ppt
TRANSCRIPT
FINAL REVIEW OF THESIS ON
TECHNO-ECONOMIC ANALYSIS OF VIADUCT SYSTEMS OF DELHI
METRO
By Sanskriti Tiwary
Masters of Building Engineering & Management
School of Planning and Architecture, New Delhi
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
Aim of the study is to arrive at the parameters and constraints leading to selection of different viaduct systems for elevated corridors for infrastructure.
Aim
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
Scope Cost, Constructability, Speed of construction and Site constraints of:
• Precast viaduct systems
• Cast in-situ viaduct systems
• Balanced cantilever viaduct systems
Limitations • Structural calculations and loading aspect
• Construction techniques for pile and pier
• Operation and maintenance
• Rail laying and alignment
• Electrical and drainage services
• Construction of metro stations
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
Viaduct ??!
Oxford Dictionary
A long bridge-like structure, typically a series of spans,
carrying a road or railway across a valley or other low
ground.
Cambridge Dictionary
A long, high bridge, usually held up by many arches,
which carries a railway or a road over a valley.
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
Viaduct System ??!
A viaduct system
comprises of a
deck resting on
pier caps which
transfer the load to
the pier and then
pile cap and piles. Piles
Pile Cap
Pier
Pier Cap
Deck
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
Viaduct Systems Studied
Category Viaduct Systems
Pre-fabricated Single Segmental U Girder
Segmental Box
Cast in-situ Single Segmental Box Girder
I girder and slab
Balanced Cantilever Extra-dosed Bridge
BCLC at Jasola-Apollo
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
Precast Viaduct Systems
It is a construction product produced by casting concrete in a
reusable mold or "formwork" which is then cured in a
controlled environment, transported to the construction site
and lifted into place.
Casting Yard
Transportation
Launching
Site
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
Single Segmental U Girder
• Precast Pre-tensioned deck
• Metro in Faridabad from Badarpur to YMCA Chowk
• Only in this system, the pier caps are also precast
• Two cranes of 400 ton and 330 ton capacity each are used to lift a 150 ton weight and 27 meter long U-girder
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
Segmental Box • Precast Post-tensioned deck
• Launcher- fixed point & variable point
• Site – Near Mayur Vihar over Yamuna & IP Extension
• The launched segments are aligned, glued and then the cables are tensioned and grouted.
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
Parameters
Single Segmental U
Girder Segmental Box
Inferences
A B
Length of
viaduct studied 12500 m 650 m
The length of A studied is twenty
times that of B
Cost per meter ₹ 3,03,200 ₹ 3,84,615 + ₹ 20,00,000
The cost per unit length of A is
less than half of B if assembling
and disassembling of launcher Is
considered
Speed of
construction
390.63 m /month
43.33 m /month
The speed of construction of A is
9 times that of B
Max. clear span 27 m 41.6 m The max. clear span achieved by B
is 1.5 times that of A
Depth of girder 1.85 m 3 m The depth of girder of B is much
more than that of A
Site constraints
The space below the
viaduct is accessible
for construction
activities
The viaduct is
constructed over a
flowing river, thus the
space below the
viaduct can’t be used
A doesn’t have the site
constraints that B has
Aesthetic
Requirements
Levelled smooth
soffit
Levelled soffit,
however joints are
visible between
segments
Comparatively A is aesthetically
much more appealing
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
₹ 6,92,308 ₹ 3,03,200
Single
Segmental U
Girder
Segmental Box
VO
LUM
E
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
Cast in situ viaduct is poured into site-specific forms and cured on site.
Cast In-Situ Viaduct Systems
Single Segmental Box Girder
I Girder and Slab
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
• Precast post-tensioned • This system is used only where the site conditions
demand • It can be considered a transition element
between different types of viaduct systems if there is a difference in the sizes of pier caps
• It is best suited for spans were precast deck is not possible and/or costly and/or launching is not possible
• It requires ground support for shuttering and thus cannot achieve greater heights.
Single Segmental Box Girder
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
• I girders are precast pre-tensioned, still this system is considered under cast in-situ due to the large amount of cast in-situ works it requires.
• The girders are lifted and rested on the pier caps.
• They are stitched together with cross beams and at the end by end diaphragms, cast in-situ.
