Rural Roads Profile(Length in km)
S.No. State (s) Total Rural Road Network Length
Total Length completed under
PMGSY (Upto Sept.15)
1 Bihar T- 1,30,642S- 57,198 34,509
2 Jharkhand T-23,903 S-16,379 11,916
3 Odisha T- 2,58,836S-58,719 33,981
4 West Bengal T- 2,99,209S-1,15,534 18,538
Source:- MoRTH (2011) T - Total S – Surfaced
S.No. State (s)
Length (Km) - NC + UG
Physical Target for
2014-15
Length achieved upto
Mar'15
Average Length construction
per day
1 2 3 4 5
1Bihar (RWD)
29003414.79 9.36
Bihar (NEAs)217.13
0.59
2 Jharkhand 703 1750.32 4.80
3 Odisha 2400 3842.68 10.53
4 West Bengal 1850 2232.88 6.12
Physical Target and Achievement(2014-15)
S.No. State (s)
Length (Km) - NC + UG
Physical Target for
2015-16
Length achieved upto
Sept'15
Average Length construction
per day
1 2 3 4 5
1Bihar (RWD)
32001575.28 8.61
Bihar (NEAs) 19.88 0.11
2 Jharkhand 1240 612.57 3.35
3 Odisha 2350 1593.63 8.71
4 West Bengal 1500 546.17 2.98
Physical Target and Achievement(2015-16 -Upto Sept. 15)
Maintenance Status (2014-15 & 2015-16)
(Rs. In Crore)
Sr.No. State (s) YearAmount
Required as per Contract
Amount Credited in
SRRDA Account
(Upto Sept.15)
Amount Utilized
(Upto Sept.15)
% Achievement
w.r.t Amount required
w.r.t Amount credited
1 Bihar
2014-152015-16
591.68 402.40 351.05 59% 87%
2 Jharkhand 60.10 60.00 14.97 25% 25%
3 Odisha 124.56 101.00 58.16 47% 58%
4 West Bengal 79.91 34.63 44.41 56% 128%
Statement Showing Maintenance Funds Required/ Received and Expenditure incurred under PMGSY-
2015-16 (Upto Sept 15)(Rs. In Crore)
S.No STATE (S)Amount
Required as per Contract
Amount Credited in
SRRDA Account
(Upto Sept.15)
Amount Utilized
(Upto Sept.15)
% Exp. W.r.t Required
% Exp. W.r.t
Releases
1 Bihar 138.26 59.62 45.68 33% 77%
2 Jharkhand 28.62 0.00 7.3 26% -
3 Odisha 56.79 53.00 34.48 61% 65%
4 West Bengal 41.67 0.00 19.81 48% -
No amount credited in 2015-16 in SRRDA account by Jharkhand and West Bengal.
State Policy on MaintenanceStates to notify their Rural Roads Maintenance
Policies (RRMPs).
A Model Policy Framework for Maintenance of Rural Roads along with a Guidance Note has already been circulated to States.
So far, only nine States (Assam, Bihar, Chhattisgarh, Himachal Pradesh, Madhya Pradesh,, Rajasthan, Tamil Nadu, Uttar Pradesh and Uttarakhand) have notified such Policies.
Jharkhand, Odisha and West Bengal to notify RRMPs.
Maintenance Sub ModuleTechnicalReceipts and Payments
Training on “Maintenance Sub Module” concluded in April 2015 (Bihar & Jharkhand have participated).
Maintenance Module of OMMAS
Maintenance Sub Module - Agreement
– Physically completed roads available for Maintenance Agreement
– Provision to continue with Same Contractor or With New Contractor
– Year wise Maintenance Cost to be provided for the Maintenance Agreement
– Maintenance Agreement provision for “During Liability Period” and “Post Liability”
Pre-requisites SRRDA
– Bank Account Details of Maintenance Fund
– Opening Balances, Receipt of Grant, Issue of Authorization to PIU.
PIU
– The Contractor details must be Present in the Contractor Master.
– The works in the Proposal module must be Sanctioned by MoRD and Physically Completed as per Execution module
– Agreement details under Maintenance sub-module must be Entered and Finalized.
– Authorized Signatory details, Bank Details and Cheque book details mandatory
– Bank Authorization balance required for posting vouchers
Maintenance Fund – Receipts and Payments
Maintenance Fund – Receipts and Payments moduleMaintenance Fund Accounts module Status as on 30th
October, 2015
Sr.No. State (s) Total PIUs
No of PIU Online
Entry completed by
first PIU
Entry completed by
last PIU
1 Bihar 102 29 March,2011August,20
15
2 Jharkhand 55 5 April,2013 April,2015
3 Odisha 65 56 March,2014 April,2015
4 West Bengal 32 23 April,2013 April,2013
• States have to provide –• date by which all PIUs would be Online• date by which Entries upto September,15 would be completed.
Use of Geo-Textiles, Waste Plastic & Cold Mix in roads under PMGSY
Usage of Geo-Textiles, Waste Plastic & Cold Mix in roads particularly rural roads is a proven environment friendly technology for increases durability and reduced maintenance cost of roads.
Ministry of Rural Development and Ministry of Textiles have agreed to collaborate in using Geo-Textiles in Rural Roads.
Ministry of Textile has designated Centres of Excellence for Geo-Textiles at Ahmedabad, Kolkata and Mumbai.
Ministry of Rural Development has issued targets for 2015-16 for use of Waste Plastic & Cold Mix for each State.
Status of R&D Sanctions and Progress(2012-13 to 2015-16)
Sr.No. State (s)
Sanctioned Completed
Total Road Length (in Km)
Amount (Rs. In Lakhs)
Length(in Km)
Amount (Rs. In Lakhs)
1. Bihar 380.42 26970.38 19.10 1539.2
2. Jharkhand 84.33 3947.00 1.00 63.43
3. Odisha 357.83 18314.72 - -
4. West Bengal 98.07 5863.75 13.42 855.42
Note: As per NRRDA records.
Environmental & Social Management Framework (ESMF) and Environmental & Social Standards (ESS)
World Bank’s Environmental & Social Management Framework (ESMF) for its projects is to be replaced by an integrated set of 10 Environmental & Social Standards (ESS).
www.worldbank.org/safeguardsconsultations.
Impact of ESS on – cost of the projects, timelines of the projects and overall project implementation (5 - 7 slides).
