the amount of USD 5
Million (Five Million) or an
equivalent amount in a freely
convertible currency in the form of a
bank guarantee form or in the form of
deposit at call from a foreign bank
duly counter guaranteed by a
Please clarify and confirm if each
member of JV/ Consortium can
submit separate Bid Bond each
complying to ITB requirements and
total value in the amount of USD 5
Million (Five Million) or an
equivalent amount in a freely
convertible currency .
No Joint Venture/consortium shall be
jointly and severally submit the bid
security
![Page 42: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/42.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 42 of 59
schedule bank of Pakistan of “A”
rating acceptable to Employer in
favour of Employer,
111. Volume I, PART-II:
PARTICULAR
CONDITIONS
OF
CONTRACT;
Clause 5.3 ;
Clause 5.3 ; Priority of Contract
Documents
The text of Sub-Clause 5.3 is deleted
and substituted by the following:
“Unless otherwise provided in the
Contract, the priority of the Contract
Documents shall be as follows:
1) The Contract Agreement (if
completed)
2) The Letter of Acceptance
3) The completed Letters of
Technical and Price Bids
4) Preamble to Conditions of
Contract
5) The Particular Conditions of
Contract
6) The General Conditions of
Contract
7) The priced Schedule of Prices
8) The completed Schedules to Bid
(A to L)
9) The Specifications
10) The Drawings
11) Any other document forming part
of the Contract.
Please clarify priority of following
parts of Volume I of Bidding
Documents;
a. Preamble to Schedule of Prices
b. Schedule of Prices included in
Vlume I & II;
c. Schedule M to Bid Technical
Performance Guarantees in respect of
Net Output and Net Heat Rate
d. Schedule N to Bid Schedule for the
Performance Tests to be Guaranteed
by the Contractor
e. Preamble to The Transaction
These do not have any priority
because of independent status.
![Page 43: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/43.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 43 of 59
112. Volume I, PART-II:
PARTICULAR
CONDITIONS
OF
CONTRACT;
Clause 8.1 ;
Clause 8.1 General Obligations:
The Contractor shall also provide all
necessary Contractor's Equipment,
superintendence, labour and except
as stated herein below, all necessary
facilities therefore including vehicles,
mobile cranes etc for Employer/
Engineer detailed below whose
changes for the period of completion
shall be included in cost of BOD
items
Please provide complete detail
including make, model and
specifications.
As per project requirements.
113. Volume I PART-II:
PARTICULAR
CONDITIONS
OF
CONTRACT;
Clause 16.5 ;
Clause16.5 Training of
Employer's/Consultant’s Staff
Volume II, Part A; General
Specifications: Clause 3.5 Training of
Owner’s Personnel
The exact details, extent and schedule
for training shall be as finalised
during detailed engineering and shall
be subject to Owner’s approval
As no scope and specifications are
included in the Bidding Documents,
we understand that Contractor will
propose based upon recommendation
of OEM / Vendor which will be
carried out immediately before
completion of O & M Contract.
Therefore, please confirm that
Training of Employer's/Consultant’s
Staff shall be part of O & M
Contract.
Not agreed.
114. Volume I PART-II:
PARTICULAR
CONDITIONS
OF
CONTRACT;
Clause 17.5
Clause 17.5 Import Permits and
Licenses & Clause 14.8
Information for Import Permits &
Licenses; “The Contractor shall
submit to the Employer in good time
such details of all Plant and
Please re-confirm that the Employer
shall arrange all Import Permits &
Licenses while Contractor will
provide necessary assistance thereof.
Employer will assist the EPC
contractor to obtain all
permit/licenses.
![Page 44: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/44.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 44 of 59
Contractor's Equipment to be
imported into Pakistan and identify
as to what assistance of the Employer
is required for obtaining by the
Contractor of all necessary import
permits or licenses”.
PART-II: GENERAL CONDITIONS
OF CONTRACT; Clause 17.4
Consents and Wayleaves
The Employer shall in due time
obtain or grant all consents including
permits-to-work, wayleaves and
approvals required for the Works.
115. Volume I PART-II:
PARTICULAR
CONDITIONS
OF
CONTRACT;
Clause 33.1
Clause 33.1 section "Payment
Procedures" point 9 Taxes, Duties
and Contingencies. The Employer
will re-imbrues the taxes and duties
and the contingencies at actual i.e
Import Taxes, Training of
Employer/Engineer Staff for Factory
Acceptance Tests, Escalation,
Variations and/or claims within 28
days after the Certificate of the
Contractor Invoice by the Engineer.