• Slabs are casted over the girders.
I Girder and Slab
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
Parameters
Single Segmental
Box Girder
I girder and slab
Inferences
C D
Length of
viaduct studied 28 m 2770 m
Length of D is almost a 100 times
that of C as only a single span of C
was required
Cost per meter ₹ 4,00,000 ₹ 2,61,733 Cost per unit length of C is 1.5
times that of D
Speed of
construction 37.33 m /month 115.42 m /month
Speed of construction of D is 3
times that of C
Max. clear span 28 m 31 m The difference in max clear span is
3 m
Depth of girder 2.25 m 2.25 m The depth of the girder is same
Site constraints
A single span was
casted on site due
to the pier cap size
constraints
No such constraint
C can be casted on site if there is a
difference in the pier cap size on
both ends, but it requires support
from ground.
Aesthetic
Requirements
Levelled soffit,
however
shuttering marks
are visible
Shows I girder and
web from below;
no smooth soffit
Comparatively C is aesthetically
more appealing
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
• Balanced cantilever construction implies construction of cantilever segments from
a pier in a balanced fashion on each side until the mid-span is reached and a
closure known as stitch segment is made with other half span cantilever
constructed from the preceding pier.
• The fundamental of the design is building a bridge deck by succession of segments
where each segment carries the weight of the next segment. Each segment is
integrated with the previous one as soon as it is strong enough. Each segment
becomes self-supporting and also becomes a base for a new segment.
Balanced Cantilever Viaduct Systems
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
The Pragati Maidan viaduct is an extra-dosed railway bridge with a main span of 93 m.
The deck cross-section has a U shape, which permits a perfect integration of the metro
system in the superstructure. The extra-dosed cables are covered by a concrete beam
that allows considering them as internal pre-stressing. This beam also increases the
stiffness of the main span.
Constraints:
• Crossing of 5 railway tracks
• Sharp plan curvature
• Railway vertical clearance
• Impossible location of intermediate piers
• No possible interruption of the railway traffic
• Minimum span length of 93 m
Extra-dosed Balanced Cantilever
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
The balanced cantilever bridge with a hundred metre long span is between Okhla
and Jasola metro stations over the Indian Railways tracks on the Central
Secretariat – Badarpur corridor. The bridge is part of the 20.16 km-long under-
construction Central Secretariat-Badarpur corridor.
Constraints:
• Crossing of 5 railway tracks
• Sharp plan curvature
• Railway vertical clearance
• Impossible location of intermediate piers
• No possible interruption of the railway traffic
• Minimum span length of 100 m
Balanced Cantilever at Jasola-Apollo
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
Parameters
Extra-dosed Bridge BCLC at Jasola-
Apollo Inferences
E F
Length of
viaduct studied 196.3 m 250 m
The length of viaduct under study is
comparable
Cost per meter ₹ 6,62,252 ₹ 2,77,000 The cost per meter of E is twice as
much as that of F
Speed of
construction 21.81 m /month 41.67 m /month
Speed of construction of F is almost
double the speed of construction
of E
Max. clear
span 93 m 100 m
The max. spans achieved are
comparable
Depth of girder 1.5 m – 3 m 2.5 m Depth of girder is comparable
Alignment Curved with a radius
of 302 m
Curved with a
radius of 300 m
Alignment is also comparable
Site constraints Railway line is
passing from under
Railway line is
passing from
under
Railway traffic cannot be
obstructed
Workers 230 130
More workers were engaged in E
than F
SANSKRITI TIWARY | BEM-539 | SCHOOL OF PLANNING AND ARCHITECTURE
Conclusion
Parameters
Single
Segmental
U Girder
Segmenta
l Box
Single
Segmenta
l Box
Girder
I girder
and slab
Extra-
dosed
Bridge
Balanced
Cantileve
r
A B C D E F
Greater Max Clear Span 1 4 2 3 5 6 High speed of Construction 6 4 2 5 1 3
Least Cost 4 1 3 6 2 5 Constraints Space constraint below the viaduct x 1 x x 1 1
Short viaduct (< 300m) x x 1 x 1 1
Long viaduct (> 300m) 1 1 x 1 x x
Aesthetic requirements 1 1 1 x 1 1 Viaduct at large heights (> 5m) 1 1 x 1 1 1