CBR Digital MAP on OMMAS
To serve as management tool for the States.
Digitized block boundaries, district boundaries to be provided.
Missing CBR Values, in proposal module to be uploaded.
CBR Digital Map feature is available on SRRDA & ITNO login under “ Dashboard” menu.
A new “Citizen Feedback Module” “Meri Sadak” has been created in public domain of OMMAS Homepage for registering feedback and complaints by citizens.
To meet the objectives of E-governance and Digital India, a new Mobile App “Meri Sadak” integrated into OMMAS for user friendly and transparent Citizen Feedback and complaint redressal system under PMGSY.
The citizens, with the use of this feedback module, can express their concerns related to slow pace, abandoned work, bad quality of PMGSY works.
Feedback on PMGSY works received on OMMAS portal
“Meri Sadak – Citizen Feedback System”
State Quality Coordinators (SQCs) will be the ‘Nodal Officer’ to handle feedback module and will dispose off the feedbacks received under “Meri Sadak” of OMMAS portal, online (7 days to 60 days).
A SOP (Standard Operating Procedure) has been developed which describes the steps for handling feedbacks submitted by Citizen and uploaded on PMGSY website (http://pmgsy.nic.in).
As per timeline for prompt feed back redressal, all feedback should be:
Acknowledged within 07 days with interim reply.
Redressed within 60 days of receipt in the organization.
States may ensure disposal of feedback in time bound manner without compromising on quality aspects.
Feedback on PMGSY works received on OMMAS portal under
“Meri Sadak – Citizen Feedback System”
Feedback Pendency
S.No.
ComplainantName
Feedback Received
Date
Interim Reply Date
Final Reply Submission
DateStatus
1 Sanjay Rai 01-07-2015 19-08-2015 30-08-2015 Final reply awaited
2 Abdullah 09-07-2015 19-08-2015 07-09-2015 Final reply awaited
3 Ravindra Kumar Reddy 17-08-2015 19-08-2015 16-10-2015 Final reply awaited
4 Rohit kumar 17-08-2015 19-08-2015 16-10-2015 Final reply awaited
5 Md Akhlaqur Rahman 26-08-2015 01-09-2015 25-10-2015 Final reply awaited
6 Dhiraj Ray 27-08-2015 01-09-2015 26-10-2015 Final reply awaited
7 Chandan kumar 25-10-2015 - - Not replied
State: Bihar (As on date 28.10.2015)
Feedback PendencyState: Odisha (As on date 28.10.2015)
S.No.
ComplainantName
Feedback Received
Date
Interim Reply Date
Final Reply Submission
DateStatus
1 Mirza Sartaz 24-10-2015 - - Not replied
Feedback PendencyState: West Bengal (As on date 28.10.2015)
S.No.
ComplainantName
Feedback Received
Date
Interim Reply Date
Final Reply Submission
Date
Status
1 Somnath Das 24-10-2015 - -
Not replied
2 Rajkiran Baraik 24-10-2015 - -
3 Asmita Poddar 25-10-2015 - -
4 Md Jasim Uddin 25-10-2015 - -
5 Saifuj Jaman 27-10-2015 - -
Pradhan Mantri Gram Sadak Yojana
Bihar, Jharkhand, Odisha and West Bengalat
Bhubneshwar
3-4 November, 2015
22
REVIEW
MEETING
Compliance of Last Review Meeting held at Guwahati/New Delhi
(February/ March, 2015)
23
Deposit 100% funds in the SRRDA Maintenance Account by 31st March, 2015 - Odisha
Odisha would reconcile the data related to eligible unconnected habitations and balance unconnected habitations and upload on OMMAS by 31st March, 2015.
Submit Comprehensive Annual Action Plan for “Swatch Bharat Abhiyan” by 30th April, 2015 for the year 2015-16.
Reconciliation of Habitation data by 30th April, 2015 – Bihar and West Bengal.
Re-checking the value of awarded works entered on OMMAS by 30th April, 2015 – All States.
Reconciliation of Habitation data by 31st May, 2015 - Jharkhand.
24
Action Taken by the StatesAll participating States during their last RRM has assured for the following:-
Trends of Physical Completion of Roads
(in km)
25
B I H A R
R WD
Physical Progress as per OMMAS
26
Year (s)
Total No. of Road Works/
Bridges sanctioned
Total length of Road Works
(in Km) sanctioned
Total No. of Road Works /
Bridges completed
Total length of Road Works
(in Km) constructed
No. of Works completed upto
Last Review Meeting
(March 15)
No. of Road works yet to complete
2000-01 298 861.87 282 819.32 282 16
2001-02 671 1531.8 600 1383 597 71
2002-03 4 53.59 3 38.34 3 1
2007-08 271 1228.96 222 1024.095 219 49
2008-09 4576 15670.94 3658 12084.48 3583 918
2011-12 670 1899.05 430 1124.878 383 240
2012-13 1446 3846.07 760 1902.88 652 686
2013-14 4463 9152.77 619 1296.52 230 3844
Total: 12399 34245.05 6574 19673.51 5949 5825
1055 in-complete road works till 2010-11 is a cause of concern, State should focus on expediting the process of completion of these in-complete road works as well as their
financial closure
B I H A R
R WD
Physical Progress as per OMMAS under
WB RRP-II
27
Year (s)
Total No. of Road Works/
Bridges sanctioned
Total length of Road Works (in Km)
sanctioned
Total No. of Road Works /
Bridges completed
Total length of Road Works
(in Km) constructed
Works completed upto Last Review Meeting
(March 15)
No. of Road works yet to
complete
2013-14 956 2287.25 123 259.97 11 833
B I H A R
R WD
Trends of Financial Progress ( Release / Expenditure in Rs Crore)
28
B I H A R
R WD
Trends of Physical Completion of Roads (in km)
29
J H A R K H A N D
Physical Progress as per OMMAS
30
Year (s)
Total No. of Road Works/
Bridges sanctioned
Total length of Road Works
(in Km) sanctioned
Total No. of Road Works / Bridges
completed
Total length of Road Works
(in Km) constructed
Works completed upto Last Review
Meeting (March 15)
No. of Road works yet to