Part II GCC & PCC Clause 1.6
Costs, Overhead Charges and Profit
Whenever by these Conditions the
Contractor is entitled to be paid cost,
Please clarify if Employer shall also
reimburse the following
a. Local Taxation. Levies, Custom
and Import Duties
b. The Vehicles, Mobile Crane etc for
Employer / Engineer
c. Employer's Witnessing of Factory
Acceptance Tests
Please clarify reimbursement at
actual if the Employer shall
reimburse as per Vendors invoice
plus 10% EPC Contractor's admin
Charges;
Not agreed.
![Page 45: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/45.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 45 of 59
such cost shall be properly incurred
and shall include any overhead
charges properly allocable thereto but
not profit unless so stated. Any profit
entitlement shall be added to cost at
the percentage stated in the Preamble.
116. Volume II PART-II: 8
General
Technical
Requirements;
Clause 8.6
Clause 8.6 Owner's Responsibilities;
If requested by the Contractor, the
Owner shall use its best endeavors to
assist the Contractor
in obtaining in a timely and
expeditious manner all permits,
approvals and/or licenses necessary
for the execution of the Contract
from all local, state or national
government authorities or public
service undertakings that such
authorities or undertakings require
the Contractor or Sub-contractors or
the personnel of the Contractor or
Sub-contractors, as the case may be,
to obtain
Please confirm to arrange all all
permits, approvals and/or licenses
necessary for the execution of the
Contract from all local, state or
national government authorities or
public service undertakings.
Employer will assist the EPC
contractor to obtain all
permit/licenses.
117. Volume I Invitation to Bid All bids must be delivered to Chief
Executive Officer at 77 – Shah Jamal
Lahore, Pakistan at or before 11:30
hours, on May 6, 2015.
The submission schedule of
Financial, EPC and O & M Bids is
too tight, Please arrange extension of
the bids submission for 45 days in
order to prepare bids.
The submission schedule has
already been extended.
![Page 46: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/46.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 46 of 59
118. Volume I Preamble to The
Transaction
Clause 4.1.
Clause 4.1.The Sponsor will inject
25% of the total Project Cost as
Equity within the Special Purpose
Vehicle (SPV) created to execute the
operations of Power Project and will
thus be entitled to a fixed return on
Equity based on the rate approved by
NEPRA within the Tariff allowed to
the SPV. These will be carried out in
accordance with the Equity Support
Agreement. The SPV will offer
collateral in the form of project assets
& cash flows and security package
including lA, PPA and FSA).
Please clarify the tariff approved by
NEPRA for this bidding project.
Tariff petition will be filed before
NEPRA upon finalization of EPC bid
price.
119. Volume I Instruction to
Bidder,
Clause 16.3:
Clause 16.3: (ii) Plant and equipment
to be supplied from outside the
Employer's country (Schedules of
Prices: II) shall be quoted on a CIF
port-of entry. In addition, the FOB
price and import duties and taxes
shall also be indicated separately.
Please inform the relevant Pakistan
taxes policy, will this project under
custom duty exemption
Bidders are advised to refer to
Policy for Power Generation
Projects, 2002 for taxes/exemption
and Federal Bureau of Revenue
(FBR).
120. Volume I Schedule of
Prices: Steam Generator (Boiler)
Manufacturers
Foster Wheeler (Finland & USA),
Lurgi Lentjes Energietechnik
(Germany),Babcock & Wilcox
(USA),GEC Alstom Stein Industrie
(Germany), Harbin Boiler (China),
Please claify is it possible to choose the manufacturer which is not mentioned hereby.
Manufactures are indicative in nature.
![Page 47: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/47.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 47 of 59
Dongfang (China), Shanghai (China),
Thermax (India), BHEL (India)
IJT(India)
Steam Turbine Manufacturers
Siemens (India), Mitsubishi (Japan),
Toyo Denki (Japan), NKK (Japan)
BHEL (India), Hangzhou (China),
Nanjing (China)
121. Volume I Particular
conditions of
Contract,
Clause 16.5:
Clause 16.5: The Contractor shall
provide such facilities for the training
of such numbers of Pakistani
engineers, engineering students,
apprentices and trade apprentices on
such sections of the Works at the Site
or on the Contractor’s premises or
Contractor selected plant
manufacturer's premises and
factories, or wherever else work is in
hand, as specified or directed by the
Project Manager/Engineer.
