practical case studies in energy efficiency projects
TRANSCRIPT
1
Practical Case Studies in Energy Efficiency Projects
Dan Lienhoop
Indiana Conference on Energy Management
August 15, 2017
2Internal Use Only
Cummins global presence
Employeesworldwide
55,400190+ Countries
and territories
6continents
148Fortune 500 rank
Founded & headquartered in Columbus,
Indiana
19194
Operating Segments
Public Use 2
2
“…we believe that our survival in the very long run is as dependent upon responsible citizenship in our communities and in the society, as it is in responsible technological, financial and production performance.”
- - J. Irwin MillerFormer Chairman and CEO
1972
Cummins legacy and core values
3
Energy footprint & goal
12,500,000gallons diesel fuel
1,490,000,000cubic feet natural gas
$150 million total energy spend
919,000,000kWh electricity
770,000 metric tons CO2e emissions
12,500,000gallons diesel fuel
1,490,000,000cubic feet natural gas
$150 million total energy spend
919,000,000kWh electricity
770,000 metric tons CO2e emissions
4
Global footprint – 2016
Public Use
3
5Public Use
Comprehensive energy strategy
Estimated savings of$40 million per year from energy efficiency efforts
6Public Use
Enhance energy management
Upgrade facilities & equipment
Efficient new construction
Increase renewable energy
1
2
3
4
4
Enhance Energy Management
7
Training
Tools
Best practices
Tech support
Employee engagement
8
Enhance Energy Management
ISO 50001: Energy Management
System
5
Upgrade Facilities & Equipment
9
2020 Plan
• Capital investment ($12M/year)
• Project hopper• Campaigns
Investment criteria
• >11% IRR, and• <$1000/ton
CO2e, or• Strategic value
Declining rate of return
• 2016: 33% IRR• 2020: 22% IRR
(projected)
IRR = internal rate of return
Compressed Air Optimization
– Supply Side
– Demand Side
10
Upgrade Facilities & EquipmentPractical Case Studies
Most of the work
is lost in heat!
Why Focus on Optimizing Compressed Air Systems?
6
Compressed Air Optimization
– Supply Side Goals
• Limit blow-off to atmosphere
• Trim/Right size to plant demand
• Decrease supply pressure
– Supply Side Project Examples
• Centrifugal air compressor controls
• Rotary screw compressor addition
• Compressed air system volume & eliminate dead heads 11
Upgrade Facilities & EquipmentPractical Case Studies
Compressed Air Optimization
– Supply Side Project Examples
12
Upgrade Facilities & EquipmentPractical Case Studies
Centrifugal air compressor controls
Provide maximum turn down
based on supply air density
ability to turn down nearly ~40%
Manage multiple compressors
optimize required number needed
manage run-time
7
Compressed Air Optimization
– Supply Side Project Examples (Continued)
13
Upgrade Facilities & EquipmentPractical Case Studies
Rotary screw compressor addition
Provide further turn down capabilities outside the range of centrifugales
further eliminates potential blow-off to atmosphere
Compressed Air Optimization
– Supply Side Project Examples (Continued)
14
Upgrade Facilities & EquipmentPractical Case Studies
Compressed air system volume & eliminate dead heads
Reduces pressure drop
potential for overall system pressure reduction
Important to engineer a volume needs solution
8
Compressed Air Optimization
– Demand Side Goals
• Find alternative energy source in lieu of compressed air
• Reduce compressed air system leaks
• Ensure new installations do not exceed 90 psi demand through management of change process
– Demand Side Project Examples
• Centrifugal blower system
• Yearly ultrasonic PM program15
Upgrade Facilities & EquipmentPractical Case Studies
Compressed Air Optimization
– Demand Side Project Examples
16
Upgrade Facilities & EquipmentPractical Case Studies
• Centrifugal blower system
• Eliminated 3 compressed air blow off stations
• two systems had 2” supply pipe, one system had 1” supply pipe
• Reduced an estimated total CFM reduction of 8,284 CFMs (1,700 MWh)
• Note: centrifugal blower systems still require electricity to operate!
9
Compressed Air Optimization
– Demand Side Project Examples (continued)
17
Upgrade Facilities & EquipmentPractical Case Studies
• Yearly ultrasonic PM program
• Regularly maintained compressed air systems use only 7% more air of total capacity compared to 25% more of an unmaintained air system
• Ultrasonic allows for inspection during production, thus finding leaks otherwise not found when machines are off
Chilled Water System Optimization
• Goals
• Cooling Tower Efficiency
• Chiller trim capabilities
• Complete shutdown during heating months
• Project Examples
• Cooling Tower Replacement
• Trim Chiller Installation & Test Chiller(s) Installation
• Dry Cooler Installation 18
Upgrade Facilities & EquipmentPractical Case Studies
10
Chilled Water System Optimization
• Project Examples
19
Upgrade Facilities & EquipmentPractical Case Studies
• Cooling Tower Replacement• Increased condenser water capacity to
allow for future (trim) chiller
• Provide cooler condenser water to chiller system, resulting in more efficient chiller operation
• up to 47% less KW/Ton during design day compared to prior system
• Reduced electric usage of 5,381 MWh/year (about $500k/year)
Chilled Water System Optimization
• Project Examples (continued)
20
Upgrade Facilities & EquipmentPractical Case Studies
• Trim Chiller Installation• Trim to plant cooling demand
• Saves estimated 230 MWh/year
• Test Chiller(s) Installation• Allows for test operations to supply
own colder and consistent chilled water for special testing
• Eliminated need for running additional 1200 ton chiller during certain engine testing (2,400 hrs/yr)
• Nets 1,944 MWh Savings/yr
11
Chilled Water System Optimization
• Project Examples (continued)
21
Upgrade Facilities & EquipmentPractical Case Studies
• Dry Cooler Installation (Free Cooling)
• Provides ability to cool air compressors via glycol to air heat exchange, when ambient air temps are under 55⁰ F
• Removes air compressor heat load from chiller system to cool ambient air, saving electricity and water
• Proved successful for future opportunities to reach stated goal
Building Envelope Improvement Examples
22
Upgrade Facilities & EquipmentPractical Case Studies
Cal wall Project• Replaced existing single pane glass panels in Bldg 82• Increased R value from 1 to 10
Dock seal and rapid roll door• Replaced 21 inefficient dock seals throughout the facility• Replaced overhead door in dock 82 with rapid roll door• Energy Savings = $36,000/year or 474 mWh/year
Roof Project (Insulation)• Added insulation to various roofs • Improved roof R value from R12 to R25 average
12
Manufacturing Group Involvement Example
23
Upgrade Facilities & EquipmentPractical Case Studies
• Henry Filter System VFD Controls Project• Controls pumps to cutting fluid
demand
• Expected Pumping Energy Reduction: 2,510 MW-hr/yr / $210,000 Annual
Efficient New Construction & Renewable Energy
24
• Cummins Downtown Indianapolis DBU HQ Office
• Seymour Engine Plant New Test Center
• Solar Installations @ Jamestown, NY (2 MW) & Bejing, China (3.6 MW)
Investigating UV Collector Technology• Supplemental heat source for steam/water boilers
• Supplemental heat source for production wash tanks
13
25
Practical Case Studies in Energy Efficiency Projects