complete
2000-01 167 897.66 167 897.66 167 0
2001-02 202 1202.81 202 1202.81 201 0
2003-04 131 647.24 128 618.74 127 3
2005-06 102 479.19 94 408.39 93 8
2007-08 352 1659.88 298 1402.519 297 54
2008-09 666 3093.5 544 2386.33 539 122
2009-10 896 3057.21 633 2006.175 276 263
2011-12 415 1388.21 136 360.916 26 279
2012-13 71 316.44 39 107.193 5 32
2013-14 820 2573.28 35 97.454 0 785
Total 3822 15315.42 2276 9488.187 1731 1546
450 in-complete road works till 2010-11 is a cause of concern, State should focus on expediting the process of completion of these in-complete road works as well as their financial closure
J H A R K H A N D
World Bank RRP-I – Already completed
World Bank RRP-II – As per OMMAS
31
Year (s)
Total No. of Road Works/
Bridges sanctioned
Total length of Road Works (in Km)
sanctioned
Total No. of Road Works /
Bridges completed
Total length of Road Works (in Km)
constructed
Works completed upto Last Review Meeting
(March 15)
No. of Road works yet to
complete
2011-12 174 696.91 67 280.24 29 107
2012-13 848 2367.20 329 860.58 123 519
Total 1022 3064.11 396 1140.82 152 626
J H A R K H A N D
Trends of Financial Progress ( Release /Expenditure in Rs Crore)
32
No Funds
released during
2013-14
J H A R K H A N D
Trends of Physical Completion of Roads in km
33
Odisha
8,889 road works i/c Bridges completed out of 11,936 and 75% length completed
Physical Progress as per OMMAS- Normal
34
Odisha
383 in-complete road works till 2010-11 is a cause of concern, State should focus on expediting the process of completion of these in-complete road works as well as their financial closure
Year (s)Total No. of Road Works sanctioned
Total length of Road /LSB
Works cleared (in Km)
Total No. of LSB Works sanctioned
Total No. of Road / LSB
Works completed
Total length of Road Works
constructed (in Km)
Works completed upto Last Review Meeting
(Feb. 15)
No. of Road works yet to
complete
2000-2001 521 1069.43 0 519 1064.64 519 2
2001-2002 571 1692.78 0 571 1692.78 571 0
2003-2004 630 2010.36 0 620 1961.52 616 10
2004-2005 418 1646.94 0 406 1604.10 401 12
2005-2006 486 1916.88 0 474 1851.93 460 12
2006-2007 443 1411.30 0 423 1338.83 408 20
2007-2008 1689 6616.51 0 1568 5944.71 1521 121
2008-2009 1432 7116.60 74 1341 6208.89 1224 165
2009-2010 122 585.69 60 141 418.25 77 41
2011-2012 1283 5143.67 0 827 2978.57 487 456
2012-2013 1334 5189.41 0 599 2054.30 181 735
2013-2014 0 10.68 141 27 1.27 0 114
Total 8929 34410.25 275 7516 27119.79 6465 1688
Physical Progress as per OMMAS- ADB
35
Odisha
120 in-complete road works till 2010-11 is a cause of concern, State should focus on expediting the process of completion of these in-complete road works as well as their financial closure
Year (s)Total No. of Road Works sanctioned
Total length of Road Works
cleared (in Km)
Total No. of LSB Works sanctioned
Total No. of Road Works completed
Total length of Road Works
constructed (in Km)
Works completed upto Last Review
Meeting (Feb. 15)
No. of Road works yet to
complete
2005-2006 261 1189.01 0 253 1119.60 247 8
2006-2007 400 1612.65 0 372 1442.29 370 28
2008-2009 644 3010.46 0 560 2535.28 545 84
2011-2012 284 1052.27 0 131 466.97 28 153
2013-2014 1131 3924.65 17 28 78.24 0 1120
Total 2720 10789.04 17 1344 5642.4 1190 1393
Trends of Financial Progress ( Release / Expenditure in Rs Crore)
36
Odisha
Trends of Physical Completion of Roads (in km)
37
3,580 road works i/c Bridges completed out of 4,982 and 73% length completed
W E S T
B E N G A L
Normal PMGSY - Physical Progress as per OMMAS
38
Year (s)
Total No. of Road Works/
Bridges sanctioned
Total length of Road Works
(in Km) sanctioned
Total No. of Road Works /
Bridges completed
Total length of Road Works
(in Km) constructed
Works completed upto Last Review Meeting
(March 15)
No. of Road works yet to
complete
2000-01 170 808.9 170 808.9 170 0
2001-02 212 1124.6 212 1124.6 212 0
2003-04 363 2004.88 363 2004.88 363 0
2005-06 149 952.5 149 952.5 149 0
2006-07 230 1645.8 226 1629.69 225 4
2007-08 335 2127.76 306 1916.389 302 29
2008-09 482 2195.25 420 1941.254 415 62
2010-11 280 1039.93 217 795.386 208 63
2011-12 231 1186.75 120 627.119 110 111
2012-13 1411 6059.39 827 3330.36 664 584
2013-14 467 1636.51 28 62.69 1 439
Total 4330 20782.27 3038 15193.77 2819 1292
158 in-complete road works till 2010-11 is a cause of concern, State should focus on expediting the process of completion of these in-complete road works as well as their financial closure
W E S T
B E N G A L
ADB- Physical Progress as per OMMAS
39
Year (s)
Total No. of Road Works/
Bridges sanctioned
Total length of Road Works (in Km)
sanctioned
Total No. of Road Works /
Bridges completed
Total length of Road Works (in Km)
constructed
Works completed upto Last Review Meeting
(March 15)
No. of Road works yet to
complete
2005-06 104 792.72 104 792.72 104 0
2007-08 109 908.09 100 807.56 100 9
2008-09 127 695.72 120 653.12 120 7
2010-11 76 443.49 72 420.26 72 4
2011-12 15 82.26 7 34.13 7 8
2012-13 14 84.17 12 75.53 11 2
2013-14 130 930.08 64 337.54 45 66
2014-15 76 637.57 0 0 0 76
Total 651 4574.14 479 3120.89 459 172
20 in-complete road works till 2010-11 is a cause of concern, State should focus on expediting the process of completion of these in-complete road works as well as their
financial closure
W E S T
B E N G A L
Trends of Financial Progress ( Release /Expenditure in Rs Crore)
40
No Funds release
d during 2012-
13
W E S T
B E N G A L
41
Sr. No.
