Precast Façade Presentation
for
The Hong Kong Institute of Surveyors
14 July 2012
Orientfunds Precast Limited
![Page 2: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/2.jpg)
Content
1) Why Prefabrication
2) Practice – JPN2
3) Design Concept
4) Types of Precast Elements
5) Transportation
6) Site Storage Area
7) Lifting Method
8) Consideration
9) Production
Orientfunds Precast Limited
![Page 3: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/3.jpg)
Why Prefabrication ? (1)
Green Construction (Global Trend)
Less Formwork & Falsework
Less Construction Waste
Less Wastewater (i.e. Less on-site Wet Trade)
Less Scaffolding
Orientfunds Precast Limited
Standardize Installation Procedure
Accelerate Construction Programme
4 or 5 day construction cycle
Shorten On-site wet trades time after
concrete structure completion
![Page 4: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/4.jpg)
Orientfunds Precast Limited
Why Prefabrication ? (2)
Good Quality
Product Consistency
Better Waterproofing
GFA and / or SC exemption – JPN No. 2
(Non-structural prefabricated external walls)
Aging Skill Labours in Hong Kong
![Page 5: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/5.jpg)
New Practice - Joint Practice Note No. 2
Permit maximum 150mm thickness in GFA exemption
GFA accountable to this
face (for in-situ)
GFA accountable to this
face (under JPN2)
Orientfunds Precast Limited
150 100
![Page 6: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/6.jpg)
Design Concept
Gravity load supported by upper level floor beam
Horizontal gap between precast façades to prevent load
transfer
Lateral wind load support by a combination of upper
level floor beam and two side walls/columns (3 sides
support)
![Page 7: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/7.jpg)
Design Concept - Waterproofing (Horizontal Joint)
Above Floor Level Level with Floor
Below Floor Level
![Page 8: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/8.jpg)
Design Concept - Waterproofing (Vertical Joint)
Precast to Precast
Stitch to insitu column Add post to form
insitu stitch
![Page 9: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/9.jpg)
Design Concept - Installation
Orientfunds Precast Limited
![Page 10: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/10.jpg)
Types of Precast Elements
Precast Lost Form
Precast Balcony / U.P.
Precast Façade – Bay Window
Precast Façade – Wall Panel
Precast Staircase
Precast Slab (semi-precast)
Precast Bathroom (volumetric precast)
Precast Beam
Precast Wall/Column
Orientfunds Precast Limited
Residential
Housing
Authority
Commercial
![Page 11: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/11.jpg)
Transportation
![Page 12: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/12.jpg)
Total Height of the load and the vehicle : Max. 4.6 m
Total Width of the load and the vehicle : Max. 2.5 m
Maximum Permitted Gross Combined Weight : 24 – 44 tonnes
(depends on types of vehicle)
Traffic Regulation in Hong Kong
Information from:
(1) Road Traffic (Traffic Control) Regulations, &
(2) Road Traffic (Construction and Maintenance of Vehicles) Regulations
Max.
4.6 m
Max. 2.5 m
![Page 13: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/13.jpg)
Site Storage Area
Recommend to store one storey per tower
![Page 14: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/14.jpg)
Lifting Method
(I) Lifting “C” Frame (「C」卡 )
(II) Lifting Beam (吊担 )
![Page 15: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/15.jpg)
Other Issue
Tower Crane
a. Number of tower crane
b. Tower Crane Capacity
Mock Up
a. What to choose? Critical / Difficult Units
b. What material to use? Timber / Metal Formwork
![Page 16: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/16.jpg)
Consideration
1. Sufficient Site Storage Area
2. Early award of aluminum window contract (6 mths prior delivery)
3. Plumb & drain and electrical embedment layout need to be approved before
mass production
4. Finishing details (tile, al. cladding, granite, glass) need to be approved
before mass production
![Page 17: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/17.jpg)
Production
![Page 18: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/18.jpg)
Production
1. Steel Cage fixing
![Page 19: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/19.jpg)
Production
2. Installation of window
![Page 20: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/20.jpg)
Production
3. Installation of steel cage
![Page 21: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/21.jpg)
Production
4. Installation of cast-in items
![Page 22: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/22.jpg)
Slump test
Making concrete cubes
Production
5. Concreting
![Page 23: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/23.jpg)
Production
6. Concreting
![Page 24: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/24.jpg)
Production
7. Demoulding
![Page 25: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/25.jpg)
Setting out line for tile application
Production
8. Tile laying
![Page 26: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/26.jpg)
Production
9. Delivery of precast elements
![Page 27: Precast Façade Presentation - HKIS · Content 1) Why Prefabrication 2) Practice – JPN2 3) Design Concept 4) Types of Precast Elements 5) Transportation 6) Site Storage Area 7)](https://reader030.vdocument.in/reader030/viewer/2022021511/5ac854a47f8b9acb7c8c9712/html5/thumbnails/27.jpg)
Thank you