ppi hdpe under

53

Upload: neil-malott

Post on 01-Nov-2014

65 views

Category:

Documents


8 download

DESCRIPTION

PPI Buried Underground HDPE PipingOthers available at PPI

TRANSCRIPT

Page 1: Ppi Hdpe Under
Page 2: Ppi Hdpe Under

© Copyright, The Society of the Plastics Industry, Inc. 1996

Page 3: Ppi Hdpe Under

Underground Installation of Polyethylene Piping

Table of Contents

Forward

Introduction 1

Flexible Pipe Installation Theory 1Deflection Control 3Acceptance Deflection 5Pipe Design Considerations 5

Pipe Embedment Materials 5

Terminology of Pipe Embedment Materials 6Classification and Supporting of Pipe Embedment Materials 7Embedment Classification Per ASTM D-2321 8Use of Embedment Materials 10Compaction of Embedment Materials 13

Trench Construction 16

Trench Width 16Trench Length 17Stability of the Trench 18

Installation Procedure 22

Trench Floor Preparation 22Backfilling and Compaction 24Backfill Placement 25Inspection 26

References and Acknowledgments 27

Appendix 1 - Simplified Installation Guidelines for Pressure Pipe A1-1Simplified step-by-step Installation A1-1

Page 4: Ppi Hdpe Under

Appendix 2 - Guidelines for Preparing an Installation Specification A2-1General Requirements A2-1Guide Specification A2-2Part 1 – General A2-2Part 2 – Products A2-3Part 3 – Execution A2-4

Appendix 3 - Basic Soil Concepts for Flexible Pipe Installation A3-1A1.0 Soil Classification A3-1A1.1 Fine Grain Soil (Clay and Silt) A3-1A1.2 Course Grain Soils A3-1A2.0 Density and Compaction A3-2A2.1 Methods of Measuring Density A3-2A3.0 Comparison of Installation of Rigid and A3-3

Flexible Pipe

Page 5: Ppi Hdpe Under

List of Figures

Figure 1 Pipe Trench 3

Figure 2 Mobilization of Enveloping Soil through Pipe Deformation 4

Figure 3 Stress Distribution for 18" HDPE Pipe in Soil box 6

Figure 4 Tamping Tool 14

Figure 5 Installing PE Pipe with a Portable Trench Shield 21

Figure 6 Pipe Support in Transition from Rigid Support to 24Normal Trench Support

Figure 7 Proper Transition from Rock Trench Bottom to 24Normal Trench Support

Figure A1 Dry Installation Bedding Requirements for A2-7HDPE Profile Wall Pipe

Figure A2 Wet Installation Bedding Requirements for A2-7HDPE Profile Wall Pipe

List of Tables

Table 1. Embedment Classes per ASTM D-2321 9

Table 2. Maximum Particle Size vs. Pipe Size 11

Table 3. Minimum Trench width in Stable Ground 17

Table 4. Suggested Minimum Length of Trench Opening (Feet) 17for Installation of Joined Length of Polyolefin Pipe

Table A2-1 Allowable Stacking Heights for F-894 Pipe A2-3

Table A2-2 Minimum Acceptable Diameter A2-9

Page 6: Ppi Hdpe Under

Foreword

Underground Installation of PE Piping is one of the chapters being prepared forinclusion in the Plastics Pipe Institute’s PPI Handbook of Polyethylene Piping, whichwill be issued as a complete volume in the future. Other topics to be addressed in thehandbook will include design of polyethylene piping systems, joining procedures,engineering properties, relevant codes and standards, and a variety of related infor-mation.

PPI is a division of The Society of the Plastics Industry, Inc. (SPI), and the major U.S.trade association representing all segments of the plastics industry.

The Municipal and Industrial (M&l) Division of PPI are producing the PPI Handbookof Polyethylene Piping. M&l membership consist of major North American manufac-turers of polyethylene (PE) pipe and fittings, PE piping materials, machinery, andequipment used for joining and installing PE piping, related test laboratories, andprofessional organizations.

PPI maintains additional groups that address other applications such as gas distribu-tion. PPI provides technical and promotional support for the effective use and contin-ued application of thermoplastics pipe and related products, consistent with the bestpublic interest. PPI membership also includes producers of polyvinyl chloride (PVC),chlorinated polyvinyl chloride (CPVC), polybutylene (PB), and crosslinked PE (PEX)piping products and materials.

For a list of other publications available from PPI and/or further information, pleasecontact:

The Plastics Pipe Institute, a Division ofThe Society of the Plastics Industry, Inc.

1801 K St. N. W., Suite 600KWashington, D.C. 20006Toll Free: (888) 314-6774Phone: (202) 974-5318

Fax: (202) 293-0048http://www.plasticpipe.org

The information in the publication was prepared by SPI/PPI as a service to its mem-bers and the industry. While prepared in good faith and believed to be accurate, SPI/PPI, its members, and contributors disclaim all liability for any loss or damage arisingfrom reliance on this information by any person. SPI/PPI does not endorse the pro-prietary products or processes of any manufacturer. Consult the product manufac-turer for specific information.

February, 1998

Page 7: Ppi Hdpe Under

Underground Installation Of Polyethylene Piping

INTRODUCTIONPiping systems are prevalent throughout our everyday world. Most of us think ofpiping systems as underground structures used to convey liquids of one sort or an-other. To the novice, the concept of pipeline installation underground sounds rela-tively straight forward: a) dig a trench, b) lay the pipe in the trench, and c) fill thetrench back in.

While this simplified perspective of pipeline construction may be appealing, it doesnot begin to address the engineering concepts involved in the underground installa-tion of a pipeline. This chapter is written to assist in the development of a compre-hensive understanding of the engineering principles utilized in the underground in-stallation of polyethylene pipe.

In the pages which follow, the reader will be introduced to the concept of a pipe soilsystem and the importance that the soil and the design and preparation of the back-fill materials play in the long term performance of a buried pipe structure. (Section1.0 through 3.0) Specific terminology and design concepts relating to the under-ground installation of polyethylene pipe will be fully discussed. This will includefundamental guidelines regarding trench design and the placement and subsequentbackfill of the polyethylene pipe. (Section 4.0)

This discussion is intended to assist the pipeline designer in the underground instal-lation of polyethylene piping materials. This chapter is not intended as a substitutefor the judgement of a professional engineer. Rather, it is felt that a comprehensivepresentation of these design and installation principles may assist the engineer ordesigner in utilizing polyethylene pipe in the broad diversity of applications that re-quire that it be buried beneath the earth.

Those individuals who are installing 24" diameter or smaller pressure pipe less than16 feet deep are advised to see Appendix 1 which includes simplified installationguidelines. These guidelines were written to be used without review of this entirechapter, however, the installer of smaller pipes would benefit from a familiarity of theprinciples of pipe installation given in this chapter.

Likewise, Appendix 2 contains a specification for large diameter (greater than 18")gravity flow pipes. For these sizes it is advised that the installer read this chapter.

Underground Installation of PE Piping - 1

Page 8: Ppi Hdpe Under

FLEXIBLE PIPE INSTALLATION THEORYMost PE piping is considered flexible. Flexible pipes include corrugated metal pipes,plastic pipes, and some steel and ductile pipes. These pipes deflect under load,such as the overburden load encountered when installed underground. The de-signer and installer of underground, flexible piping must utilize the soil to constructan envelope of supporting material around the pipe so that the deflection is main-tained at an acceptable level. The extent to which the pipe depends on this envelop-ing soil for support is a function of the depth of cover, surface loading, and the SDRor Ring Stiffness of the pipe.

In general, the supporting envelope is built by surrounding the pipe with firm, stablematerial. This envelope is often referred to as the “embedment” (see figure 1). Theamount of support provide by the embedment is directly proportional to its stiffness.So, often the embedment material is compacted. The stiffness of the material placedabove the pipe may also affect the pipe’s performance. Considerable load reductionmay occur due to arching, that is the redistribution of stresses in the soil above andaround the pipe which result in a shifting of load away from the pipe. The stiffer thebackfill above the pipe, the more arching occurs.

The designer or installer will consider not only the embedment material but also theundisturbed insitu soil surrounding the embedment and the ground water. The move-ment of the in-situ soil in the trench wall can reflect through the embedment andaffect the pipe’s performance. Therefore, careful consideration must be paid to thismaterial when planning and during installation. This will most likely affect the equip-ment involved in doing the installation and the installation procedure itself more sothan the pipe design. Of particular significance are soft clays and wet, loose silts orsands. When these materials are encountered, unstable trenching can occur withconsiderable sloughing and loosening of the trench walls during excavation. Flex-ible pipe can be installed in such ground with limited deflection as long as attention ispaid to the proper handling of these conditions.

Underground Installation of PE Piping - 2

Page 9: Ppi Hdpe Under

Figure 1Pipe Trench

Note: When groundwater levels are expected to reach above pipe, the secondary initialbackfill should be a continuation of the primary initial backfill in order to provide optimumpipe support. Minimum trench width will depend on site conditions and embedmentmaterials.

DEFLECTION CONTROLAs described previously, the load carrying capability of a PE pipe can be greatlyincreased by the soil in which it is embedded as the pipe is loaded, the load istransferred from the pipe to the soil by a horizontal outward movement of the pipewall. This enhances contact between pipe and soil and mobilizes the passive resis-tance of the soil. This resistance aids in preventing further pipe deformation andcontributes to the support for the vertical loads. The amount of resistance found inthe embedment soil is a direct consequence of the installation procedure. The stifferthe embedment material are; the less deflection occurs. Because of this, the combi-nation of embedment and pipe is often referred to as a pipe-soil system (see fig-ure2).

The key objective of a PE pipe installation is to limit or control deflection. (In thischapter the term “deflection” will mean a change in vertical diameter of the pipe,unless otherwise stated.) The deflection of a PE pipe is the sum total of two majorcomponents: the “installation deflection”, which reflects the technique and care bywhich the pipe is handled and installed; and the “service deflection”, which reflectsthe accommodation of the constructed pipe-soil system to the subsequent earth load-ing and other loadings.

Underground Installation of PE Piping - 3

Page 10: Ppi Hdpe Under

Figure 2Mobilization of Enveloping Soil Through Pipe Deformation

The “service deflection” which is usually a decrease in vertical pipe diameter, may beforecasted by a number of reasonably well documented relationships, including thoseof Watkins and Spangler(1,2), or by use of a finite element analysis such as CANDE(1,2).