State Name State Cost Total CostFund
Released by State
Month Closed
1 Bihar 53,948.6728,46,902.0
70.00 Mar-15
2 Jharkhand 23,852.04 6,80,526.71 7,782.20 Sep-15
3 Odisha 41,592.5217,81,815.0
371,061.00 Jun-15
4 West Bengal 0.0011,06,489.6
6451,7.6 Aug-15
All Cost in Lakh)
Fund Released by States w.r.t State Share
1. Details of R&D being presented in the next slides are as per records of NRRDA. However, these details have not been updated by the States on OMMAS. The length and cost of new technology portion is to be updated by the State, which has not been done in most of the cases or incorrect information updated.
2. Photographs, performance reports etc. are also to be uploaded for such works. In most of the cases photographs and performance reports are not being uploaded by the States.
42
Details of Road works Sanctioned as New Technology (R&D) Projects under PMGSY
43
S.No. State (s) Value (in lakh) Roads Length (in
Km) Technology Year of Sanction
1 Bihar
364.44 1 7.25 Silicon Aggregate 2008-09
26970.38 483 380.42RCCP, Soil
Stabilization, Fly Ash, Cold Mix, Cell Filled
2013-14
Total: 27334.82 484 387.68
2
Jharkhand
442.35 2 10.13 RBI Grade 81 2012-13
3504.65 25 74.20 RI Grade 81 & RCCP 2013-14
Total: 3947.00 27 84.33
Details of road works sanctioned as New Technology (R&D)
# State (s) Nos. of Road
Lengthin Km.
Cost in Rs. Lakhs Type Year of
Sanction
3 Odisha
2 9.5 500.23 JGT 2005-06
95 351.70 18013.00 Cold Mix / Iron Slag/ RCCP 2013-14
Total: 97 361.20 18513.00 -
4 West Bengal
2 10.5 426.96 JGT 2003-04
4 24.38 1095.32 Cell filled, RBI 2007-08
4 20.8 1193.10 JGT 2010.11
5 24.41 1459.18 JGT 2012-13
3 16.23 992.91 JGT, Cold Mix 2012-13
6 40.92 2435.42 RBI, JGT, Cold Mix 2014-15
Total: 24 137.24 7602.89
Details of road works sanctioned as New Technology (R&D)
Physical and Financial Progress under IAP
45
Habitation Connectivity for the IAP Districts
as on September, 2015
46
S.No. Name of State (s)
No. of Districts
No. of eligible Habitations
under PMGSY
No. of Habitations
cleared under PMGSY
No. of Habitations connected
under PMGSY
No. of Habitations connected
under other schemes, if any
1 Bihar 11 14529 8015 4627 1218
2 Jharkhand 17 9195 6914 3704 661
3 Odisha 18 13121 9067 6301 207
4 West Bengal 03 5963 4239 2702 0
Total: 49 42808 28235 17334 2086
SI. No. Name of State (s)
No. of District
No. of roads sanctioned
No. of road works
completed
Length of road works sanctioned
(in km)
Length of roads completed (in km)
1 Bihar 11 5473 3146 17102.16 11067.74 (65%)2 Jharkhand 17 3675 1975 15035.09 8729.72 (58%)3 Odisha 18 7422 5383 30229.65 21933.78 (73%)4 West Bengal 03 1504 751 7843.31 4465.76 (57%)
Total: 49 18074 11255 70210.21 46197.00 (66%)
Physical Progress for the IAP Districts
Financial Progress for the IAP Districts as on September, 2015
47
Sl. No. Name of State (s)No. of
Districts
Value of Projects cleared
(Rs. in Crore)
Expenditure incurred
(Rs. in Crore)
1 Bihar 11 8201.58 5198.77 (63%)
2 Jharkhand 17 4683.87 3012.90 (64%)
3 Odisha 18 11469.08 8647.55 (75%)
4 West Bengal 3 3538.04 1784.03 (50%)
Total: 49 8201.58 5198.77 (63%)
Maintenance - Financial
48
Pavement Condition Index [PCI] Data Entered
% PCI Data Enter
edState (s)
Target for PCI Data to Enter
PCI Data Entered for
Length with PCI Value Year-wise Length
Number of Rural Route Roads
Total Length
Number of
Roads
Total Lengt
h1 2 3 4 5
2013-14
2014-15
2015-16
Bihar 23,256 74,244 20,178 73,210 14,201 13,295 19,016 18,981 7,717 13,025 44,700 15,485 81%
Jharkhand
9,535 41,764 7,504 51,557 11,338 14,031 13,987 8,409 3,792 22,412 6,060 23,085 70%
Odisha 18,915 85,427 16,9221,41,88
124,244 40,792 32,462 26,445 17,939 38,625 49,615 53,640 121%
West Bengal
13,056 55,210 3,628 14,445 3,891 5,151 2,713 1,578 1,111 2,307 9,435 2,703 22%
Total: 23,256 74,244 20,178 73,210 14,201 13,295 19,016 18,981 7,717 13,025 44,700 15,485 81%
PC I
S U R V E Y
Maintenance - Financial
Financial Year (s)
Maintenance Funds
Required (As per
Contracts)
Actual Fund
Release to SRRDA
Expenditure by SRRDA during the Financial
Year
% Expenditure
w.r.t maintenanc
e funds Required
2012-13 94.33 56.25 91.60 97%
2013-14 121.23 121.23 102.92 85%
2014-15 453.42 342.78 305.37 67%
2015-16 (Upto Sept. 15) 138.26 59.62 45.68 33%
Total: 807.24 579.88 545.57 68%
(Rs. In Crore)
B I H A R
Maintenance – Financial
Financial Year (s)
Maintenance Funds
Required (As per
Contracts)
Actual Fund
Release to SRRDA
Expenditure by SRRDA during the Financial
Year
% Expenditure
w.r.t maintenanc
e funds Required
2012-13 20.58 52.00 0.96 5%
2013-14 25.13 0.00 3.97 16%
2014-15 31.48 60.00 7.67 24%
2015-16 (Upto Sept. 15) 28.62 0.00 7.3 26%
Total: 105.81 112.00 19.9 19%
(Rs. In Crore)
J H A R K H A N D
52
Rs. In Crores
Financial Year(s)
Maintenance Funds Required
(as per contracts)
Actual release to SRRDA
Expenditure by SRRDA during
the Financial Year
% Expenditure w.r.t fund required
2012-13 40.00 40.00 35.48 89%
2013-14 59.61 41.40 37.15 62%
2014-15 67.77 48.00 23.68 35%
2015-16 (Upto Sept.
