practical project risk assessment, simon white
TRANSCRIPT
Trigo White Ltd Risk Management www.trigowhite.com
Practical project risk assessment
APM Aberdeen
Robert Gordon University, Aberdeen
10th March 2015
Simon White
Consultant, Trigo White Ltd
+44 (0)7831 791 032
Trigo White Ltd Risk Management www.trigowhite.com
Risk management services
• Risk Management Plan development
• Risk workshop facilitation
• Qualitative risk assessment and analysis
• Risk register review
• Risk process design / review / implementation / audit
• Quantitative risk assessment and analysis
• Industry best practice
• Over 20 years’ consulting to a wide variety of industries
• Add value with risk management
Trigo White Ltd Risk Management www.trigowhite.com
The risk workshop
• Valuable discussion: assumptions, inter-discipline issues, allows honesty
• Structured approach, best practice
• Engage project team, management and stakeholders
• Skilled facilitation, ensuring contribution from all team members, keeping focus
• Identify, discuss and qualify risks
– Cause, risk, effect
– Probability (H / M / L …)
– Impact on schedule, cost and safety, production, operations (H / M / L …)
• Capture mitigation options and fallback options • Effect of mitigation
• Agree action owners and deadlines
• Make decisions – is it worth mitigating?
Probability Impact Score
Major scope change M VH 25
SIMOPS issues H L 17
DECC requires recycle L H 15
Delay to lift vessel arrival L M 9
… …
Trigo White Ltd Risk Management www.trigowhite.com
The risk workshop
• Risks can be ranked and summarised
• Give focus on mitigation
• Establish agreement
• Demonstrate robustness
• What are our top risks?
VH
Major
scope
change
H
DECC
requires
recycle
M
Delay to
lift vessel
arrival
LSIMOPS
issues
L M H VH
Probability
Imp
act
Trigo White Ltd Risk Management www.trigowhite.com
The risk register
• A useful live project document
• Prioritise, categorise risks
• Ranking, reporting of key risks
• Focus risk mitigation
• Track mitigation actions – progress and effectiveness
• Keep risk visible throughout planning and execution
• Risk analysis adds more value …
Trigo White Ltd Risk Management www.trigowhite.com
Inputs for a risk analysis
• Base schedule (WBS)
– Around 50-300 activities
– “Forward-driven” logic
– Can use existing schedule, or create in a workshop
• Base cost estimate (CBS)
– Around 20-50 high-level cost elements
– Allowances / contingency identified
• Any risks already identified
Trigo White Ltd Risk Management www.trigowhite.com
Quantitative risk assessment
• Quantify significant risks
– Probability (%)
– Schedule impact in days: P10, P50 and P90 (if it occurs)
– Cost impact in £: P10, P50 and P90 (if it occurs)
• Associate the risks with the schedule activities (WBS)
– E.g. “Delay to lift vessel arrival” will impact installation activities
• Associate the risks with the cost elements (CBS)
– E.g. “Delay to lift vessel arrival” will impact topsides cost
(optional)
Trigo White Ltd Risk Management www.trigowhite.com
3 4 5 6 7 8 9 10 11 12
Pro
bab
ility
den
sity
Activity cost (MM USD)
P10 P50 P90
Quantitative risk assessment
• Further quantitative assessments
– Schedule variance (-10% / +30% for engineering activities)
– Cost variance (-5% / +10% for jacket fabrication cost)
– Variance accounts for:
• Estimating uncertainty
• Risks not specifically modelled
– Correlation (topsides fabrication costs are uncertain because of common
causes)
– Series / parallel impacts (poor weather and lift vessel delay are in parallel)
Trigo White Ltd Risk Management www.trigowhite.com
Pro
bab
ility
den
sity
Total project cost (MM USD)
P10 P50 P90
23
Base = 16.4
Quantitative risk analysis
• The risk model shows the effect of the assumptions on the overall project
Base
estimate
(MM USD)
Bulks 2.3
Fabrication 5.7
Transportation 1.9
Heavy lift vessel 1.6
Hook-up and
commissioning
4.3
Project services 0.6
Total 16.4
The P90 is a "reasonably likely" worst case.
