Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber Board.

Upload: duongnga

Post on 30-Nov-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Practical Detailing for Mid-Rise Wood Frame Buildings

Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer: This presentation was developed by a third party and is not funded

by WoodWorks or the Softwood Lumber Board.

Page 2: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Type VA Detailing

•  1 Hour Rated Floor •  1 Hour Rated Wall •  Rated from Both Sides

Page 3: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Type VA Detailing

•  1 Hour Rated Floor •  1 Hour Rated Wall •  Rated from Inside Only

Page 4: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Type IIIA Detailing

•  1 Hour Rated Floor •  2 Hour Rated Wall •  Fire Retardant Treated •  Rated from Both Sides

Page 5: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Type IIIA Detailing

•  1 Hour Rated Floor •  2 Hour Rated Wall •  Fire Retardant Treated

o  Wall Framing o  Wall Sheathing

•  Rated from Both Sides

Page 6: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Type IIIA Detailing

•  1 Hour Rated Floor •  2 Hour Rated Wall •  Fire Retardant Treated

o  Wall Framing o  Wall Sheathing o  Rim Beam

•  Rated from Both Sides

Page 7: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Type IIIA Detailing

•  1 Hour Rated Floor •  2 Hour Rated Wall •  Fire Retardant Treated

o  Wall Framing o  Wall Sheathing o  Rim Beam o  Floor Joists for at least 10’ &

individually wrapped with GWB

•  Rated from Both Sides

Page 8: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Type IIIA Detailing

Page 9: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Type IIIA Detailing

Page 10: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Type IIIA Detailing

•  1 Hour Rated Floor •  1 Hour Rated Non-Bearing Wall •  Fire Retardant Treated

Page 11: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Type IIIA Detailing

•  1 Hour Rated Floor •  1 Hour Rated Non-Bearing Wall •  Fire Retardant Treated

Page 12: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Type IIIA Detailing

•  1 Hour Rated Floor •  2 Hour Rated Wall •  Fire Retardant Treated •  Rated from Both Sides

Page 13: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Type IIIA Detailing

•  1 Hour Rated Floor •  2 Hour Rated Non-Bearing Wall •  Fire Retardant Treated •  Fire Coated Plywood

Page 14: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Type IIIA Detailing

•  1 Hour Rated Floor •  2 Hour Rated Non-Bearing Wall •  Fire Retardant Treated •  Fire Coated Plywood

Page 15: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Interior Wall Detailing

•  1 Hour Rated Floor •  Non-Rated Wall

Page 16: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Interior Wall Detailing

•  1 Hour Rated Floor •  1 Hour Rated Wall

Page 17: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Interior Wall Detailing

•  1 Hour Rated Floor •  1 Hour Rated Demising Wall •  Fire Blocking Required

Page 18: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Interior Wall Detailing

•  1 Hour Rated Floor o  Parallel Framing

•  2 Hour Rated Wall

Page 19: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Interior Wall Detailing

•  1 Hour Rated Floor o  Perpendicular Framing

•  2 Hour Rated Wall •  Fire Coated Plywood

Page 20: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Interior Wall Detailing

•  1 Hour Rated Floor o  Perpendicular Framing

•  2 Hour Rated Wall •  Fire Coated Plywood

Page 21: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Interior Wall Detailing

•  1 Hour Rated Wall •  2 Hour Rated Wall

Page 22: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Interior Wall Detailing

•  2 Hour Rated Floor •  1 Hour Rated Wall - NLB

Page 23: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Interior Wall Detailing

•  2 Hour Rated Floor •  2 Hour Rated Wall – Load Bearing

Page 24: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Corridor Wall Detailing

•  1 Hour Rated •  Load Bearing •  STC 50 min •  GA File No WP 3242

o  (For acoustics)

Page 25: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Corridor Wall Detailing

•  1 Hour Rated •  Load Bearing •  Shear Wall •  NOT STC 50 min •  GA File No WP 3242 Sim

o  (For acoustics)

Page 26: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Corridor Wall Detailing

•  1 Hour Rated •  Load Bearing •  Shear Wall •  Sound Board •  STC 50 min •  NGC 2011058

o  (For acoustics)

Page 27: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Corridor Wall Detailing

•  1 Hour Rated •  Load Bearing •  Shear Wall •  Staggered Stud •  STC 50 min •  GA File No 3910

o  (For acoustics)

Page 28: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Corridor Wall Detailing

•  1 Hour Rated •  Load Bearing •  Shear Wall •  Staggered Stud •  STC 50 min •  GA File No 3910

o  (For acoustics)

Page 29: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Corridor Ceiling Detailing

•  1 Hour Rated •  6x10 Beams •  14” I Joists •  MEPF Within Rated Enclosure

Page 30: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Corridor Ceiling Detailing

•  1 Hour Rated •  Heavy Timber Construction •  3x Flooring •  MEPF Outside Rated Enclosure

Page 31: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Corridor Ceiling Detailing

•  1 Hour Rated •  9 ½” I Joists •  Dropped Ceiling •  MEPF Outside Rated Enclosure

Page 32: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Balcony Detailing

•  Bolt On Balcony •  Aluminum or Steel •  Sprinkler Requirements •  Floor Area Implications

Page 33: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Balcony Detailing

•  Framed Balcony •  Decking Options

•  Review Tested Assemblies •  Step and Slope Limitations

•  Review for Accessibility •  Venting Requirements •  Waterproofing Implications

Page 34: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Shaft Wall Detailing

•  Mechanical o  2 hour rating thru 1 hour wall o  One side with shaft wall for access

Page 35: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Shaft Wall Detailing

•  Stair •  Rating Continuous •  Only Beams Penetrate Shaft •  Secondary Stair Framing •  Furred wall for MEPF

Page 36: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Shaft Wall Detailing

•  Elevator •  Beam at Door Opening •  C-T Shaft Wall

Page 37: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Fire Wall Detailing

•  Structurally Dependent o  Seattle Only

Page 38: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Fire Wall Detailing

•  Structurally Independent •  UL U336

o  (2) 1” Shaft Wall o  H Studs o  ¾” Air Gap o  Non rated wood walls o  Breakaway clips

Page 39: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Fire Wall Detailing

•  Structurally Independent •  Two Wood Frame Walls •  Plywood Non-continuous •  Fire Coated Plywood at Rim

Page 40: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Fire Wall Detailing

•  Structurally Independent •  Two Wood Frame Walls •  Plywood Continuous •  Fire Coated Plywood at Rim •  Fire Coated Plywood at Wall Gap

Page 41: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Fire Wall Detailing

•  Structurally Independent •  Masonry Walls •  Furred Plumbing Walls

Page 42: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Structural Column and Beam Detailing

•  Column Protection o  8x8 = 1 layer GWB w/ cover o  4x4 = 2 layers GWB w/ cover o  Wood = ?

Page 43: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Structural Column and Beam Detailing

•  Column Protection o  4x4 = 2x8 wall minimum o  Wood = ?

Page 44: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Structural Column and Beam Detailing

•  Beam Protection o  Spray Applied Fire Resistive

Material

Page 45: Practical Detailing for Mid-Rise Wood Frame Buildings · Practical Detailing for Mid-Rise Wood Frame Buildings Jon Hall AIA, Quality Management Director February 23 & 24, 2016 Disclaimer:

Questions?