15)56.79 53.00 34.48 61%
Total: 224.17 182.40 130.79 49%
Maintenance – Financial
O D I S H A
Maintenance - Financial(Rs. In Crore)
Financial Year (s)
Maintenance Funds
Required (As per
Contracts)
Actual Fund
Release to SRRDA
Expenditure by
SRRDA during the Financial
Year
% Expenditur
e w.r.t maintenance funds Required
2012-13 27.35 83.59 81.14 100%
2013-14 81.31 29.67 22.66 28%
2014-15 38.24 34.63 24.59 64%
2015-16 (Upto Sept. 15)
41.67 0.00 19.81 48%
Total: 188.57 147.89 148.2 79%
W E S T
B E N G A L
Habitation Eligibility and Data Entry on OMMAS
54
Eligible Habitations, Habitations Cleared and Connected
(Since commencement – September. 2015)
Total Eligible Habitations 1,78,184Eligible Habitations of participating States 72,450
% of Total Eligible Habitations 41%
B ASED
ON
MPR
56
Unconnected Habitations Data
Item 1000+ 500+ 250+ 100+ Total
Unconnected Habitations as on 1-4-2000
14242 18080 6109 38431
Covered under State Schemes (as reported by the
State)1304 1745 745 3794
Net unconnected eligible habitations
12938 16335 5364 34637
Reported not feasible 0 0 0 0
As per cabinet approval 13048 6506 5250 24804
Already sanctioned 17697 7789 1698 27184
Total number of Unconnected Habitations Entered (as per OMMAS
Oct, 2015)
14247 18119 6661 68 39027
Balance Unconnected Habitations (as per OMMAS, Oct, 15)
8730 11762 4481 68 24973
Bihar
CN 1 and CN 6 details with maps for 68 Habitations of 100+ are awaited from the State.
57
Unconnected Habitations Data
Item 1000+ 500+ 250+ 100+ Total
Unconnected Habitations as on 1-4-2000
2637 4327 3042 10006
Covered under State Schemes (as reported by the State)
862 973 412 2247
Net unconnected eligible habitations
1775 3354 2630 7759
Reported not feasible 3 0 0 3
As per cabinet approval 1876 4479 5258 11613*
Already sanctioned 1867 3343 3259 8469
Total number of Unconnected Habitations Entered (as per
OMMAS Oct, 2015)1561 3981 4896 10438
Balance Unconnected Habitations (as per OMMAS, Oct, 15)
0 933 2341 2985
* State need to provide details of the habitations that these (3854) habitations are left out habitations of CN.
Jharkhand
58
Unconnected Habitations Data
Item 1000+ 500+ 250+ Total
Unconnected Habitations as on 1-4-2000
3703 6715 7921 18339
Covered under State Schemes (as reported by the State)
78 11 124 213
Net unconnected eligible habitations
3625 6704 7797 18126
Reported not feasible 25 0 0 25
As per cabinet approval 3752 7341 11118 22211*
Already sanctioned 3627 6009 2724 12360
Total number of Unconnected Habitations Entered (as per
OMMAS Oct, 2015)3703 6741 5751 16195
Balance Unconnected Habitations (as per OMMAS,
Oct, 15)39 335 2056 2430
* State need to provide details of the habitations that these (4085) habitations are left out habitations of CN.
Odisha
59
Unconnected Habitations Data
Item 1000+ 500+ 250+ 100+ Total Unconnected Habitations as
on 1-4-2000 12,790 10,142 2,965 25,897
Covered under State Schemes (as reported by
the State)4,232 3,024 0 7,256
Net unconnected eligible habitations
8,558 7,118 2,965 18,641
Reported not feasible 0 0 0 0
As per cabinet approval 8,051 5,485 286 13,822
Already sanctioned 7,711 4,917 1,879 14,507
Total number of Unconnected Habitations Entered (as per OMMAS
Oct, 2015)
8,558 7,118 1,879 181 17,736
Balance Unconnected Habitations (as per OMMAS, Oct, 15)
1,624 2,017 1,074 184* 4,899
West Bengal
* Now eligible as per MoRD’s advisory for 2 blocks in West Bengal
Updating of Data on OMMASStates are requested to update their data
on OMMAS particularly relating to habitations, DRRP, Core Network, Year wise sanctioned proposals, R&D, Maintenance, R&P Module etc latest by 31st December, 2015.
All physical reports will be dispensed with and all reports will be taken from OMMAS directly.
States will have to update their progress latest by 10th of next month on which all these reports will be taken from OMMAS.
60
Details of Awarded Works
In many cases data of awarded works entered by the PIUs does not appear to be realistic as it is more than 100% of the GoI sanctioned cost.
Also in some cases the data entered is in Rupees, where as it should have been in Rs. In lakhs. This has been corrected from backend by NRRDA, however, the States need to verify and confirm that the data appearing on OMMAS is correct latest by 15th November, 2015.
In many cases the data of award has not been updated on OMMAS. A check is being applied on OMMAS, so that details of award will have to be entered within 10 days from date of award
61
Quality Mechanism• Bihar• Jharkhand• Odisha• West Bengal
63
Action Taken by the StatesAll participating States during their last RRM has assured for the following:-
Submit plan for pending ATRs 1st April 2013 to 1st April, 2014 to NRRDA, with the aim of reducing ATR pendency to zero.
1st tierInspections accounted from Apr.,2015 to Oct.,2015.
(16%)
• Based on NQM observation
1st tier
• Consideration period starting from FY which involves at least one On going Works.
Status of Field Lab
2ND tier
* No. of SQMs who have uploaded Inspections in OMMAS during FY 2015-16
* Inspections taken in account from 01/04/2015.
3RD tier
Quality Summary
Inspections taken in account from 01/04/2015.
9%
13%
5%
State No. of awarded
works(in Progress)
No. of awarded
packages in Progress
No of Contractors
involved
No. of Contractor
for which at least One
work inspected
No. of Contractor
whose works not inspected even once
BR 776 753 316 21 295
JH 185 169 92 13 79
OR 672 564 346 36 310
WB 115 115 55 6 49
Contracting Agencies involved in works inspected by NQMs(For works awarded since Jan 2014 onwards)
Unsatisfactory Works found by NQM Unsatisfactory Works found by NQM
Finance and Accounting Issues
72
Bihar and West Bengal - Submit OMMAS based Audited Balance Sheet of Programme Fund and Admin. Expenses Fund for the year 2013-14 by 30th April, 2015.