Contingency at P90 = 6.6
Trigo White Ltd Risk Management www.trigowhite.com
Quantitative risk analysis
• The total contingency can be shown (on average) against the individual
costs
0
10
20
Bu
lks
Fab
rica
tio
n
Tran
spo
rtat
ion
Hea
vy li
ft v
esse
l
Ho
ok-
up
an
dco
mm
issi
on
ing
Pro
ject
ser
vice
s
Tota
l
P90 contingency:
Total base cost:
6.6
16.4
23.0Total P90 cost:MM
USD
Trigo White Ltd Risk Management www.trigowhite.com
Quantitative risk analysis
• The total contingency can also be shown against different types of risk
0
10
20B
ase
cost
Tech
nic
al r
isk
No
n-t
ech
nic
al r
isk
Tota
l
P90 contingency:
Total base cost:
6.6
16.4
23.0Total P90 cost:MM
USD
Trigo White Ltd Risk Management www.trigowhite.com
Quantitative risk analysis
• The model shows the effect of the risk on schedule as well as cost
Trigo White Ltd Risk Management www.trigowhite.com
Quantitative risk analysis
• The contribution of risks to the overall project cost or schedule can be
calculated
-1 -0.5 0 0.5 1 1.5
Variance of labour costs
Impact of SIMOPS issues
Impact of delay to lift vessel arrival
Variance of offshore labour rate
Variance of transportation rate
Impact of flotel unavailability
Impact of poor weather
MM USD
Contribution to P10 / P90cost contingency
Contribution to P50cost contingency
Trigo White Ltd Risk Management www.trigowhite.com
Quantitative risk analysis
• The total contingency can be shown (on average) phased over time
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
Jan-1
1
Jul-11
Jan-1
2
Jul-12
Jan-1
3
Jul-13
Jan-1
4
Jul-14
Jan-1
5
Jul-15
Jan-1
6
Jul-16
Jan-1
7
Jul-17
Jan-1
8
Jul-1
8
Jan-1
9
Mo
nth
ly c
ost
(M
M U
SD)
Base phasing
P10 phasing
P50 phasing
P90 phasing
Trigo White Ltd Risk Management www.trigowhite.com
All this can be …
• Practical
• Defendable
• Valuable
Trigo White Ltd Risk Management www.trigowhite.com
An example
• Offshore natural gas development
• Schedule: many assumptions, critical path, burn rates, weather
• Cost: management and partners require confidence, justification of
contingency, basis for decisions
• Production: delays hurt NPV
• Operability: shutdowns hurt NPV
• Busy multi-discipline team
• Busy project manager
• Need a meaningful risk report
Trigo White Ltd Risk Management www.trigowhite.com
Full risk report
Trigo White Ltd Risk Management www.trigowhite.com
Full risk report
• Documents risk identification and assessment process
• Shows who contributed to the process
• Includes risk register and all other assumptions
• Shows the model logic
• Gives full results
– Overall contingency on cost and schedule, with justification
– Breakdown of contingency by WBS, CBS and by risk
– Effect of mitigation
• Forms a permanent record of the team’s view of the risk to the project, at a
given point in time
• Refresh / update at each stage gate
Trigo White Ltd Risk Management www.trigowhite.com
Benefits of risk analysis
• A valuable process
– Challenge project teams and base estimates
– Express uncertainty in the team’s base assumptions
– Capture risks, assumptions, issues, and their consequences
– Encourage open discussion amongst integrated team
• Demonstrate awareness of risk – Agree and communicate the team’s view of the risk
– Justify contingency and mitigation efforts
– Allow challenges, discussion and negotiation
– Set realistic stakeholder expectations
• The risk model represents the perceived risk, and its logical
consequences
Trigo White Ltd Risk Management www.trigowhite.com
About Simon White
• Over 20 years’ experience in risk management and risk analysis
– Wide variety of industries and major projects
– Three years as UK Risk Analyst for ConocoPhillips
– Previously Senior Risk Management Consultant and trainer for Pertmaster, Primavera and
Oracle
– Risk analyst for current major oil / gas projects such as Cygnus, Clair Ridge and Jasmine,
and a major government infrastructure programme
• Recognised as one of the leading practitioners of integrated project schedule and cost
risk management and analysis
– Methods allow project risk models to be interrogated and understood by project teams and
senior management
– Designed and built commercial risk software: Predict!, Arrisca, and a contributing architect to
Primavera Risk Analysis (Pertmaster)
– Develops tools for more practical and valuable project and business risk management.
Trigo White Ltd Risk Management www.trigowhite.com
Questions?
Simon White
Consultant
Trigo White Ltd – Risk Management
+44 (0)7831 791 032