Please clarify “such number”, the
required number of trainees. All expenses are reimbursable at
actual and hence no need to
intimate the numbers of trainee at
this stage.
122. Feasibility
Report
Section 14.1.2.1
Section 14.1.2.1 "30 year' levelised
tariff model for all 8 scenarios is
enclosed as Appendix H"
We could not find the Appendix H,
which is very important for our
financial model, please provide
Already provided.
123. Feasibility
Report
Section 8.3.8
Section 8.3.8 Table 8.10 Landed cost
of Imported Coal by Road "landed
cost with Handling & Transportation
loss 14.317 PKR/TON"
Refer Feasibility Report 8.3.8 Table
8.10 Landed cost of Imported Coal
by Rail
Which Landed cost of Imported Coal
can be applied?
Price is given in PKR and US$.
![Page 48: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/48.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 48 of 59
"landed cost with Handling &
Transportation loss 14.317
PKR/TON"
Refer Feasibility Report 13.2.1
Table 13.8 Coal Price
"landed coal price 132 USD/tonne for
Imported coal
124. Feasibility
Report
Section 13.2.5
Section 13.2.5 O&M expenses
"...73% of which is include under
capacity charges and remaining 23%
is included under energy charges
according to NEPRA guidelines for
upfront tariff determination"
Please check and confirm remaining
23% or remaining 27%
Please share referred "NEPRA
guidelines for upfront tariff
determination".
Available on NEPRA website.
125. Feasibility
Report
Section 13.1.10
Section 13.1.10 Preoperative
expenses "The preoperative expenses
constitutes engineering
administration, project management
and start-up cost before the plant is
put into commercial operation. The
preoperative expenses in estimated at
the rate of 4% of works cost."
Please clarify, if PPDCL Owner has
financial arrangement or its own
equity for this preoperative expenses;
no matter what method to be applied,
the capital cost of the preoperative
expenses whether or not to be
considered in the Capital EPC Cost
part of Financial Model.
As per feasibility study
126. General Water License Please clarify if PPDCL will arrange
and bear the cost of Water License.
whether there is any additional fee or
not for obtaining Water License
Yes
127. Volume I PART-II:
PARTICULAR
CONDITIONS
OF
CONTRACT;
Clause 33.1
Clause 33.1 section "Payment
Procedures" point 9 Taxes, Duties
and Contingencies. The Employer
will re-imburse the taxes and duties
and the contingencies at actual i.e
Import Taxes, Training of
Employer/Engineer Staff for Factory
Acceptance Tests, Escalation,
Variations and/or claims within 28
This detailed terms of reimbursement
of Customs duty and import duties is
not provided, so it is difficult for us
for calculate the capital cost, Please
clarify the Customs duty and import
duties rate and confirm
reimbursement method and schedule.
EPC contractors is required to adhere to the laws of Islamic Republic of Pakistan
![Page 49: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/49.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 49 of 59
days after the Certificate of the
Contractor Invoice by the Engineer.
Part II GCC & PCC Clause 1.6
Costs, Overhead Charges and Profit ;
Whenever by these Conditions the
Contractor is entitled to be paid cost,
such cost shall be properly incurred
and shall include any overhead
charges properly allocable thereto but
not profit unless so stated. Any profit
entitlement shall be added to cost at
the percentage stated in the Preamble.
128. Volume II Part A - Section
A1 Superceded
Schedules;
Schedule 5.9: Duties & Taxes Please clarify if" Volume II - Part
A - Section A1 Superceded
Schedules"
How is the VAT for imported
equipment in Pakistan, any tax
exemption? If no, how is the VAT
tax rate for imported equipment? Pls
kindly collect such info and share
with us.
The bidders have to obtain this
information for preparation of its bid
129. Volume II Part A - Section
A1 Superceded
Schedules;
53.2 Personnel, Taxes and Duties;
The Contractor shall be responsible
for all formalities in connection with
passports, obtaining visas, police
permits, and expenses for
customs duties, if any, related to
personal goods of foreign personnel
Please clarify if considering using visas, which kind of visa is appropriate and enable Chinese supervisors to stay for a longer time.