Odisha - Submit Audit Report by 7th March, 2015 .
Bihar and Jharkhand - Clear all pending final bills by end of June, 2015 .
Odisha - Settle all pending final bills by end of April, 2015 .
73
Action Taken by the StatesAll participating States during their last RRM has assured for the following:-
BiharFinance & Account for F.Y 2014-15
Submission of Annual AccountsThe Balance Sheets of Programme Fund and Administrative Expenses Fund for the Year 2014-15 have not been submitted by the State. The Due date for submission was 30.09.2015.Action Taken Report of FY 2013-14.Action Taken Report for the year 2013-14 not furnished. ATR of 2012-13 also not furnished. Weaknesses in implementation of OMMAS
Month for which entries has been completed in OMMAS (R&P Module)
•Programme Fund:- Sept. 2015
•Administrative Fund:- Sept. 2015
•Maintenance Fund:- Sept. 2015
75
Sanction Year
Pending Financial Completion of
Physically Completed Works
2000-2001 55
2001-2002 90
2002-2003 4
2007-2008 37
2008-2009 554
2011-2012 202
2012-2013 335
2013-2014 560
Total: 1,837
Pending Final Bills1,837 number of physical completed works pending for financial completion. (i.e. 27.43 % out of 6,697 Physically completed works)
Bihar
JharkhandFinance & Account for FY 2014-15
Submission of Annual Accounts
The Balance Sheets of Programme Fund and Administrative Expenses Fund
for the Year 2014-15 have not been submitted by the State. The Due date for
submission was 30.09.2015.
Action Taken Report of FY 2013-14
Action Taken Report for the year 2013-14 not furnished.
Weaknesses in implementation of OMMAS
Month for which entries has been completed in OMMAS (R&P Module)
•Programme Fund:- March 2015
•Administrative Fund:- Aug 2015
•Maintenance Fund:- Not Closed
Pending Final Bills
662 number of physical completed works pending for financial completion.
(i.e. 24.45 % out of 2,707 Physically completed works)
Sanction Year Pending Financial Completion of Physically
Completed Works
2000-2001 72001-2002 222003-2004 152005-2006 122007-2008 262008-2009 472009-2010 822011-2012 1532012-2013 2592013-2014 39
Total: 662
Jharkhand
OdishaFinance & Account for F.Y 2014-15
Submission of Annual Accounts
Balance Sheet of Programme Fund received.
Balance Sheet of Admin Fund received.
Action Taken Report of FY 2013-14.
Action Taken Report for the year 2013-14 has been furnished. However the replies
have been incorporated in the observations of Balance Sheet of 2015-14.
ATR on Ressidual observation of FY 2014-15 raised on 14.09.2015 not furnished.
Observation in Financial Management of FY 2014-15
Excess expenditure of Rs. Rs. 369.22 crore have been met from Security Deposits
of Contractors.
TDS Rs. 12.31 Cr deducted by Bank on Interest Income : Despite of Exemption
from tax
DPR advance Rs. 9.40 Lac not adjusted
Bank Guarantee Rs. 1.95 Cr expired and not revalidated from contractors.
Stale Cheques :
Programme Fund: Rs. 7,00,62,189
Admin. Fund : Rs. 7,26,257
Non submission of Banker Certificate showing for accrued interest
Unqualified Audit Opinion given by the Statutory Auditors despite of having various shortcoming in the Audit Report.
Weaknesses in implementation in OMMAS
Month for which entries has been completed in OMMAS (R&P Module)
•Programme Fund:- June 2015
•Administrative Fund:- Aug 2015
•Maintenance Fund:- Not closed
Odisha
Pending Final Bills
1,038 number of physical completed works pending for financial completion.
(i.e. 11.70% Out of total 8,865 physically completed works)
Sanction Year Pending Financial
Completion of Physically Completed Works
2000-2001 52001-2002 52003-2004 152004-2005 42005-2006 372006-2007 252007-2008 722008-2009 942009-2010 382011-2012 3772012-2013 3192013-2014 47
Total: 1,038
Odisha
West BengalFinance & Account for F.Y 2014-15
Submission of Annual Accounts
Balance Sheet of Programme Fund received.
Balance Sheet of Admin Fund not yet received. Due date for submission was
30.09.2015
Action Taken Report of FY 2013-14.
Action Taken Report for the year 2013-14 on residual point of Programme Fund and
on Observation of Admin Fund not received.
Observation in Financial Management
Deficit Financing : There is a net deficit financing of Rs. 544.32 Cr
Discrepancies of fund received in Schedule L1 and UC : Rs. 130.82 Cr
Interest shown in Banker Certificate and Schedule of Incidental Fund in Programme
Fund differs: Rs. 12.39 Cr
Stale Cheques :
Programme Fund: Rs. 47.52 Lakh
Operation of Two Bank Accounts
Outstanding Liabilities : 451.79 Cr (Including amount payable to State Govt. : 450.19 Cr)
Outstanding Advances : Rs. 3.77 Cr. (Amount recoverable from HIT Rs. 11.43 Lac and from IOC Rs. 3.73 Lac has been pending over the years)
Bank Guarantee aggregating to Rs. 18.01 Crore has been expired
Weaknesses in implementation in OMMAS
Month for which entries has been completed in OMMAS (R&P Module)
• Programme Fund:- August 2015
• Administrative Fund:- Nov 2014
• Maintenance Fund:- Not closed
West Bengal
Pending Final Bills
361 number of physical completed works pending for financial completion.
(i.e. 10.26% Out of total 3,517 physically completed works)
Sanction Year
Pending Financial Completion of Physically
Completed Works
2000-2001 12001-2002 82003-2004 42005-2006 22006-2007 32007-2008 202008-2009 242010-2011 212011-2012 172012-2013 2042013-2014 572014-2015 0
Total: 361
West Bengal
Improvement in Accounting / OMMAS R&P Module
Revoking of month once it is finalized
The option of revoking of the month from the State finance login will be disabled by which states are revoking the months even after closure of accounts.
E-Payments
Currently operation of E-payment is optional for the States. It is advisable to operate the E-payment system for more strengthening the project.
TDS deducted by the Bank on interest
It has been seen that banks are deducting TDS on interest despite of having exemption certificate. Agencies are advised to take up the matter with banks.