The “installation deflection” may be either an increase or decrease in vertical pipediameter. An increase in vertical pipe diameter, is referred to as “rise” and is usuallya result of the forces acting on the pipe during compaction of the embedment besideit. Up to a point this may be beneficial in offsetting service deflection. Installationdeflection is not predictable by any mathematical formula, although there are empiri-cal methods for accounting for it(3).

Installation deflection is subject to control by the care used in the placement andcompaction of the pipe embedment material in relation to the pipe’s ring stiffness.For instance, compaction forces from hand operated air or gasoline tampers nor-mally cause little rise, even when obtaining densities of 95 percent, but driving heavyloading equipment or driven compactors on the embedment while it is being placedbeside the pipe may cause severe rise.

Underground Installation of PE Piping - 4

Page 11: Ppi Hdpe Under

Commonly, deflection varies along the length of the pipeline due to variations inconstruction technique, soil type and loading. Field measurements illustrating thisvariability have been made by the U.S. Bureau of Reclamation and have been pub-lished by Howard(3). Typically, this variation runs around ±2 percent.ACCEPTANCE DEFLECTION

To evaluate and control the quality of a flexible pipe installation, many designersimpose an “acceptance deflection” requirement. This is particularly important forgravity flow lines with high SDR pipe. Commonly, pressure pipes are not checkedfor deflection. The “acceptance deflection” is the maximum vertical pipe deflectionpermitted following installation. Typically, measurements are made only after mostof the initial soil consolidation occurs usually at least 30 days after installation. Thedesign engineer sets the “acceptance deflection” based on the particular applicationand type of joints. Commonly, a deflection limit of 5 percent is used, although PEpipe in gravity applications can usually withstand much larger deflections withoutimpairment. When deflection is measured past 30 days, it is common to allow for ahigher percentage. (See page on “Inspection.”)

PIPE DESIGN CONSIDERATIONS

While control of pipe deflection is a key objective in the installation of PE pipe, de-flection is not ordinarily the criteria that determines the selection of a specific pipeSDR or ring stiffness. For typical burial conditions most PE pipe, when properlyinstalled, are adequately stiff to preclude excessive deflection. However, for gravityflow applications, the design may often be controlled by the pipe’s buckling resis-tance or the compressive thrust load in the pipe’s wall. The selection of pipe designand construction requirements should be based on anticipated site conditions in-cluding trench depth, hydrostatic pressure due to ground water, superimposed staticor traffic load, and depth of cover.

PIPE EMBEDMENT MATERIALSThe embedment is the material immediately surrounding the pipe. This material maybe imported such as a crushed stone or it may be the material excavated from thetrench to make room for the pipe. In this case, it is referred to as native soil.

The embedment material should provide adequate strength, stiffness, uniformity ofcontact and stability to minimize deformation of the pipe due to earth pressures. Theearth pressure acting on the pipe varies around the pipe’s circumference (see figure3). The pressure on the crown or top will typically be less than the free field stress asis the pressure at the invert or bottom of the pipe. Often, the highest pressure maybe acting horizontally at the springline of the pipe, due to mobilization of passivepressure and arching.

Underground Installation of PE Piping - 5

Page 12: Ppi Hdpe Under

Figure 3Stress Distribution for 18 in. HDPE pipe in soil box.

Because the earth pressure is acting around the circumference, it is important tocompletely envelop the pipe in embedment. (This may vary to a greater or lesserextent depending on the earth pressure, burial depth, and SDR.) To ensure that theembedment function will always be carried out under the anticipated job conditions,the design engineer will specify the permissible pipe embedment materials and theirminimum acceptable density (compaction).

The properties of the in-situ (or native) soil into which the pipe is placed need not beas demanding as those for the embedment materials (unless it is used as the em-bedment material). But, the native soil may experience additional compression anddeformation due to the horizontal pressure exerted by the pipe and transferred throughthe embedment material. This is usually a minor effect but in some cases it canresult in additional pipe deflection. This is most likely to occur where native soils arewet and loose, soft, or where native soil sloughs into the trench during excavationand is not removed. This effect is attenuated as the trench width (or width of embed-ment material) increases. Therefore, consideration must be given to the in-situ soilto ensure that it has adequate strength to permanently contain the embedment sys-tem. This too is discussed in a following section.

TERMINOLOGY OF PIPE EMBEDMENT MATERIALS

The materials enveloping a buried pipe are generally identified, as shown by theirfunction or location (see figure 1).

Soil ArchingHorizontal Stress

Soil ArchingVertical Stress

Underground Installation of PE Piping - 6

Page 13: Ppi Hdpe Under

Foundation - A foundation is required only when the native trench bottom does notprovide a firm working platform for placement of the pipe bedding material.

Bedding - In addition to bringing the trench bottom to required grade, the beddinglevels out any irregularities and ensures uniform support along the length of the pipe.

Haunching - The backfill under the lower half of the pipe (haunches) distributes thesuperimposed loadings. The nature of the haunching material and the quality of itsplacement are one of the most important factors in limiting the deformation of PEpipe.

Primarv Initial Backfill - This zone of backfill provides the primary support againstlateral pipe deformation. To ensure such support is available, this zone should ex-tend from trench grade up to at least 75 percent of the pipe diameter. Under someconditions, such as when the pipe will be permanently below the ground water table,the primary initial backfill should extend to at least 6 inches over the pipe.

Secondary Initial Backfill - The basic function of the material in this zone is to distrib-ute overhead loads and to isolate the pipe from any adverse effects of the placementof the final backfill.

Final Backfill - As the final backfill is not an embedment material, its nature andquality of compaction has a lesser effect on the flexible pipe. However, arching andthus a load reduction on the pipe is promoted by a stiff backfill. To preclude thepossibility of impact or concentrated loadings on the pipe, both during and afterbackfilling, the final backfill should be free of large rocks, organic material, and de-bris. The material and compaction requirements for the final backfill should reflectsound construction practices and satisfy local ordinances and sidewalk, road build-ing, or other applicable regulations.

CLASSIFICATION AND SUPPORTING STRENGTH OFPIPE EMBEDMENT MATERIALS

STRENGTH OF EMBEDMENT SOIL

When selecting embedment material, consideration should be given to how thegrain size, shape, and distribution will affect its supporting strength. The followingwill help guide the designer or installer in making a choice. In general, soils with largegrains such as gravel have the highest stiffness and thus provide the most support-ing strengths. Rounded grains tend to roll easier than angular, or sharp, grainswhich tend to interlock. So, the angular grains resist shear better. Well graded mix-tures of grains (GW, SW) that is soils which contain a good representation of grainsfrom a wide range of sizes tend to offer more resistance than uniform graded soils(GP, SP). (See Table 1 for symbol definitions.)

Underground Installation of PE Piping - 7

Page 14: Ppi Hdpe Under

Aside from the grain characteristics the density has the greatest effect on theembedment’s stiffness. For instance, in a dense soil there is considerable interlock-ing of grains and a high degree of grain to grain contact. Movement within the soilmass is restricted as the volume of the soil along the surface of sliding must expandfor the grains to displace. This requires a high degree of energy. In a loose soil,movement causes the grains to roll or to slide, which requires far less energy. So,loose soil has a lower resistance to movement. Loose soil will permit more deflectionof pipe for a given load than a dense soil.

When a pipe deflects, two beneficial effects occur.

1. The pipe pushes into the embedment soil and forces the soil to start moving. Asthis occurs, a resistance develops within the soil which acts to restrain furtherdeflection.

2. Vertical deflection results in a reduction in earth load transmitted to the pipe due tothe mobilization of arching.

EMBEDMENT CLASSIFICATION PER ASTM D-2321

Pipe embedment materials have been grouped by ASTM D-2321, “UndergroundInstallation of Flexible Thermoplastic Sewer Pipe”, into five embedment classes ac-cording to their suitability for that use.

Underground Installation of PE Piping - 8

Page 15: Ppi Hdpe Under

Table 1Embedment Classes per ASTM D-2321

Average Value of E’Degree of Compactionof Embedment Mateial

1

(Standard Proctor)Class Soil Description Soil Dumped Slight Moderate Heavy

Group Symbol 85% 90% >95%

IA Manufactured aggregate, None 500 1000 3000 3000 angular open-graded and clean. Includes crushed stone, crushed shells.

IB Processed aggregate, None 200 1000 2000 3000angular dense-graded and clean. IncludesClass IA material mixedwith sand and gramel to minimize migration

II Course-grained soils, GW, GP, 200 1000 2000 3000 clean. Includes gravels, SW, SP gravel-sand mixtures, and well and poorly graded sands. Contains little to no fines (less than 5% passing #200).

II Course-grained soils, GW- GC 200 1000 5000 3000 borderline clean to SP-SM“with fines.” Contains5% to 12% fines (passing #200).

III Course-grained soils GM, GC, 100 200 1000 2000 containing 12% to 50% SM, SCfines. Includes clayey gravel, silty sands, and clayer sands.

IVa Fine-grained soils ML, CL 50 200 400 1000 (inorganic). Includes inorganic silts, rock flour, silty-fine sands, clays of low to medium plasticity, and silty or sandy clays.

IVb Fine-grained soils MH, CH No data avaliable: consult (inorganic). Includes a competent soils engineer. diatomaceous silts, elastic Otherwise use E’ equals zero. silts, fat clays.

V Organic soils. Includes OL, OH, No data avaliable: consult a organic silts or clays PT competenet soils engineer. and peat. Otherwise use E’ equals zero.

1E’ values taken from Bureau of Reclamation table of average values and modified slightly herein tomake the values more conservative.

Underground Installation of PE Piping - 9

Page 16: Ppi Hdpe Under

The lower numbered classes have larger grain sizes and thus are more suitable aspipe embedment. The materials included in each class are identified in Table 1 andgrouped in accordance with their classification per ASTM D-2487, Standard UnifedSoil Classifcation System (USCS). (See Appendix III for a general discussion of soilclassification.) A visual manual procedure for the field identification of soils is offeredby ASTM D-2488.

The supporting strength of embedment materials roughly coincides with their em-bedment class. The supporting strength or stiffness of a soil material is representedby the modulus of soil reaction, E’. Based on extensive evaluation of field and labo-ratory performance of flexible pipes, the Bureau of Reclamation of the U.S. Depart-ment of the Interior has issued a table of Modulus of Soil Reaction Values. Thistabulation of E’ values, which is reproduced with some modifications based on re-cent experience in Table 1, provides a measure of available soil support dependingon the soil embedment class and its degree of compaction. As discussed above,generally speaking, the classes with finer soils offer less supporting strength. How-ever, within any embedment class, increased compaction greatly improves a soil’ssupporting strength hence the critical role of proper compaction, particularly with thefiner-grained soils. To ensure that the pipe is always adequately supported, it is thegeneral practice to use materials and degrees of compaction resulting in an E’ equalto or greater than 750 psi, although some applications may require higher or lower E’values.