Visa rules of the respective country may be consulted to.
![Page 50: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/50.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 50 of 59
employed on the Project.
130. Volume I PART-II:
PARTICULAR
CONDITIONS
OF
CONTRACT;
Clause 17.5
Clause 17.5 Import Permits and
Licenses & Clause14.8 Information
for Import Permits & Licenses; “The
Contractor shall submit to the
Employer in good time such details
of all Plant and Contractor's
Equipment to be imported into
Pakistan and identify as to what
assistance of the Employer is
required for obtaining by the
Contractor of all necessary import
permits or licenses”.
PART-II: GENERAL CONDITIONS
OF CONTRACT; Clause 17.4
Consents and Wayleaves
The Employer shall in due time
obtain or grant all consents including
permits-to-work, wayleaves and
approvals required for the Works.
PART-II: 8 General Technical
Requirements; Clause 8.6 Owner's
Responsibilities; If requested by the
Contractor, the Owner shall use its
best endeavours to assist the
As for applying the work permits,
how is the cost and application
regulation.
PPDCL are competent Authority to
arrange all permits and approvals of
relevant Authorities, however, EPC
Contractor will provide necessary
support.
PPDCL will assist the EPC
contractor
![Page 51: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/51.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 51 of 59
Contractor
in obtaining in a timely and
expeditious manner all permits,
approvals and/or licenses necessary
for the execution of the Contract
from all local, state or national
government authorities or public
service undertakings that such
authorities or undertakings require
the Contractor or Sub-contractors or
the personnel of the Contractor or
Sub-contractors, as the case may be,
to obtain
131. Volume II Part A, Technical
Specifications-
General
Specification,
Clause 3.4,
Clause 3.4, Page 39. 11kV Pole
structure from where the EPC
Contractor shall tap 11kV
construction power supply
Whose scope does the transmission
lines of 11kV construction power
source belong to? Normally,
construction power center should
need two separate source providers.
It is the responsibility of EPC contractors
132. Volume II Part A, Technical
Specifications-
General
Specification,
Clause 1.12,
Clause 1.12, Page 3. Plant water
requirement shall be met form the
Kahna Minor that flows in front and
parallel to the plant site at a distance
of about 20m.
Whereas Refer Feasibility Report,
Clause 5.2.1, Page 15. The Bucher
Kahna water distributor has not
enough water capacity and the raw
water can be sourced from the Lahore
Branch Canal.
Please clarify where to obtain raw
water and confirm whether it has
enough water capacity.
Please clarify distances and route
plans of Bucher Kahna water
distributor and Lahore branch canal.
Please clarify and confirm that
PPDCL will obtain right of way.
Raw water source has enough water
capacity. Rout plan for water source
is available in the feasibility study.
Yes PPDCL shall obtain right of
way.
![Page 52: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/52.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 52 of 59
133. Volume II Part B, Section
B, Mechanical
Specifications,
Clause 6.1.3
Clause 6.1.3, Page 80. The coal in
two stockyard shall have adequate
storage for at least 30days coal
consumption. Coal stockpile height
will be of maximum 3m.
Whereas Refer Vol II, Part B, Section
B, Mechanical Specifications, Clause
6.3.1, Page 82. The capacity of coal
stockyard shall be adequate for
storing coal for 20 days maximum
continuous requirement (MCR).
Please confirm the required capacity
of coal stockyard.
Daily requirement of coal
consumption is provided in feasibility
study.
134. Volume II Part B, Section
B, Mechanical
Specifications,
Clause 6.3.1
Clause 6.3.1, Page 81. Deck plate of
minimum 3.15 mm thickness shall be
provided for full length of all
conveyors.
Please define where the deck plate
will be set
It depends upon the design of the
EPC Contractor.
135. General As for the general layout drawing of
the power plant
Please provide a digital soft copy of
topographic map of the plant for the
calculation of earthwork quantity.
Please provide soft copies of Tender
Drawings and Feasibility Report.
Already provided to prequalified
bidders.
136. General As for the flood stage or inland flood
level
Please provide the floodstage or
inland flood level (P=2%) near the
site location.
Bidders are advised to consult
Metrological Department.
137. 132 KV Bus bar As for the 132kV bus bar Please provide short current
impedance of positive sequence and
zero sequence refer to the 132kV
busbar excluding equipment in this
It is provided in the feasibility study.