As per the Programme Guidelines, Balance Sheet needs to be furnished by 30.09.2015. States are requested to ensure the compliance. Submission of Balance Sheet of Programme and Admin Fund on time.
Unsettled Advances.
Internal Audit.
West Bengal
Department of Administrative Reforms and Public Grievances (DARPG) has operational a web-based portal called CPGRAMS, which is accessible through http://pgportal.gov.in .
CPGRAMS is an important tool of Government to strengthen the two- way communication with citizens for effective and time-bound implementation of programme / schemes at the ground level.
The citizens, with the use of CPGRAMS portal, can express their concerns related to programme / schemes and administrative activities.
Centralized Public Grievance Redressal and Monitoring System
(CPGRAMS)
CPGRAMS is also one of the key sectors of Result Framework Document (RFD).
As per instructions / Guidelines of DARPG and also indicated in RFD, all grievances should be:
Redressed within 60 days of receipt in the organization.
The time limit of 60 days applies even if co-ordination with subsidiary offices or another Department/ Organization is involved. The position of Grievances received on CPGRAMS Portal forwarded by Ministry to NRRDA is regularly reviewed.
Centralized Public Grievance Redressal and Monitoring System
(CPGRAMS)
States may ensure disposal of grievance in time bound manner without compromising on quality aspects.
A letter has already been sent to all States / UTs from JS (RC) vide No. P-17025/75/2011-RC dated 20th September, 2013 for timely disposal of the complaints which is also uploaded on PMGSY website (http://pmgsy.nic.in) under circular section.
Centralized Public Grievance Redressal and Monitoring System
(CPGRAMS)
Pending Grievances with Bihar State
# Registration Number
Name of Complainan
t
Date of Receipt
Pendency days
(As on 31.10.20
15)
Nature of grievance
1 PMOPG/W/2015/0114739
Sh. Rajnish kumar
14-12-2014 321Poor /
substandard work
2 PMOPG/D/2015/0181609
Sh. Gaya prasad
10-08-2015 82
Pending Grievances with Jharkhand State
# Registration Number
Name of Complainant
Date of Receipt
Pendency days
(As on 31.10.201
5)
Nature of grievance
Status
1 PMOPG/D/2015/73965
Ms. Malati Singh
16-04-2015
198
Irregularity &
corruption in planning
of Rural Roads
Interim reply
submitted by State
& requested NRRDA (P-III
Division) on dated 07.10.201
5 for further
direction
2 PMOPG/E/2015/0051551
Sh. Pranab kumar mandal
03-08-201589 Labour
Issues - Contractua
l Employees
No Grievances pending in Odisha and West Bengal
90
Officers trained under various Training Programmes during 2015-16
(Upto September, 2015)
Name of State (s) Officers NominatedOfficers Attended
Bihar 67 39
Jharkhand 30 18
Odisha 110 108
West Bengal 124 116
Total: 331 281
Status of Clearances since Inception – Sept, 2015
91
Year (s) Date Phase Value in Crores
No of Roads
No of Bridges
Length in Km
2000-01 26-Feb-01 Phase-I 149.89 298 811.662002-03 02-Jul-02 Phase-II 302.98 666 1408.19
2004-08 NEAs Phase-III-VI (Batch-I) 8343.67 3509 18886.23
2007-08 15-Oct-07 Missing Links of I & II (P-1) 267.66 162 620.17
2007-08 08-Feb-08 Phase-VI (Batch-II) 256.63 109 605.812008-09 30-Jun-08 Phase-VII (P-1) 1245.87 705 2880.442008-09 05-Sep-08 Phase-VII (P-2) 1839.01 1025 3914.12
2008-09 04-Nov-08 Missing Links of I & II (P-2) 264.55 166 563.45
2008-09 27-Jan-09 Phase-VIII 2761.14 1681 5358.732008-09 17-Feb-09 Phase-VIII 125.92 71 238.522008-09 19-Feb-09 Phase-IX 1388.15 905 2593.052011-12 25-Nov-11 Phase-X 915.07 647 1899.062011-12 23-Jan-12 Phase-X 33.05 0 23 0.832012-13 08-Jun-12 Phase-XI 2439.11 1350 96 3846.122013-14 21-Nov-13 Phase-XII (WBRRP_II) 1556.52 910 46 2291.57
2013-1421-Nov-13 Phase-XIII 2411.75 1457 143 3230.0307-Feb. 14 Phase X 4194.67 2796 67 5926.67
Total: 28495.64 16457 375 55070.73
B I
H A R
Year (s) Date Phase Value in Crores
No of Roads
No of Bridges
Length in Km
2000-01 26-Feb-01 Phase-I 105.92 168 900.752001-02 26-May-01 Phase-II 230.26 202 1200.22003-04 22-Dec-03 Phase-III 135.92 131 651.922003-04 22-Dec-03 Tranchi-I 29.15 26 130.072005-06 09-Mar-06 Phase-IV 113.78 102 479.392007-08 17-Dec-07 Phase-V 499.49 353 1679.82008-09 07-Aug-08 Tranchi-II 44.90 33 150.622008-09 30-Oct-08 Phase-VI 928.22 636 2971.72009-10 21-Aug-09 Phase-VII 280.20 279 1026.42009-10 03-Mar-10 Phase-VIII 601.87 656 4 2255.22011-12 23-May-11 Phase-IX 635.19 531 49 2006.22011-12 02-Mar-12 Phase-X 68.00 9 1 103.482012-13 27-Apr-12 Phase-X 404.12 291 10 1109.22012-13 15-Oct-12 Phase-X 186.54 0 56 02012-13 26-Mar-13 Phase-XI 1235.85 773 108 2428.1
2013-1426-Aug-13 Phase-XII 30.01 19 56.0813-Feb.-14 Phase XII (B-II) 1297.43 710 91 2517.21
Total: 6826.85 4919 319 19666.32
J H A R K H A N D
94
Year (s) Date Phase Value in Crores No of Roads No of Bridges Length in Km