USE OF EMBEDMENT MATER IALS

The determination of requirements for embedment materials and their placementshould take into consideration not only their relative supporting strength but alsotheir stability under end use conditions, ease of placement and compaction, and costand availability.

Class I and Class II

Class I and Class II soils are granular and tend to provide the maximum embedmentsupport as illustrated by the high E’ values that can be achieved with them. Class Imaterial is generally manufactured aggregate, such as crushed stone. Class II ma-terials consist of clean sands and gravels and are more likely to be naturally occur-ring soils such as river deposits. Class I and Class II materials can be blended to-gether to obtain materials that resist migration of finer soils into the embedment zone(as will be explained below.) In addition, Class I and II materials can be placed andcompacted over a wide range of moisture content more easily than can other mate-rials. This tends to minimize pipe deflection during installation. The high permeabil-ity of open-graded Class I and II materials aids in de-watering trenches, makingthese materials desirable in situations such as rock cuts where water problems maybe encountered. This favorable combination of characteristics leads many design-ers to select these materials over others when they are readily and economically

Underground Installation of PE Piping - 10

Page 17: Ppi Hdpe Under

available.

Maximum aggregate size of Class I and Class II materials when used next to thepipe (i.e., bedding, haunching and initial backfill) should not be larger than thosegiven in Table 2 below. (Larger stones up to 1'/2 inches have been successfullyused, but they are difficult to shovel slice and compact.) The smaller the rock size,the easier it is to place in the haunches. Maximum size for the foundation material isnot restricted except that it should be graded to prevent the bedding stone frommigrating into it.

TABLE 2Maximum Particle Size vs. Pipe Size

Nominal Pipe Size (in.) Maximum Particle Size (in.)

2 to 4 ½6 to 8 ¾

10 to 16 118 and larger 1½

Migration

When the pipe is located beneath the ground water level, consideration must begiven to the possibility of loss of side support through soil migration (the conveyingby ground water of finer particle soils into void spaces of coarser soils). Generally,migration can occur where the void spaces in the embedment material are suffi-ciently large to allow the intrusion of eroded fines from the trench side walls. Formigration to occur, the in-situ soil must be erodible. Normally, erodible soils are finesand and silts and special clays known as dispersive clays. (Most clays have goodresistance to dispersion.) This situation is exacerbated where a significant gradientexists in the ground water from outside of the trench toward the inside of the trench;i.e., the trench must act as a drain. (Seasonal fluctuations of the ground water levelnormally do not create this condition.)

For such anticipated conditions, it is desirable when using granular materials (ClassI and II)specify that they be angular and graded to minimize migration. Roundedparticles have a tendency to flow when a considerable amount of water exists andmaterial with a high void content provides “room” for migrating particles. The ArmyCorps of Engineers developed the following particle size requirements for properlygrading adjacent materials to minimize migration:

Underground Installation of PE Piping - 11

Page 18: Ppi Hdpe Under

1) DE15 < 5DA

85

2) DE50 ³ 25D A

85

Where the D15, D50 and D85 are the particle sizes from a particle size distribution, 50%and 85%, respectively, finer by weight and where DE is me embedment soil and DA isthe adjacent in-situ soil.

Cement Stabilized Sand

One special case of Class II material is Cement Stabilized Sand. Cement StabilizedSand, once cured, is generally considered to give the same or better supportingstrength as compacted Class I material. Cement Stabilized Sand consists of sandmixed with 3-5 percent cement. To achieve proper density, the material is placedwith compaction rather than poured as with concrete. The material must be placedmoist (at or near optimum moisture content) and then compacted in lifts as a Class IImaterial. (The optimum moisture content is that moisture content at which a materialcan achieve its highest density for a given level of compaction.) If desired, deflectioncan be reduced if the cement sand embedment material is allowed to cure overnightbefore placement of backfill to grade. If the trench is backfilled immediately, cementsand will give the same support as a Class II material, but the lag factor will bereduced. Cement sand is usually placed in both the primary initial and secondaryinitial backfill zones (see figure1).

Class lIl and Class IVa

Class III and Class IVa materials provide less supporting stiffness than Class I or IImaterials for a given density or compaction level, in part because of the increasedclay content. In addition, they require greater compactive effort to attain specifieddensities and their moisture content must be closely controlled within the optimumlimit. (The optimum moisture content is that moisture content at which a material canachieve its highest density for a given level of compaction.) Placement and compac-tion of Class IVa materials are especially sensitive to moisture content. If the ClassIVa material is too wet, compaction equipment may sink into the material whereas ifthe soil is too dry, compaction may appear normal, but subsequent saturation withground water may cause a collapse of the structure and lead to a loss of support.Typically, Class IVa material is limited to applications with pressure pipe at shallowcover.

Class IVb and Class V

Class IVb and Class V materials offer hardly any support for a buried pipe and areoften difficult to properly place and compact. These materials are normally not rec-ommended for use as pipe embedment unless the pipe has a low SDR (or high ringstiffness), there are no traffic loads and the depth of cover is only a few feet. In many

Underground Installation of PE Piping - 12

Page 19: Ppi Hdpe Under

cases the pipe will float in this type of soil, if the soil becomes saturated.

COMPACTION OF EMBEDMENT MATERIALS

Compaction criteria for embedment materials are a normal requirement in flexiblepipe construction. Compaction reduces the void space between individual grainsand increases the embedment density, thereby greatly improving pipe load carryingability while reducing deflection, settlement, and water infiltration problems. Com-paction of the embedment often will increase the stiffness of the in-situ soil andprovide a sort of pre-stressing for the embedment and in-situ soils. Because of thesebenefits compaction should be considered on all projects.

Density Requirements

The required degree of compaction for an installation will be set by the designer inconsideration of height of cover, extent of live loading, water table elevation and soilproperties. Generally, the “moderate” compaction requirements listed in Table 1 arequite satisfactory. When compacting to this “moderate” level, it is suggested that theminimum target values for field measured densities be set as 90 percent StandardProctor Density. This field density requirement will ensure that the actual densitieswill always be within the “moderate” range presented in Table 1. The applicablemethod for measuring density, ASTM D-2029, Test for Relative Density of Cohe-sionless Soils, or ASTM D-698, Tests For Moisture-Density Relations of Soils andSoil-Aggregate Mixtures, will be determined by the nature of the embedment mate-rial. Generally, the density of granular soils is determined using either test, whereasthat of fine grained materials is determined by ASTM D-98. See Appendix 3 for adiscussion of the difference between density and compaction and a discussion ofthe various test methods.

Compaction Techniques

Compaction of the embedment material should be performed by the most economi-cal method available, consistent with providing uniform compaction and attaining theminimum specified density. Typical equipment used for compaction are hand heldtamping bars (see figure 4), gasoline driven impact tampers (“whackers”), vibratoryplates, and air driven impact tampers (“pogo sticks”). With crushed stone, somedegree of densification can be achieved by the technique of shovel slicing, whichconsists of cutting the soil with a shovel.

Underground Installation of PE Piping - 13

Page 20: Ppi Hdpe Under

Figure 4Tamping Tool

Compaction of the haunching material can best be accomplished by hand with tampersor suitable power compactors, taking particular care in the latter case not to disturbthe pipe from its line and grade. In 36" and larger pipe hand tampers are often usedto reach under the haunches-then they are followed-up with power compaction alongside the pipe.

When compacting the embedment near the pipe with impact-type tampers, cautionshould be taken to not allow direct contact of the equipment with the pipe. Avoidusage of impact tampers directly above the pipe until sufficient backfill (usually 12")has been placed to ensure no local deformation of the pipe. Compaction of theembedment material alongside the pipe should not cause pipe to lift off of grade, butif upward movement occurs reduce the compaction level below the springline ormove the compactor away from the pipe toward the side of the trench.

Compaction of primary initial backfill should be conducted at, or near, the material’soptimum moisture content. The backfill should be placed in layers, or lifts, that arebrought up evenly on both sides of the pipe, otherwise the pipe could be moved offalignment. Each lift should be thoroughly compacted prior to placement of the nextlayer. The maximum lift height that will allow development of uniform density willvary depending on the material, its moisture content, and compactive effort. In gen-eral, maximum lifts of approximately 12 inches for Class I, 8 inches for Class II, and6 inches for all others are adequate.

Underground Installation of PE Piping - 14

Page 21: Ppi Hdpe Under

Compaction of Class I and II Materials

Compaction by vibration is most effective with granular (Class I and II) materials.Compaction of stone does not deform the stone but it does move it into a morecompact or dense arrangement. In cases where the engineer specifies a minimumsoil density of 90 percent of Standard Proctor or higher, as for installations underdeep cover, mechanical compaction of Class I materials will be required. Impacttampers will also increase the density of Class I and II materials, primarily due tovibration. Impact tamping also acts to drive the embedment into the in situ soil,which stiffens the trench wall interface. For this reason, impact compaction of ClassI material should be considered for any application where the pipe will be below theground water table or where the stability of the in-situ soil is in question.

An alternate method of achieving compaction with Class I materials is shovel slicing.Materials having been shovel sliced thoroughly will generally yield a modulus of around1000 psi. The effectiveness of this method depends on the frequency of slicingalong the length of the pipe. This technique should be limited to dry or firm (or better)in-situ soils. Where Class I materials are dumped around the pipe without anycompactive effort (or shovel slicing), E’s may be considerably lower than those givenin the Bureau of Reclamation table. This is especially the case in wet or looseground. A few passes with a vibratory compactor will increase the density and modulusof soil reaction.

Mechanical compaction of Class II materials can be aided by slight wetting. Whenso doing, care must be taken not to saturate the material or flood the trench, particu-larly when the native trench material does not drain freely. Flooding can result inflotation of the pipe.

