pre-stressed concrete cylinder pipe (pccp) program · pdf filepre-stressed concrete cylinder...

9
Pre-stressed Concrete Cylinder Pipe (PCCP) Program Updated: September 2016

Upload: tranhuong

Post on 23-Mar-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Pre-stressed Concrete Cylinder Pipe (PCCP) Program · PDF filePre-stressed Concrete Cylinder Pipe (PCCP) Program Updated: ... (CFRP) repair versus segment replacement is based primarily

Pre-stressed Concrete Cylinder Pipe (PCCP) Program

Updated: September 2016

Page 2: Pre-stressed Concrete Cylinder Pipe (PCCP) Program · PDF filePre-stressed Concrete Cylinder Pipe (PCCP) Program Updated: ... (CFRP) repair versus segment replacement is based primarily

2

What is PCCP?

Page 3: Pre-stressed Concrete Cylinder Pipe (PCCP) Program · PDF filePre-stressed Concrete Cylinder Pipe (PCCP) Program Updated: ... (CFRP) repair versus segment replacement is based primarily

3

System Overview

Water System

Total PCCP

≥ 48" PCCP 77 miles

36" - 42" PCCP 68 miles

Wire Break Monitoring

36" - 96" PCCP

337 miles

145 miles

~ 90 miles

5,600 miles

Largest Wire Break Monitoring System in USA (Drinking Water)

Page 4: Pre-stressed Concrete Cylinder Pipe (PCCP) Program · PDF filePre-stressed Concrete Cylinder Pipe (PCCP) Program Updated: ... (CFRP) repair versus segment replacement is based primarily

4

PCCP Management Program

An Asset Management strategy for 36-inch and larger PCCP water transmission mains

Program first established in early 1980s

In 2007, WSSC initiated the current strategy using a regular inspection plan

Page 5: Pre-stressed Concrete Cylinder Pipe (PCCP) Program · PDF filePre-stressed Concrete Cylinder Pipe (PCCP) Program Updated: ... (CFRP) repair versus segment replacement is based primarily

5

WSSC’s PCCP

Program

Engineering Analysis

Inspections

Monitoring

RepairsReplacements

Forensics

Asset Management

Page 6: Pre-stressed Concrete Cylinder Pipe (PCCP) Program · PDF filePre-stressed Concrete Cylinder Pipe (PCCP) Program Updated: ... (CFRP) repair versus segment replacement is based primarily

6

Annual inspection goal is ~ 18 miles

All PCCP ≥ 48” have been inspected multiple times and continuously monitored for wire breaks

Inspection of 36” – 42” PCCP began in 2013 and is on an 8 to 10 year inspection schedule

Carryout emergency inspections - as needed

Inspections

Page 7: Pre-stressed Concrete Cylinder Pipe (PCCP) Program · PDF filePre-stressed Concrete Cylinder Pipe (PCCP) Program Updated: ... (CFRP) repair versus segment replacement is based primarily

7

Small segment Carbon Fiber Reinforced Polymer (CFRP) repair versus segment replacement is based primarily on the location of pipe

For smaller diameters (36” & 42”), dewatering, access, ventilation, etc. may necessitate segment replacement versus CFRP repair

Each location is unique

Repair and Replacement

Page 8: Pre-stressed Concrete Cylinder Pipe (PCCP) Program · PDF filePre-stressed Concrete Cylinder Pipe (PCCP) Program Updated: ... (CFRP) repair versus segment replacement is based primarily

WSSC monitors PCCP wire breaks using Acoustic Fiber Optic (AFO) Monitoring System

Current monitoring ~ 90± miles

Alerts received by WSSC staff and appropriate action taken

AFO Monitoring does not prevent pipe failure; It provides an early warning

8

Monitoring

Page 9: Pre-stressed Concrete Cylinder Pipe (PCCP) Program · PDF filePre-stressed Concrete Cylinder Pipe (PCCP) Program Updated: ... (CFRP) repair versus segment replacement is based primarily

9

Forensics