2000-01 26-Feb-01 Phase-I 170.88 521 1068.412001-02 26-May-01 Phase-II 350.00 571 1692.462003-04 10-Nov-03 Phase-III 183.56 347 998.022003-04 10-Mar-04 Phase-III (Addl.) 257.37 283 1013.92004-05 02-Mar-05 Phase-IV 398.72 418 1645.122005-06 16-Aug-05 Batch I 349.46 257 1189.12005-06 16-Aug-05 Phase-V 531.00 483 1907.642006-07 03-Oct-06 Batch II 513.81 400 1612.222006-07 03-Oct-06 Phase-VI 579.84 443 1412.652007-08 08-Nov-07 Phase-VII 2668.43 1689 6617.052008-09 14-Nov-08 Batch III 611.40 310 1498.572008-09 14-Nov-08 Phase-VIII 87.04 0 31 02008-09 05-Feb-09 Phase-VIII 1858.01 1123 4678.392008-09 17-Feb-09 Phase-VIII 106.33 0 43 02008-09 27-Feb-09 Batch IV 522.58 334 1512.012008-09 27-Feb-09 Phase-VIII (Addl.) 851.43 309 2438.212009-10 11-Mar-11 Phase-IX 402.56 122 60 585.682011-12 15-Nov-11 Phase-X 993.80 602 2497.972011-12 28-Nov-11 RRSP Tranche-I 472.75 284 1052.22011-12 23-Mar-12 Phase-XI 1007.55 681 2645.572012-13 21-Sep-12 Phase-XII (Batch-I) 1497.83 823 3143.072012-13 19-Feb-13 Phase-XII (Batch-II) 947.89 511 2046.312013-14 23-Aug-13 Phase-XII (Batch-III) 483.31 141 02013-14 23-Aug-13 RRSP Tranche-II 584.64 343 1184.062013-14 03-Jan-14 ADB RCIP Tr. III 1385.67 788 17 2741.72
Total: 17815.86 11642 292 45180.33
O D I
S H A
Year (s) Date Phase Value in Crores
No of Roads
Length in Km
2000-01 26-Feb-01 Phase-I 140.04 174 826.322001-02 22-Oct-01 Phase-II 305.48 213 1126.602003-04 30-Jun-03 Phase-III 278.31 208 955.642003-04 30-Jan-04 Phase-III (Addl.) 320.97 159 1073.942005-06 01-Apr-05 Phase-IV 311.90 152 975.532005-06 16-Aug-05 Batch I 313.71 132 999.322006-07 08-May-06 Phase-V 657.78 236 1692.792007-08 20-Sep-07 Batch II 329.71 109 908.102007-08 20-Sep-07 Phase-VI 790.25 335 2127.702008-09 26-Feb-09 Phase-VII 869.44 463 2085.742008-09 27-Feb-09 Batch III 302.10 127 696.272008-09 27-Feb-09 Phase-VII 38.68 19 112.302010-11 13-Sep-10 Batch III (Part-II) 214.84 76 443.492010-11 13-Sep-10 Phase-VIII 502.57 280 1041.042011-12 18-Nov-11 Phase-IX 612.34 247 1269.272012-13 07-Dec-12 Phase-X 3483.19 1425 6143.962013-14 30-Jul-13 Phase-XI Batch-I 523.61 150 1027.472013-14 08-Aug-13 Phase-XI Batch-II 821.65 447 1539.132014-15 31-Mar-15 ADB 328.58 76 637.57
Total: 11145.15 5028 25682.18
W E S T
B E N G A L
GIS System Web GIS is the combination of WEB &
Geographic Information System which facilitates the sharing, communication, interoperability, collaboration, and integration of geospatial information on the Web .
The system aims to establish computerized data base for core rural road network through development of web based GIS.
This system in integration with OMMAS will support development of an online reporting module on rural road works thereby establishing a comprehensive planning, management, reporting system covering both construction and maintenance works.
GIS ImplementationThe system will help to monitor progress of the PMGSY on The system will help to monitor progress of the PMGSY on
GIS maps in conjunction with OMMAS data and will GIS maps in conjunction with OMMAS data and will include: include:
Showing connectivity status of the habitation/tourist places/ Panchayat HQs on a GIS map
Physical and financial progressQuality of the roads (NQM/SQM)Roads under/ due for maintenanceSpatial QueriesRoad Queries
• Road type (e.g. NH,SH etc.)• Road Ownership (PWD, Irrigation etc.)• Stream( PMGSY, World Bank etc.)• Through routes/Link routes
SRS & Implementation ProgressSystem Requirement Study (SRS) was assigned to CDAC &
their report was accepted.Based on this report it was decided to Implement GIS
system in all PMGSY states.The project will be implemented in two phases as
indicated below: Phase – I will comprise of procurement & installation of
hardware & software at central level in NRRDA, as part of Web GIS system & integration of data from the states of Rajasthan, HP, Gujarat, Maharashtra, Punjab & Uttarakhand.
Phase – II will integrate all the remaining participating & non participating states into the Web GIS system progressively as & when they finalize / update their database.
Plan of action
C-DAC will provide the hardware i.e. Web GIS server & operating software centrally at NRRDA.
States included in phase –I i.e. Punjab, Rajasthan, Himachal Pradesh, Gujarat, Maharashtra and Uttarakhand are to prepare or update the spatial database on priority as per SRS and C-DAC specifications circulated to them.
This is to be submitted to C-DAC for integration with the OMMAS system. The spatial database will be uploaded in the server for which C-DAC has defined the system & the integration process in the SRS specification.
Present StatusMemorandum of Understanding (MOU) with CDAC has
been signed for “Implementation of Web based GIS system in all PMGSY states”.
The states have been issued advisory on dated 29.05.2015 to prepare the database in accordance with SRS & system specification given by CDAC as indicated below : To initiate action to prepare / upgrade the data base. States
included in Phase –I i.e. Punjab, Rajasthan, Himachal Pradesh, Gujarat, Maharashtra and Uttarakhand need to do it promptly.
To assess whether they require SRIS system, as suggested by C-DAC for their State. This should be considered appropriately taking view of the fact that certain states have already developed standalone GIS System.
To assess their requirement of preparing / upgrading the database & requirement of SRIS, make a cost assessment for the same and project it to NRRDA for allotment of funds.
All the states are requested to expedite this process.
Project Flowchart
102
Trends of Physical Completion of Roads (in km)
103
N E A
C P W D
Trends of Physical Completion of Roads (in km)
104
NEA
N B C C
Trends of Physical Completion of Roads (in km)
105
NE A
I R C O N
Trends of Physical Completion of Roads (in km)
106
N E A
N H P C
Trends of Physical Completion of Roads (in km)
107
N E A
N P C C
Trends of Financial Progress ( Release / Expenditure in Rs Crore)
108
B I H A R N E A