Compaction by saturation, also called flooding or water tamping, is sometimes usedto compact Class II materials. This method of compaction rarely yields Proctor den-sities greater than 75 percent, and therefore it will generally not give an E’ of 750 psior higher. Flooding is only suited for those applications where the pipe has sufficientinternal supporting strength for the design load and does not depend on the soil forside support. (When considering this method for embedment that must provide sidesupport, a geotechnical engineer should be consulted.) Compaction by saturation islimited to applications where both the embedment soil and in-situ soil are free drain-ing. Compaction should be done in lifts not exceeding the radius of the pipe or 24inches whichever is smaller. Only enough water should be placed to saturate thematerial. It should be determined through proper monitoring that the desired level ofcompaction is being attained in each lift. Compaction by saturation should not beused in freezing weather. Water jetting, or the introduction of water under pressureto the embedment material, should not be used with plastic pipe.

Underground Installation of PE Piping - 15

Page 22: Ppi Hdpe Under

Compaction of Class lIl and IV Materials

Compaction by impact is usually most effective with Class III and Class IVa materi-als. The use of mechanical impact tampers is most practical and effective. Depend-ing on the embedment material, its moisture content, and lift height, several compac-tion passes may be required. A maximum lift height of 6 inches should be usedwhen compacting by impact. Embedment density should be suitably monitored toensure that specification requirements are met.

Density Checks

It is prudent to routinely check density of the embedment material. Typically, severalchecks are made during start up of the project to ensure that the compaction proce-dure is achieving the desired density. Random checks are subsequently made toverify that the materials or procedures have not changed. Checks should be madeat different elevations of the embedment material to assure that the desired compac-tion is being achieved throughout the embedment zone.

TRENCH CONSTRUCTIONTrenches should be excavated to line and grade as indicated by contract documentsand in accordance with applicable safety standards. Excavation should proceedupgrade. Excessive runs of open trench should be avoided to minimize such prob-lems as trench flooding, caving of trench walls and the freezing of trench bottom andbackfill material, and to minimize hazards to workmen and traffic. This can be ac-complished by closely coordinating excavation with pipe installation and backfilling.

Principal considerations in trench construction are trench width, stability of the nativesoil supporting and containing the pipe and its embedment soil, stability of trenchwalls, and water accumulation in the trench. When encountering unstable soils orwet conditions, they should be controlled by providing an alternate foundation, slop-ing or bracing the trench walls, de-watering the trench bottom, or some other suchmeasure.

Trench Width

Since flexible pipe has to support, at most, only the weight of the “prism” or verticalcolumn of soil directly over the pipe, the precaution of keeping the trench as narrowas possible is not the concern that it is for a rigid pipe which can be subjected to theweight of the soil beside the prism as well as the prism itself. With PE pipe, wideningthe trench will generally not cause a loading greater than the prism load on the pipe.Trench width in firm, stable ground is determined by the practical consideration ofallowing sufficient room for the proper preparation of the trench bottom and place-ment and compaction of the pipe embedment materials, and the economic consider-ation of the costs of excavation and of imported embedment materials. Trench width

Underground Installation of PE Piping - 16

Page 23: Ppi Hdpe Under

in firm, stable ground will generally be determined by the pipe size and the compact-ing equipment used. The following table gives minimum trench width values.

The trench width may need to be increased over the values in Table 3 allow forsufficient clearance between the trench sidewalls and the pipe for compaction equip-ment. Typically for large diameter pipe (18" and larger), this required clearance willvary from 12 to 18 inches. If two or more pipe are laid in the same trench, sufficientspace must be provided between pipe so that embedment material can be com-pacted.

TABLE 3Maximum Trench Width in Stable Ground

Nominal Pipe Size (in.) MinimumTrench Width (in.)

3 to 16 Pipe O.D. + 12

18 to 42 Pipe O.D. + 18

18 and larger Pipe O.D. + 24

Trench Length

Table 4 lists the recommended lengths of trench openings for each placement ofcontinuous lengths of fused pipe, assembled above the trench. When the trenchsidewalls are significantly sloped, somewhat shorter trench openings may be used.When space or ground conditions do not permit these suggested trench openings,the pipe lengths may be joined within the trench, using a joining machine or flangedcouplings. When bell-and-spigot jointed pipe or flange-end pipe is used, the trenchopening needs to be only long enough to accommodate placement and assembly ofa single pipe length.

TABLE 4Suggested Length of Minimum Trench Opening

(Feet) for Installation of Joined Lengths of Polyolefin Pipe

Nominal Depth of Trench (Feet)Pipe Size

(in.) 3 5 7 9 11 13

½ to 3 15 20 25 30 35 404 to 8 25 30 35 40 45 50

10 to 14 35 40 45 50 55 6016 to 22 45 50 55 60 65 7024 to 42 - 60 65 70 75 80

48 - - 80 90 100 110

Underground Installation of PE Piping - 17

Page 24: Ppi Hdpe Under

Stability of the Trench

Although the native soil in which PE pipe is installed need not be as strong and stiffas the pipe embedment materials, it should provide adequate support and stablecontainment of the embedment material so that the density of the embedment mate-rial does not diminish. If the trenching conditions present construction problemssuch as trench sidewalls that readily slough or a soft trench floor that will not supportworkers or compaction, it is termed unstable. The instability is usually a condition ofthe trench and not the soil. Most often the primary cause of the instability is highgroundwater, not the soil. Even soft or loose soils can provide good support for thepipe if they are confined. The problem with unstable conditions generally occursduring the installation. When the trench is opened where groundwater is present,most soils, except firm, cohesive soils (firm clays) or cemented soils, tend to sloughoff the trench wall. This results in a trench that keeps widening with loose materialfalling into the trench floor.

Soil formations that commonly lead to unstable trenching conditions include materi-als with fine grain soils (silts or clays) saturated with water and uncemented sandssaturated with water. In some cases, where the soil has an extremely high watercontent, such as with peat or with clay (or silt) having a water content beyond theliquid limit, the soil behaves “hydraulically”, that is, the water in the soil controls thesoil’s behavior. Here, the backfill must be designed to sustain all the pressure fromthe pipe without support from the in-situ soil. These conditions may occur in satu-rated fine grained soils where the unconfined compressive strength of the soil is lessthan 500 psf or in saturated, sandy soils where the standard penetration value, N, isless than 6 blows per ft. In this case, an engineering evaluation should be made todetermine the necessity for special procedures such as a “wide” trench or perma-nent trench sheeting of the trench width.

As mentioned above, most trench stability problems occur in trenches that are exca-vated below the groundwater level. (However, the designer and the contractor shouldkeep in mind that all trenches pose the risk of collapse and therefore worker shouldnot be in trenches that are not adequately braced or sloped.) Stability can be im-proved by lowering the water table through deep wells, well-points, or other suchmeans. In some ground the permeability is such that the only option is to remove thewater after it has seeped out of the trench walls. Here the contractor will useunderdrains or sumps on the trench floor. De-watering should continue through-outthe pipe laying operation until sufficient cover is placed over the pipe so that it will notfloat.

Underground Installation of PE Piping - 18

Page 25: Ppi Hdpe Under

Stability of Trench Floor

Trench floor stability is influenced by the soils beneath the trench. The floor must bestable in order to support the bedding material. A stable bedding minimizes bendingof the pipe along its horizontal axis and supports the embedment enveloping thepipe. Generally, if the trench floor can be walked on without showing foot prints it isconsidered stable.

In many cases the floor can be stabilized by simply de-watering. Where dewateringis not possible or where it is not effective, stabilization of the trench floor may beaccomplished by various cost effective methods which can be suited to overcome allbut the most difficult soil conditions. Included among these are the use of alternatetrench foundations such as wood pile or sheathing capped by a concrete mat, orwood sheathing with keyed-in plank foundation; stabilization of the soil by the use ofspecial grout or chemicals; geofabric migration barriers; or ballasting (undercutting).A cushion of bedding material must be provided between any special foundation andthe pipe. Permanently buried timber should be suitably treated.

Stabilization by ballasting (undercutting) is the removal of a sufficient quantity ofundesirable material. This technique is frequently employed to stabilize randomlyencountered short sections of unstable soil. The extent of required over-excavationand details of accompanying construction requirements will be determined by theengineer in consideration of the qualities of the unstable soil and the specific designrequirements. The following are general guidelines:

The trench bottom should be over-excavated over the full trench widthfrom 18 to 36 inches below the pipe grade (depending on the soilstrength and pipe diameter) and then brought back to grade with afoundation of ballast material topped with Class I material. An appro-priate bedding should then be placed on the foundation. The gradingof the foundation material should be selected so that it acts as an im-pervious mat into which neither the bedding, other embedment mate-rial, nor the surrounding native soil will migrate.

These guidelines are suitable for most situations except for extremely weak soils(such as quick sands, organic silts, and peats) which may call for further over-excavation, or other special treatment:.

Stability of Trench Walls

In order to control deflection the embedment material must be placed from undis-turbed trench sidewall to undisturbed trench sidewall. Where trench walls are un-stable, it may be necessary to use trench shields, bracing, or permanent sheeting toachieve a stable sidewall while installing the pipe. Where material sloughs into thetrench it should be removed. This technique often leads to widening the trench.

Underground Installation of PE Piping - 19

Page 26: Ppi Hdpe Under

Walls of trenches below the elevation of the crown of the pipe should be maintainedas vertical as possible. The shape of the trench above the pipe will be determined bythe stability of the trench walls, excavation depth, surface loadings near the trench,proximity of existing underground structures, presence of ground or run off water,safety and practical considerations. These will determine if the trench walls may bevertical, excavated with slope or benched sides, or shored. When trench walls areshored or otherwise stabilized, the construction scheme must allow for the properplacement and compaction of pipe embedment materials. Some suggested trenchconstruction schemes follow. The final procedure must be in compliance with allapplicable safety regulations.

Sloping of trench walls in granular and cohesionless soils should be provided when-ever the walls are more than about four feet in depth or otherwise required by state,local or federal regulations. For safety, if the walls are not be sloped, they should bestabilized by alternate means such as shoring or bracing. The slope should be nogreater than the angle of repose of the materials being excavated and should beapproved by the engineer.