![Page 53: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/53.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 53 of 59
plant. Short term and long term
situations should both be considered.
(SB=100MVA)
138. Volume I Section 1.
Instructions to
Bidders,
Clause 14.6
Clause 14.6 ; Requisite Financial
Documents:
Latest available management
Accounts to be provided in relation
to:
a) The Bidder itself, and its ultimate
Parent Company;
b) Where the bidder is a Consortium
each member of the Consortium, and
where applicable, their Parent
Companies;
We are unclear what/which file
should be submitted.
Please give us your kind explanation
or suggestion.
The relevant clause 14.6 is explicitly
clear
139. Volume II Part A, Technical
Specifications-G
eneral
Specification
Clause 1.3
, Clause 1.3; There is a natural stream
flowing through the project site (as
shown in plot Plant) which will be
cut off upon acquisition and taking
over of land by PPDCL.
Clause 3.4, Storm water shall be
disposed at the nearest natural drain
identified in the area
drainage study. Diversion drain based
on area drainage study is also in the
scope of
Bidder. Terminal point shall be
existing natural drain points as
Water Course” mentioned on the plot
plan are small natural stream for
irrigation water supply to farms.
PPDCL to clarify if these natural
stream can be used for flood water
drainage.
Clause 1.3 and 3.4 are explicitly
clear.
![Page 54: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/54.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 54 of 59
identified based on area
drainage
140. Volume II Part A, Technical
Specifications-G
eneral
Specification
Clause 1.2
Refer Vol II, Part A, Technical
Specifications-General Specification,
Clause 1.2 Plant Location and Access
to Site
The proposed power plant site is
located south and alongside road on
bank of the Kahna Minor about 2 km
away from the Mull Chowk with
Latitude 31°18' 2.721" N, Longitude
74° 09' 8.465"E.
Plant location is on Mul Talib Sarai
Road which is 8ft wide asphalt road,
PPDCL to clarify if this road can be
used for access to site during
construction stage and thereafter
during O & M Stage.
Yes The EPC bidder may propose a
better option.
141. Volume II Part A, Technical
Specifications-G
eneral
Specification
Clause 1.2 &
Clause 3.4
Clause 1.2 Plant Location and Access
to Site
Clause 3.4 Approach road
M3 motor way located at distance of
about 10 km from the plant
Mul Talib Sarai Road from about 2
kM Mull Chawl to the Project Site
can also be used as permanent access
road for the plant, however if road
width is deemed insufficient due to
regular movement of fuel supply
trucks it has 6ft shoulders on both
sides which can be utilized for
widening of the road.
Coal supply is not the preview of
EPC Contractors.
142. Volume II Part A, Technical
Specifications-G
eneral
Specification,
Clause 3.4
Clause 3.4 Terminal Points , Effluent
Disposal
EPC contractor shall ensure all
effluents are treated and reused after
treatment. EPC
Contractor shall discharge treated
effluent in the nearest drain after
We suggest for effluent and sanitary
drainage from project site to Rohi
Nala which is passing about 1.5km
NW of the plant site. It seemed that
route would mostly be passing
through farm land. However, our
scope will be limited upto project site
Not agreed
![Page 55: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/55.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 55 of 59
doing Area Drainage Study (to be
carried out by EPC contractor).
boundary, while PPDCL to extend
from project site boundary to Rohi
Nala.
143. Volume II Part A, Technical
Specifications-G
eneral
Specification,
Clause 1.5
Clause 1.5; The grade level of the
total land is varying by 2m and plant
area by 1.0m. The land is sloping in
the direction from north to south
towards saline nallah at edge of the
site. This area covers mostly plane
and barren land with wide spread
patches and agriculture plants and
herbs/shrubs.
There seem significant requirement
of filling. The overall land is about
1M below road level, in addition
there are several areas even further
depressed due to soil there being
utilized at construction works in
Sundar Industrial Estate and several
bhattas (Brick Kilns) in nearby area.
The maximum depression located
was approximately 2-3M below road
level.
Please provide us updated
Topographical Surver maps and
clarify that Finshed Ground Level
will be 25 cm above Natural Ground
Level.
Upgraded topical survey is the
responsibility of the EPC Contractors
144. Volume II Part A, Technical
Specifications-G
eneral
Specification,
Clause 1.12
Clause 1.12 Raw Water Source
Plant water requirement shall be met
form the Kahna Minor that flows in
front and parallel to the plant site at a
distance of about 20m.