Shoring or bracing will frequently be required in wet fine grained cohesive type soilsand clays. Bracing or sheathing that is constructed of treated timber, steel or otheracceptable material may be used to stabilize trench walls either permanently or tem-porarily. Wherever possible, sheathing and bracing should be installed so that itsbottom extends no lower than about one-quarter of the pipe diameter below the pipecrown. When so installed, pulling the sheathing will minimally disturb the embed-ment material and the side support it provides. Sheathing that is installed to projectbelow the pipe springline should be left in place unless, as with some thinner sheath-ing, it is designed to be pulled and removed without disturbing the embedment nextto the pipe. In this case, the trench width should be increased by some 12 to 24inches depending on the pipe diameter to allow for minor disturbance to the embed-ment near the sheathing. Vibratory placement or extraction of sheeting is not ad-vised. This method can cause severe disturbance to the bedding and liquefaction ofthe surrounding soils. Where steel sheet piling is used as sheathing and is to beremoved or pulled, then, to minimize disturbance to the pipe embedment, it shouldbe installed so that it is not closer than one pipe diameter or 18 inches, whichever islarger, from either side of the pipe and the void left by removal of the sheathingshould be filled with embedment material.

Portable Trench Shield

Portable trench shields or boxes which provide a moveable safe working area forinstalling pipe can be used with flexible pipe. However, the installation technique offlexible pipe with the shield is not the same as it is for rigid pipe. In order to use theshield with PE pipe, all excavation of the trench below the pipe crown elevationshould be done from inside of the shield. That is, the backhoe operator should diginside of the shield and force the shield down as soil is removed. (The technique of

Underground Installation of PE Piping - 20

Page 27: Ppi Hdpe Under

digging out a large hole to pipe invert grade then sliding the shield into it will result inexcess deflection of PE pipe.) After placing the pipe in the trench, embedment ma-terial should be placed in lifts and the shield vertically raised after each lift is placedso that workers can shovel embedment material under the shield to fill the void cre-ated by the shield wall. Figure 5 illustrates the steps used with a Portable TrenchShield.

Figure 5Installing PE Pipe with a Portable Trench Shield

If trench soil quality and applicable safety regulations permit, it is best to use shieldsthat are placed with no portion of their sides extending lower than one-quarter of apipe diameter below the pipe crown. This minimizes the amount of lifting requiredand precludes the possibility for disturbing embedment materials. If the sides of thetrench box or shield do project below this point, then the box should be lifted verti-cally as described above, before moving along the trench.

The minimum inside clear width of the box, or shield, should allow for the minimumtrench width requirements for the pipe to be satisfied plus an additional 12 to 24inches depending on the pipe diameter.

Underground Installation of PE Piping - 21

Page 28: Ppi Hdpe Under

INSTALLATION PROCEDURE GUIDELINES

The following guidelines for the installation of PE pipe are based on the discussionsof the previous sections. The reader is advised to see PPI Technical Report TR31for more specific installation recommendations for solid wall SDR pipe. If the readeris interested in installing 24" or smaller pipes at 16 feet or less, see Appendix 1.

The installation procedure discussed in this section consists of trench floor prepara-tion, providing a sufficient stabile working platform and meeting the design graderequirements. Following pipe placement, backfill material which has been selectedwith regards to potential material migration, required density, depth of cover, weightof soil and surcharge loads is installed as follows:

1. Bedding material is placed and leveled.2. Haunching is placed and, if required, compacted as not to dis-

turb the pipe from its line and grade.3. The remainder of the primary initial backfill is placed and, if

required, compacted in lifts.4. Secondary backfill is used to protect the pipe during the final

backfilling operation and also to provide support for the topportion of the pipe.

5. The final backfill may consist of any qualifying material thatsatisfies road construction or other requirements and whenrequired must be compacted.

Trench Floor Preparation

The trench floor must have sufficient stability and load bearing capacity to present afirm working platform during construction to maintain the pipe at its required align-ment and grade and sustain the weight of the fill materials placed around and overthe pipe. The trench bottom should be smooth and free from sloughed side wallmaterial, large stones, large dirt clods, frozen material, hard or soft spots due torocks or low bearing strength soils, and any other condition that could lead to non-uniform or unstable support of the pipe. The trench bottom must be kept dry duringinstallation of the pipe and the embedment materials. All foundation and beddingmaterials must be placed and compacted according to the design requirements.Such materials should be selected to provide the necessary migration control whenrequired.

Over-excavation of the trench floor by more than 6 inches beyond grade requiresthat the over-excavation be filled with acceptable embedment material that is com-pacted to a density equal to that of the embedment material. If the over excavation

Underground Installation of PE Piping - 22

Page 29: Ppi Hdpe Under

exceeds 12 inches, it should be brought to proper grade with a suitably graded ClassI or 11 material that is compacted to the same density as that of the native soil but notless than the density requirements for the embedment materials.

In stable soils, the trench floor should be undercut by machine and then brought upto proper grade by use of a well-leveled bedding consisting of a 4 to 6 inch layer ofembedment material. This material should be compacted by mechanical means toat least 90 percent Standard Proctor Density. Class I material may be shovel slicedwhere the depth of cover permits.

In unstable soils, that may be too soft, of low load bearing capacity or otherwiseinadequate, the trench bottom must first be stabilized by soil modification, by provid-ing an alternate foundation, or by the removal of the undesirable material and re-placement with stable foundation material. A cushion of at least 4 inches of com-pacted bedding should be provided between any special foundation and the pipe.Adequacy of the stability of a trench bottom is difficult to evaluate by visual observa-tion and is therefore best determined by soil tests or at the site during installation.However, a warning of a potentially unstable soil condition is given by a trench bot-tom that cannot support the weight of workmen.

Uneven soil support conditions, where the grade line traverses both soft and hardspots, requires special consideration. Ballasting is the most frequently employedtechnique to deal with randomly encountered short sections of soft soils.

When differential conditions of pipe support might occur, such as in transitions frommanholes to trench or from hard to soft soils, a transition support region should beprovided to ensure uniform pipe support and preclude the development of shear, orother concentrated loading on the pipe. The following procedure may be used:

The soil next to the more rigid support is over-excavated to a depth ofnot less than 12 inches over a distance of 2 pipe diameters along thepipe line; over the next 2 diameters away from the rigid support, thedepth of over-excavation is gradually decreased until it meets the nor-mal trench depth. See Figs. 6 and 7. Pipe grade is then restored by theaddition of granular material that is compacted. In the case of connec-tions to manholes and buildings, the distance of over-excavation alongthe pipe length should be no less than required to reach undisturbedsoil.

Underground Installation of PE Piping - 23

Page 30: Ppi Hdpe Under

Figure 6Pipe Support in Transition from Rigid Support to Normal

Trench Support

Figure 7Proper Transition from Rock Trench Bottom to Normal

Trench Support.

Backfilling and Compaction

Backfilling should follow pipe placement and assembly as closely as possible. Suchpractice prevents the pipe from being shifted out of line by cave-ins, protects the pipefrom external damage, eliminates pipe lifting due to flooding of open trench and invery cold weather lessens the possibility of backfill material becoming frozen. Thequality of the backfill materials and their placement and compaction will largely de-termine the pipe’s ultimate deformation and alignment. Backfill material should be

Underground Installation of PE Piping - 24

Page 31: Ppi Hdpe Under

selected with consideration of potential material migration to, or from, the trench walland other layers of embedment material. Under most circumstances, compactionwill be required for all material placed in the trench from 6 inches beneath the pipe toat least 6 inches above the pipe.

The required density of the bedding, haunching and the primary and secondary ini-tial backfill material will depend on several considerations such as depth of cover,weight of soil, and surcharge loads. The minimum density for these materials shouldbe equal to 85 percent Standard Proctor Density for Class I and II materials or 90percent Standard Proctor Density for Class III or IVa materials. For Class II, III, andIVa materials, compaction will always be required to obtain these densities. Class Imaterial placed by shovel slicing will generally have a minimum density of 85 percentStandard Proctor, however, its E’ may not be greater than 750 psi. Just dumpingClass I material into the trench may produce densities near 85 percent, however,except in shallow cover without live loads, this method will normally not provide ad-equate support to the pipe as voids may exist under the pipe haunches or elsewherein the material.

Backfill Placement

Bedding performs a most important function in that it levels out any irregularities inthe trench bottom, assuring uniform support and load distribution along the barrel ofeach pipe section and supports the haunching material. A mat of at least 6 inches ofcompacted embedment material will provide satisfactory bedding.

Haunching material must be carefully placed and compacted so as not to disturb thepipe from its line and grade while ensuring that it is in firm and intimate contact withthe entire bottom surface of the pipe. Usually a vibratory compactor has less ten-dency to disturb the pipe than and impact tamper.

Primary initial backfill should be placed and compacted in lifts evenly placed on eachside of the pipe. The lifts should not be greater than 12 inches for Class I, 8 inchesfor Class II, and 6 inches for Class III and IVa materials. The primary initial backfillshould extend up to at least three-quarters of the pipe diameter to perform its func-tion of pipe side support as shown in figure 2. If the construction does not call for theuse of a secondary initial backfill, then the primary layer should extend to not lessthan 6 inches above the pipe crown. In any location where the pipe may be coveredby existing or future ground water, the primary initial backfill should extend up to atleast 6 inches over the pipe crown for pipe up to 27 inch diameter and to at least 12inches over the pipe for larger pipe.

Secondary initial backfill serves to protect the pipe during the final backfilling opera-tion and to provide support to the top portion of the pipe. Secondary initial backfillshould extend to 6 inches above pipe for pipe up to 24 inches and to 12 inches forlarger pipe. These depths can be modified slightly depending on the depth of burial,

Underground Installation of PE Piping - 25

Page 32: Ppi Hdpe Under

ground water level, and type of native soil. Compaction of this layer should be to thesame extent as that specified for the primary initial backfill. If the final backfill mate-rial contains large rock (boulder or cobble size) or clumps then 18 inches of cushionmaterial should be provided in the secondary initial backfill. Secondary initial backfillmay consist of a different material than the primary initial backfill, however, in mostcases should be a material that will produce an E’ of at least 750 psi.

The final backfill may consist of any material that satisfies road construction or otherrequirements. The material must be free of large stones or other dense hard objectswhich could damage the pipe when dropped into the trench or create concentratedpipe loading. The final backfill may be placed in the trench by machines.

There should be at least one foot of cover over the pipe before compaction of thefinal backfill by the use of self-powered compactors. Construction vehicles shouldnot be driven over the pipe until a three foot cover of properly compacted material isplaced over the pile.

When backfilling on slopes, the final backfill should be well compacted if there is anyrisk of the newly backfilled trench becoming a “French Drain”. Greater compactionmay be achieved by tamping the final backfill in 4 inch layers all the way from the topof the initial backfill to the ground or surface line of the trench. To prevent water fromundercutting the underside of the pipe, concrete collars keyed into the trench sidesand foundation may be poured around the pipe or a polyethylene waterstop can befabricated onto the pipe.

INSPECTION

One principal function of the inspector is to insure that the pipe meets the accep-tance deflection specified by the engineer. Besides seeing that the installation prac-tice of the contractor meets the specification, the inspector should periodically makedeflection measurements of the pipe. Where the pipe can be accessed inspectioncan be as simple as going through the pipe and taking diameter measurements. Forsmaller pipe, a mandrel or deflection measuring device can be pulled through thepipe.

Good installation practice consists of frequent deflection checks at the beginning ofthe project or any where there is a significant change in the installation procedure,soil formation, or materials. A prudent contractor will check deflection every 100 or200 ft under these circumstances. After the contractor is confident in the procedurethe frequency of inspection can be relaxed.

Typically, acceptance deflection is measured after the pipe has been installed for atleast 30 days. This gives the soil time to settle and stabilize. Where pipe exceeds itsacceptance limit, it should be uncovered and the embedment material should bereplaced and compacted.

Underground Installation of PE Piping - 26

Page 33: Ppi Hdpe Under

REFERENCESWatkins, R. K. Buned Structures, Foundation Engineering Handbook (ed-ited by H. F. Winterkom and H. Y. Fang), Van Nostrand Reinhold Co., NewYork, NY(1975).Spangler, M. G., Soil Engineenng, International Textbook Co., Scranton,PA (1951).Howard, A. K., The USBR Equation for predicting Flexible Pipe Deflection,Proc. Int. Conf. on Underground Plastic Pipe, ASCE, New Orleans, LA (1981).Howard, A. K., Modulus of Soil reaction Va/ues for buned Flexible Pipe,Joumal of the Geotechnical Engineering Division, ASCE, Vol. 103, No. GT1,January, 1972, pp. 3346.

ACKNOWLEDGMENTS

This chapter has been produced by an industry task force of authors and review-ers, working under the direction of Steve Sandstrum, Solvay Polymers, Inc., chiefeditor of PPI Handbook on Polyethylene Piping. Other members of the task forceinclude:

Ed Zukowski, Union Carbide Chemicals & Plastics Co., Inc.Larry Petroff8, PLEXCO/SpiroliteWilliam Adams, PLEXCO/SpiroliteRoy Wood, Phillips Driscopipe, Inc.William Nichol, Phillips Driscopipe, Inc.Will Bezner, CSR Pipeline SystemsStanley Mruk, ConsultantTim Wood, T. D. Williamson, Inc.Stephen Boros, Solvay Polymers, Inc.David Dutton, McElroy Manufacturing, Inc.James Inhofe, Central Plastics Co.Jeffrey S. McCoy, Fina Oil & Chemical CompanyDick Rainer-Handreck, Ciba-Geigy Corporation

Underground Installation of PE Piping - 27

Page 34: Ppi Hdpe Under

Underground Installation of PE Piping - 28

Page 35: Ppi Hdpe Under

APPENDIX 1

SIMPLIFIED INSTALLATION GUIDELINES FOR PRES-SURE PIPE

(Small diameter pressure pipe usually have adequate stiffness and are usually in-stalled in such shallow depths that it is unnecessary to make an internal inspection ofthe pipe for deflection.)

A quality job can be achieved for most installations following the simple steps thatare listed below. These guidelines apply where the following conditions are met:

1. Pipe Diameter of 24 inch or less.2. SDR equal to or less than 26.3. Depth of Cover between 2.5 feet and 16 feet.4. Ground water elevation never higher than 2 feet be-

low the surface.5. The route of the pipeline is through stable soil.

Stable soil is sort of an arbitrary definition referring to soil that can be cut vertically ornearly vertically without significant sloughing or soil that is granular but dry (or de-watered) that can stand vertical to at least the height of the pipe. These soils mustalso possess good bearing strength. (Quantitatively, good bearing capacity is de-fined as a minimum unconfined compressive strength of 1000 psf for cohesive soilsor a minimum standard penetration resistance of 10 blows per ft for coarse grainedsoils.) Examples of soils that normally do not possess adequate stability for thismethod are mucky, organic, or loose and wet soils.

Where the above conditions are met, the specifier can write installation specifica-tions from the following steps. The specifier should insure that all OSHA, state andlocal safety regulations are met.

The following are general guidelines for the installation of PE pipe. Other satisfac-tory methods or specifications may be available. This information should not besubstituted for the judgment of a professional engineer in achieving specific require-ments.

SIMPLIFIED STEP-BY-STEP INSTALLATIONTrenching

Trench collapses can occur in any soil and account for a large number of workerdeaths each year. In unbraced or unsupported excavations, proper attention shouldbe paid to sloping the trench wall to a safe angle. Consult the local codes. All trenchshoring and bracing must be kept above the pipe. (If this is not possible consult the

Underground Installation of PE Piping - A1-1

Page 36: Ppi Hdpe Under

more detailed installation recommendations.) The length of open trench required forfused pipe sections should be such that bending and lowering the pipe into the ditchdoes not exceed the manufacturers minimum recommended bend radius and resultin kinking. The trench width at pipe grade should be equal to the pipe outer diameter(O.D.) plus 12 inches.

De-watering

For safe and proper construction the ground water level in the trench should be keptbelow the pipe invert. This can be accomplished by deep wells, well points or sumppumps placed in the trench.

Bedding

Where the trench bottom soil can be cut and graded without difficulty, pressure pipemay be installed directly on the prepared trench bottom. For pressure pipe the trenchbottom may undulate, but must support the pipe smoothly and be free of ridges,hollows, and lumps. In other situations and for gravity drain or sewer pipe, beddingmay be prepared from the excavated material, if it is rock free and well broken upduring excavation. For gravity flow systems, the trench bottom should be gradedevenly. The trench bottom should be relatively smooth and free of rock. When rocks,boulders, or large stones are encountered which may cause point loading on thepipe, they should be removed and the trench bottom padded with 4 to 6 inches oftamped bedding material. Bedding should consist of free flowing material such asgravel, sand, silty sand, or clayey sand that is free of stones or hard particles largerthan one-half inch.

Pipe Embedment

Figure 1 shows trench construction and terminology. Haunching and initial backfillare considered trench embedment materials. The embedment material should be acoarse grained soil, such as gravel or sand, or a coarse grained soil containing fines,such as a silty sand or clayey sand. The particle size should not exceed one-halfinch for 2 to 4 inch pipe, three-quarter inch for 6 to 8 inch pipe and one inch for allother sizes. Where the embedment is angular, crushed stone it may be placedaround the pipe by dumping and slicing with a shovel. Where the embedment isnaturally occurring gravels, sands and mixtures with fines, the embedment shouldbe placed in lifts, not exceeding 6 inches in thickness, and then tamped. Tampingshould be accomplished by using a mechanical tamper. Compact to at least 85percent Standard Proctor density as defined in ASTM D-698. Under streets androads, increase compaction to 95 percent Standard Proctor density.

Underground Installation of PE Piping - A1-2

Page 37: Ppi Hdpe Under

Pressu re Testing

If a pressure test is required, it should be conducted after the embedment material isplaced.

Trench Backfill

The final backfill may consist of the excavated material, provided it is free from un-suitable matter such as large lumps of clay, organic material, boulders or stoneslarger than 8 inches, or construction debris. Where the pipe is located beneath aroad, place the final backfill in lifts as mentioned earlier and compact to 95 percentStandard Proctor Density.

END OF SECTION

Underground Installation of PE Piping - A1-3

Page 38: Ppi Hdpe Under

APPENDIX 2

GUIDELINES FOR PREPARING AN INSTALLATIONSPECIFICATION

GENERAL REQUIREMENTS

Subsurface conditions should be adequately investigated and defined prior to estab-lishing final project specifications. Subsurface investigations are necessary to deter-mine types of soil that are likely to be encountered during construction, existence ofrock, thickness of strata layers, relative quality of strata layers, presence of otherutilities, and presence of ground water. These findings are useful both in specifyingthe proper pipe for an application and in planning construction procedures.

Prior to start of construction the on-site surface conditions, including water run off,traffic and other problems should be appraised by a on-site inspections of the pro-posed pipeline location. Also, all the construction documents, including plans, sub-soil information and project specifications should be reviewed. All required permitsshould be obtained and arrangements made to insure compliance with all applicablefederal, state, and local safety regulations.

The installation should be checked throughout the construction period by an inspec-tor who is thoroughly familiar with the contract specifications, materials and installa-tion procedures. The inspection should ensure that significant factors such as trenchdepth, width, grade, pipe foundation, quality and compaction of embedment andbackfill comply with contract requirements.

The following specification may be used for most gravity drain projects in stable orde-watered trenches. Where special methods of stabilization are required as dis-cussed previously, a more detailed specification may be required.

Underground Installation of PE Piping - A2-1

Page 39: Ppi Hdpe Under

GUIDE SPECIFICATION

HIGH DENSITY POLYETHYLENE (HDPE)GRAVITY-DRAIN PIPE (F-894 PIPE)

Various construction techniques can be used for installing PE pipe. The techniquesdescribed below are considered satisfactory, but there may be other techniques whichwill work equally as well. The information below is considered reliable, but the authormakes no warranty, expressed or implied, as to the content and disclaims all liabilitytherefor. This information should not be substituted for the judgment of a profes-sional engineer in achieving specific requirements.

PART I - GENERAL

1.01 SCOPE

The work covered by this section includes furnishing all labor, equipment, and mate-rials required to supply, install, and test high density polyethylene (HDPE) pipe, in-cluding accessories, as shown on the drawings and/or specified herein.

1.02 QUALITY ASSURANCE

A. The Contractor shall submit to the Engineer in writing that the pipefurnished under this specification is in conformance with the materialand mechanical requirements specified herein.

B. Each HDPE pipe length shall be clearly marked with the following:

1. Manufacturer’s Name

2. Pipe Size

3. SDR or Ring Stiffness Constant Classification

4. Production Code Designating Plant Location, Machine, and Dateof Manufacture

1.03 SHOP DRAWINGS

A. Complete shop drawings on all piping and accessories shall be submitted tothe Engineer.

1.04 STORAGE

A. All pipe and accessories shall be stored on flat, level ground with no rocksor other objects under the pipe.

Underground Installation of PE Piping - A2-2

Page 40: Ppi Hdpe Under

B. The maximum recommended stacking height for HDPE pipe is given inTable A2.1

Table A2.1Allowable Stacking Heights for F-894 Pipe

Nominal Number ofPipe Size Rows High

18 421 424 327 330 333 236 242 248 154 1

>54 1

PART 2 - PRODUCTS2.01 GENERAL

A. Apart from the structural voids and hollows associated with some pro-file wall designs, the pipe and fittings shall be homogenous throughoutand free from visible cracks, holes, foreign inclusions or other injuriousdefects. The pipe shall be as uniform as commercially practical incolor, opacity, density, and other physical properties.