To meet the raw water requirement
during canal closure a backup
arrangement shall be made for
underground water at Kahna Minor
We suggest to use ground water only
for raw water storage which has
better quality and available
throughout the year.
Not agreed.
![Page 56: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/56.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 56 of 59
canal bank by installing deep bore
well pumps.
Clause 3.4, Terminal Points, Water
intake plant for drawing water from
existing canal as well as bore well
and complete subsequent system is in
the scope of Bidder. Water at canal
and ground water at bore well is the
terminal point.
145. Volume II Part A, Technical
Specifications-G
eneral
Specification,
Clause1.16
Clause1.16 Power Evacuation
Power Plant shall be connected with
the 132kV substation at Sunder
Industrial Estate by 4.7 km
long 132kV double circuit line with
‘RAIL’ conductor. The transmission
line shall run from the outdoor gantry
of the 132kV Switchyard at the
Power Plant to the outdoor gantry of
the 132kV switchyard at the Sunder
Industrial estate.
There is 220 KV Double Circuit
OHTL passing in the way of 132 kV
Double Circuit 132 kV OHTL from
Project Site to Industrial Estate Grid
Station. Please check with NTDC and
advise method of under crossing.
As per WAPDA existing rules and
regulations.
146. Volume II Part B, Section
A,
Clause 15
Clause 15 Ash dump (Ash Dyke);
The ash dyke height shall be
designed and constructed considering
design life of power plant as 30 years
Section 7.3 (page 76) of Feasibility
report indicates that an area of 131
Acres is required for disposing ash
for 30 years. The plot plan indicates
an area of 49 acres only. Please
arrange to check and confirm.
An area of 49 acres is adequate for
ash disposal.
147. General According to the geological data,
it is hard to determine whether
No It is an EPC lump sum contract.
![Page 57: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/57.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 57 of 59
adverse geologic condition like
expansive soil and liquefied soil.
At present. If there are similar or
other adverse geologic
conditions in the detailed survey.
The closing cost shall be
adjusted according to the actual
project quantity.
148. General The ash yard is required to store
100% ash quantity of 30 years of the
power plant in the tender documents,
hydraulic ash removal and dry ash
removal are used for ash removal
system and the soil is not allowed to
be sampled in the ash yard.
According to the calculation, the ash
quantity of 30 years of the power
plant is approximately 3.8 million m3
and only 100% ash quantity of 5
years can be stored according to the
current site condition; If ash quantity
of 30 years of the power plant is to be
realized, over 82% ash
comprehensive utilization shall be
taken into consideration.
The scheme of soil borrow in the ash
yard can not only increase the
capacity of the ash storage volume
Please refer to ITB Clause 20.2
![Page 58: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/58.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 58 of 59
but also can reduce the pressure of
earthwork outsourcing.
If the ash removal system is changed
to dry ash removal, it can only
increase a part of ash storage volume
but also can reduce the dam body
earthwork.
In addition: According to the
requirement of tender documents, a
clay core wall is required to be in the
dam body with a earthwork of
approximately 70,000 m3 and the
source of part of earthwork shall be
taken into consideration.
149. General The ash removal efficiency of
electric ash removal is required to
reach 99.99% in the tender
documents and we can promise as
ash removal efficiency of 99.8%. If
50mg/Nm3 dust discharge
concentration referred to in the
requirements of tender documents is
to be satisfied, we advise to change
the electrostatic precipitation to the
electrostatic-bag precipitator.
Please refer to ITB Clause 20.2
150. General According to the requirements of
tender documents, all the waste water
Please refer to ITB Clause 20.2
![Page 59: PPDCL_ConsolidatedClarifications03_04062015](https://reader036.vdocument.in/reader036/viewer/2022062407/563db968550346aa9a9d0b18/html5/thumbnails/59.jpg)
Consolidated Replies No.3
2x55MW (Gross) PPDCL Coal Fired Power Project Sunder Lahore Punjab Power Development Company Ltd
Page 59 of 59
treated in the plant shall be
discharged into the central control
wastewater pool (CMB) and reused
uniformly, According to the
calculation, the power plant water
supplement quantity of this scheme is
520t/h and if the waste water i reused
stepwise according to the different
drainage water quantity, the power
plant water consumption can be
reduced to save water.
151. General About the net output
2x50MW