2.02 HIGH DENSITY POLYETHYLENE (HDPE) PIPE

A. HDPE Profile wall pipe and fittings shall be manufactured in accor-dance with the requirements of {Engineer: specify appropriate ASTMdesignation here. For profile pipe designate ASTM F 894-85. For solidwall DR pipe designate ASTM F 714.}

B. HDPE profile wall pipe shall be made from a plastic compound meet-ing the requirements of Type III, Class C, Category 5, Grade P34 asdefined in ASTM D 1248 and with established hydrostatic design basis(HDB) of not less than 1250 psi for water at 73.40 F. Determined inaccordance with method ASTM D 2837. Materials meeting the require-ments of cell classification PE 334433C or higher cell classification inaccordance with ASTM D-3350 are also suitable. (Engineer: specifyappropriate HDB and Cell class as underlined above.)

C. Material other than those specified above may be used as part of the

Underground Installation of PE Piping - A2-3

Page 41: Ppi Hdpe Under

profile wall construction, for example, as a coretube to support the shapeof the profile during the processing, provided that these materials arecompatible with the PE material, are completely encapsulated in thefinished product, and in no way compromise the performance of thePE pipe product in the intended use.

PART 3 - EXECUTION3.01 PIPE LAYING

A. Before the sewer pipe is placed in position in the trench, the bottomand sides of the trench shall be carefully prepared, the required bed-ding placed, and bracing and sheeting installed where required. Thetrench shall be excavated to the dimensions shown on the Engineer’sdrawings. Each pipe shall be accurately placed to the line and gradecalled for on the drawings. Grade shall be controlled by a laser beamor batter boards and a Mason’s line. All equipment for maintaininggrade shall be furnished by the Contractor.

B. All pipe and fittings shall be inspected before they are installed.C. Pipe laying shall proceed upgrade, starting at the lower end of the

grade with the bells uphill.D. If the trench bottom does not provide a firm and stable working plat-

form, sufficient material shall be removed and replaced with approvedcompacted materials to provide a firm foundation for the pipe.

E. Pipe trenches shall be kept free from water during pipe laying, jointingand until sufficient backfill has been placed to prevent flotation of thepipe. The minimum height of backfill to prevent flotation may be ob-tained from the Engineer. The Contractor may use sump pumps, wellpoints, or other devices to remove water from the trench bottom. Smallpuddles that are no closer than 4" from the bottom of the pipe areacceptable. The contractor shall provide ample means and devices topromptly remove and dispose of all water from any source entering thetrench.

F. No connection shall be made where joint surfaces and joint materialshave been soiled by earth in handling until such surfaces are thor-oughly cleaned by washing and wiping.

G. As the work progresses, the interior of all pipes shall be kept clean.After each line of pipe has been laid, it shall be carefully inspected andall earth, trash, rags, and other foreign matter removed from the inte-rior.

H. Backfilling of trenches shall be started immediately after the pipe isplaced in the trench.

I. If the Engineer determines that no ground water will be encountered orthat the maximum height of the ground water level, which develops

Underground Installation of PE Piping - A2-4

Page 42: Ppi Hdpe Under

from seepage or other ground water movement through the existingsoil formation or the pipe trench, will not exceed the springline of thepipe during the service life of the line, the pipe shall be backfilled ac-cording to detail drawing Figure A1 titled “Dry Installation Bedding Re-quirements”.

J. If the Engineer determines that ground water will be encountered orthat the ground water level is anticipated to exceed the springline ofthe pipe during the service life of the line, backfill pipe according to thedetail drawing Figure A2, titled “Wet Installation Bedding Requirements”.

K. Shoring, sheeting, or trench shields shall be utilized in such a manneras to minimize disturbance of the backfill material beneath the pipecrown. Trench sheeting that extends below the crown should either beleft permanently in place or consist of adequately supported steel sheets1" (one inch) thick or less which can be extracted with minimal distur-bance to the pipe embedment. Where moveable trench shields areused, the following steps shall be followed unless an alternate tech-nique that does not disturb the pipe embedment can be demonstrated:

1. Excavation of the trench below the elevation of the pipe crownshall be done from inside of the trench shield to prevent the accu-mulation of loose or sloughed material along the outside of theshield. Excavation of the trench ahead of the shield at an eleva-tion below the pipe crown is not permitted unless approved by theEngineer.

2. After laying the pipe in the trench, bedding and pipe embedmentshall be placed in lifts and the shield must be lifted in steps. Asthe shield is lifted, embedment material shall be shoveled underthe shield so as to fill all voids left by the removal of the shield.

L. Bedding Material. Bedding material to be selected by Engineer. (Noteto Engineer: Bedding material to be selected by evaluating depth ofcover and E’ required to control deflection and buckling.)

When E’ = 1, 000 is required:Specify Class I material shovel sliced to a minimum density of 85 per-cent Standard Proctor, or Class II material with mechanical compac-tion to a minimum density of 90 percent Standard Proctor, or Class IIImaterial with mechanical compaction to a minimum density of 90 per-cent Standard Proctor. (Embedment Classes are defined in ASTM D-2321.)

When E’ = 2, 000 is required:Specify Class I or Class II material with mechanical compaction to aminimum density of 90 percent Standard Proctor.

Underground Installation of PE Piping - A2-5

Page 43: Ppi Hdpe Under

When E’ = 3,000 is required:Specify Class I material with mechanical compaction to a minimumdensity of 90 percent Standard Proctor.

M. Backfill material placed under the pipe haunches shall be thoroughlyshovel sliced along the length of the pipe.

N. Where compaction of backfill materials is required, compact by me-chanical means. Suitable mechanical means includes vibratory sleds,gasoline driven impact tampers, and air driven impact tampers or otherapproved means. Compact to a minimum of 90 percent Standard Proctoror as required by the Engineer.

O. Pipe embedment soil shall be placed in lifts as follows:

1. Lift thickness for Class I material shall not exceed 12 inches.2. Lift thickness for Class II material shall not exceed 8 inches.3. Lift thickness for Class III material shall not exceed 6 inches.

P. After completing backfill in the pipe zone the trench shall be back-filled to grade with native soil. Where pipe is located beneath streets,compact backfill to a minimum of 95 percent Standard Proctor orotherwise as directed by the Engineer. HDPE profile pipe shall not besubject to a roller or wheel loads until a minimum of one diameter or36" (whichever is larger) of backfill has been placed over the top ofthe pipe and a hydrohammer shall not be used until a minimum depthof one diameter or 48" (whichever is larger) of backfill has been placedover the top of the pipe.

3.03 CONNECTIONS

A. Connections to existing lines shall be made by coupling a piece ofsmooth O.D. HDPE pipe to the existing line. The coupling shall be aflexible elastomeric boot with stainless steel clamps. The coupling isto be encased in cement stabilized sand, grout, or concrete.

B. Connections to concrete manholes shall be made using smooth O.D.pipe and water stops, profile pipe cast into the concrete, or via elasto-meric sleeves or gaskets precast in the manhole. Since the particulartechnique used is highly dependent on the construction method theseconnections can not be guaranteed by the manufacturer to be leakfree.

Underground Installation of PE Piping - A2-6

Page 44: Ppi Hdpe Under

Figure A1Dry’ Installation Bedding Requirements for HDPE Profile Wall

Pipe

Figure A2Wet1 Installation Bedding Requirements for HDPE Profile Wall

Pipe

C. Connections to HDPE manholes shall be made using closure pieceswith shoulder gaskets.

A = 1/4” to 1” class I, II, or III MaterialIf cover < 18 ft - shovel sliceIf cover > 18 ft - compact to at least 90%Standard Proctor per ASTM D-698If cover > 24 ft - Use wet installation beddingrequirements (Figure A2)

S = Selected earth backfill compacted to at least90% Standard Proctor per ASTM D-698

H = 6 inches for 18” to 36” pipe.= 12 inches for 42” to 84” pipe= 18 inches for 96” to 120” pipe

F = 4 inches for 18” to 36” pipe.= 6 inches for 42” to 84” pipe= 8 inches for 96” to 120” pipe

Bd = OD + 18 inches - See Table 3= OD + 18 inches for 18” to 33” pipe= OD + 24 inches for 36” to 60” pipe= OD + 36 inches for 66” to 84” pipe= OD + 48 inches for 96” to 120” pipe

1Pipe springline elevation permanently abovegroundwater.

Compact Class I or Class II Material2 to aminimum of 90% Standard Proctor per ASTMD-698.H = 6 inches for 18” to 36” pipe.

= 12 inches for 42” to 84” pipe= 18 inches for 96” to 120” pipe

F = 4 inches for 18” to 36” pipe.= 6 inches for 42” to 84” pipe= 8 inches for 96” to 120” pipe

Bd = OD + 18 inches - See Table 3= OD + 18 inches for 18” to 33” pipe= OD + 24 inches for 36” to 60” pipe= OD + 36 inches for 66” to 84” pipe= OD + 48 inches for 96” to 120” pipe

1Pipe springline elevation permanently abovegroundwater.2Selection of bedding material to be made byEngineer based on pipe design requirements(3.01).

Underground Installation of PE Piping - A2-7

Page 45: Ppi Hdpe Under

3.04 PIPE TUNNELS AND CASING

A. The annular space between HDPE pipe and the casing pipe shall befilled with concrete grout. (Engineer: Grout is required where the pipe’sallowable hydrostatic buckling resistance is less than the water pres-sure created by groundwater entering the casing.) The Contractor’sprocedure for placing the grout shall be approved by the Engineer.After installation of pipe in casing, the casing shall be kept dewatereduntil grouting is completed. Grout shall be placed by gravity flow only.Do not pressure grout PE pipe in a casing.

3.05 INSPECTION AND TESTING

A. After completion of any section of sewer, the grades, joints, and align-ment shall be true to line and grade. There shall be no visual leakageand the sewer shall be completely free from any cracks and from pro-truding joint materials, deposits of sand, mortar or other materials onthe inside to the satisfaction of the Engineer.

B. At the Engineer’s request, a deflection test shall be performed by theContractor. The deflection can be measured mechanically by a man-drel or manually using an extension ruler. The final deflection test shallnot be made on a section of sewer until all the backfill on that sectionhas been in-place for 30 days. However, the Contractor shall deflec-tion test the first 300-400 feet of pipe after it has been backfilled inorder to verify that the installation procedures are adequate to meetthe requirements of the contract. No additional pipe shall be laid untilthis test has been successfully completed. Pipe deflection may bedetermined by direct vertical measurement of no less than 4 equallyspaced points in each pipe section or by pulling a mandrel.

For solid wall PE pipe deflection shall not exceed 5 percent of the l.D.For profile pipe, deflection shall not exceed 5 percent of base l.D. asindicated in Table A2-2

All excess deflections shall be corrected. The Contractor shall correctthe deficiency and retest the pipe.

Underground Installation of PE Piping - A2-8

Page 46: Ppi Hdpe Under

Table A2-2Minimum Acceptable Diameter

Nominal Minimum AcceptablePipe Size Base l.D. Diameter

(in.) (in.) -5% of Base l.D. (in.)

18 17.34 16.4721 20.26 19.2524 23.19 22.0327 26.11 24.8030 29.02 27.5733 31.94 30.3436 34.86 33.1242 40.67 38.6448 46.48 44.1654 52.29 49.6860 58.10 55.2066 63.91 60.7172 69.72 66.2384 81.34 77.2796 92.96 88.31

C. The Contractor shall conduct either an infiltration test or a water test forleakage as determined by the Engineer. Testing shall be conducted inaccordance with all applicable safety standards.

1. Infiltration Test

Infiltration shall not exceed 50 gallons per 24 hours per inch ofdiameter per mile of sewer. Contractor shall furnish all supplies,materials, labor, service, etc., needed to make infiltration orexfiltration tests including water. No separate payment will bemade for equipment, supplies, material, water, or services.

Any leakage, including active seepage, shall be corrected wheresuch leakage exists until the pipelines meet the requirements ofthe allowable leakage specifications.

Infiltration tests shall be made when groundwater level is 18inches or more above the top of the outside of the pipe.

2. Water Test

When normal groundwater does not stand at a level outside the

Underground Installation of PE Piping - A2-9

Page 47: Ppi Hdpe Under

pipe so as to enable infiltration tests to be made to the satisfac-tion of the Engineer, the Contractor shall make exfiltration testsby filling the pipe or sections thereof with water to a head of notless than 2 ft. above the top of the outside of the pipe and ob-serving the amount of water required to maintain this level.

3.06 CLEANUP

A. After completing each section of the sewer line, the Contractorshall remove all debris, construction materials, and equipmentfrom the site of the work, grade, and smooth over the surface onboth sides of the line and leave the entire right-of-way in a clean,neat, and serviceable condition.

END OF SECTION

Underground Installation of PE Piping - A2-10

Page 48: Ppi Hdpe Under

APPENDIX 3

BASIC SOIL CONCEPTS FORFLEXIBLE PIPE INSTALLATION

A1.0 Soil Classification

The embedment soil surrounding a flexible pipe prevents pipe from deflecting throughits shear strength and stiffness. Shear strength enables the soil to resist distortionmuch like a solid body. Shear strength, or shear resistance as it is often called,arises from the structure of the soil’s fabric. Soil is an assemblage of (1) mineralparticles such as silica or aluminum silicates, (2) water, and (3) air. Mineral particlescan range in size from the large, such as boulders, to the microscopic, such as thecolloidal particles making up clay. The size of the individual soil particles or grainshas a significant effect on the soil’s behavior. Embedment soil is classified aseither”fine” grained or”coarse grained

A1.1 Fine grain soil (clay and silt)

Very small (colloidal) size soil particles are capable of adsorbing large quantities ofwater, as much as 10 times their own weight. These particles attract each other toproduce a mass which sticks together. This property is called cohesion or plasticity.Soils containing such particles are referred to as “cohesive” and include clayey soils.Cohesion gives clayey soils resistance to shear. The strength of clayey soils isdependent on the amount of water within the soil. As the content of water increases,the shear resistance decreases. Therefore, when using clays as pipe embedmentbeneath the ground water level one must exam its sensitivity to water. Fat clays(CH), which are highly expansive, usually make poor embedment materials. (CH isthe USCF soil classification symbol for fat clay.) Lean clays (CL), or other clayshaving relative low sensitivity to water, sometimes can be used for embedment.

While silts possess little to no cohesion they are composed of very fine grains, whichmakes them behave somewhat like clay in that they can contain a high percentageof water. It is also common for silt and clay to occur together. So the generalclassification schemes for pipe embedment usually treat silts and clays similarly.(USCF symbols for inorganic silts are ML and MH and for organic silts OL and OH.)

A1.2 Coarse grain soils

Assemblages of larger sized particles such as sands (S) and gravels (G) do notexhibit plasticity. Water has less effect on these materials. These soils are called“cohesionless” or “granular.” Normally, cohesionless soils have high shear resis-tances. When a mass of cohesionless soil is sheared individual grains either roll,slide, fracture, or distort along the surface of sliding. Likewise, many cohesive soilscontain grains of sand, so they can exhibit significant shear resistance. These mate-

Underground Installation of PE Piping - A3-1

Page 49: Ppi Hdpe Under

rials make excellent embedment in wet or dry conditions.

A2.0 Density and Compaction

When discussing the installation of embedment material two terms are used exten-sively. They are compaction and density. These terms are defined, herein, to assistthe reader.

Density refers to the weight of a particular volume of soil As discussed above soilconsists of three materials or phases: a mineral phase, water, and air. As the soil iscompacted the mineral phase may undergo some change but typically the air andwater are expelled from the soil and the overall volume is reduced. The weight of themineral phase stays the same. Thus, a given weight of mineral phase occupies asmaller volume after compaction. Typically, when densities are given they are basedon the dry unit weight of the soil (which is the weight of the mineral phase only)occupying a given volume, say a cubic foot.

Compaction , on the other hand, refers to the amount of energy imparted into thesoil to reduce its volume. Typically, more energy, often called compactive effort, isrequired to increase the density of a fine grain soil than a coarse grain soil. Onereason for this is that the fine grain soil has cohesion which must be overcome inorder for the mineral phase particles to be pushed closer together. Another reasonis that it is harder to force the water out of a fine grain material because of its lowpermeability.

A2.1 Methods of Measuring Density

There are two general categories of density measures. One method involves im-parting a standard amount of energy into the soil, say a fixed number of blows with aspecified weight. The Standard and Modified Proctor density tests are such meth-ods. The other measure involves comparing the in place density with the most denseand least dense arrangement that can be achieved with that soil. An example of thismethod is the Relative Density test.

The Proctor Density is the most common method used with pipe embedment and willbe discussed in somewhat more detail. Typically, a soil sample is taken from theembedment material and tested in the laboratory, where a precisely defined amountof compaction energy is applied to it, which compacts the sample to its Proctor den-sity. (This amount of energy is defined by the particular Proctor test, whether it is theStandard Proctor defined in ASTM D-698 or the Modified Proctor defined in ASTMD-1599. It is essentially independent of the soil type.) Then the sample is dried andits density measured. This density is the standard for this material and is consideredto be 100 percent of the Proctor density. The technician then makes measurementof the density (dry unit weight per cubic ft.) of the compacted embedment in the fieldusing, say, the nuclear density gauge. That density can then be compared with the

Underground Installation of PE Piping - A3-2

Page 50: Ppi Hdpe Under

density obtained in the laboratory. The comparison is usually expressed in percent.Typically, the field density must be at least 90 percent of the laboratory density. Inthis case, we would say the minimum density is 90 percent of the Proctor.

For pipe installation the important factor is soil stiffness. Because two soils arecompacted to the same Proctor density will not mean that the two soils provide equalsupporting stiffness for the pipe. A crushed stone at 90 percent Proctor will be muchstiffer than a clay compacted to 90 percent Proctor. This fact is illustrated by thedifferent E’ values assigned to these materials at these densities. In the case of thecrushed stone its E’ equals 3000 psi whereas the clay has an E’ of only a 1000 psi.Methods used to measure soil stiffness such as the California Bearing Ratio test arenot convenient for field testing of pipe Therefore, it is common to measure andmonitor density.

A3.0 Comparison Of Installation Of Rigid And Flexible Pipe

The underground installation of PE piping is similar to the installation of other pipingmaterials. The performance of the pipe will depend on the quality of the installation.Most PE piping is considered flexible, which means that the pipe will depend to someextent on the support of the embedment soil. Often the installation of flexible pipe iscontrasted with the installation of rigid pipe, but general requirements for both typesof pipe are similar. A narrow trench keeps loads on both types of pipe at a minimum.Both pipes require firm, stable bedding and uniform support under the haunches.The major difference between the two types of pipes is that the flexible pipe requiresside support, whereas the rigid pipe does not. Side support comes from the place-ment of firm, stable material beside the pipe. Often this is the same material usedbeside the rigid pipe with the exception that the material must be compacted. Suffi-cient space alongside the pipe must be provided for compacting the embedmentmaterial. The trench backfill placed above the pipe can be treated in the samemanner for both flexible and rigid pipe. The denser the material above the pipe, thesmaller the load applied to the pipe.

PE pipe interacts advantageously with the embedment soil. The viscoelastic proper-ties of PE and most soils are similar. As the pipe deflects, much of the earth istransmitted by arching action to the soil around the pipe. Thus the need for stablesoil beside the pipe. Rigid pipe is typically manufactured from materials that are notcompliant with soil deformation. As the soil settles load accumulates on the rigidpipe. If this load exceeds the pipe materials’ yield strength, the pipe will fail by asudden rupture or crack. PE is a ductile material that can yield. Under excessiveloads, PE pipe will deform without cracking. The deformation is often sufficient torelieve the accumulated stresses, so performance is not interrupted.

Deflection is usually the main criterion for judging the performance of a flexible pipe.Pipes that deflect have two advantages over rigid pipe: (1) the deflection permits therelease of accumulated stresses which promotes arching and causes a more uni-

Underground Installation of PE Piping - A3-3

Page 51: Ppi Hdpe Under

form distribution of earth pressure around the pipe and (2) the deflection affords aconvenient method of inspecting the quality of the installation - generally the lessdeflection the better the installation.

END OF SECTION

Underground Installation of PE Piping - A3-4

Page 52: Ppi Hdpe Under
Page 53: Ppi Hdpe Under